Beruflich Dokumente
Kultur Dokumente
Rev
Date
Description
1999
Checked
Approved
DL
GES C.55
Page 2 of 44
Rev 0 1999
INDEX
SEC
HEADING
PAGE
1.0
SCOPE OF SPECIFICATION
1.1
1.2
Introduction
Other NOC Specifications
4
4
2.0
DEFINITIONS
2.1
2.2
Technical
Contractual
5
5
3.0
3.1
3.2
3.3
3.4
3.5
3.6
3.7
6
8
24
26
27
29
31
4.0
INSTRUMENT INSTALLATIONS
31
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
General
Compliance with Drawings/Specifications
Instrument Mounting and Accessibility
Instrument Piping/Tubing
Piping and Tubing Supports
Instrument Cable Installation
Earthing
Materials
Air Supply Piping
Fabrication
31
33
33
36
37
38
38
38
38
38
5.0
39
5.1
5.2
Quality Assurance
Quality Control
39
39
GES C.55
Page 3 of 44
Rev 0 1999
SEC
HEADING
6.0
40
6.1
6.2
Inspection
Acceptance
40
41
7.0
DOCUMENTATION
41
7.1
7.2
7.3
41
42
42
8.0
42
42
42
43
43
43
44
44
8.1
8.2
8.3
8.4
8.5
8.6
8.7
PAGE
GES C.55
Page 4 of 44
Rev 0 1999
1.0
SCOPE
1.1
Introduction
1.1.1
This specification covers the minimum requirements for the calibration, inspection and testing of
instrumentation prior to commissioning. The user should bear in mind that this is a general specification
which must be matched to project operational and functional requirements to provide an installation
which is fit for the purpose intended.
1.1.2
In the event of any conflict between this specification and the attachments, or with any of the applicable
Codes and Standards, the Vendor/Contractor shall inform the Owner and obtain written clarification or
authorisation from the Owner before proceeding with the work as failure to do so shall indicate full
compliance; any remedial work then necesary shall be at the Vendor/Contractor's expense.
1.1.3
This General Engineering Specification together with the Scope of Work defined for the project will
form part of the Purchase Order/Contract and applies to equipment for refineries, onshore oil and gas
installations and processing facilities, including equipment purchased either directly or as part of a
package.
1.1.4
The Vendor/Contractor should note that this specification and its reference documents do not cover
each and every detail, the Vendor/Contractor is expected to be familiar with current good practice for
the installation and testing of instruments and hardware indicated.
1.1.5
This specification does not cover non-commodity type instrumentation such as analysers, control and
safety systems as well as computer based systems. The specific requirements of these shall be specified
on project specific basis.
1.1.6
It is the Vendor/Contractor's responsibility to ensure that the complete system is inspected and tested
throughout all stages to ensure a smooth and trouble free start of the plant and without any danger to the
operations personnel.
1.1.7
In the event of any conflict between this specification, the Purchase Order/Contract and any other
applicable Codes and Standards the Vendor/Contractor shall inform the Owner. Written clarification on
how to proceed shall be obtained from the Owner before proceeding with the affected portion of the
work.
1.2
Site Data
GES C.01
GES C.02
GES C.54
GES J.01
GES J.12
GES J.13
GES J.16
GES J.17
GES L.35
GES X.06
2.0
DEFINITIONS
2.1
Technical
GES C.55
Page 5 of 44
Rev 0 1999
Contractual
The commercial terms used in this specification are defined as follows:
Owner
The oil and gas company, an associate or subsidiary, who is the end user of the equipment and facilities.
GES C.55
Page 6 of 44
Rev 0 1999
Vendor
The company supplying the equipment and material.
Contractor
The main contractor for a defined piece of work
Sub-Contractor
A company awarded a contract by a Contractor to do part of the work awarded to the Contractor.
Inspection Authority
The organisation representing the Owner or Vendor/Contractor that verifies that the equipment and
facilities have been designed, constructed, inspected and tested in accordance with the requirements of
this specification and the Purchase Order/Contract.
Inspector
A qualified individual representing the Owner, Vendor/Contractor or the assigned Inspection Authority,
who verifies that the equipment and facilities have been designed, constructed, inspected and tested in
accordance with the requirements of this specification and the Purchase Order/Contract.
3.0
3.1
API 527
API 550
API 551
API 552
Transmission Systems
API 554
API 555
Process Analysers
BS 5501
GES C.55
Page 7 of 44
Rev 0 1999
BS 6739
BS 7671
IEC 60529
IEC 60751
(BS EN 6667)
ISO 9003
Quality Systems - Model for Quality Assurance in Final Inspection and Test
GES C.55
Page 8 of 44
Rev 0 1999
the system of area classification, equipment protection classifications, gas groups and the classification
of maximum surface temperatures. Whilst in general, equivalences exist between the two systems, it
should not be assumed that equipment suitable for use under one system, is necessarily suitable for use
under the other system. Reference shall be made to GES L.35 and the latest issue of NFPA 70 and the
NEC Electrical Code Handbook.
3.2
3.2.1
General
3.2.1.1
The Vendor/Contractor's personnel shall be competent, qualified and fully conversant with the types of
equipment to be tested. They shall also be familiar with Owner's Safety Regulations as all work shall be
carried out in accordance with these regulations.
3.2.1.2
A schedule (down to a loop level) shall be provided by the Vendor/Contractor and agreed by the Owner.
This schedule will define the overall sequence of the testing on the project. Any subsequent deviations
from this schedule shall be agreed in writing.
3.2.1.3
The Vendor/Contractor responsible for the pre-installation testing of instruments shall supply a fully
equipped workshop for this purpose, unless otherwise agreed. The workshop shall have a clean section
of bench reserved for electronic instruments and test gear isolated from the area used for mechanical
tests. The workshop shall be dust free and shall incorporate clean, dry and secure storage facilities.
Clean sterile areas and lifting facilities and appropriate utilities shall also be available.
3.2.1.4
The Vendor/Contractor shall submit with his Tender a comprehensive list of the test equipment to be
used. This will be reviewed and agreed with the Owner before testing is commenced.
A list of typical test equipment is shown in Section 3.6.
The Vendor/Contractor shall be responsible for supplying all test equipment, tools and consumables
used during testing and calibration.
3.2.1.5
All test equipment shall be approved by the Owner and shall have a standard of accuracy better than the
manufacturer's stated accuracy for the instrument(s) to be tested. All test equipment shall have a valid
calibration certificate from a recognised authority and be suitable for use in a hazardous area (where
appropriate). It is the Vendor's/Contractor's responsibility to ensure that his equipment is suitable for
use within the area of testing.
The test and calibration equipment shall be calibrated in the units of measurement selected for the
project.
3.2.1.6
The cable testing shall be carried out as described in the BS 7671 IEE Wiring Regulation latest Edition
unless specified otherwise in this specification or in the Purchase Order/Contract.
3.2.1.7
The Vendor/Contractor shall obtain approval from the Owner before power or pneumatic supplies are
switched on to any panel or section of plant.
3.2.1.8
The Owner shall be informed immediately of any defects which cannot be rectified or of any instrument
which cannot be calibrated within a reasonable period of time. This notification shall be confirmed in
writing.
3.2.1.9
The approval of the Owner shall be obtained in writing before any non-standard modifications or
adjustments are made.
3.2.1.10
The Vendor/Contractor should take note that certain areas of the plant may be supplied as preassembled units (PAU). These are to be delivered to site completely piped and wired to interface
points. Upon completion of the hook-up of these PAUs the Vendor/Contractor shall complete the loop
GES C.55
Page 9 of 44
Rev 0 1999
On completion of each test, the stage reached in the testing procedure shall be indicted by fixing to
each instrument or installation a coloured label conforming to the following code:Blue
Yellow
Green
Red
White
This identification shall be shown on all components in the loop, thereby making all personnel aware of
the current status of any installation.
3.2.1.12
All instruments that fail under test are to be returned to the project warehouse and the details of the
failure are to be passed to the Owner who will determine the action to be taken.
3.2.1.13
Where the pre-installation test is not specified or where circumstances prohibit the carrying out of the
prescribed test, the Vendor/Contractor shall agree a test method with the Owner. This will apply to
those instruments delivered as an integral part of a PAU, in which case the Vendor/Contractor shall,
upon delivery of PAU, carry out an `inspection upon receipt' to ensure that no physical damage has
occurred during transit from the fabrication yard. This premise will only apply if the loop dossier
prepared by the PAU Fabricator included documentary evidence that the instrument has undergone all
the necessary pre-installation test, pressure test, piping and cable tests.
Should this documentary evidence not be available for any item then the Vendor/Contractor shall carry
out all such tests as part of his scope.
3.2.1.14
Upon completion of pre-commissioning the installation shall be made ready for process commissioning
and all extra work such as setting zero elevations and suppressions, filling liquid seals, adjusting purge
rates, etc. will be completed by the Vendor/Contractor.
3.2.1.15
All test and check results shall be recorded, on the standard forms listed in Section 8 and attached to this
specification. Approval signatures shall be obtained where appropriate.
3.2.1.16
The Vendor/Contractor is responsible for producing Quality Assurance dossier for each installation and
type of material employed. One dossier shall be produced for each loop (or part loop). The content of a
dossier will contain, as a minimum, the following:
Certification documents;
Engineering Data Sheets for all instruments;
Installation Hook-Up Drawings (where relevant);
Check/Test record sheets duly completed for each instrument and the materials used;
Instrument Loop Diagram;
Mark-ups required for any corrective measures to be undertaken by others.
3.2.1.17
All equipment for use in hazardous areas must be tested in accordance with the requirements of BS
5345 or equivalent standards.
3.2.2
Pre-Installation Testing
3.2.2.1
The object of pre-installation testing is to ensure that each instrument and all bulk material has been
supplied in accordance with its specification, is functionally correct and is in working order.
GES C.55
Page 10 of 44
Rev 0 1999
3.2.2.2
All instruments shall, wherever possible, be subjected to pre-installation test and this test shall
commence as soon as practicable after the receipt of the instrument on site. If the equipment is to be
stored for a long period of time then these tests shall be carried out near the date of instrument
installation. The tests shall be performed in the manner described herein, any adjustment being made in
accordance with the manufacturer's instruction.
3.2.2.3
In general all tests shall simulate as closely as possible design process conditions, by the use of
Manometers, Potentiometers, Resistance Bridges, Dead Weight Testers, Test Pressure Gauges, etc.,
utilising hydraulic, electric or pneumatic supplies.
3.2.2.4
No tests shall be carried out on electronic instruments until an adequate warm-up period has elapsed.
Wherever possible, instruments shall be energised for at least 24 hours prior to testing.
3.2.2.5
All shipping stops shall be removed from the instruments before starting the test procedures.
Miscellaneous components, e.g. charts, oil, ink cartridges shall be correctly installed.
3.2.2.6
All instruments, except as noted herein, are to be calibrated in both the upscale and downscale
directions and, if necessary, adjusted until their accuracies are within the limits stated by the
manufacturer. Upon completion the results of each test shall be recorded on the appropriate form,
witnessed by the Owner's representative and the completed forms added to the loop dossier and handed
to the Owner.
3.2.2.7
Upon completion of tests the instrument shall be drained, as a precaution against mixing with dangerous
process fluid and if necessary blown through with dry air. Where applicable, shipping stops shall be
replaced.
3.2.2.8
After testing, all connections and entries shall be temporarily sealed to prevent subsequent ingress of
moisture and dirt.
3.2.2.9
Insulation and continuity tests shall be made on drummed electrical cable prior to use.
3.2.3
3.2.3.1
General:
a)
Instrument testing should preferably be carried out in a calibration workshop, except where
instruments form part of an integrated system or control panel where tests may be carried out in
the control room after installation using portable test gear and/or simulation equipment.
b)
The instrument to be tested should be mounted in the correct plane on a rigid and vibration-free
stand or structure.
c)
Before commencing any tests, the following checks shall be carried out:
-
The instrument shall be checked for damage in any way (e.g. damage to doors, linkages,
etc). Any such damage must be rectified before any tests are attempted;
The data plate on the instrument shall be checked against the information contained on
the instrument specification sheet;
The available power source, whether electric, pneumatic or hydraulic, shall be checked
against what is called for on the instrument specification;
A check shall be carried out to make sure that a suitable means is available for simulating
the required process conditions and that test gauges or meters are available with a
sufficient degree of accuracy for the tests to be performed;
GES C.55
Page 11 of 44
Rev 0 1999
b)
3.2.3.3
Pneumatic
-
Make sure that the air supply to pneumatic instruments is clean, dry and oil free.
