Beruflich Dokumente
Kultur Dokumente
Interest factor
(P/F,i,n)
(F/P,i,n)
(P/A,i,n)
(A/P,i,n)
(F/A,i,n)
(A/F,i,n)
(P/G,i,n)
(P/Ai,i,n)
Equation
P = F(1 + i)-n
F = P(1 + i)n
P = A[(1+i)n - 1]/[i(1+i)n]
A = P[i(1+i)n]/[(1+i)n - 1]
F = A[(1+i)n - 1]/i
A = Fi/[(1+i)n - 1]
P = G[(1+i)n - in - 1]/[i2(1+i)n]
P = Ai[1-(1+g)n(1+i)-n]/[i-g]
IRR
NPV
None
None
Excel Function
PV(Rate,Nper,,Fv,Type)
FV(Rate,Nper,,Pv,Type)
PV(Rate,Nper,Pmt,,Type)
PMT(Rate,Nper,Pv,,Type)
FV(Rate,Nper,Pmt,,Type)
PMT(Rate,Nper,,Fv,Type)
none
none
IRR(Values, Guess)
NPV(Rate,Values)
-$400,000
$60,000
$60,000
10.00
0.08
Cash Flow
-$400,000
$60,000
$60,000
$60,000
$60,000
$60,000
$60,000
$60,000
$
$
$
years
fraction
8
9
10
Present value,
beginning year 1?
$60,000
$60,000
$120,000
Initial
Annual
Salvage
-$400,000
$402,605
$27,792
-$400,000
$402,605
$27,792
-$59,612
$60,000
$4,142
-$59,612
$60,000
$4,142
-$863,570
$869,194
$60,000
-$863,570
$869,194
$60,000
30396
ount (year n)
ries (uniform)
c gradient series
c gradient series
er compounding period.
Total
Comment
Typed Equation
$4,530
PMT
2. Convert all amounts in years with negative net benefit (i.e., where costs were larger than benefits) to present
worth (PWC)
3. Convert all amounts in years with positive net benefit (i.e., where benefits were larger than costs) to present
worth (PWB)
4. The benefit cost ratio is PWB / PWC.
5. You'll get the same answer if you use annual worth or future worth.
If you want to identify the best alternative using the incremental benefit cost ratio method, continue.
6. When comparing two alternative with the same benefit or cost, choose the alternate with the largest benefitcost ratio.
7. If neither benefit or cost is the same, compute the Present worth and present cost for each alternative and
follow the remaining steps.
8. Discard any alternative with PWB / PWC less than 1
9. Oder remaining alternatives from lowest to highest cost and number 1, 2,,P.
10. For projects 1 and 2 compute the incremental PWB / PWC, i.e., (PWB 2-PWB1) / (PWC2-PWC1)
11. If the incremental PWB / PWC ratio is greater than 1, keep project 2. If it is less than 1, keep project 1.
12. Repeat, comparing the next project to the best project identified so far. Keep repeating until only one (the
best) project is left.
Payback Period
Undiscounted
1. Create a cash flow table for the project.
2. Determine the cumulative cash flow for each period.
3. Identify the period (if there is one) during which the cumulative cash flow becomes positive.
Discounted
1. Create a cash flow table for the project.
2. Estimate the present worth of the cash flow for each period.
3. Determine the cumulative present worth cash flow for each period.
4. Identify the period (if there is one) during which the cumulative cash flow becomes positive.
5. Use the equation given above to calculate the exact payback period, if necessary. We won't bother.
A
-50000
-4000
10000
15000
9
Interest
B
-25000
-5000
10000
10000
9
C
-70000
-10000
30000
25000
3
Projects
B
-$25,000
$5,000
$5,000
$5,000
$5,000
$5,000
$5,000
$5,000
$5,000
$15,000
C
-$70,000
$20,000
$20,000
-$25,000
$20,000
$20,000
-$25,000
$20,000
$20,000
$45,000
0.08
A
-$50,000
$6,000
$6,000
$6,000
$6,000
$6,000
$6,000
$6,000
$6,000
$21,000
Alternate
C
-$70,000
$20,000
$20,000
$45,000
-$50,000
-$25,000
-$70,000
-$45,000
Answer :
+
$6,000
+
$5,000
+
$20,000
(P/F,i,6) +
Project
i = 0.08
x (P/A,i,9) +
$15,000 x (P/F,i,9) =
x (P/A,i,9) +
$10,000 x (P/F,i,9) =
x (P/A,i,9) +
-$45,000 x (P/F,i,3) +
$25,000 x (P/F,i,9) =
$3,364
-$5,015
$11,237
-$50,000 x (A/P,i,9) +
-$25,000 x (A/P,i,9) +
-$70,000 x (A/P,i,3) +
Answer :
$6,000
$5,000
$20,000
Project
+
+
+
$15,000 x (A/F,i,9) =
$10,000 x (A/F,i,9) =
$25,000 x (A/F,i,3) =
(d) Determine the internal rate of return for each project using the graphical method, to the nearest integer (as %).
