Sie sind auf Seite 1von 10

1 of 10

PRODUCTIVITY RATES
SL. NO.
01 GENERAL REQUIREMENT
TEMPORARY FACILITIES

DESCRIPTION

a.
Watchman & Curing
b.
Site Cleaning
c.
Fencing
d.
Fixing of Light Weight Scaffolding
02 SITE WORK
EARTH WORK
Excavation
a.
Soft Soil (Hand Tools)
b.
Hard Soil (Hand Tools)
c.
Soft Soil
d.
Hard Soil
e.
Soft Soil
f.
Hard Soil
Backfilling
a.
Filling in foundation, plinth
b.
Level, Compaction
c.
Spreading 200 mm layer (Subkha, Road Base)
d.
Compaction 200 mm layer (Subkha, Road Base)
PAVING & SURFACING
Interlock Paving
a.
Compaction/ Levelling
b.
Spreading Sand and Brushing
c.
Laying Tiles
d.
Filling, Compaction
Precast Kerb Stone
a.
Excavation & Blinding for kerbstone
b.
Laying Kerbs

Issued
MANPOWER

(Duration x 2H)

----------1H
--1H

2H
2H
1M + 2H
1H
1H
1M + 2H

OUTPUT

--1
50
70

Hand Tools
Hand Tools
Shovel
Shovel
JCB
JCB

m/Day
m/Day
m/Hr
m/Hr
m/Hr
m/Hr

3
1
40
25
20
10

Shovel
Roller Compr.
Shovel
Roller Compr.

m/Hr
m/Day
m/Hr
m/Day

30
100
100
200

Roller Compr.

m/Day
m/Day
m/Day
m/Day

200
200
60
150

R.M/Day
R.M/Day

10
35

1C + 2H + 1P
1C + 1H

1H
1H

UNIT

Day
Day
Rm/Day
m/Day

(Dhs.Contract Value/
50,000) Helper-Day

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

1-Sep-11

Plate Compr.

2 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
c.
Kerb stone on curved lines
d.
Hunching

Issued
MANPOWER
1M + 1H
1M + 1H

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

UNIT
R.M/Day
R.M/Hr

1-Sep-11
OUTPUT
15
20

3 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
03 CONCRETE
CONCRETE FORMWORK
Shuttering (with supports)
a.
Shuttering Of Blinding
b.
Shuttering Of Footing (Plywood)
c.
Shuttering Of Footing (Plates)
d.
Shuttering Of Stub Column
e.
Shuttering Of Strap/ Tie Beam (Plywood)
f.
Shuttering Of Strap/ Tie Beam (Plates)
g.
Shuttering Of Wall
h.
Shuttering Of Column 20 x 20
I.
Shuttering Of Column 20 x 40
j.
Shuttering Of Beam with support
k.
Shuttering Of Roof Slab
l.
Shuttering Of Lintel
m.
Shuttering Of Copying beam 20 x 20 cm
n.
Shuttering Of Parapet
o.
Shuttering Of Arch Lintel
p.
Expansion Joints/ Ground Slab
q.
Shuttering of beam& column for 8m to 12m high
r.
Shuttering of staircase
s.
De-shuttering works
CONCRETE REINFORCEMENT
Reinforcement (Tightening for Cut & Bend Steel)
a.
Reinforcement of Footing
b.
Reinforcement of Stub Column
c.
Reinforcement of Strap Beam
d.
Reinforcement of Tie Beam
e.
Reinforcement of Wall
f.
Reinforcement of Column

Issued
MANPOWER

1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 2H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H
1C + 1H

1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

UNIT

m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
L.M/Day
m/Day
m/Day
20% of shuttering works