Connect the air supply and adjust the air supply regulator to the correct setting e.g. for a
standard transmitter with operating range of 3-15 psig (20 - 100kPag).
Connect the output to a suitable test gauge via a capacity chamber approximately 0.1
gallons (0.5 litre) capacity.
Take care to ensure that all pneumatic connections are leak-free. If in doubt, test joints
with soap solution or similar.
Where instrument air is not available from the normal instrument air supply system, the
Vendor/Contractor shall provide a source of dry air for calibration purpose.
Electronic
-
Electrical supply shall have frequency and stability characteristics equal to the permanent
supply.
Instrument power packs - where the equipment of the final system cannot be used, the
Vendor/Contractor shall provide a direct current (DC) supply of the required voltage and
characteristics.
Care should be observed when connecting electrical power supplies to the electrical and
electronic instrumentation. Checks shall be made to ensure correct voltage and frequency
on AC supplies and where DC is used, check that the voltage regulation and any
suppressed ripple are within instrument manufacturer's specifications. Correct polarity of
supply and proper grounding are crucial to solid state equipment.
Connect the output to a suitable test meter, preferably a Digital Volt Meter, across the
circuit dropping resistor.
GES C.55
Page 12 of 44
Rev 0 1999
Owner.
3.2.4
Pressure Instruments
3.2.4.1
A compressed air source or nitrogen can usually be used for pressure ranges up to 100 psig (700 kPag).
3.2.4.2
Pneumatic calibrators are available with a variety of pressure ranges, but generally are not suitable for
ranges below 60"wg (0-15 kPa).
3.2.4.3
For ranges below 60"wg (15 kPa), liquid filled manometers should be used with a suitable precision air
reducing valve.
3.2.4.4
For pressure ranges above 100 psi (700 kPa) a hydraulic dead weight tester should be used.
3.2.4.5
Hand held pressure pumps may also be used for signal generation for pressures up to 1psi (0.7 kPa).
These are particularly useful where testing is being carried out in the field, e.g. for loop testing.
3.2.5
3.2.5.1
On pre-installation testing DP transmitters, the variable pressure source is normally connected to the
High Pressure Connection and the Low Pressure Connection must be freely vented to the atmosphere.
3.2.5.2
After the initial calibration test, the high and low pressure sides of the meter element shall be subjected,
in turn, to a static pressure equal to the maximum expected working pressure. The calibration test shall
then be repeated to ensure that the results are unaffected by the static pressure loading.
3.2.5.3
Differential pressure transmitters used for fiscal metering and high accuracy metering applications shall
be calibrated at the operating pressure.
3.2.6
3.2.7
Temperature Instruments
3.2.7.1
Filled Systems:
For calibration of thermal systems, a temperature calibration bath equipped with an agitator and a
certified thermometer is required. Several types are generally available, the most common being:Liquid Filled:
Glycol/Water
Water
Oil
Fluidised Bed:
Temperature calibration baths are generally only suitable for use in workshop. If required for use in the
field, they must only be used under cover and in a non-hazardous environment.
3.2.7.2
3.2.7.3
Thermocouple:
GES C.55
Page 13 of 44
Rev 0 1999
Thermocouple emfs are to be normally simulated by the use of a precision milli-volt signal generating
source in conjunction with standard calibration tables.
3.2.8
3.2.9
Level Displacers
External cage displacers are generally tested in situ owing to their physical size but alternatively may be
tested in a test rig or by the suspended weight method. If checked in a test rig the instrument shall be
dried after testing and appropriate preservative applied prior to reinstallation in permanent location.
3.2.9.1
3.2.9.2
3.2.10
b)
Where the instrument ultimate service is other than water, check the manufacturer's instructions
for the method of compensating for the SG at the operating temperature.
c)
Make sure that the vessel isolation valves are completely closed.
d)
Connect a graduated glass or plastic column parallel to the displacer chamber via the bottom drain
connection or gauge tapping.
e)
Make sure that the top of the displacer chamber is freely vented to the atmosphere.
f)
The level can then be varied by injecting water into the chamber. This is usually done by using a
water container and a hand pump connected via the bottom drain connection.
This method involves the substitution of the displacer by calibration weights equal to the resultant
downwards force of the displacer at the required calibration points (refer to the manufacturer's
handbook for method of calculation).
b)
This method is generally used for displacers designed for top of tank mounting or with extra large
float chambers.
c)
In order to use the `weight method' it is necessary to fabricate a test rig in the workshop and to
remove the top section of the instrument containing the float arm, from the displacer caging.
Analysis Instruments
Calibration checks are usually carried out on analysers by injecting known samples into the sample
conditioning systems. This must be decided for each type of analyser by reference to the manufacturer's
handbook or by consultation with the instrument Vendor/Contractor and shall be agreed with the
Owner.
Complex analyser systems usually require specialist personnel from the analyser manufacturer to assist
in pre-calibration and commissioning and are generally outside the scope of the Vendor/Contractor's
responsibility.
GES C.55
Page 14 of 44
Rev 0 1999
3.2.11
Calibration Test
3.2.11.1
This procedure applies to transmitting, receiving and direct reading instruments other than local
pressure gauges, temperature gauges or switches.
3.2.11.2
Where instruments form part of a distributed system and where factory tests have been carried out, the
testing procedure shall be agreed with the Owner.
a)
b)
3.2.12
Calibration Test
-
Raise the process input signal and record the corresponding output signal and/or scale
readings at 0, 25, 75, 100% of the instrument range. The readings must always be taken
when the signal is in a `rising' state.
Lower the process input signal and again record the corresponding output signal and/or
scale reading at 100, 75, 25, 0% of the instrument range. The readings must always be
taken when the signal is in a 'falling' state.
The percentage error calculated from the above tests shall not exceed the
manufacturer's stated limits for accuracy and hysteresis.
After the tests have been completed the instrument shall be identified with a coloured
sticker.
3.2.13
b)
GES C.55
Page 15 of 44
Rev 0 1999
c)
Set Integral or Derivative actions (if fitted) to minimum action (integral to maximum time setting
and derivative to minimum);
d)
Check that the settings of any set point limit stops allow full scale pointer movement;
e)
Adjust the set-point to 50% of scale and set the auto/manual transfer switch to 'Auto';
f)
The controller output should now read 50% i.e. 8 psi (60 kPa) or 12mA or if there is a deviation
scale, it should be at null balance point (centre scale);
g)
Move the set-point upscale and downscale whilst observing the output meter. The output meter
should continuously track (follow) the set point and the deviation pointer should always read null.
Always allow time (say two minutes) at each set-point setting to permit the controller to balance
correctly;
h)
With the controller set-point and output at 50% as described in step 6 above, move the
proportional band setting from minimum to maximum. During this movement, the output or null
balance pointer should remain stationary;
i)
Then change the auto/manual transfer switch to `manual', whence it should be possible to vary the
output manually from 0 to 100% of the output scale;
j)
In the event of the controller performing incorrectly, adjustments should be made in accordance
with the manufacturer's instructions until satisfactory test results are obtained;
k)
After completing the above tests satisfactorily, return the controller action to the correct mode
required for service operation. The controller adjustments should be left with settings of 100%
Proportional Band and minimum Integral and Derivative action;
NOTE : The full calibration checking of Proportional, Integral or Derivative functions is not
normally required but the Owner reserves the right to request the checking of these functions in
accordance with the manufacturer's instructions.
3.2.14
3.2.14.1
For controllers connected directly to the process, it is necessary to simulate the process variable as
described under 3.2.3.3.
3.2.14.2
A suitable power supply shall be connected and in the case of pneumatic controllers a capacity chamber
0.1 gallons (0.5 litre) shall be connected to the output to give the system stability.
3.2.14.3
An output gauge must also be provided if one does not already exist on the controller.
3.2.14.4
3.2.14.5
Controller Alignment:
a)
Set the controller action to 'direct' and the auto/manual transfer switch to 'Auto'.
b)
c)
Adjust the Integral or Derivative settings (if fitted) to minimum action. (Integral to maximum time
setting and derivative to minimum).
d)
e)
Increase the process variable to mid-scale at which point the controller output should change from
GES C.55
Page 16 of 44
Rev 0 1999
minimum to maximum.
3.2.14.6
f)
If this does not occur, make adjustment in accordance with the manufacturer's instructions.
g)
When correct changeover occurs, reverse the controller action and re-check the operation to
ensure that the controller is correctly aligned.
h)
Controller Synchronisation:
a)
Having checked the alignment as above in 3.2.14.5, set the controller action to the required mode
for operation, and set the Proportional band to 100%.
b)
c)
The controller is normally synchronised at 50% of the output range e.g. 8 psi (60 kPa) or 12 mA
and should therefore indicate mid output range when the set-point and the process variable are at
mid-scale.
d)
With the controller set up at mid-scale as above, adjust the Proportional Band setting from
minimum to maximum, during which the output pointer should remain stationary.
e)
In the event of the controller performing incorrectly, adjustments should be made in accordance
with the manufacturer's instructions and the tests repeated.
f)
Change the auto/manual transfer switch to 'manual', whence it should be possible to vary the
output manually from 0 to 100% of the output scale.
g)
After completing the above tests satisfactorily, return the controller action to the correct mode
required for service operation. The controller adjustment should be left with settings of 100%
Proportional Band and minimum Integral and Derivative action.
NOTE : The full calibration checking of Proportional, Integral or Derivative functions is not normally
required but the Owner reserves the right to request the checking of these functions in accordance with
the manufacturer's instructions.
3.2.15
Pressure Gauges
3.2.15.1
3.2.15.2
The Gauge Comparator should be firmly fixed to a bench. A test gauge of range comparable to the
gauge under test is fitted to one branch of the comparator. The gauge to be tested is fitted to the other
branch and the hand pump on the comparator operated in order to check the gauge against the readings
of the test gauge.
Readings shall be checked for pressures corresponding to 0, 50 and 100% of the range of the gauge
under test.
Actual gauge readings shall be noted for both rising and falling signals.
3.2.15.3
Test gauges shall have an accuracy of or better than 0.25% of full scale and shall be periodically
checked (12 months maximum) for accuracy against a dead-weight tester.
3.2.16
Pressure Switches
3.2.16.1
Pressure switches shall be tested at their operating point using either a compressed air source or a dead-
GES C.55
Page 17 of 44
Rev 0 1999
weight tester depending upon the range of the switch under test. A continuity test-circuit shall be
connected across the contacts to ensure correct operation.
3.2.16.2
Care should be taken to ensure that the switch operation is in the correct mode, i.e. with a rising or
falling signal according to the instrument specification.
3.2.16.3
Where the switching differential is stated in the specification, this shall also be checked.
3.2.17
3.2.17.1
Local temperature indicators (dial thermometers) shall be checked using a temperature bath as described
in 3.2.7.1.
3.2.17.2
They shall normally be checked at approximately 50% of the range unless agreed otherwise with the
Owner.
3.2.18
Temperature Switches
3.2.18.1
Temperature switches shall be tested at their operating point using a temperature bath as described in
Section 3.2.7.1. A continuity test-circuit shall be connected across the contacts to ensure correct
operation.
3.2.18.2
Care shall be taken to ensure that the switch operation is in the correct mode, i.e. with a rising or falling
signal according to the instrument specification.
3.2.18.3
Where the switching differential is stated on the specification this shall also be checked.
3.2.19
Level Switches
Float switches shall be tested mechanically prior to installation with a continuity test-circuit connected
across the contacts to ensure correct operation. Care shall be taken to ensure that the switch operation
mode is correct.
3.2.20
Solenoid Valves
3.2.20.1
3.2.20.2
3.2.20.3
Check the operation of the valve by operating the switch and observing correct changeover action.
