Beruflich Dokumente
Kultur Dokumente
INTRODUCTION
Introduction
Project portfolio management (PPM) is a set of business practices and a process that
allows organizations to control projects and achieve organizational objectives as a
strategic portfolio and confirm the arrangement of programs and projects. This improved
the efficiency and performance of the project. PPM is a combination of project
management and project programme management. In projects, the use of PPM was very
helpful to make projects more progressive. Vinopal (2012) concluded that PPM made
projects more successful and gave a proper direction for achieving the desired goals.
Study analyzed the gap of projects success with or without PPM. This made projects
success easy to achieve by adopting specified direction. In PPM project efficiency and
performance were directly related with stakeholders who directly participate in the
project activities. How performance of projects in PPM can be improved by stakeholder
engagement? In PPM the success achieved by following the PPM traditions.
Project management is the application of knowledge, skills, and requirements to achieve
project success. According to the Project Management Institute (PMBOK, 2013), project
management processes were guided by five steps: initiation, planning, executing,
monitoring, controlling, and closing. Most of the literature focused on people to follow
the critical practices for project success. This also focused on quality of human
interaction, motivation and decision making practices for project success. There was a
performance gap of adoption of critical factors in different organizations (Davies,
2002).In project management, project managers interaction and decision making were
essential for project success. For good decision making, stakeholders were involved in
the projects which lead projects towards the success. Now the question was that why
stakeholders were important in decision making in projects and what were their role?
Decision making and negotiation was important for both single and portfolio projects.
More than two projects were managed in portfolio. This era required multiple projects to
obtain the benefit and success of project portfolio management.
The above literature described about the PPM working traditions, goal clarity and was
specific to work according to the requirements. It made projects more flourishing in
PPM. Young and Conboy (2013) concluded that current body of PPM knowledge
suffered from a number of conceptual problems and highlighted issues. These problems
were lack of cumulative traditions, clarity, parsimony and applicability. Further they
analyzed the performance gap between different organizations. Problems occurred in
PPM due to gap of work which was not fulfilled by proper processes. Goal clarity and
working style of project team matched with the project needs. This leads towards good
project performance and high success level.
Project portfolio management success was also related with the strategies which had been
used for the projects successful completion. Strategies had direct impact on the project
portfolio management success. Amarl et al (2009) described that strategies improved the
progress of the project or organization which reduced the problems, minimize risk and
cost, reduce threats and improve performance. Study measured the gap between different
organizations performance level by using different strategies (Amarl, Antonio, Aroujo,
&Madalena, 2009). By applying good strategies in projects according to the project
requirements, it provided better results for PPM success. Selection of strategy was the
part of the planning. Project planning made many things clear like which strategy should
be used for the selected project.
Planning of project was the first and the most important phase in the project portfolio
management. Plan-do-check-action planning cycle explained in management to improve
the organization performance. Planning cycle defined the communication at each level of
the organization to made projects successful. All planning requirements which were
essential for single project also required for multiple projects in project portfolio. Study
also discussed the terms, project breakdown structure, organization breakdown structure
and information breakdown structure. Planning requirements are not only for single
projects but also for project portfolios (Platje, Seidel and Wadman, 1994). Planning phase
closely related with the decision making process. Planning and decision making played
the vital role in the project portfolio management.
Decision making was the central part of the project portfolio management. Good decision
making always helped to achieve the project success. In some critical situations, a
committee required accurate decisions by project stakeholders. Committee also made
decisions about the project portfolio selection and other necessary issues. Sometimes
decision makers did not agree on one decision, they had differences on their own basis,
and then decision support systems helped decision makers to reach on some consensus. In
the same situation project analysis and support system were also helpful for decision
makers to make decisions correctly. Study by Ghasemzadeh and Archer (2000 )
mentioned some techniques which were helpful in decision making. Decision making
was helpful when all stakeholders agreed on one decision. Clashes in decision making
created many errors in the projects. Stakeholders engagement improved the efficiency of
the work in the project portfolio management. Processes in project portfolio management
were also essential in goal achievement. Goal and role clarity of stakeholders were
significant for gaining the good performance in PPM. Stakeholders involvement had a
great effect on the PPM. Internal and external stakeholders directly and indirectly
affected the PPM success positively.
In every project and portfolio processes, stakeholders had significant importance.
Stakeholders followed the specified processes to obtain the desired goal. Existence of
organization was associated with a higher rate of adoption of processes and tools that
come close to risk management. Study of Riaz and Micheal (2001) measured the gap
between highly adopted and low adopted processes and tools of risk management. Some
differences identified across various industrial sectors and different organizational
cultures. They also mentioned the results of the high and low level adoption of processes
(Raz & Micheal, 2001). Different organization cultures also had significant effect on the
project portfolio management success. Human skills were always helpful for the project
portfolio management success.
Human resource management had important part in the project success. Completion of
any project was impossible without human resource management. Human skills of
project manager had greatest influence on project management practices. Technical and
communication skills of stakeholders had much influence on PPM. The difference
4
measured between career path of project manager and operational manager (Sabaa,
2001). Study supported the above statement that human resource had great impact on the
project portfolio management success. Project managers were directly engaged with the
project success. Skills of project managers were influenced positively, which were useful
for project portfolio management success. Stakeholders engagement had much influence
on the project portfolio management success.
Stakeholders had great value in the project portfolio management success. There were
different kinds of stakeholders. According to this study managers were involved in the
important projects and procedures. Primary stakeholders of the firm treated with high
appreciation while secondary stakeholders were some time ignored due to some loss or
wrong decision. To increase the corporate social relations, all stakeholders like
employees, customers and shareholders should provide equal rights, so that all of these
can work better with high motivation (Clarkson, 1995). Stakeholder engagement was
vital but all types of stakeholders should give equal rights to get involved in the project
portfolio management success. It was necessary to give right of equality to all
stakeholders to achieve the good performance of project portfolio management.
The literature highlighted various factors affecting the project portfolio management
performance. One important element was involvement of internal and external
stakeholders. Involvement of stakeholders enhanced the performance of PPM. Beringer,
Jonas & Kock (2013) found positive results about the impact of some internal
stakeholders on the PPM success. The underlying study illustrates the impact of internal
and external stakeholders on project portfolio management success. In literature there
was a gap related to the impact of external stakeholders on the PPM success. In present
study results were based on both internal and external stakeholders in PPM and their
impact on PPM success. Therefore present study filled the gap that exists in the literature.
Kock, 2013), but the impact of internal and external stakeholders engagement were not
still measured collectively. One major reason is that this study was not still verified in
Pakistan in this context.
Research Questions
In context of Pakistans IT Industry, the following research questions have been
developed for the study:
1. What is the effect of internal stakeholders engagement on project
portfolio management success?
2. What is the effect of external stakeholders engagement on project
portfolio management success?
3. What is the effect of customers engagement on project portfolio
management success?
4. What is the effect of suppliers engagement on project portfolio
management?
6
Chapter 2 deals with explaining past studies related to the variables of study. The
literature is surveying facilitated in understanding the associations among variables.
Chapter 3 discussed the research methodology adopted for analyzing the data gathered
for the study. This section comprises sampling techniques, statistical techniques and
details on the instrument adopted to gather data from respondents.
Chapter 4 explained the analysis and result portion of the study. This section deals with
descriptive statistics to analyze sample properties and inferential statistics to analyze the
association of variables under study.
Chapter 5 is the last section of the study and deals with findings of the study and
inferences made in the light of past studies. This section also highlights the major
limitations in the study and recommendations for future research in this area.
CHAPTER 2
LITERATURE REVIEW
projects were handled and preceded with the help of human resource. Human resource is
essential factor in project management. In fact for project success, skills, abilities and the
efforts of human resource were as important as the other important factors. HRM was one
of the imperative elements in project management success. HRM was the most
significant element in the organization success. Study analyzed the gap between project
and organization success due to HRM (Belout, & Gauvreau, 2004). Project Management
was an effective method for accomplishing the goals of a project. HRM and projects are
main part of the project management. There was an explanation about project and project
management. Projects are closely related to the project management. In fact project
management was incomplete without successful projects. There was a link between
project and project management.
Study of Munns and Bjeirmi (1996) explored the relationship between project and project
management activities. Project management included many things which made any
project successful or unsuccessful. Many internal and external involvements were
prejudiced the project management in a positive way. Project management had to face
many economic and financial aspects; it had complex areas which cannot be easily
handled. All these factors collectively moved towards project management success. Right
project can succeed without the success of project management, but for successful project
management there is always a need of successful projects (Munns & Bjeirmi, 1996). For
successful projects, there was a need of their own specifications. Project management
played important role in the success of projects, but project requirements were the main
point to be focused. Some other factors also affected the project success and project
needs; there was a need of all those things which were compulsory or related to the
project success. These elements are time, cost and scope.
Project success was depending on many factors which made project easier to achieve.
Four important factors were discussed in the following study of White & Fortune (2002),
which made projects successful. Project success and failure were two aspects of projects.
For Project's complete perfection, all the important factors should be added. Because of
these projects results as a success, but due to some imperfections projects always end up
as a failure. Four most important factors (realistic schedule, adequate resources, clear
11
objective and support from senior management) affected most of the project success.
Study measured the gap between performance of different projects which lead towards
the project success or failure (White & Fortune, 2002). This study adopted the four
important elements to assess the project performance. By following these four techniques
project was leading towards the good performance. By ignoring these elements projects
faced errors or imperfections in work. These factors also reduced the uncertainty
management in project management.
Chances of risk always present in project management. In fact in each business and large
or small projects, in every case risk was always there. Uncertainty was the situation when
something was going wrong in the project and some kind of error occurred at any time.
Uncertainty management was important element of the project management. Uncertainty
management was an approach of facilitated assimilation with project management earlier
in the Project Life Cycle (PLC) after that threat sloping Project Risk Management (PRM)
process affected the PPM. There were a gap measured between the project risk
management and uncertainty management. Further study was recommended on
uncertainty management (Ward, & Chapman, 2003). Study explained that uncertainty
management handled and controlled at the start of Project Management especially in
project life cycle. Project was moved towards the project risk management process and
then uncertainty management. There was a gap mentioned between project risk
management and project uncertainty management which reduced the level of
performance. Project risk can be avoided and reduced with the help of project
stakeholders. Whenever project associated persons or stakeholders did not achieve
projects objectives, projects had to face many challenges. Involvement of many valued
and essential stakeholders made projects successful. There was a need of stakeholder's
engagement to reduce the risk in the projects.
Project management was related to a lot of essential knowledge and management areas,
which made clear path for the achievement of desired goals. Main processes of
management and engagement of stakeholders made projects easier to achieve its success.
Adoption of different techniques was making clear understanding of the project
requirements and achievements. Project Management knowledge and skills made more
12
14
Project portfolio management was also helpful in reducing errors and increasing the
productivity of the projects.
Project Portfolio Management reduced many issues in the projects by monitoring all the
projects collectively and another good thing was that it reduced the time of project
completion as well as reduced the cost of project. Results of the study of Catherine
&Robert (2010) explained that increase in adoption of PPM level had a positive impact
on the return on the projects in the portfolio and had a negative impact on the number of
project related problems. There was a gap between problem solving and success level in
different companies by adopting PPM (Calderini, Reyck, Cockayne, Lockett, Moura &
Sloper, 2005). According to this literature adoption of PPM increased the performance of
the projects. PPM reduced the problems and gave better results for the improvements of
projects. Project portfolio management was successful in the project management in
present research. PPM reduced many issues in the projects by monitoring all the projects
collectively. Another good outcome was that it reduced the time of project completion as
well as reduced the cost of project. Further researcher explained that project portfolio
management made it possible to achieve the strategic goals in a successful manner.
Project portfolio management was a field in which projects were monitored and
completed for improved performance in comparison with previous project performance.
Project performance was enhanced by introducing the project portfolio management in
the organization. Organizations gave value to project portfolio management in achieving
their strategic goals. It was better to start with improvement and development of portfolio
processes. There was need of good collaboration and interaction between portfolio
managers to discuss the project processes. Integration system was established to select
and screen the project proposals (Filippov, Mooi, &Weg, 2012). The project managers
had important role in the project portfolio management success. Interaction and
collaboration of project managers with other team members made projects successful.
Project managers are the main stakeholders in the project portfolio management. For
organizations development and improvement, every organization tried to implement new
strategies in their own company to enhance the productivity. Stakeholder's engagement
required to increase the PPM success.
15
This was important for organizations to make new and innovative strategies because they
had to compete with other organizations in the market. Projects were also handled in
other sectors like service and manufacturing companies in the same way as in IT sector.
Project portfolio management was also used in the manufacturing and service industry.
Project portfolio management made projects successful by using different rules and
techniques. This depended on the nature and requirement of the projects. Study explained
the relationship between project portfolio management and competitive advantage in
service and manufacturing industries. Dynamic capability used in PPM and compare the
results of service industry and manufacturing companies. PPM enhanced the outcomes
with dynamic capability (Killen & Hunt, 2010). Dynamic capability was also used to
increase the performance of the projects in the service and manufacturing industry. Some
other abilities and capabilities also discussed in the studies to augment the impact of the
project portfolio management. Proper techniques, skills, procedures and abilities made
project portfolio management successful in any area of implementation.
Organizations made collaboration with project portfolio management, and improved
results for getting good performance in a successful way. Organizations demand good
results to achieve the organizations desired goals. Killen et al (2008) indicated that the
project portfolio management and organizational capabilities improved the organizations
success and enabled to get advantage from the other organizations in this competition.
Study explored that managers enhanced competitive advantage by using their abilities,
procedures and appropriate strategies. They also increased the investment to make PPM
stronger. Learning investment and organizational capabilities can be improved by skilled
managers and planned work (Killen, Hunt, &Kleinschmidt, 2008). According to the study
different kinds of strategies, processes and organizational capabilities had been used for
the successful project portfolio management. Involvement of project managers was
necessary for better project performance. Managers were included in the internal
stakeholders. Internal stakeholders were directly involved in the PPM success. Some
techniques mentioned for getting the good results of project portfolio management in
organizations. Techniques included learning investment and organizational capabilities.
