Beruflich Dokumente
Kultur Dokumente
29,2012
Ref.No.:PPEP001Rev.00
METHODSTATEMENT
STRINGINGOF30KVOVERHEADLINE
FOR
2X30MWCFPPINPOMALAA
PT.ANTAM(PERSERO)Tbk,INDONESIA
FEBRUARY2012
PT.WASAMITRAENGINEERING
TABLE OF CONTENT
Page
1. Work Procedure and Job Safety Analysis .......................................................... 2
1.1
Preparation ................................................................................................ 2
Others. ....................................................................................................... 2
General Condition...................................................................................... 2
2.2
2.3
Procedure .................................................................................................. 3
2.4
Others ........................................................................................................ 4
Preparation
1) Man Power.
2) Necessary tools.
All necessary electrical tools shall be passed inspection.
3) Work Permit.
Permit shall be obtained from PLN & local government.
4) Installation of scaffolding.
Install of scaffolding for work access and inspection before use.
1.2
1.3
Others.
1) Barricade, sign board and temporary protection.
To be kept in container or job side and to be placed as required, refer to
each activity.
2) First aid box must be available on job site.
2. Method Statement
2.1
General Condition
Height of existing 20kV tower or pole is 13 meters, for new 30kV pole is 10
meters. Therefore, installation of 30kV overhead line will be under 20kV
existing PLNs transmission line.
2.2
Preparation Work.
1) Ensure all the necessary electrical and hand tools complete already.
2) Ensure that storage of materials not obstruct to road traffic and public
facilities.
3) Puller preparation
-
4) Preparation tensioner
-
5) Installation of roller
-
2.3
Procedure.
1) Before start the work, existing 20kV line must be shut down for a while.
2) Install scaffolding at the existing 20kV pole span, which crossing with
new 30kV line.
3) After the existing 20kV transmission line shut down, ensure that no
electrical power at existing conductor cable using grounding device or
Jin Pole.
4) Install the permanent safety nets under the 20kV transmission line
which crossing with new 30kV line and install warning sign under 20kV
line for safety guidance.
5) After point 3 and 4 finish, 20kV line can be operated.
6) During stringing work, the contractor shall take all necessary steps to
insure proper temporary grounding of the cables and equipment.
7) Ensure new pole at crossings with existing 20kV line shall be finish
before stringing work.
8) Install scaffolding at new pole.
9) First Conductor phase Stringing
-
2.4
Others
1) Cleaning area after work finished.
2) At the work area of cabling works shall be provide of security and safety
person for control activity.
3. Location of Work
As per attached drawing
ATTACHMENT
Page 93 of 109
20kV PLN
overhead line
New 30kV
transmission line
Crossing with
existing 20kV PLN
overhead line