3.2.20.4
Check the tightness of shut-off by connecting a flexible tube to the outlet port or ports and immersing
the free end in water to ensure that the valve closure is bubble-tight at the stated design pressure.
3.2.20.5
Check, where applicable, time to activate, electrical and manual reset, override and time delay features
as called for in the valve specification.
3.2.20.6
3.2.21
Flow Elements
3.2.21.1
Flow elements, e.g. orifice plates, venturis, V/A meters, turbine meters, etc., shall not be installed until
line flushing has been completed.
3.2.21.2
Manufacturers' test certificates shall normally be accepted for flow elements which cannot usually be
tested in the field including turbine meters and magnetic flow meters. Omission of tests shall be agreed
GES C.55
Page 18 of 44
Rev 0 1999
Before installation the flow element should be checked to ensure that the data and material specification
stamped on the data plate or tab handle agree with the specification.
3.2.21.4
After installation turbine meters shall be tested regularly, preferably in the medium they usually carry. If
used on custody transfer application they must be regularly and frequently checked by the meter prover.
Electromagnetic flowmeters do not, as a rule, require testing unless suspected of being faultly. If so,
electodes should be checked for cleanliness. Electronics can be checked in the lab if suitable test
equipment is available. Alternatively, exchange for new to see if the problem is rectified.
Orifice plates shall be regularly checked for flatness and quality of profile. Sharp edged plates shall
have a sharp upstream edge that is free from cuts. Only if there is any suggestion that the bore may have
changed must it be checked with Vernier callipers; if a change has occured, the cause must be
determined and eliminated before a new plate is installed.
3.2.21.5
3.2.22
Control Valves
3.2.22.1
General:
a)
These tests may be carried out in the instrument workshop or, as is more often the case, in situ
after the valve has been installed in the line. Tests should preferably not be carried out until the
valve is in its final operating state, i.e. after line flushing operations have been completed.
NOTE : Where circumstances dictate that line flushing and hydrostatic testing have to occur with
the valve in situ, the valve packing must be checked and replaced if damaged.
3.2.22.2
b)
Check that the valve and data plate agree with the control valve specification.
c)
Check that, where specified, a lubricator is fitted and that it is charged with the correct lubricant.
d)
Note the dry operating range (bench-set) of the diaphragm actuator from its data plate or
specification sheet. Do not use an additional positioner with the valve.
b)
Connect a suitable regulated air supply together with an accurate test gauge to the diaphragm case
connection.
c)
Increase the air pressure to load the diaphragm and check the valve spindle position from the valve
stem position indicator. The travel should be checked at the following positions: 0, 25, 75, 100%
of the valve stroke.
d)
Where necessary, adjust the valve spring tension nut to obtain the correct start point and re-test.
e)
Where necessary, check that the speed of operation from fully open to fully closed is within the
limits stated on the specification sheet.
f)
When requested by the Owner, the hysteresis shall be checked by using a micrometer dial
indicator clamped to the valve stem and repeating the travel test with rising and falling signals at
0, 25, 75, or 100% of valve stroke. The hysteresis should be within + 5% of the valve stroke
GES C.55
Page 19 of 44
Rev 0 1999
When tight shut-off is an important criterion, a test rig must be fabricated comprising a blind
flange on the valve outlet fitted with a 0.25" (6mm) bleed pipe and a suitable rated isolation valve
from the centre of the flange. The open end of the bleed pipe shall be immersed in a container of
water so that discharge bubbles can be observed. The valve inlet shall be connected to a source of
pressure equal to the valve shut-off pressure.
The specified signal corresponding to the valve closed position under normal operating conditions
shall be applied to the valve actuator and, if necessary, adjustments made to the valve until the
leakage bubble-rate is within the specified tolerance.
h)
3.2.22.3
Where an air failure lock-up relay or other accessory device is incorporated, it shall be checked for
correct operation (on air failure) in accordance with the instrument specification.
Note the dry operating range (bench-set) of the diaphragm actuator from its data plate or
specification sheet, i.e. bench-set of actuator irrespective of positioner.
b)
c)
Where the positioner is fitted with a bypass valve (normally omitted on split-range service), switch
the valve to the `bypass' position and connect a variable air supply with test gauge to the signal
input connection.
d)
Where no positioner bypass is fitted, disconnect the air connection from the actuator case and
connect in the variable air supply with test gauge direct to the diaphragm head.
e)
The actuator must then be checked for travel, independent from the positioner, with rising and
falling signals at 0, 25, 75 and 100% of valve stroke.
f)
Where necessary, check that the speed of operation, from fully open to fully closed, is within the
limits stated on the specification sheet.
g)
After checking the valve stroke without the positioner, the stroke shall be checked with the
positioner in service. Connect an air supply to the positioner 'supply' connection and adjust to
6psig (42kPag) above the maximum operating range of the actuator.
Switch the positioner bypass valve to the `on' position. If no bypass is fitted, reconnect the
positioner output to the actuator and connect the variable air supply to the positioner signal
connection.
If necessary, adjust in accordance with the manufacturer's instructions and then re-test.
h)
3.2.22.4
If required, hysteresis, tight shut-off and air failure tests shall be carried out.
Other Actuators:
a)
Control valves with other types of actuators, e.g. piston operators, air cylinder operators,
electro/hydraulic or electric motor operators, shall be tested for stroking and failure action in
accordance with the manufacturer's instructions. Tests shall be carried out using correct pressures.
b)
Where limit switches or torque switches are fitted these shall be checked using a continuity test
set, for correctness of setting and for operation. On motorised valves, care shall be taken to check
GES C.55
Page 20 of 44
Rev 0 1999
the setting of the limit switches before putting power on to the actuator.
3.2.23
3.2.23.1
General:
a)
The testing of safety relief valves shall be carried out by qualified personnel and the following
tests are given as a guidance when within the Vendor/Contractor's scope. All test methods must
be agreed with the Owner before being put into operation.
b)
The following standard is applicable to this procedure:API Standard 527 - Seat Tightness of Pressure Relief Valves
3.2.23.2
c)
It is important that Safety Relief Valves are stored in a secure warehouse with the valves standing
vertically. When received, the valve blanking plates should be checked for damage which could
have allowed the passage of foreign material into the inlet nozzle and the body cavity.
d)
If Safety Relief Valves are shipped without test-gags in place, then it will be necessary to strip
down every valve to ensure that there has been no damage on seats or discs during transit and to
remove any loose material.
Test Rig:
a)
Safety relief valves are normally tested in a workshop which shall be equipped with a suitable test
rig.
The test rig design shall be such that there is no possibility of the formation of rust or scale which
could be blown through into the valve under test. A suitable nozzle with gaskets, adaptor flanges
and bolts or clips shall be incorporated so that the relief valve under test may be mounted rigidly
in a vertical position.
b)
Compressed air is preferred as a test fluid but bottled inert gas may be used if air is not available at
the required pressure. The test fluid should be filtered to ensure that no particles of foreign matter
are passed through into the valve under test.
c)
If a test gas other than air is used, the test rig must be installed in a freely ventilated location.
d)
For High Pressure duties, hydrostatic testing may be required using a purpose built test rig which
should be operated in accordance with the manufacturer's instructions. On hydrostatic test rigs, all
piping and fittings in contact with water shall be of stainless steel.
e)
To control the test pressure, a precision reducing valve and test pressure gauge (minimum 150mm
diameter) with recitable maximum pointer shall be provided on the inlet side. The reducing valve
and gauge ranges shall be selected to cover the range of relief valve set pressures to be tested.
f)
The outlet flange of the relief valve shall be provided with a suitable mating flange or clamp-on
cover plate which shall be fitted to the valve only when the seat leakage test is carried out. This
flange shall incorporate the following:
-
a safety plug to prevent the downstream side of the relief valve from becoming over
pressurised in the event of inadvertent popping of the relief valve. The safety plug shall
be designed to blow at, say 3 psig (20 kPag).
NOTE : The bleed pipe and safety plug may be combined into one item by inserting the
GES C.55
Page 21 of 44
Rev 0 1999
3.2.23.4
3.2.23.5
Test Procedure:
a)
Safety relief valves shall be tested immediately prior to installation. If installation is deferred, the
protective flange covers shall be refitted and the valve stored in a vertical position. When required
for service the valve must be re-tested.
b)
All tests on safety relief valves shall be recorded on the test sheet and the signatures of witnesses
shall be obtained as required.
c)
Before popping the relief valve the outlet flange shall be removed.
b)
c)
The relief valve "cold set pressure" shall be ascertained and entered on the test record sheet. This
pressure should be found on the valve data plate or on the valve data sheet.
d)
The test pressure shall be increased slowly until the relief valve is observed to pop and the
pressure (as indicated by the `maximum' pointer on the test gauge) shall be noted on the test record
sheet. If the difference between the measured popping pressure and the cold set pressure is outside
acceptable tolerances, the valve setting shall be adjusted in accordance with the manufacturer's
instructions.
e)
The test pressure shall then be lowered and the reseating pressure noted and checked that it agrees
with the relief valve manufacturer's data.
Immediately after the popping test as described in Section 3.2.23.4, the test pressure shall be
lowered and held at 10% below the set pressure or 5 psig (35 kPag) minimum for the duration
specified in API 527.
b)
The outlet flange shall be refitted complete with safety plug and the open end of the bleed pipe
shall be immersed in water to a depth of 0.5" (13mm) below the surface. The leakage rate in
bubbles per minute will then be checked in accordance with API 527.
c)
Failure of the leakage test shall be corrected by dismantling the valve and lapping the disc and seat
in accordance with the manufacturer's instructions.
d)
After testing, the valve shall be identified by a suitably coloured sticker, see Section 3.2.1.12.
NOTE : During testing to API 527 using the cup method, it is possible for air leakage to occur
around the top bonnet flange, the outlet flange made off for the test and the cap. These should be
soap tested during the test to prove that there is no leakage. Alternatively, a flooded seat test
should be nominated for valves having discharge flanges greater than 2" (50mm) and, after such a
GES C.55
Page 22 of 44
Rev 0 1999
test, the body cavity shall be thoroughly dried with instrument air.
3.2.24
3.2.24.1
This typical procedure (Vendor/Contractor's actual procedure must be followed) assumes that the probe
requiring check is installed on the machine and powered up.
a)
=
=
=
b)
c)
Connect a digital voltmeter (D.V.M) (selected to measure D.C voltage) to the common and
negative signal connections on the proximeter without disconnecting the circuit.
d)
Remove the vibration probe from its permanent position and mount on horizontal mounting on the
wobulator (rotating tilted table).
e)
f)
The indication on the D.V.M. will now read -21 volts or above.
g)
Mount the micrometer on the wobulator, ensuring that the correct target is on the micrometer (the
target should be of the same material as the machine shaft that is to be monitored).
h)
Before clamping move the micrometer (and thus the target) towards the probe gently until the
target just touches the probe.
i)
j)
k)
The micrometer is now backed off by 0.1mm and reading taken from the D.V.M. This process is
repeated until a complete set of figures are obtained (the final plot should be when a reading of 16 volts is indicated).
l)
m)
The vibration probe will be used in the range -7 to -11 volts so the nearest readings to -7 volts on
the D.V.M. are plotted. The same applies for the -11 value.
n)
The span is calculated by subtracting these values the resultant different i.e. the span in mm is
divided by 25.4 to convert to imperial measurement. This figure is now thousands of an inch.
o)
The span figure in imperial can now be divided into the recorder span volts, this should give a
value of 200mv/0.001".
p)
q)
If the probe is measuring radial vibration replace the probe to its permanent position and adjust the
gap to -9 volts.
r)
Axial probes will require the shafts to be centralised and then gap set to -9 volts.
GES C.55
Page 23 of 44
Rev 0 1999
3.2.25
3.2.25.1
Microprocessor based control systems are not covered by this procedure except in so far as the tests
detailed can be applied to components of a system.
3.2.25.2
On site check-out and pre-commissioning should usually be carried out by specialist personnel from the
equipment vendor or alternatively by reference to the manufacturer's instructions.
3.2.25.3
Nevertheless, the basic requirement remains that every input and output signal must be checked through
from its field initiation point to control room display unit or vice versa. All control and logic functions
must be checked for operability in accordance with the manufacturer's stated performance
characteristics.
