Beruflich Dokumente
Kultur Dokumente
Abstract
The Energy Tower (ET) is a power plant project which uses hot dry air and seawater to produce electricity. An optimized design of a
system that is a combination of an ET, pumped storage and seawater desalination plant is considered. A model set covering each
subsystem, and results of the optimized design for a project in the area of Eilat are presented. The additional benet from combining the
systems comes from an efcient use of the energy in the brine water coming from the desalination process, and from using pumped
storage in an unconventional way. The benets of the combined system lead to an increase of 14% in the annual net prot, compared to
the sum of prots from optimally designed stand-alone systems.
r 2007 Elsevier Ltd. All rights reserved.
Keywords: Energy Tower; Power system optimization; Optimal design; Desalination; Pumped storage
1. Introduction
The Energy Tower (ET) includes a new technology
which uses hot dry air and seawater to produce electricity.
Different aspects of the ET, including the modeling of the
formation of droplets and wind ow are found in [14].
Pumped storage is a method to store energy by
converting electrical energy to potential energy by pumping
water to an upper reservoir. The potential energy can be
converted again to electrical energy when desired by letting
the water ow down through a hydro-electric turbine
generator. A desalination plant is used to desalinate a
seawater by the principle of reverse osmosis (RO). These
three systems can be installed as stand-alone systems;
however, by combining them together, additional prot
can be obtained due to savings in initial investments and
energy usage, compared to the sum of prots from the
stand-alone systems. This paper includes descriptions of
models, formulation of an optimization problem for the
optimal design and analysis of results obtained for a
ARTICLE IN PRESS
598
Notations
prX
PTUR
Qbrine_sec
qi
qbr
qbrine
Qdes_sec
Qfeed_sec
Qi
qspr
R
RTloss
SR
Vmax,i
Z*
Z1
Greek
bi
gi,k
Dhbooster
Dhrec_tur
Zb
Zp,i
ZT
rbrine
rw
Abbreviations
ET
IRR
LP
O&M
RO
SRY
Energy Tower
internal rate of return
linear programming
operation and maintenance
reverse osmosis
short reference year
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
(P2) to the spraying system at the top of the tower. The air
that comes out from the bottom of the tower is cold, humid
and contains brine droplets. The brine droplets fall on the
ground and the brine is conveyed to the brine reservoir
(V3), and from there it is returned to the sea by gravity.
A scheme of the stand-alone pumped storage plant is
shown in Fig. 3. Water is pumped from the lower reservoir
(V1) to the upper reservoir (V2) using reversible pumps
(PREV2a) during low-demand hours. The water from the
upper reservoir ows by gravity to the lower reservoir
during peak hours, operating the reversible pumps as water
turbines generators. Water is pumped from the sea by the
low head pumps (P1) in order to compensate the water loss
due to evaporation.
A scheme of the stand-alone RO desalination plant is
shown in Fig. 4. Water is pumped from the sea using low
head pumps (P1), through a pipe (L1) to the reservoir (V1),
where primary treatment is performed. Water from the
599
V2
q3_up
q3_down
P1
q1
L1
L3
hres2
PREV2
V1
hres1
SEA
L9
htower
E.T.
q9
turbinesgenerators
P1
q1
L1
V1
q10
P2c
V3
L11
hres1
SEA
Fig. 2. A scheme of the stand-alone ET.
q11
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
600
membranes array
Qdes sec
P1
Qfeed
V1
desalinated
water
P2
Qbrin
L1
hres1
q1
REC_TUR
L11
SEA
recovery
turbinegenerator
L9
V2
+
E.T.
q9
q3
Qdes_sec
L3
R.O.
booster
Qfeed
P2a
P1
q1
V1
P2b
turbinesgenerators
q10
P2c
V3
2_p
PREV2a
L1
Qbrine
q4
q8
q2_t
L11
q11
SEA
Fig. 5. Scheme of the combined system that includes an ET, pumped storage and a desalination plant.
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
(1)
601
Qdes_sec m; h
,
Qfeed_sec m; h
SR 1
(2)
Cp
.
C feed
(3)
1
1 ,
Zb
(4)
(5)
Z.
Bloss
Dhbooster
(6)
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
602
about 11 times higher than the energy losses when using the
booster pump. However, there is a disadvantage of
spraying the RO brine water. The increase of salt
concentration of the spraying water leads to a decrease of
the generated power from the ET. The concentration of the
spraying water is an input to the one-dimensional ET
model [2,3]. For a stand-alone ET, the concentration of the
spraying water is the same as the concentration of the
seawater. In the combined system, the concentration of salt
in the spraying water is found from
C spr m; h
(8)
(9)
C feed
.