By implementing these techniques and strategies with the help of the project
16
which were inadequate project level activities, lacking resources, competencies and
methods, lacking commitment, unclear roles and responsibilities, inadequate portfolio
level activities, inadequate information management and inadequate management of
project-oriented organization. They recommended further research on development of
managerial practices (Elonen & Artto, 2002). They also analyzed that some elements
raised the productivity of the project portfolio management success; on the other hand
some other factors declined the efficiency and productivity of the project portfolio
management success. Balance in all these factors was necessary and involvement of the
internal and external stakeholders was also compulsory who administered the work
according to the need. Some models and matrixes also helped to diminish these errors in
project portfolio management success.
In project portfolio management, strategies were getting much importance because by
implementing these strategies, project success could be achieved, which leads towards
project portfolio management success. By implementing the strategies of business and
adopting different kind of models projects were easier to achieve their goals and clarify
many project requirements. Study of Dickinson et al (2001) explained it cannot be said
that dependency matrix and optimization model condensed all problems and issues of
project portfolio processes. But it provided some additional tools and techniques to
confirm the achievement of PPM success by following these portfolio management
strategies. Three goals of project portfolio management were to maximize the value of
the portfolio, provide balance and the strategy of the business. Dependency matrix and
optimization model provided means to get maximum benefit from multiple projects in
information technology portfolio (Dickinson, Thornton, & Graves, 2001). By adopting
these techniques it was easier to achieve the project portfolio management success.
Further study discussed that project portfolio management was discussed in the IT
projects and previous research also supported that this IT sector was suitable for PPM
related study.
Project portfolio management projects were mostly handled in the IT sector and adoption
of project portfolio management made projects more successful. Study of Reyck et al
(2005) explored that most of the work of project portfolio management had been done in
18
the IT projects. Three stages of classification of the project portfolio management were
defined. There were a correspondence between the project portfolio processes and
improvement of the projects and portfolios. Study found a strong correlation between
increase in the adoption of project portfolio processes and decrease in the project related
problems. There were also a strong relationship between Project portfolio management
adoption and project performance (Reyck, Cockayne, Lockett, Calderini, Moura,
&Sloper, 2005). Their study analyzed that increase in adoption of PPM enhanced the
good performance of the projects. Adoption of PPM gave positive results and increased
the success level of projects. Project portfolio management success linked with many
essential elements which were discussed in the above studies. In PPM projects success
can be improved by involvement of internal and external stakeholders in projects.
Engagement of stakeholders gave positive results in PPM success. Stakeholders critically
linked with the PPM. How stakeholder engagement gave positive results? Which factors
were involved with stakeholders engagement to achieve the PPM success? Selection of
appropriate strategies also increased the accomplishment of projects in PPM. In PPM,
selection and use of strategies according to the project were significant.
PPM was aligned with the projects as relating strategies of the organizations with the
projects. PPM improved the success rate of the projects as well as organization. Study
measured the gap of projects progress in different years. Study of Heisting (2012)
mentioned that project portfolio management strategies increased the success level of the
projects and organizations. Project portfolio management strategies were changed after
some time period for improvement in performance (Heiskanen, 2012). Different kinds of
projects needed different types of strategies according to the requirements of the projects.
New strategies used for project success in PPM according to the need.
Project management and project portfolio management both used strategies according to
their requirements. Advancement in Project Portfolio Management was more appropriate
and successful in comparison with Project Management by applying three strategies.
Strategies were used according to their needs and to gain the competitive advantage in
market. The difference in enhancement of project management and project portfolio
management was measured (Killen, Jugdev, Drouin, & Petit, 2012). According to this
literature three strategies were used to improve the project performance. These three roles
or strategies were increased the efficiency of project portfolio management which
enhanced the performance. To made project portfolio management more advanced these
strategies were helpful according to this study. New and advanced strategies, processes or
techniques enhanced the project performance in project portfolio management. Strategies
were directly involved in the project portfolio management. This made projects
successful and lead towards the high level of attainment of project success.
Researchers further referred different sets of strategies and prepositions. This was
depended upon the nature of the projects which were working under the project portfolio
management. Some projects were specifically needed appropriate set of strategies which
were suggested by the previous studies, while some other projects did not think that these
prepositions were suitable for them. This was completely depending upon the nature of
the projects which were handled in the project portfolio management. Project portfolio
structuring and project success were analyzed and outlined by four prepositions. Strategic
orientation, Project Portfolio Management and project success had direct relationship
with the strategies. Study measured the gap between four prepositions to analyze the
20
project success (Meskendahl, 2010). This study was analyzed that four strategies were
introduced for the project success and project portfolio management success. By adding
these strategies in the projects, project structure can be improved and provide better
performance than the previous performance. In project portfolio management success
many other factors were also included rather than strategies like involvement of
stakeholders. Stakeholders were the management resource persons who made these
strategies useful for the project success. For successful project portfolio management
success, there was required direct relationship between the strategies and engagement of
stakeholders with their defined roles.
Strategies were directly linked with the stakeholders of PPM. Stakeholders engagement
directly affected the PPM performance. Strategies were implemented in the projects by
internal stakeholders. Stakeholders engagement in PPM was one reason of the projects
success. How stakeholders can implement better strategies in projects to achieve the PPM
success? Strategies were the segment of framework in PPM. Framework of project was
the guideline at which projects were managed according to planned schedule. Good
strategies and good decision making was very helpful and gave advantage to PPM. By
using appropriate strategies according to project type, it improved project portfolio
management performance and reduced its completion time and resources.
projects in project portfolio management. This also solved many problems and issues.
Project portfolio management closely correlated with the stakeholder engagement. Many
problems can be solved by stakeholders engagement. Internal and external both
stakeholders were important in project portfolio management success. How stakeholders
engagement solved problems in the project portfolio management? Selection of projects
was also associated with the stakeholders engagement.
project portfolio management according to the current situation. Sometimes PPM had to
face risk in decision making related to project selection. Uncertainty level was always
high in tangible projects of project portfolio management.
In project portfolio management selection of projects were related with risk and
uncertainty management. In every phase projects had to face the risk. There was always
uncertainty level high in the projects which were handled in natural environment. So
there was margin of risk in the selection of projects. Both moments and uncertainty were
important in portfolio selection. Results showed that it was important to integrate higher
order moments in portfolio selection. Different methods were used to analyze the level of
uncertainty and errors (Harvey, Liechty, Liechty, & Mller, 2004). They mentioned the
high level projects which were monitored in the project portfolio. They were also trying
to explain that as discussed above in small projects risk and uncertainty level was always
high. In the same way in project portfolios risk level also very high where a large number
of projects were handled at the same time. High level and high budget projects were
included in the project portfolio management. High level models, analysis and techniques
were preferred in the project portfolio management to reduce the risk level. For good
decision making some standards were introduced to follow in project handling. By
following the mentioned techniques project decision making made project portfolio
management more successful.
New and tested approaches for decision making provided a new way towards the
successful PPM. In project portfolio management decision making was the essential
process. Study of Linton et al (2002) mentioned the approach of decision making in
selection of portfolio projects. Decision making approached in two ways accept or reject
the project proposal. Study highlighted a method Value Creation Model (VCM) for
selection of projects in portfolio. Date Envelopment Analysis (DEA) made project
acceptable in portfolio (Linton, Walsh, &Morabito, 2002). They analyzed that approaches
used for good decision making had visible impact on the project portfolio management
success. In project portfolio decision making was a very critical process on which overall
project success depended. This process should be handled very critically specially in case
of project portfolio management success. Decision making in the projects and selection
25
Decision making was also important in the framework of project portfolio management
success.
Selection of framework for specified project was as important as the selection of projects
in PPM. Each project success was depended upon its framework and other essential
factors. Different steps were involved in the selection of the framework. Accurate and
working framework helped to achieve the desired goals in the project portfolio
management. For project portfolio selection framework was suggested as an integrated
decision support system, and need to test it in real decision making situations. Study
measured the gap between different processes of decision making for project portfolio
selection (Archer & Ghasemzadeh, 1999). Selection of projects was also an important
step in project portfolio management as well selection of framework. Proper framework
should follow for projects and decision making in project portfolio management to
improve the PPM success. Further study mentioned the nine knowledge areas which were
key elements of the framework in the IT projects.
Human resource management introduced nine key knowledge areas for IT projects
framework. By using these areas project success can be enhanced. Projects were
successful when follow the 9 key knowledge areas of Human Resource Management
(HRM) properly. These key areas were already mentioned above with extension of 10 th
key area. Study measured the gap of performance between project managers using
limited key knowledge areas and all knowledge areas of Human Resource Management.
Future research recommended finding the other key knowledge areas rather than Human
Resource Management for project management (Naqvi, 2009). One newly introduced
knowledge area which was related to this study is stakeholder management.
Stakeholders engagement was very important in the project portfolio management
success (PMBOK, 2013). Stakeholder management was essential key area of the project
management. Stakeholders engagement made framework stronger towards PPM goals.
According to this literature framework of each project was vital, it made project
dimensions clear towards goal and guide the project managers in a proper way to achieve
desired goals. Improvement in framework increased the project success. Programme
management and stakeholder management were related with each other. Stakeholders
27
were main components of the framework and they influenced the PPM success more
bitterly. Stakeholders participation enhanced the success level of projects in PPM.
Improvement in framework reduced the risk level. Risk management was also effective in
PPM. Risk management in advance was saved projects from big losses.
the previous projects helped improving the effectiveness of projects in the project
portfolio management.
There were unlimited ways to handle the risk in the project portfolio management. Some
techniques were standardizes to observe those risks which were normally common in
many projects. Techniques were developed by monitoring the different kinds of errors in
the project portfolio management. To reduce these risks some standards were adopted.
Study explained that portfolio risk managed in two ways. First was that provided some
sources to the single projects to get experiences from the previous projects within the
portfolio. Second was common risks and issues were identified and avoid these risks for
the other projects so that project risks can be managed. By controlling the portfolio risk in
project portfolio management, project portfolio success can be achieved more perfectly
(Olsson, 2006). He focused on two ways by which project risk management can be
overcome. Get experience from the previous mistakes in the projects. Avoid these errors
in the coming projects, projects portfolio success can be enhanced by using these
techniques. Learn something from past mistakes and go for new achievements. Control
over project helped a lot to handle the projects successfully in the project portfolio
management and avoid projects from risks.
Main aspects in project management were controlling and monitoring. Controlling was
the central phase. In this phase most of the errors were automatically reduced by good
monitoring. Stakeholders were directly related with the project management processes.
Internal stakeholders like project managers were the source of risk reduction in the
project portfolio management and also play vital role in controlling and monitoring
processes of project. If Controlling and monitoring were perfectly managed then risk and
uncertainty were automatically decreased. Risk and control of project were improved by
implementing good project management strategies. There was a gap of strategies in
project management. If project processes and strategies were not well defined and not
implemented in a proper way in projects then uncertainty level was always high in PPM
(Atkinson, Crawford, & ward, 2006). They mentioned the strategies which helped to
control the risk and uncertainty in the project portfolio management success.
Stakeholders involvement much helped to reduce the risk in the projects. Involvement of
29
internal stakeholders like project managers enhanced the effectiveness of the project in
the project portfolio management success. If project risk management was properly
managed in project portfolio management (PPM), it increased the efficiency of projects
and also enhanced the performance of projects in PPM. Work was already available in the
literature related to the risk management as explained above. Stakeholder management is
newly introduced area of project management and recent studies were focusing on the
stakeholder management. Stakeholders association in PPM reduced the risk and
increased the performance of projects. Internal stakeholders were involved in the project
practices; they better handle the risk in PPM. How stakeholder engagement reduced the
risk in PPM? Good practices were reduced the risk in PPM. Practices in PPM increased
the accomplishment of the projects. Adoption of good practices was leading PPM toward
achievements and high level of success.
stakeholders made practices more useful for the project portfolio management? Practices
were essential for single projects as well as for multiple projects. Performance of single
project also affected the whole PPM success. Single project was the base of PPM.
effect of project portfolio quality as well as project portfolio success (Teller, Unger,
Kock, & Gemnden, 2012). Literature supported the complex projects. According to the
study more complex projects gave more achievements in the project portfolio
management. Internal and external both stakeholders engagements were significant in
projects. Especially in single projects, engagement of stakeholders made projects easier
to accomplish. Importance of stakeholders engagement was equal in single and PPM
projects. Stakeholders contribution in single and PPM projects was vital for project
achievement. Why stakeholders engagement was important in single and multiple
projects? In PPM project managers also had much contribution in PPM success. Skills of
project managers and project portfolio managers control the most of PPM processes.
right project and allocate both budget and resources for successful completion of the
portfolio projects. There was a gap measured of methods and processes for the project
portfolio completion (Miguel, 2008). For successful project completion allocation of
resources and budget was compulsory for a project. New things could be added in the
projects after implementation of these two important parts. Project innovation and new
product development lead projects towards the project success in PPM. There was
positive relationship between the organizational teamwork and innovation which go
towards goal achievement. Innovation was always related with the inter-organizational
activities. Improvements and new ideas made possible to innovate the projects with new
ideas and techniques. Authors analyzed positive relationship between inter-organizational
collaboration and innovative performance.
As above explained about the innovation, furthermore, the impact of innovative
performance differ depending on the nature of the partners involvement. Researcher
strongly suggested that the relevance of adoption of a portfolio move projects towards the
inter-organizational collaboration within the framework of innovation strategies (Faems,
Looy, & Debackere, 2005). By innovation of the projects, performance of project
portfolio management enhanced. Study of Faems et al (2005) also described the
importance of the stakeholders. By increasing the level of stakeholder engagement,
project innovative performance increased. There were different techniques which were
used for increasing the project performance in the project portfolio management.