3.2.25.4
All checks must be recorded on loop tests sheets and included in the appropriate loop dossier.
3.2.25.5
3.2.25.6
3.2.26
3.3
Pressure Testing
3.3.1
General
3.3.1.1
The object of this phase of the testing procedure is to ensure that all instrument piping and tubing is
pressure tight to the specified working/testing conditions.
3.3.1.2
The pressure testing of any site fabricated equipment, i.e. cooling chambers, capacity pots, catch pots,
etc., shall be witnessed by the Owner unless this has been waived, in which case test certificates must be
submitted.
3.3.1.3
Under no case shall any instrument, other than control valves and thermowells, be subject to test
pressures.
3.3.1.4
Prior to testing and cleaning all lines shall be disconnected from the instrument and blocked off. Before
and after testing, all lines shall be flushed and blown down with water or air (as appropriate) to remove
all contamination.
3.3.1.5
The instrument piping and tubing to be tested can be classified in the following categories:
a)
b)
c)
The pressure testing of air supply piping, transmission tubing and process impulse pipework on a given
loop shall be completed before the final loop testing. Thus, if the transmitter has to be disconnected for
loop testing, only one connection has to be re-checked.
GES C.55
Page 24 of 44
Rev 0 1999
3.3.2
3.3.2.1
The main instrument air header from the source up to and including the first isolation, i.e. branch shut
off valves usually on the pipe track, will be tested by others unless otherwise specified.
The following tests assume that the instrument air compressors and dryers have been commissioned and
an instrument air supply established at the specified working conditions, i.e. clean, dry and oil free.
3.3.2.2
Branch air lines to individual instruments shall be disconnected immediately upstream of, and adjacent
to, the instrument air filter regulator and blown through with clean air, until clear of all foreign
materials.
3.3.2.3
The open end(s) shall be blanked off and a suitable test pressure gauge connected into the system.
3.3.2.4
The isolation valve immediately upstream of the piping to be tested should be opened and, when the line
is pressurised, the valve is closed. This test shall have a duration of 10 minutes and the test gauge shall
be observed in order to detect leakage. In addition all joints shall be checked by the application of soap
solution or similar and leaking joints remade as necessary.
3.3.2.5
On completion of the test, the line shall be reconnected and the joint(s) not previously proven checked
with soap solution or similar.
3.3.2.6
The pipe shall then be identified by a suitably coloured sticker as stated in Section 3.2.1.12.
3.3.2.7
If a permanent air supply has not been established prior to these tests, an alternative source of clean, oilfree, dry air or nitrogen from either storage cylinders or an oil-free compressor with dryer shall be used.
3.3.3
Transmission Tubing
3.3.3.1
Each individual tube shall be disconnected at both ends and blown through with clean, oil-free, dry air.
3.3.3.2
The tubes shall then be blanked off and pressurised to 20 psig (137 kPag) from an existing air supply,
via a pneumerstat or bubble bottle. After pressurising, the bubble rate shall be less than one bubble in
10 seconds. If an air supply is not readily available, the tubes may be pressurised using a foot pump and
with a manometer teed into the system. With the pressure source isolated the reading shall not fall.
3.3.3.3
The tube shall then be reconnected and, when an air supply is established, the joints not proven shall be
tested with soap solution. This may be achieved by setting the transmitter/controller outputs to
maximum.
3.3.3.4
3.3.3.5
The tubing shall then be identified by a suitably coloured sticker as stated in Section 3.2.1.12.
3.3.4
3.3.4.1
After fabrication, process impulse piping shall, where practical, be disconnected at both ends for
flushing and testing.
3.3.4.2
After flushing the line with water, one end shall be blanked off and the other shall be connected to a
hydraulic pump with a suitable test gauge fitted. The line shall then be pressurised to 1 times the
maximum working pressure (corrected for temperature) or the test pressure of the associated process
line or vessel, whichever is the greater. The line shall then be isolated from the pressure source and the
pressure must not fall.
GES C.55
Page 25 of 44
Rev 0 1999
3.3.4.3
After testing, the lines shall be blown dry and reconnected to the instrument manifold and all manifold
valves shall be checked for tight shut-off.
3.3.4.4
For close coupled instruments, e.g. line mounted d/p cells, the pipes shall be disconnected at the
instrument only and tested as per Sections 3.3.4.1, 3.3.4.2 and 3.3.4.3 up to the initial isolation.
3.3.4.5
During hydraulic tests on the main process lines, instruments must be disconnected to ensure that initial
isolation are leak proof. During flushing, it is the Instrument Tester's responsibility to ensure that all
installed instruments are suitably and positively isolated from the process line. Instruments fitted with
manifolds must have their bypass valve open.
3.3.4.6
The Instrument Tester must ensure that all instrument pressure tappings have been drilled through the
pipe wall.
3.3.4.7
All instrument equipment and piping hydro-statically tested with water shall be thoroughly dried out on
completion of the test.
3.3.4.8
No pressure tests shall be carried out on the process impulse piping or hydraulic lines unless these are
authorised by the Owner in writing.
3.4
3.4.1
3.4.1.1
Immediately after cables are laid and before any connection* all thermocouple, electric and electronic
instrument wiring shall be checked for polarity, continuity and insulation resistance between conductors
and between conductors to earth. These tests MUST be carried out before final loop tests.
*WARNING - Severe damage may be caused to barriers and electronic equipment if inadvertent
meggering of cables is carried out after connection.
Continuity and insulation resistance checks shall be carried out using the proper test equipment to
comply with the requirements of BS 7671 (IEE Requirements for Electrical Installations), or the rules
and regulation with which the installation has to comply.
3.4.1.2
3.4.1.3
Other tests on IS circuits (e.g. for loop impedance, inductance, L/R ratio, etc), shall be carried out,
where required, by agreement with the Owner.
3.4.1.4
The cables shall then be identified by a suitably coloured label as stated in Section 3.2.1.12.
3.4.2
GES C.55
Page 26 of 44
Rev 0 1999
3.5
Loop Testing
3.5.1
General
3.5.1.1
The object of loop testing is to ensure that all instrumentation components in a loop are correctly
calibrated and are in a state ready for plant commissioning.
3.5.1.2
The procedures to be adopted in carrying out these tests is detailed below, but in general the completed
instrument loop shall be tested as one system and, where necessary, adjustments shall be made to ensure
that the loop is fully operational as a system and is correctly calibrated. All associated alarms, trips and
indicators shall be checked during loop testing.
3.5.1.3
Those loops of which part is located on a process package unit shall be tested in their entirety; i.e. the
total loop shall be functionally tested including those items located on the process package units.
3.5.1.4
3.5.1.5
Loop testing of remote control loops is a two-man operation, one man in the field and one man in the
control room. These men must be provided with adequate means of remote communication, i.e. field
telephones or two-way radios, as approved by the Owner.
3.5.1.6
During loop testing, the Vendor/Contractor's electrical section representative shall normally be in
attendance to check his inter-related sections of work during trip and alarm checks. The instrument
tester will request his attendance giving adequate notice.
3.5.1.7
Loop testing shall not be carried out on electronic equipment until an adequate warm-up period has
elapsed. Where possible instruments shall be energised for at least 24 hours prior to testing.
3.5.1.8
In all instances, the Owner's representative will witness the final loop tests and countersign the test
certificates. The Owner shall be given adequate notice of final tests so that the necessary witnesses may
be made available.
3.5.1.9
Upon completion, a test certificate for every installation recording all results, shall be handed to the
Owner. The certificates for any tests not witnessed shall be accompanied by the Owner's written
confirmation that witnessing has been waived.
3.5.1.10
On completion of loop testing all controllers shall be left with CORRECT ACTION and with 100%
Proportional Band setting. Derivative and Integral functions shall be set at minimum action.
3.5.1.11
Before commencement of tests, inspect the loop, setting air/electrical supplies where appropriate.
Check in particular that control valves air supply pressures are set in accordance with the
specification.
3.5.1.12
For electronic loops check polarities, measure the loop impedance and make the necessary
compensating adjustments. Ensure the loop impedance tester is of a type that will not damage a field
connected instrument.
3.5.1.13
Manually or by simulated process input signals instrument output signals equivalent to at least 0, 50 and
100% of the instrument range shall be generated, both rising and falling, to check the response of all
other instruments and control valves in the loop.
3.5.1.14
No electronic loop shall be powered until proof of continuity and insulation tests having been
successfully completed is available.
GES C.55
Page 27 of 44
Rev 0 1999
3.5.1.15
3.5.1.16
For special notes on electrical temperature instruments see Sections 3.2.7 and 3.5.3.
3.5.2
3.5.2.1
Switch the controller to manual operation and by applying the appropriate signals ensure that the control
valve or valves stroke correctly. Valve positioner gauges shall also be checked during this stage.
3.5.2.2
Apply an actuating signal to the controller equivalent to 50% of the instrument range and adjust the
manual regulator output to 50%. Adjust the controller set-point to 50% and, by switching the
auto/manual transfer switch, check for `bumpless' transfer. Using the manufacturer's instructions, adjust
where necessary until satisfactory `bumpless' transfer is achieved.
3.5.2.3
Check alarm and trip actions by varying the actuating signals and adjust as necessary.
3.5.2.4
Where interlock inputs have already been proven during measurement and control loop tests, these
inputs shall be by-passed. All other inputs shall be proven. The complete interlock system shall then be
checked for correct sequence of operation, and all output devices shall be shown to work satisfactorily.
3.5.2.5
Where a part of the plant has been classified as a hazardous area caution is necessary if final loop
testing is performed after the introduction of hydrocarbons, or other potentially hazardous material into
the plant. Such tests shall be under the direct supervision of the Owner under the Work Permit system.
3.5.2.6
The appropriate national codes and local regulations shall be followed where a flameproof or explosionproof or safety purged enclosure needs to be opened to simulate operation. This normally involves a
periodic gas test in the area. Note that, in any case, power should be switched off prior to removing and
replacing enclosure covers.
3.5.2.7
Where intrinsically safe circuits are used at field sensors, no restriction is normally encountered,
providing test equipment does not infringe intrinsic safety certification.
3.5.2.8
Locally mounted controller or transmitting only loops shall be tested in a similar manner to that
specified above omitting transmitter and/or auto/manual checks as necessary.
3.5.2.9
After each loop is satisfactorily tested, the controller shall be switched to manual and identified by a
suitably coloured sticker as specified in Section 3.2.1.12.
3.5.3
3.5.3.1
Thermocouples and resistance thermometers shall be removed from their wells and checked for damage.
The resistance of each resistance thermometer shall be measured at ambient temperature and resistance
and temperature noted.
3.5.3.2
3.5.3.3
To assist in the identification of thermocouple compensating cable conductors, the following guide is
given:
a)
For compensating cables having insulation colour coded to British Standard BS 1843 : 1987, the
negative wire is always coloured BLUE.
b)
GES C.55
Page 28 of 44
Rev 0 1999
3.5.3.4
For galvanometer deflection type installations using thermocouples, compensating lead resistances shall
be adjusted.
3.5.3.5
Where a two-wire resistance thermometer system is employed, 'make up' resistances shall be adjusted.
3.5.3.6
For three and four-wire resistance thermometer installations, extra care must be taken to ensure the
correct connections.
3.5.3.7
3.5.4
3.5.4.1
Analytical and Special Installation shall be checked according to manufacturer's instructions and/or by
agreement with the Owner (see also Section 3.2.10).
3.5.4.2
Trips and alarms not previously covered in the loop tests, e.g. initiating devices which stop/start pumps,
etc. shall be checked in conjunction with the Owner. (See Section 3.5.1.2).
3.5.4.3
All systems shall be checked for 'fail safe' operation which will include the checking of 'burn out'
features on thermocouple installations.
3.6
Test Equipment
3.6.1
General
The following is a list of typical test or calibration equipment which may be required by a
Vendor/Contractor for on-site Instrument testing and Pre-commissioning and loop testing.
The test and calibration equipment shall be calibrated in the units of measurement selected for the
project.
All test equipment shall be approved by the Owner.
3.6.2
Low Pressure, Hand-Held Pressure Pump (ranges up to 14.8 psi (100 kPa)).
Liquid filled Manometer (for ranges below 1.45 psi (10 kPa)).