1 RSR
(10)
(11)
5. Results
The algorithm for the optimal design of the stand-alone
systems and the combined system that includes an ET, a
desalination plant and pumped storage was programmed in
the MATLAB environment, and implemented with data
from a potential site in the Eilat area, Israel. The main
input parameters are listed in Table 1. Table 2 shows the
optimal design of the combined system, and the results for
these systems as stand-alone systems. Table 3 shows
the summary of the performance of the stand alone and
the combined systems. Table 4 shows the summary of the
economy parameters of the stand alone and the combined
systems. The number in parentheses in these tables is the
sum of the sizes of the same parameter in all systems, in
case stand-alone systems were installed.
The lower reservoir V1 in the combined system is smaller
compared to the stand-alone systems, since it does not have
to contain all the water from the upper reservoir V2, as in
the stand-alone pumped storage. Only some amount of the
water ows through the reversible pump PREV2a to
the lower reservoir, while some amount of the water from
the upper reservoir is used as spraying water, see Fig. 5.
Recall the explanations in Section 3. Since some amount of
the water is returned to the lower reservoir, this amount of
water does not have to be pumped from the sea. So the
Table 1
Main input parameters for the model implementation
Parameter
Units
Value
m
m
km
m
million m3/year
%
m$
$/kW
$/kW
%
1280
400
40
500
20
50
450
400
320
5
Table 2
The optimal design of the components of the stand-alone and the
combined systems
Symbol
Units
E.T.
p.s.
desl
E.T.+p.s.+desl
V1
V2
V3
Q1
Q3
Q9
Q11
P1
P2a
PREV2a
TUR2a
P2b
P2c
REC_TUR
Pbooster
Ptotal
PTUR
103 m3
103 m3
103 m3
m3/s
m3/s
m3/s
m3/s
MW
MW
MW
MW
MW
MW
MW
MW
MW
MW
261
35
20.2
27.8
3.3
22
226
248
629
1000
1000
0.2
39.7
0.1
235
168
235.1
17
3.1
0.6
2.7
10.5
3.6
13.2
780 (1278)
1000
67
21.5 (23.3)
40.4
30.1
3.7 (3.9)
23.1 (24.8)
113
170
121
40
121
0.4
467.5 (496.3)
669
The number in parentheses is the sum of the sizes of the same component
in all systems, in case stand-alone systems were installed. Legend: E.T.
ET, p.s.pumped storage, desldesalination plant.
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
603
Table 3
A summary of the performance of the stand-alone and the combined systems
Parameter
Units
E.T.
p.s.
desl
E.T.+p.s.+desl
kWh/year 109
kWh/year 109
kWh/year 109
million m3/year
m3/s
MW
3.713
1.621
2.092
347
10.98
114
0.427
0.602
0.175
1.5
167
0.073
0.073
40
3.911 (4.140)
1.974 (2.296)
1.937 (1.844)
379 (388.5)
11.38
281
The number in parentheses is the sum of the sizes of the same parameter in all systems, in case stand-alone systems were installed. Legend: E.T.ET,
p.s.pumped storage, desldesalination plant.
Table 4
A summary of the economics of the stand-alone and the combined systems
Parameter
Units
E.T.
p.s.
desl
E.T. +p.s.+
desl
Initial investment
Annual investment return
Annual energy costs
Annual O&M costs
Total annual costs
Total annual incomes
Annual net prot
IRR (30 years)
m$
m$/year
m$/year
m$/year
m$/year
m$/year
m$/year
%
885
66.6
116.0
20.6
203.3
272.1
68.8
15.1
140
12.7
14.9
2.4
29.9
45.5
15.6
20.1
44
3.4
4.8
4.2
12.4
13
0.6
8.2
1099 (1069)
84.3 (82.6)
109.5 (135.7)
25.3 (27.2)
219.1 (245.6)
315.9 (330.6)
96.8 (85.1)
16.3 (15.5)
The number in parentheses is the sum of the sizes of the same parameter in
all systems, in case stand-alone systems were installed. Legend: E.T.ET,
p.s.pumped storage, desldesalination plant.
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
604
Gross power
Pumping power
Net power
800
700
600
500
[MW]
400
300
200
r
D
ec
em
em
be
be
er
ov
N
r
be
pt
em
O
ct
ob
st
Au
gu
ly
Ju
ne
Se
-200
Ju
ay
M
ril
Ap
ch
ar
M
ar
ru
Fe
b
Ja
-100
nu
ar
100
Fig. 6. Combined system: Gross power, Pumping power, and Net power during the short reference year (SRY).
