Rev 3
SAIC NUMBER
SAIC-N-2039
PROJECT TITLE
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
A.
MECH-
CONTRACTOR / SUBCONTRACTOR
ACCEPTANCE CRITERIA
QR NUMBER
15-Dec-09
EQPT CODE
ITEM
No.
30-Jun-08
DATE APPROVED
REFERENCE
PASS
FAIL
N/A
RE-INSP DATE
General Requirements
Refractory systems for specific equipment meet requirements
specified in SAES-N-100 Table 3 "Mandatory Refractory Systems":
A1
SAES-N-100,
Para. 9.1
B.
B1
Pre-Application Document Review Requirements & Layout Checks for Fireclay Brick Refractories
(SAES-N-130 Procedure)
Approved Detail drawings are available. Layout & surveys have been
completed to assure verification of the levelness & plumbness of fireclay
brick installation.
SAES-N-130,
Para. 8.3
C.
Equipment (Mixer & Brick Saw, etc) & Work Area Staging Requirements
C1
Number and type of mixers are adequate & back-up mixer is available.
Manufacturer
Recommendations are available/followed in this regard.
Brick saw is available on site in good condition with existing safeguards
C2
Note: Bricks are never split mechanically using hammer & chisel
C3
C4
SAES-N-130,
Para. 8.3
SAES-N-130,
Para. 8.3
The set-up location of mixer & equipment is correct relative to work site.
SAES-N-130,
Para. 8.3
The condition of mixers & equipment are good & well cleaned.
Area cleanliness prevents fouling of the refractory.
SAES-N-130,
Para. 8.3
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-N-100 -- Refractory Systems (30 Jan 2007)
2. SAES-N-130 -- Installation Requirements-Fireclay Bricks (30 Jan 2007)
NOTES:
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
QC Inspector
PID Representative
Performed Inspection
QC Supervisor
Name, Organization,
Initials and Date:
Y = YES
Page 1 of 1
N = NO F = FAILED