Present Worth
Project A Project B Project C
$19,000
$30,000
$45,000
$15,111
$26,973
$38,110
$11,525
$24,179
$31,800
$8,213
$21,595
$26,014
$5,151
$19,203
$20,702
$2,316
$16,985
$15,819
-$311
$14,927
$11,325
-$2,750
$13,015
$7,184
-$5,015
$11,237
$3,364
-$7,122
$9,581
-$165
-$9,084
$8,036
-$3,428
-$10,914
$6,594
-$6,448
-$12,621
$5,247
-$9,248
-$14,217
$3,987 -$11,846
-$15,709
$2,807 -$14,260
-$17,107
$1,701 -$16,505
-$18,416
$662 -$18,595
-$19,646
-$313 -$20,543
-$20,800
-$1,230 -$22,361
-$21,886
-$2,094 -$24,059
-$22,907
-$2,907 -$25,648
i
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
0.1
0.11
0.12
0.13
0.14
0.15
0.16
0.17
0.18
0.19
0.2
i* =
6%
17%
Ne t Pre se nt Worth
Using the formulas from part a, determine the present worth for a number of values of i. Identify the i's that give PW = 0.
$50,000
Project A
Project B
$40,000
Project C
$30,000
$20,000
$10,000
$0
0
0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2
-$10,000
-$20,000
i* is the interest rate that gives zero net PW.
-$30,000
9%
Note: I've used the IRR formula, but the answers can be read off of the Table or Chart.
PC
B/C ratio
$74,988
0.93
$56,234
1.20
$95,771
1.01
Project
I've taken the Project Summary and converted benefits to present worth benefits
and costs to present worth costs. Do problems this way if you have access to project summary.
PC
B/C ratio
$50,000
0.90
$25,000
1.45
$105,600
1.03
Project
I've taken the Cash Flow table and converted the positive yearly amounts to PW
(present worth), and the negative yearly amounts to PC (present cost).
A
Csh Flw, $
-$50,000
$6,000
$6,000
$6,000
$6,000
$6,000
$6,000
$6,000
$6,000
$21,000
B
Cum, $ Csh Flw, $
-$50,000 -$25,000
-$44,000
$5,000
-$38,000
$5,000
-$32,000
$5,000
-$26,000
$5,000
-$20,000
$5,000
-$14,000
$5,000
-$8,000
$5,000
-$2,000
$5,000
$19,000
$15,000
C
Cum, $ Csh Flw, $
-$25,000 -$70,000
-$20,000
$20,000
-$15,000
$20,000
-$10,000 -$25,000
-$5,000
$20,000
$0
$20,000
$5,000 -$25,000
$10,000
$20,000
$15,000
$20,000
$30,000
$45,000
Cum, $
-$70,000
-$50,000
-$30,000
-$55,000
-$35,000
-$15,000
-$40,000
-$20,000
$0
$45,000
Answer: Payback is in the first year with a positive cumulative cash amount.
(g) Identify the payback year, discounted
End of
Year
0
1
2
3
4
5
6
7
8
9
Csh Flw, $
-50,000
6,000
6,000
6,000
6,000
6,000
6,000
6,000
6,000
21,000
A
PW, $
-50,000
5,556
5,144
4,763
4,410
4,083
3,781
3,501
3,242
10,505
B
PW, $
-25,000
4,630
4,287
3,969
3,675
3,403
3,151
2,917
2,701
7,504
Answer: Payback is in the first year with a positive cumulative cash amount.
C
PW, $
-70,000
18,519
17,147
-19,846
14,701
13,612
-15,754
11,670
10,805
22,511
Cum, $
-$70,000
-$51,481
-$34,335
-$54,181
-$39,480
-$25,868
-$41,622
-$29,953
-$19,147
$3,364
More Examples
Example 1
Compare Two Alternatives using Present Worth Analysis and Annual Cash Flow Analysis.