Strategies and techniques were always helpful to increase the performance of the project
portfolio management. The product portfolio management focused on all techniques and
processes of PPM for good performance and good quality of work. Study of Cooper et al
(1999) measured the gap between four performance techniques. Further research
recommended towards product innovation (Cooper, Edgett & Kleinschmidst, 1999).
There were different elements which affected the project portfolio performance. Different
techniques used for the performance measurement. Research and development was also
important area to discuss in this context. This also pushed the innovation strategies to be
used and provide best results in a positive way.
33
Research and development was vast area to discuss. In project portfolio management R &
D need special attention for innovation of the projects. Overall performance of the project
portfolio management depended upon these essential and critical phases of the projects.
Portfolio management processes successfully developed to help executives to achieve
their desired objectives by R&D. For better results they had to make balance between
short term pressure and future, long term needs of organization and see R&D direction
was meeting with the objectives. A gap of performance between good performing and
poor performing organizations was measured (Cooper, Edgett & Kleinschmidst, 2001).
Project innovation directly measured the performance gap of project portfolio
management. Good and bad performance depended upon the R&D objectives and
innovation strategies. From this literature, present study analyzed that product innovation
was positively correlated with the progress of the project portfolio management. With the
innovation in products, processes and strategies there will be a positive change in the
projects completion time in PPM. Many other factors also improved the project portfolio
management. Engagement of stakeholders enhanced the effect of innovation in the
Project portfolio management. How stakeholders helped to improve the products and
projects?
organization.
performed skillfully made projects outcome possible to achieve. Further some leadership
styles were discussed which were adopted according to the project requirements.
Leadership controlled by project and project portfolio managers who were very close to
the project and had direct involvement. Leadership always worked at upper level.
Decision making occurred at the top management while other managers had to follow the
instructions. Study of Kissi et al (2013) mentioned that the project managers leadership
effect on the project success and performance. Transformational leadership of portfolio
managers increased the project performance at corporate level. Study analyzed the gap of
project performance due to transformational portfolio managers at corporate and middle
level managers (Kissi, Dainty &Tuuli, 2013). Study analyzed the gap in the performance
at two levels. Leadership work perfectly at top level, but study analyzed the leadership at
middle and top level. Top and middle managers engagement with each other improved
the project performance in PPM.
There were many leadership styles which were used according to the requirement.
Leadership worked on that place more perfectly where it was really needed. Study
mentioned that strong relationship of project managers with his/her team lead towards the
project success. Project managers leadership style would be according to the project
type. Project managers needed to used his skills according to the project requirements and
increased the project performance. By increasing the communication within the team, it
provided positive results towards the project success (Yang, Huang, & Wu, 2011).
According to this literature leadership style associated with the project requirements.
Strong relationship within the team members was also affecting the project results
positively. Study of Yang et al (2011) mentioned that project managers engagement with
other stakeholders gave desired outcomes.
Leadership styles of project portfolio managers affected the performance of PPM. For
successful project completion, project leaders had to change their behavior with their
team. Personnel working style should match at each stage of the project with the project
activities. Skills of project managers and project portfolio managers were considered as
internal stakeholders abilities in PPM. Stakeholders abilities directly affected the PPM
performance. How stakeholders skills effect the PPM success? In successful project
35
interface enhanced the work quality and also gave better results for project success. Study
suggested that top management team and middle managers should be aware of their role
with good understanding because their understanding enhanced the interface process. Top
management team more perfectly performed their duties and made good interface
processes (Raes, Heijltjes, Glunk, & Roe, 2011).They mentioned that involvement of
both top management and middle management were essential. In comparison with middle
management, top management involvement provided better results in PPM. Most
important factor which made successful of any project was project managers skills,
abilities, experience, leadership and decision making skills. Involvement of stakeholder
and customers were also helpful for the projects in PPM. How stakeholder engagement
enhanced the effect of role of internal stakeholders? Engagement of stakeholders directly
involved in the project portfolio management success.
stakeholders
was
useful
for
these
activities.
Stakeholder
and quality standards for its projects (Naqvi, Aziz, & Rehman, 2011). Stakeholder
communication resolved primary level problems in the project portfolio management
success. Primary determinants time, scope and cost were controlled in its best way by
stakeholder communication. Further study was recommended that integration between
stakeholders had positive impact on the project portfolio performance.
Engagement of internal and external stakeholders was essential for the project portfolio
management goal achievement. Relationship with all type of stakeholders enhanced work
activity in a positive manner. Involvement of managers at different designation also
benefitted the projects. Integration between different stakeholders group was very
important for project success and good performance. Good communication and
continuity between mentioned groups like senior management, project core team and
project recipients stakeholders groups made projects successful. The agreement for
perception of project success between these three groups was managed to gain the best
project performance (Davis, 2014). The engagement of internal and external stakeholders
made projects more successful. Good communication and continuous relationship
between all stakeholders made project achievements easier to achieve in project portfolio
management.
studies also supported the senior management involvement and their effective
communication in project portfolio management.
Further study focused on the relationship of the senior management. Skills of senior
managers enhanced the project activities in effective manner. Study of Unger et al (2012)
promoted senior management involvement to perform as strategic managers by adopting
an effective project portfolio culture in which termination of projects gave positive results
in a successful way. Managers focused on effective communication, so that other
stakeholders of project portfolio also influenced positively on project portfolio
management success. Future research recommended to investigate the different types of
involvement differently and its impact on the project termination quality and project
portfolio management success (Unger, Kock, Gemnden, & Jonas 2012). Researchers
mentioned the relationship between stakeholders by good communications. This
enhanced the project portfolio management performance. Internal stakeholders had direct
impact on the project portfolio management success.
Following hypotheses were developed to test the relationship of the internal stakeholders
engagement with the PPM:
H1: The greater the Internal Stakeholders Engagement in PPM, the better
prospects for success of PPM.
Internal stakeholders directly affected the project portfolio management success. Internal
stakeholders included different kind of managers. Study researched about the internal
stakeholders and their impact on the project portfolio success. Study described that
Project managers, project portfolio managers, senior managers and line managers had
positive or significant effect on the portfolio project success. Study analyzed the gap of
the significance level of different internal stakeholders on the project success. Further
research recommended on external key stakeholders who directly involved in the project
portfolio management success (Beringer, Jonas & Kock, 2013). Study mentioned the
different managers who had direct impact on the project portfolio management success.
Some internal stakeholders had significant impact on the project portfolio management
success. Beringer et al (2013) used role clarity as a moderator for their study and role
clarity moderated the relationship some of the managers on PPM success. How internal
39
40
41
Framework was the development of the project planning in which strategies, processes
and other techniques were defined which were used for the project successful completion.
Suppliers were also the part of that framework in which strategies selected for projects.
Study analyzed the framework that identified the short and long term strategic processes
related to supplier involvement (Echtelt, Wynstra, Weele, & Duysters, 2004).They
mentioned that by planning and execution of strategic processes and techniques can be
used to achieve the short term objectives and long term objectives can also be gained by
adding the supplier involvement. Authors further analyze that how companies achieve
desired goals by adding the supplier involvement? Supplier engagement showed results
in a positive way for project success.
Study mentioned that supplier involvement was beneficial for the project goal
achievement. Study of Echtelt et al (2006) analyzed that strategies used to achieve the
short and long term objectives by adding processes and involvement of the suppliers. By
adding the supplier involvement these things work with more perfection. Above studies
mentioned that now supplier engagement added in projects by decision making
approaches. New product development was a process in which companies go forward for
competition in the market. Suppliers played an important role in this era. For new product
development engagement of external stakeholders enhanced the compatibility of the
product. Companies need to set a decision making strategic processes to create a good
supplier involvement. Supplier engagement was essential for short term as well as long
term policies for new project development. There was a need to identify right partners
and perfect supplier involvement from suppliers. Companies also need to get guidelines
and directions from decision making processes for supplier engagement in projects
(Echtelt, Wynstra, Weele, &Duysters, 2006). Researchers mentioned that decision making
strategies were developed to enhance the supplier engagement in the projects. Echtelt et
al (2006) also mentioned there was need of right decision making and new strategies for
the supplier engagement. Supplier engagement improved the new product development
strategies.
Many things were related with the suppliers. Some errors made it favorable for the
projects and on the other hand some factors made it unfavorable for the projects. Previous
42
study analyzed the supplier involvement benefitted the project portfolio success in a
positive way. The possible negative and positive effects of supplier engagement on the
new product development in an organization were focused. Negative effects of supplier
engagement in new product development were communication barriers, skills and
knowledge barriers and commitment barriers. Positive effects of supplier involvement
were effectiveness and efficiency of short term product increased when suppliers were
involved. Supplier involvement also increased the product value and quality (Witlox,
2010). He mentioned some positive and negative sides of the supplier involvement.
Supplier engagement provided a lot of signs of achievements in positive direction.
External stakeholders engagement made goals clear and enhanced the project portfolio
management achievements. How external stakeholders had positive impact with
moderating effect of role clarity on the project portfolio management success? There was
a need to identify the involvement of internal stakeholders as well as external
stakeholders both had significant effect on project portfolio management success. Internal
stakeholders and external stakeholders helped to improve project outcomes and success.
In project portfolio management stakeholders had much influence on the projects in a
positive way to achieve projects desired goal. Both internal and external stakeholders
were significant to achieve the overall project accomplishment in project portfolio
management. Role clarity was affecting the variables as a moderator; it increased the
efficiency of the internal and external stakeholders and had encouraging impact on the
project portfolio management success. How internal and external stakeholders had
positive impact on the project portfolio management with moderating effect of role
clarity?
moderator. So, role clarity moderated the independent variables depend upon the nature
of variables. Following hypotheses were developed to test the effect of role clarity as a
moderator:
H4: Role clarity moderates the relationship between internal stakeholders
engagement and project portfolio management success.
H5: Role clarity moderates the relationship between customer's engagement and
project portfolio management success.
H6: Role clarity moderates the relationship between supplier's engagement and
project portfolio management success.
Internal stakeholders like top managers, and project managers had significant effect on
the project portfolio management success with moderation effect of role clarity. External
stakeholders like customers and suppliers engagement also show significant effect on the
project portfolio management success with moderation effect of role clarity. Beringer et
al (2013) described that role clarity had moderating effect on the project portfolio
management success. Role clarity enhanced the significance level of some internal
stakeholders and increased the success of PPM. Some internal stakeholders engagement
had direct relationship with the role clarity. It made clear to the managers to perform their
role in PPM. Role clarity also made clear directions to external stakeholders for their role
in PPM. It increased the impact of external stakeholders on PPM. How role clarity made
directions clear to internal and external stakeholders?
Above literature explained about different factors which directly or indirectly affected the
performance of the PPM. Factors which had positive effect on the PPM performance and
success were involvement of internal stakeholder and managers. In this literature
involvement of external stakeholders was not yet explored, and also effect of both
internal and external stakeholders on the PPM performance accomplishment was not yet
studied. This study intends to find the impact of internal and external stakeholders on the
Project Portfolio Management success.
44
Independent Variables
Moderator
Dependent Variable
Kissi et al (2013), Voss & Kock (2013) and Beringer et al (2013) focused on the impact
of the internal stakeholders on project portfolio success and Voss and Kock (2013)
explored that relationship value of external stakeholders e.g. customers with moderating
effect of portfolio characteristics and external turbulence increased the performance in
PPM. The current study determined the impact of both internal and external stakeholders
on PPM success.
Beringer et al 2013 related this research with the stakeholder theory in project portfolio
management perspective. Freeman (1984) defined a stakeholder as any group or
individual who can affect or is affected by the achievement of the organization's
objectives. Based on this definition Beringer et al 2013 defined project portfolio
stakeholders as any group or individual in an association with a project portfolio, such
that the cluster or individual can affect or is affected by the attainment of the portfolio's
objectives with moderating role of role clarity. So this theory also supported the present
study because study perceived that stakeholders engagement have significant effect on
the project portfolio management success with moderating effect of role clarity.
45
The present study understand from the literature that involvement of internal stakeholders
had positive effect on the PPM success but involvement of external stakeholders in PPM
was not yet explored. So this intends to find the impact of internal as well as external
stakeholders on the project portfolio management success. Above literature was the
source to identify the variables used in this study. Figure 2.1 depict intensity of senior
managers engagement, intensity of line managers engagement, intensity of project
portfolio managers engagement and intensity of project managers engagement as
independent variables of internal stakeholders, while intensity of customers engagement
and intensity of suppliers engagement are also independent variables but part of external
stakeholders. Project portfolio management success is a dependent variable. Present study
measured the project portfolio management success by strategic fit and average project
success. Role clarity is the moderating variable. The demographic variables to be used in
the current research are Software House Title, Total Work Experience , Total work
Experience of managing portfolios , Team Strength , Annual Revenue , Duration of
Existence of Software House , Specialty of Software House , Span of Software
house , CMMI Ranking , Software House Certifications , Software House Clients ,
Number of Portfolios , Number of Projects in one Portfolio , Number of Projects Lead
Successfully , Number of Project Portfolio Managers , Number of Project Managers ,
Project Worth , Information is Given About and Designation of the Respondents.
46
CHAPTER 3
RESEARCH DESIGN AND METHODOLOGY
47
This chapter covered the research design and methodology used in identifying and
evaluating the relationship among independent and dependent variables under this study.
Independent, dependent and moderating variables were mentioned in the model (Figure
2.1). The history of constructs had been explained in the model and further quantitative
analysis had been used to identify the outcome. It was aimed to identify the impact of
stakeholders engagement on project portfolio management success, in IT sector Lahore,
Pakistan.