Kg/Day
Kg/Day
Kg/Day
Kg/Day
Kg/Day
Kg/Day

1-Sep-11
OUTPUT

35
15
20
5
12
20
14
10
10
12
10
6
6
12
6
70
8
12

400
250
300
350
400
300

4 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
g.
Reinforcement of Beam
h.
Reinforcement of Solid Slab
I.
Reinforcement of Lintel
j.
Reinforcement of Copying beam 20 x 20 cm
k.
Reinforcement of Parapet
l.
Reinforcement of Arch Lintel
m.
Reinforcement of Staircase
Mesh Reinforcement
a.
Mesh Reinforcement
CAST IN PLACE CONCRETE
Casting Concreting (Readymix)
a.
Cast. Blinding 5cm
b.
Cast. Blinding 10cm
c.
Cast. Blinding 5cm, 10cm
d.
Cast. Of Footing
e.
Cast. Of Footing (Pump)
f.
Cast. Of Strap/ Tie Beam
g.
Cast. Of Tie Beam (Pump)
h.
Cast. Of Ground Floor Slab 10cm
I.
Cast. Of Ground Floor Slab 15cm
j.
Cast. Of Ground Floor Slab 20cm
k.
Cast. Of Wall
l.
Cast. Of Column
m.
Cast. Of Beam of Slab
n.
Cast. Of Roof Slab
o.
Cast. Of Lintel
p.
Cast. Of Copying beam 20x20cm (upto 2.5m)
q.
Cast. Of Copying beam 20x20cm (above 2.5m)
r.
Cast. Of Parapet

Issued
MANPOWER
1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H
1SF + 1H

UNIT
Kg/Day
Kg/Day
Kg/Day
Kg/Day
Kg/Day
Kg/Day
Kg/Day

OUTPUT
300
300
150
200
300
150
250

1SF + 2H

m/Day

300

1M + 2H
1M + 2H
2M + 4H
2M + 4H
3M + 8H
1M + 6H
2M + 6H
3M + 5H
3M + 5H
3M + 5H
1M + 1C + 3H
1M + 4H
1M + 4H
2M + 2C + 5H
1M + 2H
1C + 5H
1C + 5H
1M + 1C + 4H

m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
Nos./Hour
RM/Day
RM/Day
m/Day

30
40
250
40
120
20
50
30
45
60
40
4
12
50
4
150
60
10

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

1-Sep-11

Pump
Pump
Pump

Pump

Pump

Pump

5 of 10

PRODUCTIVITY RATES
SL. NO.
s.
t.
u.
04 MASONRY
BLOCK WORK
Solid Block
a.

DESCRIPTION

Issued

Cast. Of Arch Lintel


Cast. Of Neck Column
Cast. Of Staircase

MANPOWER
1M + 3H
1M + 3H
1C + 1H

200mm Solid Block upto 2.5m Height

1M + 2H

Nos./Day

140

1M + 1H
1m + 2H
1M + 1H
1M + 1H
1M + 2H
1M + 2H
1M + 1H

Nos./Day
Nos./Day
Nos./Day
Nos./Day
Nos./Day
Nos./Day
Nos./Day

150
140
150
180
140
100
120

1M + 1H
1M + 1H

m/Day
m/Day

10
8

1P + 1H
1P + 1H

m/Day/Coat
m/Day/Coat

50
40

3E + 3H

m/Day

250

3E + 3H

m/Day

175

3E + 3H
3E + 3H
3E + 3H

m/Day
m/Day
m/Day

350
150
250

Hollow Block
a.
100mm Hollow Block upto 2.5m Height
b.
100mm Hollow Block -2.5m to 6m Height
c.
150mm Hollow Block - upto 2.5m Height
d.
200mm Hollow Block - upto 2.5m Height
e.
200mm Hollow Block - 2.5m to 6m Height
f.
200mm Block Work above 6m Height
g.
200mm Block Work including pointing
Claustra Block
a.
Claustra Block 200 x 200
b.
Claustra Block 150 x 150
05 METALS
STRUCTURAL METAL FRAMING
Steel Structure
a.
Painting of steel structure columns
b.
Painting of steel structure rafters
Erection of steel structure main frame (Eave Height upto
c.
6m span upto 25m)
Erection of steel structure main frame (Eave Height more
d.
than 6m span upto 36m)
e.
Fixing of Single Skin Sheet (Roof)
f.
Fixing of single skin sheet (Walls)
g.
Single skin with fibre glass insulation (Roof)

