Beruflich Dokumente
Kultur Dokumente
Revision: 02
Project Title:
Page 1 of 8
Table of Contents
1
ASSUMPTIONS ....................................................................................... 4
2.1
2.2
2.3
3.2.1
3.2.2
3.2.3
3.3
3.4
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 2 of 8
Scope of Document
This document has been produced to outline the philosophy for the
emergency shutdown system which shall be installed to protect personnel,
asset and the environment from hazards associated with the operation of the
pipeline and offshore facility part of the Kingsnorth Carbon Capture & Storage
Project. This will also involve any onshore pipeline emergency shutdown
requirements.
1.2
The offshore project consists of a circa 270 km dry CO2 pipeline from
Kingsnorth Power Station on the Isle of Grain to a new Offshore Normally
Unmanned Installation (NUI) to utilise the depleted Hewett gas reservoir.
Note: The offshore project boundary starts at the exit of the compressor and
includes the onshore metering and pig launcher.
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 3 of 8
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 4 of 8
2 ASSUMPTIONS
The offshore Emergency Shutdown (ESD) system architecture will be
consistent with its Integrity Level classification. There is an opportunity to
have an offshore integrated control and safety system. Integrated in terms of
peripheral devices and supplied by one vendor with segregated safety and
control hardware.
The ESD system manufacturer should be the same as for the onshore carbon
capture part of the Project. This will offer continuity between onshore and
offshore plant.
2.1 Hydraulic Actuated Valves
It is recommended offshore actuated spring return valves are supplied by
hydraulic motive power. This will keep the actuator weight and size to a
minimum. Valve closure times shall account for potential of water hammer in
dense phase operation.
2.2 Emergency Electrical Equipment
Typical offshore emergency electrical equipment to remain operational during
an emergency are as listed below:
Emergency/Escape/Helideck Lighting;
Emergency Communications;
Platform Control System including Pipeline Integrity System;
ESD System;
Fire and Gas System;
Public Address and General Alarm System;
Navaids and markings;
Temporary Safe Refuge (TSR)/Equipment Room Ventilation (HVAC)
Systems fed from the emergency switchboard.
Emergency electrical equipment will normally be supplied from the emergency
generator. Selected items will have an Uninterruptible Power Supply.
2.3
Remote Operability
The NUI will require a remote trip from Kingsnorth Power Station and a local
offshore trip used while the facility is manned.
Kingsnorth CCS Demonstration Project
The information contained in this document (the Information) is provided in good faith.
E.ON UK plc, its subcontractors, subsidiaries, affiliates, employees, advisers, and the Department of Energy and Climate Change (DECC) make no
representation or warranty as to the accuracy, reliability or completeness of the Information and neither E.ON UK plc nor any of its subcontractors,
subsidiaries, affiliates, employees, advisers or DECC shall have any liability whatsoever for any direct or indirect loss howsoever arising from the use of the
Information by any party.
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 5 of 8
3 DESIGN REQUIREMENTS
3.1
The objectives of the ESD system are to shutdown the pipeline and injection
facilities to:
Protect the facility personnel;
Protect the environment;
Protect the plant and equipment on the facility.
The ESD system objectives shall be met by:
Provision of self acting mechanical devices or systems where appropriate;
Automatically sensing an abnormal facility operational or equipment
condition. Note Safeguarding interfaces for - heater failure; power failure;
inadvertent valve opening; blocked outlet and intertrips between onshore and
offshore needs to be confirmed by a separate study;
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 6 of 8
3.2
The Shutdown Hierarchy shall be based on the following three generic levels
of Shutdown; presented in descending order of priority:
3.2.1
TPS is defined as the total isolation of the platform from external sources of
process gas and deactivation of all process and non-essential utility systems.
It is only initiated manually from dedicated push-buttons locally or from
onshore Kingsnorth Power Station.
3.2.2
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 7 of 8
The adoption of a failsafe principle de-energise to trip shall apply to all final
actuating devices and the ESD system. Shutdowns shall de-energise solenoid
valves, trip motors, heaters etc, resulting in closure of spring return ESD
valves or de-energising of motor, thyristor circuits.
Dependent upon the choice of manufacturer, it may be possible to purchase
an integrated control, ESD, and Fire & Gas system compatible with the
onshore carbon capture systems.
The control, ESD, and Fire & Gas functionality will be segregated for reasons
of independence and differing integrity requirements. An integrated system
i.e. from one system vendor would give common peripheral components in
the communications, reporting, logging, operator interface areas and one
maintenance contract.
The ESD shall be provided with a reliable Uninterruptible Power Supply which
will be available for the period required to manage the emergency.
KCP-GNS-SHE-DPR-0001
Revision: 02
Project Title:
Page 8 of 8
4 MANDATORY REFERENCES
UK Statutory Instruments, Codes and Standards
SI 2005/3117
SI 1995/743
SI 1996/913
BS EN 61508
BS EN 61511
API RP-14C
5 PROJECT REFERENCES
1. Genesis Report No. KCP-GNS-PCD-STU-0001 Rev 03 Kingsnorth
Carbon Capture & Storage Project Basis Of Design For Studies
Phase 1A
2. Genesis Drawing No. KCP-GNS-PCD-PFD-0003 Rev 01 - Kingsnorth
Carbon Capture & Storage Project PFD Offshore & Transport System
CO2 Process System Demo Phase (Base Case)
3. Genesis Drawing No. KCP-GNS-PCD-PFD-0004 Rev A1 - Kingsnorth
Carbon Capture & Storage Project PFD Offshore & Transport System
CO2 Process System Full Flow Scenario