(D1 and D9), and the other step includes a search of all
other variables. The sub problem with the xed
diameters was formulated as a LP problem, where most
functions were approximated as linear functions, and a
few highly non-linear functions were approximated as
piece-wise linear functions. The other subproblem,
which includes nding the optimal diameters when all
other variables are xed, is solved analytically by lowdimensional optimization of the objective function.
2. The design of the combined system was found with input
parameters that correspond to a potential site near the city
of Eilat, Israel. The results of the stand-alone systems were
compared with the results of the combined system. The
comparison shows that by combining a desalination plant
and pumped storage with an ET, there is an additional
benet due to an increase of the energetic efciency in the
combined system, compared to the efciency of the standalone systems. The installation cost of the combined
system is not necessarily lower than the sum of installation
costs of the stand-alone systems, since sometimes the
optimal combination of the systems enables a higher net
prot by increasing the sizes of some components in the
system. An implementation of the algorithm showed that
the additional benet from combining the systems lead to
an increase of 14% in the annual net prot, compared to
the sum of prots from the stand-alone systems, when
optimally designed. The annual net prot from the
combined system was found to be 41% higher than the
annual net prot from a stand-alone ET. A new operating
point is obtained by combining the systems, which involves
an increase of the size of most components in the system,
due to an increase of the attractiveness of operating the
ET. Another big advantage of the combined system is the
increase of the guaranteed power at peak hours in January
from 110 [MW] in the stand-alone system to 300 [MW] in
the combined system.
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
subject to :
Axpb
Aeq x beq
lbpxpub,
A:1
aij xj pbj ;
i 1; . . . ; N ineq .
j1
The matrix Aeq and the vector beq include the parameters
of the matrix form of the equality constraints:
N
vars
X
aeq;ij xj beq;j ;
i 1; . . . ; N eq .
j1
605
Table 5
The relevant equations of the LP problems
Zi ,
(A.2)
where Z is the annual prot (with a minus sign), not
including constant costs [1000 $/year] and Zi are as follows,
where Zi cjxj, and the variable xj is bolded.
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
606
Reservoirs installation:
X
C resi prRESi Vi
Z1
LP1 : i 1; 3;
LP3 : i 1;
A:4
(A.5)
Pipes installation:
X
Z4
C pipe ; ia Li prLi =103 Qi
LP4 : i 3; 11.
A:14
(A.7)
vi m; h V i p0
A:6
Turbines installation:
Z 5 C tur prTUR PTUR.
A:13
pi m; h Pi p0
LP2 : i 3;
k1
LP1 : i 1; 3; LP2 : i 1; 2;
LP3 : i 1; LP4 : i 1; 2; 3
LP1 : i 11;
bk avg_maint=103
A.2.3. Constraints
Hourly water volumes in the reservoirs cannot exceed
the capacities of the reservoirs:
15
XX
C elec_prod m; h q9;k m; h.
A:3
days_in_monthm
LP2 : i 1; 2;
LP4 : i 1; 2; 3.
10
X
q1;k m; h Q1 p0,
A:15
(A.16)
k1
A:8
q2p m; h Q2 p0,
(A.17)
q2t m; h Q2 p0,
(A.18)
q4 m; h Q4 p0,
(A.19)
C elec_cons m; h p1 m; h.
A:9
A:10
A:11
bk m; h q9;k m; h PTURp0.
(A.22)
10
X
q1;k m; h
k1
(A.21)
C elec_cons m; h pump2a=106 q4 m; h:
(A.20)
k1
q9;k m; h Q9 p0,
k1
15
X
m 1; . . . ; 12
A:23
days_in_monthm
h 1; . . . ; 24,
A:12
v2 m; h 1 v2 m; h 3:6 q3 m; h
3:6 0:5 evap_disch; m 1; . . . ; 12;
h 1; . . . ; 24,
ARTICLE IN PRESS
E. Omer et al. / Renewable Energy 33 (2008) 597607
v3 m; h 1 v3 m; h
3:6 q11 m; h
15
X
pi m; h
brine_coef k m; h q9;k m; h 0,
k1
m 1; . . . ; 12
h 1; . . . ; 24.
A:25
Ni
X
607
gi;k qi;k m; h 0
k1
A:31
10
X
q1;k m; 24
k1
m 1; . . . ; 12,
A:26
v2 m; 1 v2 m; 24 3:6 q3 m; 24
3:6 0:5 evap_disch;
m 1; . . . ; 12,
A:27
v3 m; 1 v3 m; 24
3:6 q11 m; 24
15
P
k1
m 1; . . . ; 12,
A:28
h 1; . . . ; 24.
A:29
q9;k m; h q4 m; h Qdes_sec m; h,
k1
m 1; . . . ; 12;
h 1; . . . ; 24.
A:30