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

UNIT
m/Day
m/Day
m/Day

1-Sep-11
OUTPUT
5
4
12

6 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
h.
Single skin with fibre glass insulation (Wall)
I.
Sandwich panels (Roof)
j.
Sandwich panels (Wall)
k.
Corner Flashing & Trims, etc
l.
4m x 4m Double Sliding Door
m.
Wall or roof opening + frames (1.0m x 1.0m)
n.
Ridge Ventilator
o.
Gutter/ Down Spout
07 MOISTURE THERMAL CONTROL
WATER PROOFING & DAMP PROOFING
Polythene Sheets
a.
Polythene under footings
b.
Polythene under slab
c.
Polythene under tie beam
Bitumin Paint
a.
Cold Bituminuous Painting
b.
Hot Bituminous Painting
Bituminous Membrane
a.
Bituminous Membrane + Protection Board
SEALERS
Construction Joint
a.
Flexel Board
b.
Sealant
09 FINISHES
PLASTER
Internal Plaster
a.
Ceiling Plaster
b.
Wall plaster upto 3m Height

Issued
MANPOWER
3E + 3H
3E + 3H
3E + 3H
1E + 3H
1E + 3H
1E + 3H
1E + 3H
1E + 3H

UNIT
m/Day
m/Day
m/Day
Rm/Day
Nos.
Nos.
Nos./Day
Rm/Day

OUTPUT
100
250
150
80
1
8
6
70

1C + 1H
1C + 1H
1H

m/Day
m/Day
Rm/Day

200
1000
200

1H
2H

m/Day/Coat
m/Day/Coat

100
60

1C + 1H

m/Day

30

1C + 1H
1H

Rm/Hr
Rm/Hr

18
7

1M + 1H
1M + 1H

m/Day
m/Day

10
20

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

1-Sep-11

7 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
c.
Wall plaster 3m to 6m Height
d.
Wall plaster above 6m Height
e.
Fixing of Plaster Mesh
f.
Fixing of Corner beed
External Plaster
a.
Wall plaster upto 3m Height
b.
Wall plaster 3m to 6m Height
c.
Wall plaster above 6m Height
TILES
Mosaic
a.
Floor Mosaic Tiles
b.
Mosaic Skirting
c.
Mosaic Steps (Riser & Tread)
d.
Mosaic Polishing
Ceramic
a.
Fixing of Ceramic Wall Tiles (Glue Type)
b.
Grouting of Ceramic Wall Tiles
c.
Fixing of Ceramic Wall Tiles (Cement Mortar Type)
d.
Fixing of Ceramic Floor Tiles 20 x 20cm
e.
Fixing of Ceramic Floor Tiles 30 x 30cm
f.
Fixing of Ceramic Floor Tiles 50 x 50cm
g.
Grouting of Ceramic Floor Tiles
h.
Ceramic Skirting
PVC Tiles
a.
PVC Tiles
b.
PVC Skirting
Marble
a.
Marble Wall
b.
Marble Floor
c.
Marble Skirting

Issued
MANPOWER
1M + 2H
1M + 2H
1C + 1H
1M + 1H

UNIT
m/Day
m/Day
Rm/Day
Rm

OUTPUT
17
15
90
30

1M + 1H
1M + 2H
1M + 2H

m/Day
m/Day
m/Day

20
18
15

1M + 1H
1M + 1H
1M + 1H
1Po + 1H

m/Day
Rm/Day
Rm/Day
m/Day

15
40
14
100

1M + 1H
1M + 1H
1M + 1H
1M + 1H
1M + 1H
1M + 1H
1M + 1H
1M + 1H

m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
m/Day
Rm/Day

10
30
8
12
15
20
40
30

1M + 1H
1M + 1H

m/Day
Lm/Day

35
40

1M + 1H
1M + 1H
1M + 1H

m/Day
m/Day
Rm/Day

6
15
30

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

1-Sep-11

8 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
d.
Marble Steps (Riser & Treads)
Floor Screed (50mm)
a.
Floor Screed (50mm)
b.
Cement Skirting
Wooden Skirting
a.
Timber