Precision Sealed Mercury Manometer (ranges up to approx. 14.5 psi (100 kPa)).
3.6.3
GES C.55
Page 29 of 44
Rev 0 1999
NOTE: All test instruments to be provided with test leads complete with test probes, clips and
distribution terminals.
3.6.4
Digital voltmeters (DVM) with an accuracy of +/- 0.1% of range or better and with a
discrimination of 10v or better and incorporating an internal calibration/standardising feature and
0.1% calibration resistors.
Portable Multimeter.
Dual-Beam Oscilloscope.
Client approved portable radio transmitter/receiver sets for loop testing. These should be certified
intrinsically safe if they are to be used during plant start-up and they should not conflict with the
plant radio system.
Portable IBM compatible PC with protocol test software loaded for testing serial links.
NOTE: Test certificates shall be provided showing when the test equipment was last calibrated.
Calibration should have been within the previous three months.
3.7
3.7.1
Brackets and supports supplied by the Vendor/Contractor and other materials not already protected in an
approved way shall be primed and painted in accordance with GES X.06, with the exception of
GES C.55
Page 30 of 44
Rev 0 1999
instrument stainless steel boxes, compression fittings and tubing which shall not be painted.
3.7.2
Where supporting steelwork or cable trays are cut or drilled, the exposed surfaces shall be primed and
painted in accordance with the painting specifications to the satisfaction of the Owner.
4.0
INSTRUMENT INSTALLATIONS
4.1
General
4.1.1
The Vendor/Contractor shall carry out the Contract work in accordance with the contract documentation
and this Specification. including the completion and obtaining of approval signatures for all the
General Forms, Calibration and Test certificates of Installation Checklist and Acceptance forms listed in
Section 8.0 of this specification.
4.1.2
The Vendor/Contractor is expected to handover a fully operable system and any defects in the design,
omissions or discrepancies found which would impede the achievement shall be brought to the Owner's
attention without delay.
4.1.3
The Vendor/Contractor may or may not be responsible for the purchase of bulk items such as tubing,
pipe, instrument isolation valves, air filter regulators in accordance with the Scope of Work
documentation issued by the Owner.
The Vendor/Contractor is to provide and install all items such as channel, clips, supports, clamps,
brackets, stands, sunshades as well as all necessary welding, painting, wiring, junction boxes, tubing,
fittings etc., that are required to complete the installation and connection of instruments as there are
acquired from the suppliers, Any further items to be supplied by the Vendor/Contractor e.g. 3 way
manifolds, airsets will be clearly marked on the material take-off Instrument Schedule (Index).
4.1.4
The Vendor/Contractor shall include for a project status reporting system. At least one report shall be
provided per week. The report shall be generated using a database format to be agreed and a hard copy
and a floppy diskette transfer shall be required. The report shall list all the items covered under the
Scope of Work on the vertical side and the following activities on the horizontal side:
-
Receiving;
Calibration;
Installation - Process hook-up;
Pressure tested;
Electronic hook-up to instrument;
Conduit run;
Cable run/wire connected;
Panel Connection;
Power Supply Connection;
Pneumatic Air Supply;
Tubing Connected;
Tested;
Documentation complete;
Commissioning;
Loop Check;
Start-Up;
Comments/remarks.
4.1.5
In order to avoid damaging the instrument or degrade its accuracy, all in-line devices including control
valves but except thermowells shall be removed when the piping is being flushed, cleaned or pressure
tested. The device shall be replaced by a spool piece during the tests.
4.1.6
Air header supply piping shall be part of the Vendor/Contractor's scope of work.
GES C.55
Page 31 of 44
Rev 0 1999
4.1.7
When accepting deliveries, the Vendor/Contractor shall inspect the equipment and materials against the
Instrument Index, Specifications and Purchase Order/Contract to ensure that quantity, type, ranges etc,
are as specified. By receipt of the delivered supplies the Vendor/Contractor shall be deemed to have
acknowledged that all equipment and materials are complete and satisfactory in every respect. Any
damage shall be notified in writing using the Damage/Fault Report Form (Section 8.1) to the Owner for
immediate action.
4.1.8
The Vendor/Contractor may also be responsible for safe storage of the instruments and materials. The
Vendor/Contractor shall report any defects or shortages immediately to the Owner. Equipment
damaged or broken subsequent to issue and prior to final acceptance, in terms of the contract, shall be
re-issued by the Owner and fitted by the Vendor/Contractor. All the costs of such replacements shall be
borne by the Vendor/Contractor.
4.1.9
If the Vendor/Contractor is required to store the received instruments and control systems, then he shall
provide adequate storage space whilst indoors, secure, protected from unauthorised tampering, free
from fire hazard and clean and dry.
4.1.10
All instruments, wherever possible, shall be kept in their original shipping cartons until these are
installed. To avoid damage to the instruments, separate storage space shall be maintained apart from
areas in which large items and equipment are stored.
4.1.11
All electronic equipment shall be kept in an air conditioned store. The contractor shall discuss the need
for a bonded store.
4.1.12
Where instruments are taken from the stores temporarily, e.g. for pre-installation testing, they shall be
returned and stored in this original packing.
4.1.13
If the Vendor/Contractor is responsible for storing all instrumentation and control systems, it shall be
the Vendor/Contractor's responsibility to issue all stored equipment prior to the installation. The
Vendor/Contractor shall maintain accurate records showing equipment and material received, stored,
issued and installed.
4.1.14
Special tools shall be handed over to the Instrument Engineer in the Construction Team,
4.2
4.2.1
The Vendor/Contractor is expected and required to comply in detail with the documentation and
drawings issued by the Owner.
4.2.2
Where the Vendor/Contractor feels that slight deviations, slight modifications or slight additions
improve the design, or expedite his work, he may bring these to the attention of the Owner. However,
any such modifications, exceptions deviations or additions must be agreed and confirmed in writing and
approved by the Owner prior to commencing the work. If such modifications affect price, any price
alterations must also be agreed in writing prior to commencing the work.
4.2.3
The Vendor/Contractor shall keep a record of all agreed changes and shall, immediately following
completion, provide `As-Built' copies of the drawings showing the implementation of the agreed
alteration.
4.2.4
The Vendor/Contractor shall be responsible for correcting free of charge any part of the installation
which is found not to be in accordance with the Owner's documentation (except for a previously
identified agreed and documented deviation Sections 4.2.2 and 4.2.3 above). The Vendor/Contractor
shall also replace at his cost any materials necessary to complete such corrective work.
4.2.5
The Vendor/Contractor shall also be responsible for obtaining material certificates, letters of
conformity, hazardous area certificates and where appropriate detail drawings for submission to the
GES C.55
Page 32 of 44
Rev 0 1999
4.3.1
Each instrument or item of equipment to be installed shall be inspected to check that its data plate and
other details (especially the pressure rating) agrees with the specification and, where appropriate, that is
has been pre-calibrated. The instrument shall then be installed in the correct orientation in its intended
location on brackets, a sub-panel, mounting post or pedestal ensuring that it is levelled, plumbed and
firmly secured.
4.3.2
Instruments shall not be installed until heavy duty mechanical work adjacent to their installation has
been completed.
4.3.3
The installation of instruments which are mounted in-line or direct to a vessel nozzle and which will be
mechanically installed by others, shall be supervised by the Vendor/Contractor's instrument personnel
where necessary and checked for correct installation.
These items typically include the following:
Orifice plates;
Control valves;
Relief valves;
Bursting discs;
In-line flowmeters (PD meters, VA meters, etc);
Level displacers;
Special analyser probes;
Thermowells;
Level gauge glasses;
Level switches.
NOTE: The Vendor/Contractor will retain responsibility for the correctness of the above installation
and shall ensure that suitable flushing or cleaning has been carried out prior to installation.
4.3.4
The installation of fire and gas detectors especially those in ducts and voids and the extinguishant
system will be supervised by the Owner.
4.3.5
Where necessary, instruments shall be secured to the nearest suitable firm steelwork so as to be, as far
possible, unaffected by vibration. Process lines or handrails shall not be used for supporting
instruments, unless specifically allowed by project documentation.
4.3.6
Welding or drilling of any structural steelwork, piping equipment or vessel for the purpose of mainly or
supporting items of instrumentation shall be done only after the Vendor/Contractor has obtained
acceptance from the Owner. Drilling of vessels is normally prohibited in any event.
4.3.7
Instruments shall be located so that they do not obstruct access or walkways and so that they are
protected from damage by passing or falling objects and clear of venting and drainage points of
condensate, water and process fluids from adjacent plant equipment. They shall be located away from
potential fire risk and spillage areas and sources of vibration. The location of instrumentation, impulse
pipe runs, vents, drains, cable trays, etc, shall not cause a hazard to either personnel or equipment.
4.3.8
Where welds are allowed, these shall be ground smooth, prepared and painted in accordance with the
painting specifications used on the project to match support or stand prior to the installation of tubing
tray or instrument.
4.3.9
Supports and stands shall be fabricated so that these do not become a trough or trap for spilled liquids.
They shall be painted by the Vendor/Contractor to match the supporting structure.
GES C.55
Page 33 of 44
Rev 0 1999
4.3.10
All indications instruments and instruments requiring adjustments including F & G detectors shall be
accessible for servicing from floor level, walkways, permanent ladders or platforms. Orifice plates, line
mounted flow transmitters, thermocouples, etc, may be accessed by temporary means provided they are
less than five metres above floor level. Above five metres they are normally provided with permanent
access, although in some instances portable platform access may be required. Access by temporary
means is defined as used of a mobile access platform (cherry picker). Scaffold or ladders are not
deemed temporary access. Heavy items e.g. large valves and meters must have provision for lifting
equipment access.
4.3.11
Pedestal mounted instruments shall be located at a height of between 4.5 and 5 ft (1.4 and 1.5m) above
floor level or permanent platforms, unless site conditions dictate otherwise (eg. where vibration could
be a problem, a shorter pedestal may be desirable). 2 ft (0.75m) clearance shall be provided to allow for
rodding out if needed.
4.3.12
All indicating instruments shall be readily readable from operating positions, floor level or permanent
platforms. Gauge glasses shall be readable from access ladders and, preferably, readable from any
control valve which controls the process.
In those cases where instruments will be removed later for pressure testing or plant flushing the gasket
may be temporary compressed material, when reinstalling prescribed material must be used.
4.3.13
When locating pedestal mounted flowmeters care must be taken to ensure that the elevation of the
orifice installation is suitable so that sufficient slope in the impulse piping is obtained.
4.3.14
Field mounted instruments shall be installed so that the manufacturer's data plate, zero and span
adjustments and manifold valves are accessible. Each instrument shall be securely tagged with the item
tag number and service descriptor engraved on a permanent label. Electrical connections and associated
wiring shall be clearly and securely marked with the identification numbers shown on the Project
Drawings.
4.3.15
Control valves shall be located in accordance with the piping detail drawings and, in general, should be
accessible from floor level of permanent platforms. Clearance shall be allowed above the control valve
to allow for servicing of the actuator and below for servicing the valve internals where applicable.
Suitable clearances shall also be allowed to give access to manual handwheels, valve positioners and
other accessories.
4.3.16
Care shall be taken in locating tapping points to keep the impulse lines as short as possible.
4.3.17
Care shall be taken that the forces developed by the expansion of piping or vessels will not damage
instrument or impulse piping.
4.3.18
All pressure instrument fitted with blow-out vents shall be mounted with a clearance equal to at least
one blow-out vent diameter between the vent and the nearest obstruction surface.
4.3.19
Modifications to prefabricated panels must not be made without the Owner's written approval. Items
such as miniature control valves, solenoid valves, etc., for mounting behind panels, and whose position
is not previously specified, shall preferably be rack mounted on an approved framework.
4.3.20
Any tubing or conduit penetrations through walls or floors shall be properly sealed, watertight and dust
tight. Any holes or slots in walls, floors, or ceilings where cables or tubing pass through between
hazardous areas and non hazardous areas shall be sealed after installation of the cables or tubings in
accordance with the electrical code applicable and in effect at the site.
