Sie sind auf Seite 1von 7

Date:Feb.

29,2012
Ref.No.:PPEP001Rev.00

METHODSTATEMENT
STRINGINGOF30KVOVERHEADLINE

FOR

2X30MWCFPPINPOMALAA
PT.ANTAM(PERSERO)Tbk,INDONESIA

FEBRUARY2012
PT.WASAMITRAENGINEERING

TABLE OF CONTENT

Page
1. Work Procedure and Job Safety Analysis .......................................................... 2
1.1

Preparation ................................................................................................ 2

1.2 Personal Protective Equipment ................................................................. 2


1.3

Others. ....................................................................................................... 2

2. Method Statement .............................................................................................. 2


2.1

General Condition...................................................................................... 2

2.2

Preparation Work ............................................................................................ 2

2.3

Procedure .................................................................................................. 3

2.4

Others ........................................................................................................ 4

3. Location of Work. ............................................................................................... 4


4. Attachment
a. Power Plan Layout

PT. WASA MITRA ENGINEERING


POMALAA CFPP 2 X 30MW

Method Statement for Installation of 30kV Conductor


(Crossing with existing 20kV PLNs Overhead Line)

1. Work Procedure and Job Safety Analysis.


1.1

Preparation
1) Man Power.

Safety Induction for workers by Safety Officer.

Tool Box meeting before start of work.

2) Necessary tools.
All necessary electrical tools shall be passed inspection.
3) Work Permit.
Permit shall be obtained from PLN & local government.
4) Installation of scaffolding.
Install of scaffolding for work access and inspection before use.

1.2

Personal Protective Equipment


Appropriate equipment, e.g. helmet, safety shoes, goggle, masker, safety
harness and other equipment, shall be given to related persons before
commencing work.

1.3

Others.
1) Barricade, sign board and temporary protection.
To be kept in container or job side and to be placed as required, refer to
each activity.
2) First aid box must be available on job site.

2. Method Statement
2.1

General Condition
Height of existing 20kV tower or pole is 13 meters, for new 30kV pole is 10
meters. Therefore, installation of 30kV overhead line will be under 20kV
existing PLNs transmission line.

2.2

Preparation Work.
1) Ensure all the necessary electrical and hand tools complete already.
2) Ensure that storage of materials not obstruct to road traffic and public
facilities.

STRINGING OF 30KV OVERHEAD LINE

PT. WASA MITRA ENGINEERING


POMALAA CFPP 2 X 30MW

3) Puller preparation
-

Placement of engine puller in place has been determined previously

Dig a hole for anchor engine

4) Preparation tensioner
-

Placement of a tensioner in place has been determined previously

Transporting and Placing Conductor on location tensioner

Preparing Conductor on Drum Stand (drum jack)

5) Installation of roller
-

Installation of roller for conductors at pole to be done

6) Hold the rope


-

Connecting the rope puller and tensioned with polypropylene 12 mm

7) Stringing Wire Rope 12 mm


-

Stringing wire rope 12 mm with polypropylene 12 mm which had


been held earlier.

2.3

Procedure.
1) Before start the work, existing 20kV line must be shut down for a while.
2) Install scaffolding at the existing 20kV pole span, which crossing with
new 30kV line.
3) After the existing 20kV transmission line shut down, ensure that no
electrical power at existing conductor cable using grounding device or
Jin Pole.
4) Install the permanent safety nets under the 20kV transmission line
which crossing with new 30kV line and install warning sign under 20kV
line for safety guidance.
5) After point 3 and 4 finish, 20kV line can be operated.
6) During stringing work, the contractor shall take all necessary steps to
insure proper temporary grounding of the cables and equipment.
7) Ensure new pole at crossings with existing 20kV line shall be finish
before stringing work.
8) Install scaffolding at new pole.
9) First Conductor phase Stringing
-

Held the rope polypropylene 12 mm

Pulling the wire rope 12 mm with polypropylene 12 mm which had


been held earlier

Pull the conductor and polypropylene 12 mm with wire rope 12 mm

STRINGING OF 30KV OVERHEAD LINE

PT. WASA MITRA ENGINEERING


POMALAA CFPP 2 X 30MW

Pulling the wire rope 12 mm with polypropylene 12 mm

Repeat the procedure until it is fixed three conductors

10) Second Conductor phase Stringing


-

Repeat the first phase Stringing

11) Third Conductor phase Stringing


- Repeat the second phase Stringing
12) Place the tension insulator sets
-

Place the tension insulator sets in tower

Conductor pieces one by one and "press" in the tension clamp


conductor to be connected to the insulator sets.

2.4

Repeat the procedure to all the conductors

Others
1) Cleaning area after work finished.
2) At the work area of cabling works shall be provide of security and safety
person for control activity.

3. Location of Work
As per attached drawing

STRINGING OF 30KV OVERHEAD LINE

ATTACHMENT

PT Antam (Persero) Tbk, 2 x 30 MW CFPP In Pomalaa, Indonesia


Inquiry Documents of M&E Erection Work

Page 93 of 109

20kV PLN
overhead line

New 30kV
transmission line

Crossing with
existing 20kV PLN
overhead line

Das könnte Ihnen auch gefallen