A
Initial Costs
Annual Net Revenue
Lifetime
Salvage (at Lifetime)
Interest
B
-$200,000
$50,000
5
$20,000
-$400,000
$70,000
10
$0
0.08
A
-$200,000
$50,000
$50,000
$50,000
$50,000
-$130,000
$50,000
$50,000
$50,000
$50,000
$70,000
B
-$400,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
OR
22262.96
22262.96
69705.70 Pick B
69705.70
Equations
PV
NPV
OR
3317.84
3317.84
10388.20 Pick B
10388.20
PMT & PV
PMT & NPV
OR
48064.07
48064.07
150489.37 Pick B
150489.37
Present Value
Annual Worth
FV & PV
FV & NPV
Example 2
Calculate internal rate of return
A
0.08
10
MARR = Minimum Acceptable Rate of Return
Initial Costs
Annual Net Revenue
Lifetime (years)
Salvage (at Lifetime)
-$200,000
$50,000
5
$20,000
-$400,000
$70,000
10
$0
A
-$200,000
$50,000
B
-$400,000
$70,000
-200
50
$50,000
$50,000
$50,000
-$130,000
$50,000
$50,000
$50,000
$50,000
$70,000
50
50
50
70
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
10.4%
Note: you'll get the same i* for A based on the 5 year lifetime.
Rate of return analysis by plotting:
PWNB
Interest
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
0.10
0.11
0.12
0.13
0.14
Net PW
A
$120,407
$102,505
$86,122
$71,109
$57,330
$44,666
$33,009
$22,263
$12,343
$3,173
-$5,316
-$13,186
-$20,493
-$27,286
Net PW
B
$262,991
$228,781
$197,114
$167,763
$140,521
$115,206
$91,651
$69,706
$49,236
$30,120
$12,246
-$4,484
-$20,163
-$34,872
$300,000
$250,000
$200,000
$150,000
$100,000
$50,000
$0
-$50,000
A
B
$150,000
$100,000
$50,000
$0
-$50,0000.01
0.03
0.05
0.07
0.09
0.11
0.13
Interest Rate
i* is where each plot has PWNB = 0.
Rate of return analysis using Solver (Excel Add-in)
Set Target Cell (Present Worth)
By Changing Cell (i*)
$0.0000
0.1036
$0
0.1173
Initial Costs
Annual Net Revenue
Lifetime (years)
Salvage (at Lifetime)
Interest
B
-$400,000
$70,000
10
$0
0.08
A
$358,380
B
$469,706
$336,117
$400,000
1.07
1.17
Keep costs and benefits separate.
Note: You'll get the same ratio for Annual worth or future worth calculations
Example 4
Payback Period Analysis - undiscounted.
A
Initial Costs
B
-$200,000
-$400,000
Alternate Calculations
A
$310,739
$288,476
1.08
Identify Costs and Benefits by yea
$50,000
5
$20,000
$70,000
10
$0
0.08
A
-$200,000
$50,000
$50,000
$50,000
$50,000
$70,000
B
-$400,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
A: Payback occurs at the end of year 4, but then new equipment is purchased and
cum cash flow goes negative again, until year 8.
B: Payback occurs during year 6
Example 5
Payback Period Analysis - Discounted.
A
Initial Costs
Annual Net Revenue
Lifetime
Salvage (at Lifetime)
Interest
B
-$200,000
$50,000
5
$20,000
-$400,000
$70,000
10
$0
0.08
A
-$200,000
$50,000
$50,000
$50,000
$50,000
$70,000
B
-$400,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
$70,000
(Bonus Analysis)
MARR
comparison life
cceptable Rate of Return
2
3
4
5
6
7
8
9
20
$20,000
$20,000
$20,000
$200,000
$20,000
$20,000
$20,000
$20,000
$0
0.13
i* =
Which is higher than MARR, so pick larger project (B).
A
B
0.11
0.13
ternate Calculations
B
$469,706
$400,000
1.17
entify Costs and Benefits by year
Incremental Benefit Cost Analysis (Based on Costs & Benefits by Year method)
B-A
Incremental Present Worth Benefits
$158,967
Incremental Present Worth Costs
$111,524
1
2
3
4
5
6
7
8
9
10
Year method)