4.3.21
Analysis instruments shall be installed/housed in accordance with the specifications and drawings. If
electrical trace heating cable has been pre-engineered but proves to be too long at site, the additional
(centre) cable shall be installed in such a manner that is does not cross over. Cross over heating cables
GES C.55
Page 34 of 44
Rev 0 1999
If short length tapes are used then the contractor shall provide dedicated step-down transformers where
required. Such transformers and their installation shall be approved by the Owner.
4.3.23
Where capillary systems are used, they shall be continuously supported and protected, with any excess
length coiled. The installation shall not introduce any standing errors.
4.3.24
Instruments shall be installed so that in service their temperature does not exceed 158F (70C) or the
manufacturers limits. Vendor/Contractor shall provide sunshades for instruments which are not suitable
for mounting in the ambient temperatures stated in GES A.06.
4.3.25
Pressure gauges shall be installed so that their blow-out protectors are not obstructed and with
protectors facing away from operator. Gauges up to and including 6" (150mm) dial size may be close
coupled and supported by their own connections provided screwed pipe fittings are used.
4.3.26
Temperature detecting elements shall be installed in thermowells with the sensing elements and
thermowell in thermal contact. The detecting element shall be terminated with sufficient cable slack to
allow removal from the thermowell without disconnecting.
4.3.27
4.4
Instrument Piping/Tubing
4.4.1
Instrument piping and tubing shall be routed bearing in mind the following considerations, such that,
where possible, they:
a)
are kept as short as possible consistent with good practice and accessibility.
b)
c)
do not interfere with the accessibility or removal of process equipment (e.g pumps, motors,
exchanger bundles, valves, etc).
d)
e)
avoid areas where spillage is liable to occur (e.g. from overflowing tanks).
f)
are clear of drainage points of condensate, water and process fluids from adjacent plant
equipment.
g)
avoid areas of where escaping vapours or corrosive gasses could present a hazard.
h)
run clear of process piping and provide sufficient clearance from piping which may require
insulation.
4.4.2
Pipes or tubes installed, but not connected, shall have the ends closed in an approved fashion to prevent
the entry of foreign material. For a period of up to one week adhesive tape may be used, for longer
periods caps or plugs shall be used.
4.4.3
Where instrument pipes/tubes are run parallel to each other, joints should be systematically staggered
and neatly off-set with sufficient clearance to permit the breaking and re-making of any joint without
moving adjacent piping.
4.4.4
Horizontal runs of pipes and tubes shall have pipes/tubes laid vertically one above the other as far as
possible and shall be run with the minimum number of changes of direction consistent with good
practice, and neat appearance.
GES C.55
Page 35 of 44
Rev 0 1999
4.4.5
Where compression fittings are used the fittings shall be installed in strict accordance with the
manufacturer's recommendations. After fitting, brass fittings to be sprayed with a PTFE coating or
taped with self amalgamating tape. Only persons familiar with double ferrule fittings and who attend
Vendor/Contractor related initiation course shall be permitted to make any connections. Threads for
screwed fittings will be specified by the Owner. The Vendor/Contractor must ensure that the specified
thread and thread sealants are used.
4.4.6
Any discrepancies between the materials/fittings specified and the materials/fittings provided shall be
brought to the Owner's notice without delay.
4.4.7
Access for heat tracing and lagging shall not be restricted. An adequate stand off allowance shall be
provided.
4.4.8
The number of joints in pipework shall be kept to a minimum consistent with good practice. Bending is
preferred, where practical to joints/elbows.
4.4.9
Provision shall be made for differential movement between tapping point and the instrument.
4.4.10
Instrument pipework, tubing vents and drains shall be installed so as not to cause a hazard to personnel
or equipment.
4.4.11
PTFE tape shall not be used as a thread sealant on instrument air lines downstream of filter regulator,
including transmission and controller output signals. Where required, a proprietary brand of sealing
compound shall be used and shall be applied sparingly so that there is no intrusion of the compound into
the air lines. Thread sealants may be forbidden on certain analysers (e.g. moisture, chromatograph) in
which case only PTFE tape only shall be used.
4.4.12
All pneumatic signal tubings shall be cleaned by blowing through with clean dry air before connection
to instruments.
4.4.13
Sufficient slack shall be provided in all air tubing to avoid strain on the instrument connections and to
facilitate dismantling of the instruments. All control valves and direct vessel mounted transmitters shall
have an extra loop in their air tubing for maximum flexibility.
4.4.14
All impulse piping shall be self draining and in general be run with a slope of not less than 1 in 12
except where otherwise specified. Direction of slope is to be downward from the process for liquid
service and upward from the process for gas service.
4.4.15
Where length of prenmatic transmission to being exceeds 200 ft (60m) the Owner should be consulted
as to be necessity of installing signal booster relays.
4.4.16
The Vendor/Contractor must pay special attention to the correct siting of vents and drains to ensure they
are at the highest or lowest points of the piping run.
4.4.17
4.4.18
Hydraulic systems charged on site shall be flushed through until an acceptable degree of fluid purity is
achieved. The Vendor/Contractor responsible shall submit to the Owner for approval a Method
Statement and the means by which the agreed level of purity is to be measured. Provisionally this can
be taken as NAS 1638 class 8.
4.5
GES C.55
Page 36 of 44
Rev 0 1999
4.5.1
Piping or Tubing and their supports shall be kept free from vibrating structures or equipment.
4.5.2
GES C.55
Page 37 of 44
Rev 0 1999
Piping and tubing runs shall be adequately supported and fixed at distances not exceeding those in the
following table.
SIZE
SIZE
MAXIMUM DISTANCE BETWEEN
SUPPORTS OR CLIPS
IMPERIAL
METRIC
Tubing
_" OD and less
3 feet (1.0m)
" OD Multicore
12mm
3 feet (1.0m)
Piping
_" to " NB
1" NB
1.5" NB
10-12mm
25mm
40-50mm
4.5.4
Three or fewer stainless tubes may in certain cases be secured by appropriate clips at 3 ft (1.0m)
intervals to painted mild steel strip not less than 16 SWG/1 (1.6mm) or laid in small section angle bar.
4.5.5
Capillaries of filled systems shall be run independently of other lines and shall be continuously
supported using mild galvanised or pressed steel angle with clips at 1.5 ft (0.5m) intervals.
4.6
4.7
Earthing
Earthing installations shall be in accordance with GES J.17 and the Project Earthing System Drawings.
4.8
Materials
4.8.1
Mounting materials containing asbestos and asbestos in non-composite form shall not be used.
4.8.2
4.8.3
Instrument cabling, terminations and junction boxes shall be permanently identified in accordance with
approved Electrical Hook-up/Schematics.
4.9
4.10
Fabrication
4.10.1
Pipes or tubes, particularly those containing flammable, toxic or corrosive materials, shall be located
where the chance of molten zinc falling on to stainless steel from associated galvanised structures or
(zinc chromate paint, etc) in the event of fire, is eliminated or reduced as far as possible, owing to the
danger caused by zinc embrittlement of stainless steel.
GES C.55
Page 38 of 44
Rev 0 1999
4.10.2
Specialised installation may be required for F & G detectors, particularly for associated pneumatic
devices e.g. frangible loops and remote injectors for gas detectors. These shall be as per the project
detailed drawings.
5.0
5.1
Quality Assurance
5.1.1
5.1.2
Vendors/Contractors shall submit a Proposed Quality Control Plan with his proposal and a Definitive
Version within two weeks of receiving an order.
5.2
Quality Control
5.2.1
5.2.1.1
Instruments and panels which cannot be installed upon delivery must be housed in a properly
constructed and properly ventilated store and protected from dust and damp.
5.2.1.2
Throughout the construction period, instruments which are not provided with housings shall be
adequately protected by covering with heavy plastic bags of an approved type or by applying more
robust protection where necessary. Protection of instruments and provision of covers, silica get etc.
shall be the responsibility of the Vendor/Contractor.
5.2.1.3
Reference shall be made to the requirements of GES C.01 and GES C.02.
5.2.2
5.2.2.1
The Vendor/Contractor shall not allow any materials used for testing purposes to remain on or be
retained in any piece of finished work.
5.2.2.2
The Vendor/Contractor shall be responsible for protecting installed equipment from damage and
pilferage, and shall ensure that all overs, caps, screws and weather protection, etc. are replaced at the
end of each test.
5.2.2.3
Material and equipment used for testing purposes shall be adequately protected and stored at approval
storage locations until required.
5.2.2.4
All tests shall be carried out by skilled tradesman with proven experience of the type of work involved
using certified/calibrated test apparatus.
5.2.2.5
Only the best testing practices are to be used and all testing must be performed to the satisfaction of the
Owner who shall be consulted on any point requiring clarification. The Vendor/Contractor is free to
suggest to the Owner alternative methods for the execution of the test where this would result in
improvement.
GES C.55
Page 39 of 44
Rev 0 1999
5.2.3
5.2.3.1
The Vendor/Contractor shall not allow rubbish and scrap material from his operations to remain on or
be retained in any piece of finished work. All such rubbish and scrap shall be collected daily and be
deposited at places approved by the Owner.
5.2.3.2
The Vendor/Contractor shall be responsible for protecting installed equipment from damage, and
pilferage, and shall ensure that all covers, caps, screws and weather protection, etc. are replaced at the
end of each working day.
5.2.3.3
Material and equipment not immediately required shall be adequately protected and stored at approved
storage locations until required.
5.2.3.4
The drilling, cutting or welding of tanks, vessels, pipework or steelwork shall not be carried out without
the prior approval of the Owner in writing. Drilling cutting or welding of pressure vessels is not
permitted in any circumstances.
5.2.3.5
All installation work shall be carried out by skilled tradesmen with proven experience of the type of
work involved. The Vendor/Contractor is to submit CVs of his personnel with the bid.
5.2.3.6
Only the best trade practices are to be used, and all work must be performed to the satisfaction of the
Owner who shall be consulted on any point requiring clarification. The Vendor/Contractor is free to
suggest to the Owner alternative methods of the execution of the work where this would result in
improvement.
5.2.3.7
Upon completion of the work the Vendor/Contractor shall promptly remove his equipment and return to
the relevant place any unused material supplied by the Owner. Finally, the Vendor/Contractor must
clear the site of all rubbish and scrap deposited by himself and ensure that all installed equipment is
clean to the satisfaction of the Owner.
5.2.3.8
The Vendor/Contractor shall ensure that adequate precautions are taken during the use and storage of
gas cylinders and the cylinders left unattended are isolated at the main stop valve. All safety regulations
and site instructions regarding the handling and storage of gas cylinders shall be observed.
6.0
6.1
Inspection
6.1.1
The provisions of this section are in addition to and without prejudice to any more detailed provisions
for inspection and/or testing contained in the Purchase Order/Contract.
6.1.2
In order to confirm that the requirements of the Purchase Order/Contract are met the Owner shall have
the right, but not the obligation, at all times to inspect, test and examine all materials and equipment
provided and all work or services or documentation relating thereto performed by the
Vendor/Contractor or any Sub-contractor.
6.1.3
If the Owner so requires, the Vendor/Contractor shall inspect, test or re-test any equipment or materials
provided by the Vendor/Contractor in order to confirm that the requirements of the Contract are met.
The Owner shall have the right to witness any test of any part of the work. The Vendor/Contractor shall
in respect of any inspections or tests give the Owner the relevant period of notice stated in the Purchase
Order/Contract but the notice shall never be less than 48 hours.
6.1.4
No part of the work shall be covered up or put out of view without the approval of the Owner's
Representative. If any part of the work is closed or covered over before the required inspection or
witnessing and without agreement by the Owner's Representative, then, if required by the Owner's
GES C.55
Page 40 of 44
Rev 0 1999
Representative the part of the work must be opened or uncovered for inspection or witnessing of testing
and re-closed or recovered by the Vendor/Contractor.
6.1.5
If the Owner become aware of any symptoms suggesting that any workmanship, services, materials,
equipment and/or any part of the work may not comply with the Purchase Order/Contract, then the
Owner's Representative may order work to stop in order to allow such symptoms to be investigated.
The Owner may conduct such investigations by itself and/or third party, and the Owner may instruct
Vendor/Contractor to carry out such investigations either concurrently or independently. In all cases,
the Vendor/Contractor shall co-operate with the upmost diligence in such investigations. Such
investigations may include tests and opening up.