1. To fill the questionnaire (provided under Appendix: III) used for this study with
titles Software House Title, Total Work Experience , Total work Experience
of managing portfolios , Team Strength , Annual Revenue , Duration of
48
Bougie, 2013). Since March 2014 onward the researcher concentrated on compiling the
thesis.
3.1.5 Population
The study set its population to be the groups who were managing projects in portfolios,
undertaking considerable IT projects of different types and scopes within the selected
software houses within the city of Lahore, Pakistan. The study identified and selected its
population based on some important factors described next. As the data was collected in
between November 2013 to March 2014, the study selected the software houses who are
managing their projects in a portfolio. Information was gathered about those software
houses that were managing project in portfolios, during the June 2013 to March 2014, the
recent project portfolios can be identified in selected software houses. This was done to
make sure that the data is valid and reliable about IT project portfolios. It was necessary
to find the accurate and realistic data about the project portfolios which is being handled
in the present time. IT professionals remembered their recent project portfolios so that
they can provide us better information related to recent work rather than past project
portfolios.
Focal persons identified were CEOs of software houses and project managers and other
managers who are involved in project management. We had taken the population
primarily from Arfa Kareem Software Technology Park (STP) and then other large
software houses in Lahore by following the pasha list. Primarily in pilot survey about 30
software houses were identified and number of software houses where projects in
portfolios are managed, in Arfa Kareem Software Technology Park are 28, list is given in
table 3 in Appendix 1. According to pilot survey number of C.E.Os, project managers
and other managers in Arfa Kareem 30 software houses is approximately 90.
Respondents will be C.E.Os and their nominated project managers and other managers
who are managing projects in portfolio in software houses. List of respondents is given in
table 3 in Appendix 1. In complete research survey 87 software houses according to
Pasha registered list were identified and about 65 software houses were managing their
projects in portfolio. Their details are provided in the Appendix 1. Lists of the respondent
detail in table 3, pasha registered software houses list in table 1 and Arfa Kareem
50
C.E.Os and project managers of the software houses in IT industry Lahore Pakistan
already has been validated by the Beringer et al (2013) in the Germany.
customers and from the customers were accordingly 0.85 and 0.74. Validity was
assessed by test retest. The five point scale ranging from 1(strongly disagree) to
5(strongly agree) had been used.
4. Section 4 of the questionnaire consisted of questions related to the Independent
Variables for Internal Stakeholders; About Managers and Senior Management
Involvement two variables was added in this section from different studies. First
variable which was about managers adopted from the study of (Kissi et al., 2013).
This instrument contained 22 items and as it was used this instrument in this
study. Second variable was senior management involvement (SMI). This
instrument adopted from the study of Unger et al (2012). This instrument
contained 7 items and all these items had been used in this study. Validity of this
scale has assessed by confirmatory factor analysis and significance of variables
was 0.96. Reliability assessed by Cronbachs alphas, Cronbachs coefficients was
between 0.89.The five point scale ranging from 1(strongly disagree) to 5(strongly
agree) had been used.
5. Formal Permission on email has been obtained on each variable by respective
Researchers.
Strongly
Disagree
Disagree
Neutral
Agree
Strongly Agree
54
1
2
3
4
5
CHAPTER 4
RESULTS AND DISCUSSIONS
This chapter discussed the descriptive and inferential statistics drawn from the
relationship of the independent, dependent and moderating variables under study. The
descriptive portion of statistics roofed the characteristics of the variables, whereas the
inferential statistics helped to generate the results by analyzing the relationship among
variables under this study.
55
ISE
RVC
RVS
RC
PPS
Valid
100
100
100
100
100
Missing
showed that out of 100 respondents 25(25%) were C.E.Os, 51(51%) were project
managers, 8(8%) were IT managers and 16(16%) were other managers who filled the
questionnaire. This implies that most of the respondents are project managers in the
software houses.
Table 4.2 Frequency distribution for demographic variable: Designation of Respondent
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
C.E.O/ Director
25
25.0
25.0
25.0
Project Manager
51
51.0
51.0
76.0
IT Manager
8.0
8.0
84.0
Others
16
16.0
16.0
100.0
Total
100
100.0
100.0
Designation - Frequency
ceo
it manager
others
project manager
25%
51%
8%
16%
Figure 4.1 Pie Chart for Frequency distribution of demographic variable: Designation of Respondent
4.2.2 Gender
Nominal scale was used to collect the responses about gender of the respondents. The
Table 4.3 and figure 4.2 showed that out of 100 respondents 92(92%) were Males and
8(8%) females. This implies that most of the employees in the software houses are males.
57
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
male
92
92.0
92.0
92.0
female
8.0
8.0
100.0
Total
100
100.0
100.0
Gender -Frequency
female
male
8%
92%
Figure 4.2 Pie Chart for Frequency distribution of demographic variable: Gender
that most of the respondents have experience of above 10 years of managing the projects.
Since most of the respondents were experienced therefore the study perceived that the
data was credible.
Table 4.4 - Frequency distribution for demographic variable: Experience of Respondent
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Up to 2
9.0
9.0
9.0
2-6
24
24.0
24.0
33.0
6 - 10
20
20.0
20.0
53.0
Above 10
47
47.0
47.0
100.0
Total
100
100.0
100.0
Experience - Frequesncy
2 TO 6
6 TO 10
ABOVE 10
9%
UP TO 2
24%
46%
20%
Figure 4.3 Pie Chart for Frequency distribution of demographic variable: Experience of Respondent
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Up to 2
34
34.0
34.0
34.0
2-6
22
22.0
22.0
56.0
6 - 10
16
16.0
16.0
72.0
Above 10
28
28.0
28.0
100.0
Total
100
100.0
100.0
6 TO 10
ABOVE 10
UP TO 2
22%
33%
16%
28%
Figure 4.4 Pie Chart for Frequency distribution of demographic variable: Experience of PPM
employees, 3(3%) respondents were from those software houses who had 100 to 200
employees and 9(9%) respondents were from those software houses who had above 200
employees. This study implies that most of the software houses have employees less than
50.
Table 4.6 - Frequency distribution for demographic variable: Employees
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Less than 50
69
69.0
69.0
69.0
50 - 100
19
19.0
19.0
88.0
100 - 200
3.0
3.0
91.0
Above 200
9.0
9.0
100.0
Total
100
100.0
100.0
Employees - Frequency
100 to 200
50 to 100
ABOVE 200
less than 50
3%
19%
9%
69%
Figure 4.5 Pie Chart for Frequency distribution of demographic variable: Employees
million revenue annually, 11(11%) respondents were from those software houses who
earn up to 1-2$ million revenue annually and 26(26%) %) respondents were from those
software houses who earn up to above 2$ million revenue annually. This study showed
that most of the software houses were highly budgeted and reputed.
Table 4.7 - Frequency distribution for demographic variable: Revenue
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Up to 1$ million
63
63.0
63.0
63.0
Between 1 - 2$ million
11
11.0
11.0
74.0
Above 2$ million
26
26.0
26.0
100.0
Total
100
100.0
100.0
Revenue - Frequency
Above 2$ million
between 1 to 2$ million
up to 1$ million
26%
63%
11%
Figure 4.6 Pie Chart for Frequency distribution of demographic variable: Revenue
exist, 10(10%) respondents were from those software houses who had 2 to 4 years to
exist, 7(7%) respondents were from those software houses who had 4 to 6 years to exist
and 77(77%) respondents were from those software houses who had 2 to 4 years to exist.
This implies that most of the software houses have existence of above 6 years, it means
software houses were more competent and providing high quality work in project
portfolios.
Table 4.8 - Frequency distribution for demographic variable: Existence of S.H
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Less than 2
6.0
6.0
6.0
2-4
10
10.0
10.0
16.0
4-6
7.0
7.0
23.0
Above 6
77
77.0
77.0
100.0
Total
100
100.0
100.0
Existence - Frequency
2 to 4
4 to 6
Above 6
Up to 2
6% 10%
7%
77%
Figure 4.7 Pie Chart for Frequency distribution of demographic variable: Existence of S.H
that 2(2%) respondents were from those software houses who deal in databases, 4(4%)
respondents were from who deal in mobile apps, 8(8%)respondents were from those who
deal in websites, 86(86%) respondents were from those who deal in multiple
technologies. This showed that most of the software houses were dealing in all
technologies. This supported the diversity of the operations of software houses.
Table 4.9 - Frequency distribution for demographic variable: Specialty
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Databases
.8
2.0
2.0
Mobile apps
1.5
4.0
6.0
Websites
3.1
8.0
14.0
86
86.0
86.0
100.0
100
38.6
100.0
Multiple Technologies
Total
Specialty - Frequency
DATABASES
MOBILE APPS
MULTIPLE TECHNOLOGIES
WEBSITES
8% 2% 4%
86%
Figure 4.8 Pie Chart for Frequency distribution of demographic variable: Specialty
figure 4.9 showed that 18(18%) respondents were from those software houses who deal
within Pakistan, 8(8%) deal within subcontinent, 14(14%) deal within Asia and 60(60%)
deal across the world wide. These percentages mentioned that most of the software
houses were operating internationally.
Table 4.10 - Frequency distribution for demographic variable: Span of Software House
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Within Pakistan
18
18.0
18.0
18.0
Within Subcontinent
8.0
8.0
26.0
Within Asia
14
14.0
14.0
40.0
60
60.0
60.0
100.0
Total
100
100.0
100.0
Span - Frequency
across the world wide
within asia
within pakistan
within subcontinent
14%
18%
60%
8%
Figure 4.9 Pie Chart for Frequency distribution of demographic variable: Span of Software House
respondents were from those software houses who had level 1, 22(22%) have level 2,
47(47%) had level 3 and 3(3%) had level 4. These percentages mentioned that most of
the software houses have level 3 of CMMI ranking; it means these software houses have
high certification due to high quality of work and good reputation.
Table 4.11 - Frequency distribution for demographic variable: CMMI Ranking
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Level 1
28
28.0
28.0
28.0
Level 2
22
22.0
22.0
50.0
Level 3
47
47.0
47.0
97.0
Level 4
3.0
3.0
100.0
Total
100
100.0
100.0
Level 2
Level 3
Level 4
3%
28%
46%
22%
Figure 4.10 Pie Chart for Frequency distribution of demographic variable: CMMI Ranking
showed that 46(46%) respondents were from those software houses who was ISO
certified, 19(19%) had IEEE certified, 24(24%) had both ISO and IEEE certified and
11(11%) had other certifications. This implies that most of the software houses in Lahore
were ISO certified.
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
ISO certified
46
46.0
46.0
46.0
IEEE certified
19
19.0
19.0
65.0
Both a and b
24
24.0
24.0
89.0
Others
11
11.0
11.0
100.0
Total
100
100.0
100.0
Certification - Frequency
Both A & B
IEEE Certified
11%
45%
ISO Certified
Others
24%
19%
Figure 4.11 Pie Chart for Frequency distribution of demographic variable: Certifications
67
The clients of the software houses were divided into four main groups like international,
national, local and both a and b. The Table 4.13 and figure 4.12 showed that 69(69%)
respondents were from those software houses who had International clients, 19(19%) had
national clients, 2(2%) had local clients and 10(10%) had both international and national
clients. These percentages mentioned that due to high quality not only national clients but
also international clients relied on the services provided by software houses in Lahore.
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
International
69
69.0
69.0
69.0
National
19
19.0
19.0
88.0
Local
2.0
2.0
90.0
Both a and b
10
10.0
10.0
100.0
Total
100
100.0
100.0
Clients - Frequency
Both A & B
International
19%
Local
National
10%
2%
69%
Figure 4.12 Pie Chart for Frequency distribution of demographic variable: Clients
The number of portfolios in the software houses was divided into four main brackets like
less than 2, 2 to 4, 4 to 6 and above 6. The Table 4.14 and figure 4.13 showed that
40(40%) respondents were from those software houses who had dealing with less than 2
portfolios, 18(18%) had dealing with 2 to 4 portfolios, 14(14%) had dealing with 4 to 6
portfolios and 28(28%) had dealing with above 6 portfolios. These percentages showed
that mostly software houses were managing less than two portfolios at a time, but in one
portfolio large number of projects were monitored.
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Less than 2
40
40.0
40.0
40.0
2-4
18
18.0
18.0
58.0
4-6
14
14.0
14.0
71.0
Above 6
28
28.0
28.0
100.0
Total
100
100.0
100.0
4 to 6
Above 6
Less than 2
18%
39%
14%
28%
Figure 4.13 Pie Chart for Frequency distribution of demographic variable: No of Portfolios
The number of projects in the software houses was divided into four main categories like
Less than 2, 2 to 4, 4 to 6 and above 6. The Table 4.15 and figure 4.14 showed that
10(10%) respondents were from those software houses who had dealing with less than 2
portfolios, 14(14%) had dealing with 2 to 4 portfolios, 14(14%) had dealing with 4 to 6
portfolios and 62(62%) had dealing with above 6 portfolios. The study perceived that
mostly software houses were dealing diversified and large number of projects.
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
2-4
10
10.0
10.0
10.0
4-6
14
14.0
14.0
24.0
6-8
14
14.0
14.0
38.0
Above 8
62
62.0
62.0
100.0
Total
100
100.0
100.0
4 to 6
6 to 8
Above 8
10%
14%
62%
14%
Figure 4.14 Pie Chart for Frequency distribution of demographic variable: No of Projects
The number of projects successful in the software houses was divided into four main
groups like 2 to 4, 4 to 6, 6 to 8 and above 8. The Table 4.16 and figure 4.15 showed that
9(9%) respondents were from those software houses who had dealing with 2 to 4 projects
successful, 11(11%) had dealing with 4 to 6 projects successful, 20(20%) had dealing
with 6 to 8 projects successful and
successful. These results showed that most of the projects were successfully managed by
software houses in Lahore.