Issued
MANPOWER
1M + 1H

EQUIPMENT

UNIT
Rm/Day

1-Sep-11
OUTPUT
10

1M + 1H
1M + 1H

m/Day
Rm/Day

50
25

1C + 1H

Rm/Day

100

1M

Rm/Day

10

False Ceiling
a.
False Ceiling - Suspended Type

1C + 1H

m/Day

30

Dry Wall Partition


a.
Dry wall Partition

1C + 1H

m/Day

20

1M + 1H
1M + 1H

m/Day/Coat
m/Day/Coat

100
100

1P
1P
1P
1P

m/Day/Coat
m/Day/Coat
m/Day/Coat
m/Day/Coat

200
80
100
60

1P + 1H

m/Day/Coat

50

Threshold
a.

Threshold

PAINTING & WALL COVERINGS


Tyrolene (Cullamix)
a.
Tyrolene over plastered surface
b.
Tyrolene over block wall
Normal Paint (Emulsion/Oil)
a.
Primer
b.
Stucco (Putty)
c.
Emulsion Paint
d.
Oil Paint
Epoxy Painting
a.
Epoxy Painting
10 MECHANICAL
PIPE & FITTINGS

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

9 of 10

PRODUCTIVITY RATES
SL. NO.
DESCRIPTION
Copper & PVC Pipes
a.
" to 1" Copper Pipe (Hot Water)
b.
" to 1" PVC Pipe
c.
2" to 3" PVC Pipe
d.
4" to 6" PVC Pipe
PLUMBING FIXTURES
Plumbing Fixtures
a.
Shower Tray
b.
Kitchen Sink
c.
Urinals + Partition
d.
Wash Basin
e.
W/C Asian
f.
W/C Western
g.
Bidet
h.
Booster Pump
I.
Manhole 60cm to 90cm
PLUMBING APPLIANCES
Plumbing Appliances
a.
Water Heater
11 ELECTRICAL
RACE WAYS
Race Ways
a.
Conduits
b.
Trunking
CONDUCTORS & GROUNDING
Conductors & Grounding
a.
Laying Cables

Issued
MANPOWER

UNIT

OUTPUT

1Pl + 1H
1Pl + 1H
1Pl + 1H
1Pl + 1H

Rm/Day
Rm/Day
Rm/Day
Rm/Day

12
20
75
60

1Pl + 1H
1Pl + 1H
1Pl + 1H
1Pl + 1H
1Pl + 1H
1Pl + 1H
1Pl + 1H
1Pl
1M + 1H

Nos/Day
Nos/Day
Nos/Day
Nos/Day
Nos/Day
Nos/Day
Nos/Day
Nos/Day
Nos/Day

2
2
3
2
2
2
2
1
2

1Pl + 1H

Nos/Day

1El + 1H
1El + 1H

Rm/Day
Rm/Day

50
50

1El + 2H

Rm/Day

150

WIRING
- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

1-Sep-11

10 of 10

PRODUCTIVITY RATES
SL. NO.
Wiring
a.
Wiring
BOARDS
Boards
a.
b.

D.B's
M.D.B's

DESCRIPTION

Issued
MANPOWER

UNIT

OUTPUT

1El + 1H

Rm/Day

300

1El + 1H
1El + 1H

Nos/Day
Nos/Day

2
1

- C = Carpenter, M = Mason, P = Painter, SF = Steel Fitter, E = Erector, H = Helper, Po = Polisher, El = Electrician, Pl = Plumber
- One Day is considered as 8 working hours.

EQUIPMENT

1-Sep-11

Das könnte Ihnen auch gefallen