6.1.6
If such investigations do reveal non-compliance with the Purchase Order/Contract and if in the Owner's
Representative's opinion such non-compliance is the responsibility of Vendor/Contractor, then the
Owner's Representative may order further investigation and/or further opening up of work to determine
the full extent of the problem.
6.1.7
The Owner shall have the right to reject any workmanship, services, materials, equipment and any part
of the work which does not conform with the Purchase Order/Contract. The Vendor/Contractor shall
remove promptly any items so rejected and shall immediately repair or replace the same and shall carry
out such further inspections or tests on other parts of the work as the Owner may require to ensure that
there are no similar parts of the work that fail to conform with the Purchase Order/Contract.
6.1.8
Neither failure on the part of the Owner to inspect the work or witness or test or to discover defects nor
failure to reject work performed by the Vendor/Contractor which is not in accordance with the Purchase
Order/Contract shall relieve the Vendor/Contractor from any liability or obligation under the Purchase
Order/Contract.
6.2
Acceptance
The work will be accepted, in the opinion of the Owner or his representative, subject to satisfactory
results of all tests, provision of agreed documentation and any other condition or requirements that may
be satisfied in accordance with the requirements of the Purchase Order/Contract.
7.0
DOCUMENTATION
7.1
7.1.1
Section 8.0 in this specification outlines various calibration certificates, check lists and other associated
blank forms. These may be modified by the Vendor/Contractor for use but any modifications shall be
agreed with the Owner in writing. The Owner's approval of any such modifications shall not limit in
any way Vendor/Contractor's responsibility for testing, or in any additional testing that may prove to be
necessary.
7.1.2
The Vendor/Contractor may also add any tests and check lists which he considers necessary but subject
to the Owner's approval.
GES C.55
Page 41 of 44
Rev 0 1999
7.2
Contractor's Data
7.2.1
Prior to final inspection the Vendor/Contractor shall supply a stipulated number of copies of wiring
diagrams, operating and maintenance instructions and renewal parts lists for each type of piece of
equipment installed by him as part of his work.
7.2.2
All authorised changes and deviations from the drawings made by the Vendor/Contractor shall be
recorded by him on a set of drawings which will then be handed over to the Owner before the final
inspection of the work.
7.3
7.3.1
The Vendor/Contractor shall keep a detailed record of installed work which differs from the Project
drawings.
7.3.2
As a minimum this shall be achieved by neat marking up of prints in red of the Project drawings.
7.3.3
This record shall be kept up to date and will be subject to the Owner's inspection.
7.3.4
All "As Built" drawings shall be stamped "As Built" in bold red letters and shall be signed off, checked,
approved and dated.
8.0
8.1
8.2
8.3
8.5
Fire and Gas Systems Installation and Pre-Commissioning Check List Forms
Fire Detectors (General) (2 sheets)
Manual Alarm Call Point (MAC)
Heat Detector (Typically Combined Rate of Rise and Fixed Set Point) (2 sheets)
Alarm Contact and Switched Device Detector - Loop Acceptance Certificate
Smoke Detector (Typically Duct Type) (2 sheets)
Gas Detector (Specific Type) - Typically Line of Sight
Gas Detector - Loop Acceptance Certificate (2 Sheets)
Linear Heat Detector (2 sheets)
Indicator Lamp
Fire Detector (IR/UV Type Only) (2 sheets)
Fire and Gas Cable
Fire and Gas Audible Device
Sprinkler System Water Flow Switch
8.6
8.7
GES C.55
Page 42 of 44
Rev 0 1999
GES C.55
Page 43 of 44
Rev 0 1999
S:\NOC9077\ADMIN\SPECIFICATIONS\C-SERIES\C-55\GESC55RF
INSTRUMENT
DAMAGE / FAULT REPORT
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
TAG No.
MODEL No.
MANUFACTURER
SERIAL No.
LOCATION
ORDER No.
ITEM
of
YES / NO
PRINT NAME
PAYMENT DUE
YES / NO
SIGNATURE
DATE
COMPLETED BY
AFFIRMED BY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5501r0.xls
PUNCH LIST
INSTRUMENT
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
EQUIPMENT No.
SYSTEM
of
CERTIFICATE No.
ITEM No
CATEGORY `A'
DESCRIPTION
MATERIAL
REQ No
CATEGORY
TYPE
DATE
CLEARED
SIGNED
STAMP
CATEGORY `B'
ITEMS THAT CAN BE REPAIRED, COMPLETED OR CORRECTED AT A LATER DATE AND WHICH
ALLOWS THE EQUIPMENT TO BE OPERATED WITHOUT JEOPARDISING PLANT OR PERSONNEL
PRINT NAME
SIGNATURE
DATE
VENDOR / CONTRACTOR
OWNER
CONSTRUCTION TEAM
COMMISSIONING TEAM
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5502r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL No.
DRAWING No.
SERIAL No.
ZONE 1
of
ZONE 2
N/A
SERIAL No.
SUPPLY CORRECT
CONDITION SATISFACTORY
INSTRUMENT CALIBRATION
TEST EQUIPMENT USED
INITIAL CALIBRATION
FINAL CALIBRATION
INPUT
OUTPUT
UNITS
UNITS
INPUT
ERROR
OUTPUT
UNITS
UNITS
ERROR
INSTALLATION INSPECTION
INSTRUMENT INSTALLED CORRECTLY
REFERENCE DRAWING No
LOOP CONTINUITY
CABLE Nos.
REFERENCE DRAWINGS
JUNCTION BOX No.
PANEL No.
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5503r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
DESCRIPTION
SYSTEM
EQUIPMENT No.
MANUFACTURER
TYPE
MODEL No.
DRAWING No.
SERIAL No.
CHECKED TO DATA
LOCATION
of
SHEET No
DATA
CALIBRATION/TEST PROCEDURE NO.
b
a
YES
NO
SPECIFIED OD:
ACTUAL OD (c):
SPECIFIED ID:
ACTUAL (a):
MATERIAL:
YES
NO
(b):
YES
NO
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5504r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL No.
DRAWING No.
SERIAL No.
LOCATION
RANGE
FLUID
OPERATING PRESSURE
REQUIRED ACCURACY =
ZONE 1
of
ZONE 2
N/A
RISING VALUE
0
50%
FALLING VALUE
100%
50%
APPLIED PRESSURE
PRESSURE GAUGE
READING
(A) IN WORKSHOP
(B) ON PLANT
YES
NO
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5505r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
of
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL No.
DRAWING No.
SERIAL No.
LOCATION
INPUT RANGE
OUTPUT RANGE
ZONE 1
YES [ ]
RISING VALUES
0
25%
50%
ZONE 2
FALLING VALUES
75%
100%
75%
50%
25%
(A) IN WORKSHOP
(B) ON PLANT
YES
NO
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5506r0.xls
N/A
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SYSTEM
HAZARDOUS AREA
MANUFACTURER
LOCATION
MODEL NO.
SERIAL NO.
LOCATION
TRANSMITTER RANGE
S.G.
FLUID
TYPE
OPERATING PRESSURE
CONTROL ACTION
FLANGE RATING
ZONE 1
of
ZONE 2
N/A
RESULTS
IN WORKSHOP
ON PLANT
YES
NO
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5507r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL NO.
DRAWING No.
SERIAL NO.
LOCATION
ACCURACY CORRECT
SUPPLY CORRECT
CHECKED ONLINE
CHECKED OFFLINE
ZONE 1
of
ZONE 2
INPUT
OUTPUT (GAIN X 1)
0
25
50
75
100
75
50
25
0
RESET RESPONSE SATISFACTORY
DERIVATIVE RESPONSE SATISFACTORY
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5508r0.xls
N/A
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL No.
DRAWING No.
SERIAL No.
LOCATION
INPUT RANGE
OUTPUT RANGE
ZONE 1
ZONE 2
of
N/A
RISING VALUES
APPLIED INPUT SIGNAL
25%
50%
FALLING VALUES
75%
100%
75%
50%
25%
YES
NO
(A) IN WORKSHOP
(B) ON PLANT
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5509r0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
TAG No.
SHEET
of
ITEM NO.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
ZONE 1
MODEL No.
DRAWING No.
SERIAL No.
LOCATION
FLUID
RANGE F(C)
ZONE 2
N/A
SPECIFIED ALARM/
TRIP SETTING
RISING VALUES
0
25%
50%
FALLING VALUES
75%
100%
75%
50%
25%
APPLIED TEMPERATURE
TRANSMITTER READING
OUTPUT - BARS/mA
APPLIED mV SIGNAL
EQUIVALENT TEMPERATURE
INDICATED TEMPERATURE
APPLIED RESISTANCE VALUE
EQUIVALENT TEMPERATURE
INDICATED TEMPERATURE
APPLIED TEMPERATURE
ACTUAL TEMPERATURE
ALARM TRIP TEMPERATURE (IF APPLICABLE)
RISING
FALLING
T/C BURN OUT TIME TAKEN FOR FULL SCALE DEFLECTION (IF APPLICABLE) AND DIRECTION
UP SCALE
DOWN SCALE
MULTIPOINT
INDICATOR/RECORDER POINT No.
IN WORKSHOP
ON PLANT
YES
NO
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5510r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL NO.
DRAWING NO.
SERIAL NO.
LOCATION
INPUT RANGE
OUTPUT RANGE
ZONE 1
of
ZONE 2
N/A
SIGNAL
TYPE
RISING VALUES
0
25%
50%
FALLING VALUES
75%
100%
75%
50%
25%
APPLIED INPUT
EQUIVALENT OUTPUT
ACTUAL OUTPUT
YES
NO
YES
NO
(A) IN WORKSHOP
(B) ONPLANT
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5511r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
DESCRIPTION
LOCATION
P & ID No.
LOOP No.
of
SERIAL No
TEST DETAILS
CALIBRATION FIGURES
CALIBRATION POINTS
RISING
FALLING
UNITS
INPUT A
INPUT B*
INPUT C*
OUTPUT
COMMENTS:
SIGNATURE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5512r0.xls
DATE
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
MODEL No.
TYPE
DRAWING No.
SERIAL No.
LOCATION
of
ZONE 1 ZONE 2
N/A
THROTTLING
OPENS
CLOSES
SIGNAL FAILURE
POSITIONER CAM
ON/OFF
STAYS PUT
OPENS
LINEAR
CLOSES
OTHER (STATE)
2. CALIBRATION:
INPUT RANGE
%
psig(kPag)
BENCH SET
POSITIONER IN
BENCH SET
POSITIONER IN
0
25
50
75
100
75
50
25
0
LIMIT STOPS SET
3. SEAT LEAKAGE TEST
VALVE SEAT
METAL TO METAL
TEST FLUID
TEST PRESSURE
MANUFACTURER'S SPECIFIED LEAKAGE RATE
SOFT
BAR G
ACTUAL LEAKAGE
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5513Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL No.
SERIAL No.
DRAWING No.
VENDOR / CONTRACTOR CERTIFICATION
LOCATION
of
ZONE 1 ZONE 2
N/A
4. ANCILLARY EQUIPMENT:
OPEN LIMIT SWITCH(ES)
TAG NO:
SET AT
* BEFORE OPEN
TAG NO:
SET AT
* BEFORE CLOSED
MODEL NO.
TAG NO:
OPERATION SATISFACTORY
MODEL NO.
TAG NO:
OPERATION SATISFACTORY
VOLUME TANK
INSTALLATION SATISFACTORY
MODEL
N2 CHARGE SATISFACTORY
HYDRAULIC / PNEUMATIC PILOT OPERATION SATISFACTORY
LIMIT STOPS SET
ELECTRICAL ACTUATOR: MANUFACTURER
MANUAL OPERATION SATISFACTORY
VOLTAGE
MODEL NO.
MODEL NO.
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5513Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG NO.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL NO.
DRAWING NO.
SERIAL NO.
LOCATION
LOOP NO.
of
ACTUAL RANGE
OF SCALE
RUN `A'
RUN `B'
RUN `C'
SET POINT
RISING
SET POINT
FALLING
IN WORKSHOP
ON PLANT
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5514r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
ZONE 1
MODEL NO
DRAWING NO.