Table 4.16 - Frequency distribution for demographic variable: Projects Successful
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
2-4
9.0
9.0
9.0
4-6
11
11.0
11.0
20.0
6-8
20
20.0
20.0
41.0
Above 8
60
60.0
60.0
100.0
Total
100
100.0
100.0
4 to 6
6 to 8
Above 8
9%
11%
60%
20%
Figure 4.15 Pie Chart for Frequency distribution of demographic variable: Projects Successful
The number of project portfolio managers in the software houses was divided into four
main brackets like Less than 2, 3 to 4 and 5 to 6 and above 6. The Table 4.17 and figure
4.16 showed that 77(77%) respondents were from those software houses who had Less
than 2 project portfolio managers, 7(7%) had 3 to 5 project portfolio managers, 15(15%)
had 5 to 6 project portfolio managers and 1(1%) had less than 6 project portfolio
managers. From this the study perceived that most of the software houses in Lahore
employed less than 2 project portfolio managers.
Table 4.17 - Frequency distribution for demographic variable: Project Portfolio Managers
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Less than 2
77
77.0
77.0
77.0
3-4
7.0
7.0
84.0
56
15
15.0
15.0
99.0
Above 6
1.0
1.0
100.0
Total
100
100.0
100.0
5 to 6
Above 6
Less than 2
1% 7%
15%
77%
Figure 4.16 Pie Chart for Frequency distribution of demographic variable: Project Portfolio Managers
The number of project managers in the software houses was divided into four main
brackets like Less than 2, 2 to 4, 4 to 6 and above 6. The Table 4.18 and figure 4.17
showed that 4(4%) respondents were from those software houses who had less than 2
project managers, 18(18%) had 2 to 4 project managers, 18(18%) had 4 to 6 project
managers and 60(60%) had above 6 project managers. The study explained that most of
the software houses in Lahore employed more than six project managers with good skills
and experience.
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Less than 2
4.0
4.0
4.0
2-4
18
18.0
18.0
22.0
4-6
18
18.0
18.0
40.0
Above 6
60
60.0
60.0
100.0
Total
100
100.0
100.0
5 to 6
Above 6
Less than 2
4% 18%
18%
60%
Figure 4.17 Pie Chart for Frequency distribution of demographic variable: Project Managers
The project worth of software houses was divided into three main categories like less
than 1 million, between 1 & 2 million and more than 2 million. The Table 4.19 and figure
4.18 showed that 29(29%) respondents were from those software houses had project
worth of less than 1 million, 37(37%) had project worth of between 1 & 2 million and
34(34%) had project worth of more than 2 million. The study implies that software
houses in Lahore were highly reputed and high budgeted, and also managing high
budgeted projects.
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
29
29.0
29.0
29.0
38
38.0
38.0
67.0
33
33.0
33.0
100.0
Total
100
100.0
100.0
between 1 to 2 million
29%
up to 1 million
33%
37%
Figure 4.18 Pie Chart for Frequency distribution of demographic variable: Project Worth
74
Frequency
Percent
Valid Percent
Cumulative
Percent
Valid
Top Manager
30
30.0
30.0
30.0
Line Manager
6.0
6.0
36.0
8.0
8.0
44.0
Project Manager
34
34.0
34.0
78.0
Both a and d
22
22.0
22.0
100.0
Total
100
100.0
100.0
line managers
project managers
top managers
30% 22%
6%
8%
33%
Figure 4.19 Pie Chart for Frequency distribution of demographic variable: Information About
75
Minimum
Maximum
Mean
Std. Deviation
Variance
ISE
100
3.00
5.00
4.0597
.41875
.175
RVC
100
3.00
5.00
4.0764
.41221
.170
RVS
100
3.00
5.00
4.0560
.47254
.223
RC
100
3.00
5.00
4.1400
.38815
.151
PPMS
100
1.00
5.00
3.8700
.93701
.878
100
Table 4.21 shows that Variance of Internal Stakeholders Engagement (ISE) which is an
independent variable (0.175) is lesser than its standard deviation (0.41875), which
mention that most of the respondents remained higher than the mean value for this
variable. The mean value is 4.0597. Results indicate that software houses have
involvement of internal stakeholders. Mean value more than 3.5 and standard deviation
less than 1 show positive response (Sekaran & Bougie, 2013). This study explains that
internal stakeholders have much involvement in the project portfolio management
success. Internal stakeholders like top managers, line managers, project portfolio
managers and project managers have much involvement in the project portfolio
management success.
Variance of Relationship Value of Customers (RVC) which is independent variable is
(0.170) which is lesser than its Standard Deviation (0.41221), which shows that most of
the respondents remained higher than the mean value for this variable. The mean value is
4.0764. Result shows that involvement of external stakeholders like relationship value of
customers is high. In software houses mostly customized projects are managed thats why
76
customer involvement is high in this study. This study mentions that external stakeholders
like relationship value of customers also show high involvement in the project portfolio
management success.
Variance of Relationship Value of Suppliers (RVS) which is independent variable is
(0.223) which is lower than its standard deviation (0.47254), which shows that most of
the respondents remain much higher than the mean value for this variable. The mean
value for this variable is 4.0560. Results mention that involvement of external
stakeholders like relationship value of suppliers is also high. This study shows that
involvement of external stakeholders as relationship value of suppliers is also high in
project portfolio management success.
Variance of moderator Role Clarity (RC) is (0.151) smaller than its standard deviation
which is (0.38815), which describe that most of the values go higher than the mean value
for this variable. The mean value is 4.1400 for this variable. Mean value is much high of
this variable. Mean value above than 3.5 shows that variable is performing higher than its
average value which is good or in favor of the study (Sekaran & Bougie, 2013).
Descriptive results for this study mention that moderator have much involvement in
increasing the project portfolio success. Role clarity enhances the level of success for
project portfolio management in this study. Role clarity has positive results in the favor of
this study.
Variance of the project portfolio management (PPMS) success which is a dependent
variable is (0.878) is lower than its standard deviation (0.93701), which explain that most
of the values remain higher than the average value. The mean value is 3.870 for this
dependent variable. All independent variables have mean values greater than 3.5. This
shows that all the independent variables and moderating variable has positive impact on
the dependent variable project portfolio management success.
77
Correlations were calculated to test the planned relationship and involvement among the
dependent and independent variables. Pearsons coefficient of correlation have been used
by using SPSS 20.0
4.4.1 Pearsons Correlation
Pearsons correlation was used because the study planned a linear relationship between
variables with one another. All independent and dependent variables show significance at
0.05. Table 4.22 describes the Pearsons coefficient of correlation among different
variables.
Table 4.22 Pearsons Coefficient of Correlations
Pearson Correlation
ISE
RVC
RVS
RC
PPM
S
ISE
RVC
RVS
RC
PPMS
.605**
.522**
.479**
.244*
.000
.000
.000
.014
Sig. (2-tailed)
N
100
100
100
100
100
Pearson Correlation
.605**
.806**
.674**
.427**
Sig. (2-tailed)
.000
.000
.000
.000
100
100
100
100
100
Pearson Correlation
.522**
.806**
.609**
.380**
Sig. (2-tailed)
.000
.000
.000
.000
100
100
100
100
100
Pearson Correlation
.479**
.674**
.609**
.310**
Sig. (2-tailed)
.000
.000
.000
100
100
100
100
100
Pearson Correlation
.244*
.427**
.380**
.310**
Sig. (2-tailed)
.014
.000
.000
.002
100
100
100
100
78
.002
100
79
6. The Pearsons coefficient of correlation (r) for RC and RVS is (0.609). Normally
variables with a Pearsons coefficient of correlation between .40 to 0.70 and
significance at p-value are less than 0.05 are assumed to be correlated week to
strong (Sekaran & Bougie, 2013). So relationship strength between RC and RVS
is also strongly correlated because (r = 0.609, p < 0.05). RC and RVS show
strongly positive correlation between these two variables.
7. The Pearsons coefficient of correlation (r) for PPMS and ISE is (0.244).
Normally variables with a Pearsons coefficient of correlation less than .40 and
significance at p-value are less than 0.05 are assumed to be weakly correlated
(Sekaran & Bougie, 2013). So relationship strength between PPS and ISE is
strongly correlated because (r = 0.244, p < 0.05). PPMS and ISE show weak
positive correlation between these two variables.
8. The Pearsons coefficient of correlation (r) for PPMS and RVC is (0.427).
Normally variables with a Pearsons coefficient of correlation more than 0.40 and
significance at p-value are less than 0.05 are assumed to be correlated (Sekaran &
Bougie, 2013). So relationship strength between PPMS and RVC is correlated
because (r = 0.427, p < 0.05). PPMS and RVC show positive correlation between
these two variables.
9. The Pearsons coefficient of correlation (r) for PPMS and RVS is (0.380).
Normally variables with a Pearsons coefficient of correlation near to 0.40 or
exact 0.40 and significance at p-value is less than 0.05 are assumed to be
correlated (Sekaran & Bougie, 2013). So relationship strength between PPMS and
RVS is correlated because (r = 0.380, p < 0.05). PPMS and RVS show positive
correlation between these two variables.
10. The Pearsons coefficient of correlation (r) for PPMS and RC is (0.310). Normally
variables with a Pearsons coefficient of correlation near to 0.40 or exact 0.40 and
significance at p-value is less than 0.05 are assumed to be correlated (Sekaran &
Bougie, 2013). So relationship strength between PPMS and RC is slightly
correlated because (r = 0.310, p < 0.05). PPMS and RC show positive correlation
between these two variables.
80
Tolerance
VIF
(Constant)
ISE
RVC
RVS
RC
.622
.270
.342
.526
1.606
3.707
2.925
1.900
Table 4.23 mentions the scores of the variance inflation factor of independent variables.
Table also mentions the values of tolerance for each independent variable. The value of
tolerance > 0.20 will be favorable and score of variance inflation factor < 10 will be
acceptable (Freund et al., 2010). The scores of variance inflation factor of all independent
variables are less than 10 and values of tolerance for each independent variable is more
than 0.20, so there is no Multicollinearity among the independent variable
81
Internal Stakeholders
Engagement (ISE)
Relationship Value of
Customers (RVC)
Relationship Value of
Suppliers (RVS)
Role Clarity
Project Portfolio
Management Success
(PPMS)
Overall
Cronbachs Alpha
0.967
No. of Items
29
0.905
11
0.929
10
0.790
0.908
4
6
0.973
60
Table 4.24 showed the values of Cronbachs alpha and number of items by each variable.
The study used Cronbachs alpha for finding the reliability of items. Cronbachs alpha
measured if items in chosen instrument are significantly correlated. Reliability values
above 0.60 were good and significant (Sekaran & Bougie, 2013). The overall model
reliability is 0.973which is highly reliable and individual variables reliability is also with
high values as explained in the table 4.24.
82
Model
1
2
3
R Square
Adjusted R
Std. Error of
Square
the Estimate
.244
.060
.050
.97460826
.329
.108
.090
.95418768
.145
.118
.93905352
.381
Table 4.25 highlight the value of R square is 0.145 for the internal stakeholders
engagement which is an independent variable. According to the (Sekaran & Bougie,
2013) R square > 0.25 is significant and show strong relationship between independent
and dependent variable. For independent variables R square less than 0.25 is also
acceptable. And standard error < 1.0 also show strong relationship among independent
and dependent variables. Table 4.25 mention (R square = 0.145, standard error =
0.93905). These results show positive relationship between internal stakeholders
engagement, role clarity and project portfolio success. According to the results show in
table 4.25 internal stakeholders engagement have positive relationship with the project
portfolio management success.
83
Sum of
df
Mean Square
Sig.
6.226
.014b
5.867
.004c
5.423
.002d
Squares
1
Regression
5.914
5.914
Residual
93.086
98
.950
Total
99.000
99
Regression
10.684
5.342
Residual
88.316
97
.910
Total
99.000
99
Regression
14.345
4.782
Residual
84.655
96
.882
Total
99.000
99
Unstandardized Coefficients
Standardized
Sig.
.000
1.000
2.495
.014
.000
1.000
Coefficients
Std. Error
(Constant)
-3.349E-015
.097
Zscore(ISE)
.244
.098
(Constant)
-1.015E-015
.095
Zscore(ISE)
.125
.109
.125
1.141
.257
Zscore(RC)
.250
.109
.250
2.289
.024
(Constant)
-.057
.098
-.586
.559
Zscore(ISE)
.101
.108
.101
.936
.351
Zscore(RC)
.234
.108
.234
2.172
.032
.121
.059
.195
2.038
.044
Interaction1
(ISE*RC)
Beta
.244
Table 4.26 mentions the results of ANOVA. Model show values (F = 5.423, p = 0.002).
Sekaran & Bougie (2013) explained p < 0.05 considered significant. So model for
84
R Square
Adjusted R
Std. Error of
Square
the Estimate
.427
.182
.174
.90906264
.478
.229
.213
.88729329
Table 4.28 highlight the value of R square is 0.229 for the customers engagement which
is an independent variable. According to the (Sekaran & Bougie, 2013) R square > 0.25 is
85
significant and show strong relationship between independent and dependent variable.
For independent variables R square less than 0.25 is also acceptable. And standard error
<1.0 also show strong relationship among independent and dependent variables. Table
4.28 mention (R square = 0.229, standard error = 0.88729). These results show positive
relationship between customer engagement and project portfolio success. According to
the results show in table 4.28 customer engagement has positive relationship with the
project portfolio management success.
Table 4.29 ANOVA for RVC
Model
Sum of
df
Mean Square
Sig.
21.797
.000b
14.374
.000c
Squares
1
Regression
18.013
18.013
Residual
80.987
98
.826
Total
99.000
99
Regression
22.633
11.316
Residual
76.367
97
.787
Total
99.000
99
Table 4.29 mentions the results of ANOVA. Model show values (F = 14.374, p = 0.000).
Sekaran & Bougie, (2013) explained p < 0.05 considered significant. So model for
customers engagement is highly significant according to these results. Overall model for
this independent variable shows positive and significant results.
86
Model
Unstandardized Coefficients
Standardized
Sig.
.000
1.000
4.669
.000
-.879
.382
Coefficients
Std. Error
(Constant)
-3.595E-015
.091
Zscore(RVC)
.427
.091
(Constant)
-.084
.095
Zscore(RVC)
.391
.090
.391
4.333
.000
.125
.052
.219
2.422
.017
Interaction2
(RVC*RC)
Beta
.427
Table 4.30 show the results of beta coefficients and significance level for the customers
engagement. Model mention the values for customer engagement ( = 0.391, p = 0.000)
it means customers engagement have positive and highly significant relationship with
the project portfolio management success Sekaran & Bougie, 2013 explained p < 0.05
considered significant. This Results of the interaction of customers engagement and role
clarity shows that ( = 0.219, p = 0.017). According to these results role clarity as a
moderator is working. Customer engagement is also significant with the moderating
effect of the role clarity. Customers engagement has significant effect on the project
portfolio management success. Customers engagement with moderator also enhanced
the effect on the project portfolio management success.
4.6.3 Verification of Suppliers Engagement
Verification of suppliers engagement had been explained by the following tables.
Table 4.31 Model Summary for RVS
Model
1
2
Adjusted-R
S.E.
of
Square
Square
Estimate
.380
.145
.136
.92949893
.430
.185
.168
.91217905
87
the
Table 4.31 highlight the value of R square is 0.185 for the suppliers engagement which is
an independent variable. According to the (Sekaran & Bougie, 2013) R square > 0.25 is
significant and show strong relationship between independent and dependent variable.
For independent variables R square less than 0.25 is also acceptable. And standard error <
1.0 also show strong relationship among independent and dependent variables. Table 4.31
mention (R square = 0.185, standard error = 0.91217). These results show positive
relationship between supplier engagement and project portfolio success. According to the
result supplier engagement has positive relationship with the project portfolio
management success.
Model
Sum of
df
Mean Square
Sig.
16.588
.000b
10.990
.000c
Squares
1
Regression
14.331
14.331
Residual
84.669
98
.864
Total
99.000
99
Regression
18.289
9.145
Residual
80.711
97
.832
Total
99.000
99
Table 4.32 mentions the results of ANOVA. Model show values (F = 10.990, p = 0.000).
Sekaran & Bougie (2013) explained p < 0.05 considered significant. So model for
suppliers engagement is highly significant according to these results. Overall model for
this independent variable shows positive and significant results
88
Model
Unstandardized Coefficients
Standardized
Sig.
.000
1.000
4.073
.000
-.786
.434
Coefficients
Std. Error
(Constant)
-2.952E-015
.093
Zscore(RVS)
.380
.093
(Constant)
-.077
.098
Zscore(RVS)
.330
.095
.330
3.488
.001
.127
.058
.206
2.181
.032
Interaction3
(RVS*RC)
Beta
.380
Table 4.33 show the results of beta coefficients and significance level for the suppliers
engagement. Model mention the values for supplier engagement ( = 0.330, p = 0.001) it
means suppliers engagement have positive and highly significant relationship with the
project portfolio management success Sekaran & Bougie (2013) explained p < 0.05
considered significant. This Results of the interaction of suppliers engagement and role
clarity shows that ( = 0.206, p = 0.032). According to these results role clarity as a
moderator is working. Suppliers engagement is also significant with the moderating
effect of the role clarity. Suppliers engagement has significant effect on the project
portfolio management success. Suppliers engagement with moderator also enhances the
effect on the project portfolio management success.
89
Hypothesis
H1
H2
H3
H4
H5
H6
Beta
Significanc
0.101
0.391
0.330
0.195
0.219
0.206
e
0.351
0.000***
0.001***
0.044***
0.017***
0.032***
show significant and positive relationship between customers engagement and project
portfolio management success ( = 0.391, p = 0.000). Hypothesis for customer
engagement is accepted.
H3: The more effectively suppliers engagement during PPM, the better prospects for
Success of PPM.
This hypothesis explained positive relationship between suppliers engagement and
project portfolio management success. According to the study presumption analysis also
show significant and positive relationship between suppliers engagement and project
portfolio management success ( = 0.330, p = 0.001). Hypothesis for suppliers
engagement is substantiated.
Hypotheses for Moderation
The study tends to explore the impact of internal stakeholders engagement (top
managers, line managers, project portfolio managers and project managers) and external
stakeholders engagement (customers and suppliers) with moderating effect of role clarity
on the project portfolio management success. The study tends to examine mediation
effects through three hypotheses. Which are explained as given:
H4: Role clarity moderates the relationship between internal stakeholders
engagement and project portfolio management success.
H5: Role clarity moderates the relationship between customer's engagement and
project portfolio management success.
H6: Role clarity moderates the relationship between supplier's engagement and
project portfolio management success.
Table 4.34 mentions the results of the hypotheses. Hypothesis for internal stakeholders
engagement is 4. In the model assumed that internal stakeholders engagement have
positive relationship with moderating effect on the project portfolio management success.
According to the study presumptions analysis also show that internal stakeholders
engagement have significant and positive effect with moderation on the project portfolio
management success ( = 0.195, p = 0.044). Hypothesis related to the internal
stakeholders engagement (ISE) with moderation (RC) have significant and positive on
the project portfolio management success (PPMS) is substantiated.
91
Table 4.34 also mentions the results of the hypotheses for external stakeholders
engagement. Hypothesis 5 mentions the positive effect of customers engagement with
moderating effect on the project portfolio management success. Analysis also favors the
study presumptions. Analysis show that role clarity moderates the relationship between
customers engagement and project portfolio management success ( = 0.219, p = 0.017).
Hypothesis for customers engagement (RVC) with moderation (RC) have positive and
significant effect on the project portfolio management success (PPMS) is substantiated.
Table 4.34 also mentions the results of the hypotheses for external stakeholders
engagement. Hypothesis 6 mentioned the positive effect of suppliers engagement with
moderating effect of role clarity on the project portfolio management success. Analysis
also favors the study presumptions. Analysis show that role clarity moderates the
relationship between suppliers engagement and project portfolio management success (
= 0.206, p = 0.032). Hypothesis for suppliers engagement (RVS) with moderation (RC)
have positive and significant effect on the project portfolio management success (PPMS)
is substantiated.
4.8 Findings
The study explains that most of the respondents had designation of project managers in
the software houses (i.e.51%). Majority of the respondents were males in the software
houses (i.e. 92%). Most of the respondents had overall experience above 10 years in the
software houses (i.e. 47%). Mostly respondents had experience of project portfolio
management up to 2 years in the software houses (i.e. 34%). Most of the software houses
had employees less than 50 (i.e. 69%). Mostly software houses had annual revenue up to
1$ million (i.e. 63%). Mostly software houses existed from 2 to 4 years (i.e. 77%). Most
of the software houses were deal in multiple technologies (i.e. 86%). Most of the
software houses had span across the world wide (i.e. 60%). Mostly software houses had
CMMI ranking at level 3 (i.e. 47%). Mostly software houses had certifications of ISO
(i.e. 46%). Most of the clients of the software houses were international (i.e. 69%).
Mostly the number of portfolios in the software houses was less than 2 (i.e. 40%). Mostly
the number of projects in the software houses was above 8 (i.e. 62%). Mostly the number
of projects in the software houses successful was above 8 (i.e. 60%). Mostly number of
92
project portfolio managers in the software houses was from 3 to 4 (i.e. 77%). Most of the
software houses had number of project managers above 6 (i.e. 60%). Most of the
software houses deal with the projects of worth 1 to 2 million (i.e. 38%). In this
instrument mostly information was provided about the top managers (i.e. 34%).
1. The study perceived the positive and significant relationship between the internal
stakeholders engagement (ISE) and project portfolio management success
(PPMS), literature also explained that internal stakeholders engagement have
significant effect on the project success (Beringer, et al. 2013), but results show
that internal stakeholders engagement (ISE) does not have significant effect on
the project portfolio management success (PPMS) ( = 0.101, p = 0.351). Study
perceived the positive and significant relationship between the internal
stakeholders engagement (ISE) and project portfolio management success
(PPMS) with moderating effect of the role clarity (RC). Results also favor the
study and show positive significant effect of the internal stakeholders
engagement on the project portfolio management success with moderating effect
of the role clarity (RC) ( = 0.195, p = 0.044).
2. Study perceived the positive and significant effect of customers engagement
(RVC) on the project portfolio management success (PPMS), results also prove
the perception of the study and show that customers engagement (RVC) has
positive and significant effect on the project portfolio management success
(PPMS) ( = 0.391, p = 0.000). Study also perceived that customers engagement
(RVC) has also significant and positive effect on the project portfolio
management success (PPMS) with moderating effect of the role clarity (RC).
Results also mention that customers engagement (RVC) has significant effect on
the project portfolio management success (PPMS) with moderation of role clarity
(RC) ( = 0.219, p = 0.017).
3. Study perceived the positive and significant effect of suppliers engagement
(RVS) on the project portfolio management success (PPMS), results also prove
the perception of the study and show that suppliers engagement (RVS) has
positive and significant effect on the project portfolio management success
(PPMS) ( = 0.330, p = 0.001). Study perceived that suppliers engagement
93
(RVS) has also significant and positive effect on the project portfolio management
success (PPMS) with moderating effect of the role clarity (RC). Results also favor
that suppliers engagement (RVS) has significant effect on the project portfolio
management success (PPMS) with moderation of role clarity (RC) ( = 0.206, p =
0.032).
Table 4.35 Hypotheses Status
#
H1
H2
H3
H4
H5
H6
Hypotheses
The greater the internal stakeholders engagement in PPM,
the better prospects for success of PPM.
The greater the customers engagement in PPM, the better
prospects for success of PPM.
The more effectively supplier engagement during PPM, the
better prospects for success of PPM.
Role clarity moderates the relationship between internal
stakeholders engagement and project portfolio management
success.
Role clarity moderates the relationship between customer's
engagement and project portfolio management success.
Role clarity moderates the relationship between supplier's
engagement and project portfolio management success.
94
Status
Rejected
Accepted
Accepted
Accepted
Accepted
Accepted
CHAPTER 5
CONCLUSION AND RECOMMENDATIONS
This Chapter explains the conclusion of the study. This section also mentions the
limitations and recommendations for future research.
95
Conclusion
Based on the finding in chapter 4 internal stakeholders engagement (ISE) have
insignificant effect on the project portfolio management success (PPMS) while study
predicted the positive and significant effect of internal stakeholders engagement on the
project portfolio management success. In IT industry Lahore, Pakistan internal
stakeholders which consisted on the top managers, line managers, project portfolio
managers and project managers. Internal stakeholders are not engaged with the project
portfolios significantly thats why results show insignificance in their relationship.
Further involvement of role clarity which is working as a moderator shows significant
relationship
between
internal
stakeholders engagement
and project
portfolio
management success. It means role clarity (RC) enhance the effect of internal
stakeholders engagement (ISE) on the project portfolio management success (PPMS).
By defining the role to each stakeholder within the organization, it gives positive results
to the project portfolio management success. In this case role clarity shows full
moderation for the internal stakeholders engagement. Internal stakeholders engagement
is 14.5% explained in this model. Internal stakeholders engagement show positive
relationship between the project portfolio management success. External stakeholders
engagement has significant effect on the project portfolio management success. In IT
sector software houses mostly deal with the customize projects. Based on finding 2 in
chapter 4 customers engagement is necessary in this perspective. Finding 2 explain that
customers engagement has significant effect on the project portfolio management
success. So results show high level of significance for the customers engagement. Role
clarity also moderates the relationship of the customers engagement and project portfolio
management success. But these findings show partial moderation because customers
engagement is already highly significant and with moderation it also shows good
significance. Customers engagement is 22.9% explained by the model. Finding 3 in
chapter 4 for suppliers engagement also mention significant relationship between the
supplier engagement and project portfolio management. In IT sector some services and
raw material are used from the outside of the organization. The suppliers are also directly
engage with the project requirements. Suppliers also enhance the success of the project
portfolio management success. Finding 3 in chapter mentioned that suppliers
96
engagement have significant effect on the project portfolio management success. Results
with the moderating effect of role clarity show also good significance. But before
moderation significance level is high. It means moderation also enhanced the effect of the
suppliers engagement but partially. Suppliers engagement is 18.5% explained by the
model. All these independent variables are tested independently. All independent
variables show significant effect separately. So final results explained that internal and
external stakeholders engagement has significant impact with moderating role of role
clarity on the project portfolio management success.
Recommendations
1. Internal stakeholders engagement has insignificant impact on the project
portfolio management success without moderation. Role clarity necessary for the
internal stakeholders. Role clarity explained and direct internal stakeholders
towards their roles and responsibilities. Maximum results had been achieved from
the project portfolio management with engagement of internal stakeholders.
2. External stakeholders engagement like customers engagement has high level of
significance. Customers engagement has significant impact on the project
portfolio management success without moderation. It means there is partial
moderation of rile clarity for the customers. Customers engagement is also show
significant results with the moderation but level of significance is high before
moderation. So moderation is working partially with customers engagement.
97
Discussion
Purpose of this study was to find the relationship between stakeholders engagement and
project portfolio management success. In project portfolio management success
stakeholders were involved significantly or insignificantly while in study of Beringer et
al (2013) showed that internal stakeholders like top managers and project managers had
significant effect on the project portfolio management while line managers and project
portfolio managers had insignificant effect on the project portfolio management.
(Beringer et al., 2013) also explained that growing task of role clarity did not have
noteworthy effect of all internal stakeholders on the project portfolio management
success. Role clarity moderate the relationship of line managers and projects mangers,
while in case of project portfolio managers and top managers role clarity was not
effecting. Studies which have used role clarity as a moderator explained here. Role clarity
was used to moderate the relationship between role ambiguity and athlete satisfaction.
Role clarity moderated the relationship of both of these (Bray, Beauchamp, Eys, Carron,
2005). Another study explained that need for role clarity did not moderate the relationship
between the degree of role clarity and job satisfaction (Miles, Petty, 1975). Role clarity
used as moderator in both studies but in one it was moderating the relationship and in
another study it was not working as moderator. In this study role clarity moderated the
relationship strongly between the internal stakeholders and project portfolio management
98
success. In case of external stakeholders role clarity partially moderated the relationship
between external stakeholders and project portfolio management success. Voss and Kock
(2013) also found positive relationship values of customers. They found significant effect
of customers relationship value on the project portfolio management success. Customer
knowledge management had direct impact on the project performance (Yang et al., 2014).
The present study finds significant effect of internal stakeholders on the project portfolio
management success with distinct effect of their role clarity. Internal stakeholders
engagement like senior managers, line managers, project managers and project portfolio
managers all have significant and strong relationship with the project portfolio
management success with moderating effect of role clarity. While external stakeholders
engagement like customers and suppliers has significant and vital relationship with the
project portfolio management success and with moderation it partially moderated the
project portfolio management Success. Long term objectives gained by adding the
supplier involvement (Echtelt et al., 2004). Supplier involvement increased the product
value and quality (Witlox, 2010). He found positive effect of suppliers engagement in
the project and product development. This study found positive and significant effect of
the suppliers engagement on the project portfolio management success. In an
organization there was need of the role clarity to find positive and significant outcomes
because within the organization role clarity defined and clarify the roles of the managers.
In case of external environment role clarity did not perform well. The reason of this is
that in external environment we cannot hold the things and cannot define the role as
within the organization. In external environment there was things are continuously
changing and these changes also affect the customers and suppliers who are directly and
indirectly attached with the organization's performance. That's why role clarity partially
moderated the relationship between the external stakeholders and project portfolio
management success. Results of this study mentioned that external stakeholders have
significant effect on the project portfolio management success.
99
1. The current research model can be applied in other sectors e.g. construction, and
textile projects.
2. Further research can be done by adding more variables related to external
stakeholders in the current research model.
3. This study has been conducted in the IT sector in Lahore Pakistan, in other major
cities like Karachi and Islamabad might have different and better results.
Bibliography:
Ahmed, R., Azmi, N., Masood, T. M., Tahir, M., & Ahmad, S. M. (2013). What Does
Project Leadership Really Do? International Journal of Scientific & Engineering
100
Research, 4, 1-8.
Alvi, H., T. (2013). Impact of Moral Identity, Love of Money, Religiosity, and
Spirituality on Ethical Intention in Marketing-Moderating Effect of Ethical Work
Climate. Comsats Institute of Information Technology, Lahore, Pakistan.
A Guide to the project management body of knowledge (2013), (5th ed.), Pennsylvania,
Project Management Institute, Inc.
Amarl, Antonio, Aroujo, & Madalena. (2009). Project portfolio management phases: A
technique for strategy alignment. World Academy of Science, Engineering and
Technology, 58, 560-568.
Archer, NP. & Ghasemzadeh, F. (1999). An integrated framework for project portfolio
selection. International Journal of Project Management, 17(4), 207-216.
Atkinson, R., Crawford, L., & ward, S. (2006). Fundamental uncertainties in projects and
the scope of project management. International Journal of Project
Management, 1, 190-220.
Beringer, C., Jonas, D., & Kock, A. (2013). Behavior of internal stakeholders in project
portfolio management and its impact on success. International Journal of
Project Management, 31, 830 - 846.
Blichfeldt, S., B., & Eskerod, P. (2008). Project portfolio management Theres more to
it than what management enacts. International Journal of Project Management,
26, 357-365.
Bray, R. S., Beauchamp, R. M., Eys, A. M., & Carron, V. A. (2005). Does the Need for
Role Clarity Moderate the Relationship between Role Ambiguity and Athlete
Satisfaction? Journal of Applied Sport Psychology, 17, 306-318.
Belout, A., & Gauvreau, C. (2004). Factors influencing project success: the impact of
human resource management. International Journal of Project Management,
22(1), 1-11.
Bliese, D.P., & Castro, A.C. (2000). Role clarity, work overload and organizational
support multilevel evidence of the importance of support. Work & Stress, 14, 6573.
101
Catherine, P. K., & Robert, A. H. (2010). Dynamic capability through project portfolio
management in service and manufacturing industries. International Journal of
Managing Projects in Business, 3(1), 157169.
Carlsson, C., Fuller, R., Heikkila, M., & Majlender, P. (2007). A fuzzy approach to R&D
Project portfolio selection. International Journal of Approximate Reasoning, 44,
93105.
Calderini, R. S., Reyck, D. B., Cockayne, G. Y., Lockett, M., Moura, M., & Sloper, A.
(2005). The impact of project portfolio management on information technology
projects. Ashridge business school u.k.
Cooper, R. G., Edgett, J. S., & Kleinschmidst, J. (2001). Portfolio management for new
product development. Product Development Institute INC, 31(4), 1-39.
Cooper, R. G., Edgett, J. S., & Kleinschmidst, J. (1999). New product portfolio
management: practices and performance. International Journal of Project
Management, 16, 333-351.
Clarkson, E. B. M. (1995). A Stakeholder Framework for Analyzing and Evaluating
Corporate Social Performance. The Academy of Management Review, 20, 92117.
Davis, K. (2014). Different stakeholder groups and their perceptions of project success.
International Journal of Project Management. 32, 189-201.
Davies, C, T. (2002). The real success factors on projects. International Journal of
Project Management, 20, 185-190.
Dickinson, W. M., Thornton, C. A., & Graves, S. (2001). Technology Portfolio
102
,12, 138.
Mazzocchi, M. (2008). Statistics for marketing and consumer research: SAGE
Publications Limited.
Martinsuo, M., &lehtonen, P. (2007). Role of single project management in achieving
portfolio management efficiency. International Journal of Project Management,
25, 56-65.
Munns, K. A., & Bjeirmi, F.B. (1996). The Role of Project Management in achieving
Project Success. International Journal of Project Management, 14(2), 81-87.
Miles, H. R., & Petty, M. M. (1975). Relationships between role clarity, need for role
clarity, and job tension and satisfaction for supervisory and nonsupervisory roles.
18(4), 1-8.
Naverauskas, B., & Ciutiene, R. (2011). The theoretical approach to project portfolio
Maturity management. Economics and management, 16, 1-7.
Naqvi, H. I., Aziz, S., & Rehman, U. K. (2011). The impact of stakeholder
communication on project outcome. African Journal of Business Management,
5(14), 5824-5832.
Naqvi, H, I. (2009). Framework of IT project management: Human Resource
Management. U.S.A: LAP (Lambert academic publishing).
Olsson, R. (2006). Risk management in a multi-project Environment: An approach to
Manage portfolio risks. International Journal of Quality and Risk Management,
25, 1-12.
Platje, A., Seidel, H., & Wadman, S. (1994). Project and portfolio planning cycle:
Project-based management for the Multi-project challenge. International Journal
of Project Management, 12(2), 100-106.
Parise, S., & Casher, A. (2003). Alliance portfolios: Designing and managing your
network of Business-partner relationships. Academy of Management Executive,
17(4), 1-17.
Rosell, T. D. (2013). Knowledge Integration and Innovation in Buyer-Supplier
Collaborations. Linkping University, Sweden.
106
Raes, L.M.A., Heijltjes, G.M., Glunk, U., & Roe, A.R. (2011). The Interface of Top
Management Team and Middle Managers: A Process Model. Academy of
Management Review, 36, 102-126.
Ross, M. (2007). Project portfolio management planning: A method for prioritizing
projects. LLC, 31, 1-8.
Reyck, D. B., Cockayne, G.Y., Lockett, M., Calderini, R. S., Moura, M., & Sloper, A.,
(2005). The impact of project portfolio management on information technology
projects. International Journal of Project Management, 23, 524537.
Raz, T. & Micheal, E. (2001). Use and benefits of tools for project risk management.
International Journal of Project Management, 19(1), 9-17.
108
APPENDIX I
Table 1 PASHA List
Sr
N
o
#
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Company Name
CEO Name
No. of
employe
es
7vals
AbacusConsulting
ABM Info
Tech(private)
limited
AGCN Pakistan
(pvt) Ltd
APEX consulting
Pakistan
Application
Management
outsourcing services
(AMOS) Global Pvt
Ltd
ARBISOFT
PRIVATE LTD
Arwen Tech (pvt.)
Limited
Autosoft Dynamics
(pvt.) Limited
Avanceon
AZM Computer
Services (pvt.) Ltd
B Solutions
Bahria Enterprise
Systems and
Technologies
(BEST)
Bramerz Private
Limited
CIKLUM
PAKISTAN (pvt.)
Syed Ali
Asad Ali Khan
Azam Sultan
Ayed.ali@7vals.com
Asad.khan@abacus-global.com
azamsultan@abmgroup.com
20
2000
62
Muhammad Faisal
Ahad Rao
Syed Sardar Ali
Faisal.rao@agnc-pakistan.com
60
Sardar.ali@apexconsulting.biz
52
Azhar H. Shore
a.shore@amos-global.com
35
Yasser Bashir
Yasser.bashir@arbisoft.com
100
Abdul
QadirSubhani
Mr. Lutfullah
Khan
Qadir.subhani@arwentech.com
150
ceo@autosoftdynamics.com
120
Ghulam Mustafa
Kamboh
FazalAshfaq
Muhammad Azam
gmk@azm.com.pk
30
fazal@bsolutions.pk
ceo@best-bf.com
5
35
ZeeshanSaleem
Zeeshan@bramerz.pk
55
Khushal Khan
109
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
Ltd
Comstar
Information
Systems Associates
Ltd.
Confiz Solutions
Corvit Networks
CTO 24/7 Private
Limited
CureMD Healthcare
DGHarbour
DGS Private
Limited
Ebryx SMC Pvt.
Ltd
Edusys Pakistan
Expert Systems
(pvt) Ltd
Efro Tech Services
Five Rivers
Technologies(pvt)
Ltd
FOURGEN
Information
Systems(pvt) Ltd
Future Now
Technologies (pvt)
Ltd
GAMEVIEW
PAKISTAN
(PRIVATE)
LIMITED
GCS (PVT) LTD
GenITeam
Goldtime (pvt) Ltd
i2c
IBM
Inbox Business
Technologies Pvt.
Ltd
INFOGISTIC
Sami Bajwa
sbajwa@comstar.com.pk
125
Muhammad Raza
Saeed
Kashif-ul-Haq
Amin Ansari
Raza.saeed@confiz.com
150-200
aansari@cto247pk.com
90
Bilal Hashmat
Muhammad
Rahimtoola
Faizan Ali Siddiqi
Bilal.hashmat@curemd.com
m.rahimtoola@dgharbour.com
375
25
Faizan.siddiqi@dgsworld.com
480
M. Ahrar Naqvi
Ahrar@ebryx.com
60
Nouman.ali.syed@gmail.com
Khalid@expertsystems.net
nadir@efrotech.com
Hasan.rizvi@fiveriverstech.com
45
Ather Sultan
chawla
Ather.sultan@fourgensys.com
60
Muhammad
HanifMian
drhanif@tfntech.com
150
IRFAN
GAZANFER
VIRK
IRFAN@GAMEVSTUDIOS.CO
M
300
Mr. ShahidMuneer
KhurramSamad
Naveed Ahmed
Amir wain
Humayun Bashir
Ghias Khan
Shahid@gcspvt.com
Khurram@geniteam.com
naveed@goldteam.co.uk
awain@i2cinc.com
humayun@pk.ibm.pk
Ghias.khan@inboxbiz.com
130
42
18
330
500
Sajjad Kirmani
110
Sajjad.kirmani@infogistic.com
20
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
Private Limited
InfoTech
Private
Limited
Innovative
Integration Pvt Ltd
Intagleo
Systems
Pvt. Ltd
IT Minds Limited
Kabot International
(PVT)Ltd.
LMK
Resources
Pakistan (Pvt) Ltd
LumenSoft
Technologies
Pvt.
Ltd.
Maison Consulting
and Solutions
Mantaq Systems
Naseer
Ahmad Naseer.akhtar@infotechgroup.co
Akhtar
m
Syed Ahmer Ghazi Ahmer.ghazi@innovativeintegrati
on.net
Amar Ali
amarali@intagleo.co.uk
250
asif.shah@itminds.biz
arif.toor@kabotintl.com
22
70
AtifRais Khan
akhan@lmkr.com
600+
Abdul Aziz
aziz@lumensoft.biz
28
Sultan Hamdani
shamdani@maison-global.com
135
HashimZulfiqar
Ali
Marriala
Muhammad
Consultants
Arfaeen Iqbal
Mindstorm Studios
Babar Ahmed
Monet Pvt Ltd
Ali
Abbas
Sikander
Naseeb Networks
Monis Rahman
National Consulting Ahsan Saleem
for Business and
Management
Solutions (Private)
Limited
hashim.ali@mantaq.com
15
Arfaeen@marriala.net
10
babar@mindstormstudios.com
abbas.sikander@monetonline.com
monis@naseebnetworks.com
ahssaleem@ncbms.com.pk
20
11
NetSol
Off-Road Studios
salim.ghouri@netsoltech.com
Waqas@offroadstudios.com
1000
38
anjum.chohan@open-silicon.com
60
Salim Ghauri
Muhammad
Waqas
OPEN-SILICON
ANJUM
PAKISTAN
FAROOQ
(PVT)LTD
CHOHAN
Ora-Tech Systems Aspy N. Fatakia
(Pvt )Ltd
Ovex Technologies Faisal S Khan
Pakistan
(Pvt)
Limited
111
20
35
42
115
aspy.fataki@ora-tech.com
fkhan@ovextech.com
210
57
58
69
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
amirhussain@enpointe.com
550
ceo@ozitechnology.com
35
jauher@palmchip.com
Muqtaza.shah@panasiangroup.co
m
Moin.sabri@sabritech.com
Akif.rahman@sakonent.com
Sohail.qadir@sensys.com
40
Javed Iqbal
iqbalsitara@gmail.com
13
Zafar Khan
Ghulam Ali
Salman Iqbal
zkhan@sofizar.com
ali@softsolutions.com.pk
salman@softech.com.pk
64
10
85
Farhan Masood
RabiyaJunaid Aziz
fm@solotechcorp.co.uk
sashraf@ssidecisions.com
16
150
Iqbal Ahmed
Iqbal@synergy.net.pk
160
MoinSabri
Akif Rahman
SohailQadir
AroojAlam Khan
Mr.
Ashraf Ashraf.kapadia@systemsltd.com
Kapadia
Techaccess Pakistan Syed Iqtidar Zaidi izaidi@techaccesspak.com
Private Limited
The
Resource NadeemElahi
Naeem.elahi@trdworld.com
Group
TkXel
UmairJaved
umair@tkxel.com
TMR
Consulting Mian Muhammad mianramzan@tmrc.com.pk
(Private) Limited
Ramzan
Tricast
Media ARSLAN KHAN Arsalan.khakwani@tricastservices
Private Limited
KHAKWANI
.com
Viper Technologies KhushnoodAftab
k.aftab@viper.pk
Pvt Ltd.
Visionary Computer Zahid Raza
zahid@vcs.com.pk
Solutions PVT Ltd
VopiumAktieselskab QaisarJaved
Qaiser.javed@vopium.com
Pvt Ltd.
Wavetec
Private Ahmed Fraz
Ahmed.fraz@wavetec.com
112
50
125
78
1200
150
1500
109
30
51
200
46
150
82
83
Limited
Zahdan
Technologies
Limited
Dzine Media
Mr.
shehzad@zahdangroup.com
Pvt ShehzadShabbirDa
har
Usman Shajoor
Usman.shakoor@dzinemedia.com
30
13
Software
House
Ebryx
Adress
In
Portf
olio
Office # Yes
1, floor
#
4,
Arfa
softwar
e
technol
ogy
park,
No. of
Projects
2
113
No. of
Project Succes
CEO
Manage
s
Name
rs
Ratio
3-4
100% Ahrar
Naqvi
CEO Email
Address
ahrar@ebryx.co
m
346-B
Ferozpu
r Road,
Lahore
Pakista
n.
ADDVAN Office #
TUM
17,
Floor #
10, Arfa
STP.
Frag
Office #
Games
7, floor
#
4,
Arfa
STP.
Microsoft Office #
Innoation 1,
Centre
Floor #
5, Arfa
STP.
Inbox
Office #
3,
Floor #
5,
Arfa
STP.
Interactiv Office #
e Groups 2,
Floor #
5, Arfa
STP.
Logica
Floor #
Solutions 7, Arfa
STP.
Nespak
Floor #
7,
Arfa
STP.
Tower
Office #
Yes
10-15
10-15
90%
Shahzad
Hamid
yes
6070%
RehmanR
afique
yes
100%
Ziad
Bashir
yes
Local
15-20
level 2,
internatio
nal level
1.
100%
Ghias
Khan
yes
10-15
10
100%
Shahid
Mahmud
yes
2-3
7080%
Usman
Ahmad
yes
2-3
90%
Amjad A.
Khan
yes
5-6
100%
Ajmal
114
rehman@fraggames.com
ajmal@theto
Technolo
gies
1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
4,5
floor #
7, Arfa
STP.
National Office # yes
Engineer 2, floor
s (NETS #
8,
Internati Arfa
oal)
STP.
Loxvo
Floor # yes
Technolo 8, Arfa
gies
STP.
Zero
Office # yes
Billion
12,
floor #
8, Arfa
STP.
Fork
Tech
Floor #
8, Arfa
STP.
Total
Office #
Softwares 19,
Services
floor #
8, Arfa
STP.
Zitech
Floor #
8, Arfa
STP.
Future
Floor #
Technolo 8, Arfa
gies
STP.
ITD
Floor #
Pakistan 8, Arfa
STP.
Rent VM Office #
14,
floor #
8, Arfa
STP.
Mobius
Floor #
Hussain
30
80%
60%
7080%
WaqqasAl Waqqas.alvi@zer
vi
obillion.com
no
Upto 15 3
for small
projects,
2
for
large
projects.
1
1
50%
Noor
Khawaja
nkhawaja@forkp
article.com
yes
3-4
80%
Haseeb
Ali Gill
Haseeb.gill@tota
lsoftwareservices
.com
Yes
4-5
75%
MesbahR
ehan
yes
2-3
60%
yes
70%
yes
6070%
yes
80%
115
Jahangir
Ahmad
wertech.com
Jahangir.ahmad
@netsinternational.com
Networks
2
0
Incubato
rs
2
1
Viper
2
2
Bayt.com
2
3
Seven
Centric
2
4
SoftRove
2
5
ILMA
Soft
2
6
Comcast
2
7
Fast
Services
8, Arfa
STP.
Office #
7, floor
#
8,
Arfa
STP.
Office #
8, floor
#
8,
Arfa
STP.
Office #
20,
floor #
10, Arfa
STP.
Office #
17,
floor #
10, Arfa
STP.
Office #
18,
floor #
10, Arfa
STP.
Office #
15,
floor #
10, Arfa
STP.
Office #
13,
floor #
10, Arfa
STP.
Office #
10,
floor #
10,
yes
10-15
90%
yes
150-200
80%
yes
Above
75%
RabeaAta
ya
yes
5-6
50%
Saad
Mubarak
saad@7centric.c
om
yes
2-3
2-3
100%
Omer
Mukhtar
Omer.mukhtar@
softrove.com
yes
5-6
100%
Syed
Iftikhar
Hussain
Shah
no
100%
Cyrus
cyrusjan@comca
Saood Jan st.net
yes
10
2-3
7080%
Rana
Farooq
116
Hammad
Tariq
Hammad.tariq@i
ncubator.pk
2
8
2
9
3
0
ArfaST
P.
Dell
Office # yes
8, floor
#
10,
Arfa
STP.
GCS Pvt Office # yes
Ltd
7, floor
#
10,
Arfa
STP.
TeraData Floor # yes
15, Arfa
STP
4-5
100%
14-15
Above
90%
ShahidM
uneed
Above
10
10
100%
Khurram
Rahat
117
Khuram.rahat@t
eradata.com
Name
1
2
HarisShahid
Farhan Shah
Zaigham Butt
Mirza Asif
Baig
Majid Imtiaz
Waqas Ashraf
Salma N.
Waseem
Muneeb
Syed
FaheemAthar
Imran Naqvi
Jawad
Jahangir
Ahmad
Shahbaz
Ashraf
Fuad Khalid
Masood Abbas
Hasnain Naqvi
10
Hafiz
Zafarullah
Sadaan Saeed
11
12
13
WaqqasAlvi
Noor Khawaja
Haseeb Ali
Company
Name
Inbox
Inbox
Microsoft
innovation
centre
Interactive
Group
Logica IT
Solutions
Logica IT
Solutions
Logica IT
Solutions
Nespak
Tower
Technologies
Tower
Technologies
Tower
Technologies
Nets
International
National
Engineers
Nets
International
Nets
International
Nets
International
Nets
International
Loxvo
Technologies
Zero Billion
Fork Tech
Total Software
118
Email Address
Haris.shahid@inboxbiz.com
Farhan.shah@inboxbiz.com
v-zaikra@microsoft.com
Asif.baig@iacgrp.com
Majid.imtiaz@logicait.pk
moneeb@nespak.co
faheemathar@thetowertech.com
Jahangir.ahmad@netsinternational.com
Shahbaz.ashraf@ne.co.pk
fuad.khalid@nets-international.com
Masood.abbas@netsinternational.com
Hasnain.naqvi@netsinternational.com
Hafiz.zafrullah@netsinternational.com
Sadaan.saeed@loxvo.com
Waqqas.alvi@@zerobillion.com
nkhawaja@forkparticle.com
Haseeb.gill@totalsoftwareservices.c
14
15
16
17
Gill
JawadAmjad
M.Tahir
Tallat
Haider Ali
Turab
Sajjad
Hammad
Tariq Aziz
M.Farhan Ali
Rabia Tariq
18
19
20
21
22
23
24
25
RehmanRafiqu
e
Ammad Aziz
Saad Mubarak
Omar Mukhtar
Usman
M.Irfan
Choudhary
Bashir
Hameed
Sohail Saeed
KhurramRahat
Zitech
Future
Technologies
ITD Pakistan
Rent VM
Mobius
Networks
Incubators
Viper
Ebryx
om
Jawad.amjad@ozitechnology.com
tahir@future.com.pk
tallat@itdpak.com
Haider.turab@rentvm.com
sajjad@mobius.pk
Hammad.tariq@incubator.pk
Tariq.aziz@viper.pk
Farhan.ali@ebryx.com
ADDVANTU
M
Frag Games
Rabia.tariq@addvantum.com
Bayt.com
Seven Centric
SoftRove
ILMA Soft
Fast Services
Dell
Ammad-aziz@bayt.net
saad@7centric.com
Omar.mukhtar@softrove.com
usman@ilmasoft.com
sales@fastservices.pk
Basher_hemeed@dellteam.com
Sohail.saeed@gcspvt.com
Khuram.rahat@teradata.com
119
rehman@frag-games.com
Scales Name
Role Clarity
Project Portfolio Management
Success
Average Project Success
Strategic Fit
Customer Relationship Value
Relationship Value for the
customers
Relationship Value from the
customers
Supplier Relationship Value
Relationship Value for the
suppliers
Relationship Value from the
suppliers
About Managers
Senior
Management
Involvement
120
Items
1,2,3,4
5,6,7
8,9,10
11, 12, 13, 14
15, 16, 17, 18, 19, 20, 21
APPENDIX II
Preliminary Survey Questions
121
APPENDIX III
INSTRUMENTS (Questionnaire for data collection)
122
Dear Respondent,
I am student of MS (Project Management) in COMSATS Institute of Information and
Technology. I want to conduct research on impact of Stakeholder's engagement on
Project Portfolio Management Success, in IT sector Lahore, Pakistan. It would be highly
appreciated, if you spare some time from your busy schedule to answer few questions
mentioned below. Your response will be kept confidential. I will be very thankful to you
for your cooperation.
123
a) Male
b) Female
b) 2 - 6 c) 6 - 10 d) above 10
b) 2 - 6 c) 6 -10
d) above 10
b) 2 4
c) 4 6
d) Above 6
e) Others
Span of Software House:
a) Within Pakistan
World Wide
b) Within Subcontinent
c)
Within Asia
d) Across the
b) Level 2
c) Level 3
d) Level 4 e) Level 5
b) IEEE certified
c) Others .
124
c) Local
d) Others
Number of Portfolios:
c) 4-6
a) 2-4
b) 4-6
c) 6-8
d) above 8
a) 2-4
b) 4-6
c) 6-8
d) above 8
a) Less than 2
b) 2-4
c) 4-6
d) above 6
d) Above 6
d) Above 6
b) Line Manager
Items
Strongly
Disagree
c)
Disagree
Neither
Agree nor
Disagree
Agree
Strongly
Agree
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Our customers
actively engage in
value creation.
Our customers
provide us with
essential
information on the
market and / or
competitors.
Our customers
actively promote
us at other
potential
customers due to
the quality of our
output.
Our customers
contribute
substantial ideas
for new projects.
Our customers
provide us
information on
potential
customers.
We fulfill needs of
our suppliers.
Our suppliers are
very satisfied with
our orders which
we give to them.
Problems
encountered by our
suppliers are
quickly being
handled.
Most of our
suppliers are longterm.
Most of our
suppliers are
127
reliable.
27
Our suppliers
actively engage in
value creation.
28
Our suppliers
provide us with
essential
information on the
competitors.
29
Our suppliers
actively promote
us at other
potential suppliers
due to the quality
of our orders.
30
Our suppliers
contribute
substantial ideas
for new projects.
31
Our suppliers
provide us
information on
potential market.
32
Is always
seeking
new
opportun
ities for
the
unit/depa
rtment/
organizat
ion
33
Paints an
interesting
picture of the
future for our
group.
34
Has a clear
understanding
128
35
of where we
are going.
Inspires others
with his/her
plans for the
future.
36
Is able to get
others
committed to
his/her dreams
of the
future.
37
Leads by
doing rather
than simply by
telling.
Provides a
good model to
follow.
Leads by
example.
Fosters
collaboration
among work
groups.
Encourages
employees to
be team
players.
38
39
40
41
42
43
Develops a
team attitude
and spirit
among his/her
129
44
45
46
47
48
employees
Shows us that
he/she expects
a lot from us.
Insists on only
the best
performance.
Will not settle
for second
best.
Acts without
considering my
feelings.
Shows respect
for my
personal
feelings.
49
Behaves in a
manner that is
thoughtful of
my personal
needs.
50
Treats me
without
considering my
personal
feelings.
Has provided
me with new
ways of looking
at things which
used to be a
puzzle for me.
Has ideas that
have forced me
to think some
of my own
ideas I have
51
52
130
53
54
55
56
57
never
questioned
before.
Has stimulated
me to think
about old
problems in
new
ways.
Our senior
management
has expert
knowledge in
multi-project
and project
portfolio
management.
Our senior
management
invests a lot of
time in
steering the
project
portfolio.
Our senior
management
makes
sufficient
human and
financial
resources
available for
the steering of
the project
portfolio
Our senior
management
adheres to the
official process
131
58
59
60
132