SERIAL NO.
of
ZONE 2
N/A
SERIAL NO.
TEST DETAILS
CALIBRATION FIGURES
SWITCH POINTS
RISING
FALLING
UNITS
INPUT A
INPUT B*
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5515r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
EQUIPMENT No.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
MODEL NO.
DRAWING No.
SERIAL NO.
LOCATION
of
ZONE 1
ZONE 2
N/A
1. REFERENCE INFORMATION
DESCRIPTION
SCHEMATIC
CONNECTION DIAGRAM
MOTOR/HEATER NUMBER
SWITCHGEAR
CUBICLE
CONTROL CABLE
VOLTAGE (COIL)
TAG NO
TIMER
INPUT
NO.
RELAY
2. TESTS
TAG
CHECKED
VA
CONTACT RATING
OUTPUTS
SIMULATED
REMARKS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFY AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5516r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG No.
of
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
ZONE 1
MODEL No.
DRAWING No.
SERIAL No.
LOCATION
ZONE 2
N/A
SERIAL No.
TEST DETAILS
VALVE SIGNAL RANGE
AIR FAILURE:
OPEN
CLOSES
STAY PUT
SIGNAL FAILURE:
OPEN
CLOSES
STAY PUT
HYDRAULIC FAILURE:
OPEN
CLOSES
STAY PUT
POWER FAILURE:
OPEN
CLOSES
STAY PUT
TEST RESULTS
OPEN/CLOSING TIME
SIGNAL
TIME
MIN
MAX
OPEN
CLOSE
CLOSE
OPEN
MIN
MAX
OPEN
CLOSE
CLOSE
OPEN
TEST PRESSURE
DROPS/MIN
BUBBLES/MIN
TAG No.
CALIBRATION RANGE
CHECK SATISFACTORY
REMARKS
SOLENOID VALVE
SOLENOID VALVE
LIMIT SWITCH
LIMIT SWITCH
PRESSURE SWITCH
PRESSURE GAUGE
PRESSURE GAUGE
PUSH BUTTON RESET
COMMENTS: (Commissioning Representative to witness this test)
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5517r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG NUMBER
SUBSYSTEM
DESCRIPTION
LOCATION
P & ID No.
of
DATA
REV:
BALANCED OR CONVENTIONAL
ORIFICE SIZE:
INLET SIZE
OUTLET SIZE:
SERIAL No.
SPRING No.
TEST EQUIPMENT
LETTER:
SERIAL No.
BACK PRESSURE
COLD SET PRESSURE
TEST DETAILS
DURATION OF TEST
DESIGN PRESSURE
RE-SEAT PRESSURE
TEST MEDIUM
ATTACHED
TO FOLLOW
COMMENTS:
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5518Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
PSV TAG
NUMBER
P & I DIAGRAM
LOCATION
DATE CALIBRATION
of
INSTALLATION
REFERENCE
DATE
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5518Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
SYSTEM
TAG NO.
TYPE / MODEL
of
MANUFACTURER
PROXIMATOR
SERIAL No.
DRAWING No.
PROXIMATOR MODEL
PROBE RESISTANCE
PROXIMATOR VOLTAGE
SIGNED
COMMENTS:
(A) IN WORKSHOP
(B) ON PLANT
PRINT NAME
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5519r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
DESCRIPTION
LOCATION
EQUIPMENT NUMBER
of
Test Equip.
Serial No.
Test Equip.
Serial No.
2. Pneumatic Signal:
Test Gas
Test Pressure psig(kPag)
Test Duration
Test Equipment
TUBE NO
TO
FROM
DRAWING NO.
DIA X LENGTH
(i)
(ii)
(iii)
(iv)
3. Pneumatic Supply
Test Gas
Test Pressure (kPag)
Test Duration
Test Equipment Used
Test Equip.
LINE NO
TO
FROM
Serial No.
DRAWING NO.
DIA X LENGTH
(i)
(ii)
(iii)
(iv)
TUBING FLUSHED CLEAN
YES
NO
N/A
YES
NO
N/A
YES
NO
N/A
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5520r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
DESCRIPTION
LOCATION
EQUIPMENT NUMBER
of
Test Equip.
Serial No.
TO
FROM
DRAWING NO.
DIA X LENGTH
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
3. Hydraulic Systems Cleanliness Test (State Cleanliness Class Achieved)
COMPONENT
RESULTS
TEST 1
TEST 2
SUBSEQUENT TESTS
SYSTEM TUBE
ACTUATOR
YES
NO
N/A
YES
NO
N/A
YES
NO
N/A
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5521r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
EQUIPMENT NUMBER
LOCATION
TAG NUMBER
ISOMETRIC NUMBER
HOOK-UP NUMBER
of
P & ID NUMBER
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5522r0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
SHEET
of
ITEM NO.
P & ID NO.
AREA/SYSTEM
LOCATION
MANUFACTURER
MODEL NO.
SERIAL NO.
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
leak tested
satisfactory
satisfactory
9
11
Installed Correctly
12
Materials Correct
13
14
15
16
Location Correct
17
18
19
20
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5523Ar0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
TAG NO.
SHEET
of
ITEM NO.
AREA/SYSTEM
P & ID NO.
LOCATION
MANUFACTURER
MODEL NO.
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
MEASURING ELEMENT
21
22
23
Pressure Tested
24
25
26
27
Insulation Correct
TRANSMITTER/CONTROLLERS
28
Range Correct
29
30
31
Set Manual/Auto
32
33
34
Proportional/Reset/Rate
35
36
37
Set Local/Remote
38
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5523Br0.xls
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
of
AREA/SYSTEM
INSTRUMENT TAG NO.
ITEM
PNEUMATIC HOOK-UP
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
equipment removal
3
10 All air supply and signal tubing correct size, type and
undamaged
11 Tubing bends correct radius and made correctly
12 All connections made off correctly, deburred, reamed
and cleaned
13 Tube/pipe fittings to specification
14 Correct thread compound (or PTFE Tape) used
15 Signal line identified as specification on each side of
transit
16 Brass fitting and valves in corrosive areas coated with
PVC or taped
17 Installation in accordance with specification
18 As-Built drawings completed
19 All lines blown clean
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5524r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
of
AREA/SYSTEM
CABLE NO.
CABLE SIZE
CONDUCTOR SIZE
OUTER COLOUR
TYPE
DRUM NO.
DRAWING SCHEDULES
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for whichS:\c-series\c-55\DC5525r0.xls
it is supplied by NOC.
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
SHEET
of
ITEM NO.
PROJECT
AREA/SYSTEM
LOCATION
EQUIPMENT NUMBER
CABLE NO.
SIZE
DRAWING NO.
CORE SIZE
TYPE
ITEM
DESCRIPTION OF CHECK
YES
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Crimp connections correct size and type for terminal and wire
24
25
26
27
28
As-Builts marked up
29
NO
N/A
COMMENTS
Comments
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5526r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
of
PROJECT
AREA / SYSTEM
MANUFACTURER
DRAWING NUMBER
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
for purpose
4
System complete
Lidding installed
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5527r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
AREA SYSTEM
EQUIPMENT NUMBER
CABLE NUMBER
DRAWING NUMBER
SIZE
CORE SIZE
TYPE
ITEM
of
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5528r0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
EQUIPMENT NO.
SHEET
of
ITEM NO.
AREA CLASSIFICATION
ZONE 1
ZONE 2
N/A
IP RATING
DRAWING NO.
LOCATION DRAWING
SPECIFICATION NO.
SERVICE
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
chaining
frames or metallic condition.
6
Resistance =
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5529r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
MANUFACTURER:
AREA / SYSTEM:
LOCATION:
PHILOSOPHY:
EQUIPMENT NO:
GA DWG:
TEST PROCEDURE:
SCHEMATIC:
SERVICE:
LOGIC:
IP RATING:
ITEM
DESCRIPTION OF CHECK
YES
NO
General
Equipment located as per drawing and adequate
access provide for
2 Installation complete to drawing
3 Equipment identification correct
4 Suitable area classification zone
5 Certification label and number correct
6 Cable gland certified size and type correct
7 Apparatus marking correct
8 Apparatus complete and undamaged
9 Apparatus free of accumulated dust / dirt / grease
10 Lamp rating / type are correct
N/A
of
ZONE 2
N /A
COMMENTS
Drg No.
Voltage:
Temperature Rating:
11 Correct fuses are fitted
12 Apparatus waterproof / gland to specified rating
13 Condition of enclosure gaskets / seals satisfactory
14 Bolts / glands / stoppers are correct and tight
15 Apparatus free from unauthorised modification
16 Cables supported / clipped / protected correctly
17 Earthing satisfactory and to specification
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5530Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
MANUFACTURER:
AREA / SYSTEM:
LOCATION:
PHILOSOPHY:
EQUIPMENT NO:
GA DWG:
TEST PROCEDURE:
SCHEMATIC:
SERVICE:
LOGIC:
IP RATING:
ITEM
DESCRIPTION OF CHECK
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
YES
NO
N/A
of
ZONE 2
N /A
COMMENTS
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5530Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
MANUFACTURER:
AREA / SYSTEM:
LOCATION:
PHILOSOPHY:
EQUIPMENT NO:
GA DWG:
TEST PROCEDURE:
SCHEMATIC:
SERVICE:
LOGIC:
IP RATING:
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
of
ZONE 2
N /A
COMMENTS
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5530Cr0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
MANUFACTURER:
AREA / SYSTEM:
LOCATION:
PHILOSOPHY:
EQUIPMENT NO:
GA DWG:
TEST PROCEDURE:
SCHEMATIC:
SERVICE:
LOGIC:
IP RATING:
ITEM
1
2
3
4
1
2
3
4
5
DESCRIPTION OF CHECK
YES
NO
N/A
of
ZONE 2
N /A
COMMENTS
Ex 'p' Enclosures
Purge ducting / piping and pressurised enclosures
are complete and in good condition
Safety certification for safety device monitoring the
flow of protective gases checked
Safety valve set to correct pressure
Pressure / flow adequate and indicators, timers,
alarms and interlocks function correctly
Equipment marked and tagged in accordance with
the relevant standard BS EN50014/50016/NFPA496
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5530Dr0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
MANUFACTURER:
AREA / SYSTEM:
LOCATION:
PHILOSOPHY:
EQUIPMENT NO:
GA DWG:
TEST PROCEDURE:
SCHEMATIC:
SERVICE:
LOGIC:
IP RATING:
ITEM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
DESCRIPTION OF CHECK
YES
NO
N/A
of
ZONE 2
N /A
COMMENTS
16
17
18
19
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5530Er0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
AREA / SYSTEM
DESCRIPTION
CERT / STD
CERT NO.
SERIAL NO.
MANUFACTURER
of
MODEL NUMBER
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
GENERAL
1
2
Drg No.
Cert No.
6
7
8
9
10
11
12
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NO
S:\c-series\c-55\DC5531Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
AREA / SYSTEM
DESCRIPTION
CERT / STD
CERT NO.
SERIAL NO.
MANUFACTURER
of
MODEL NUMBER
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
15
16
17
18
19
22
Check that the label on door or box (including its I.P. rating
is correct to the approved drawing.
Check that the box and door are undamaged, that the weather
sealing is intact and that the inside is clean and dry
Check that the cable glands are secure and that there is no
damage to the cables
Ch'k that all unused cable entry holes are securely blocked off
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NO
S:\c-series\c-55\DC5531Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
AREA/SYSTEM
DESCRIPTION
ITEM/TAG NUMBER
CERT/STD
CERT NO.
SERIAL NO.
MANUFACTURER
of
MODEL NUMBER
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
30
31
32
33
35
36
37
38
39
40
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NO
S:\c-series\c-55\DC5531Cr0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
AREA / SYSTEM
DESCRIPTION
CERT / STD
CERT NO.
SERIAL NO.
MANUFACTURER
of
MODEL NUMBER
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
Check that the impedance between the main I.S. bar and the
earth bar in the sub-station or switchroom is less than
1
Where there are two cables connecting the earth bars
together, disconnect one of the cables at one end and
measure the resistance between the earth bars and the
disconnected cables. Record the measured value.
Reconnect the cable, disconnect the other cable and repeat
the measurement. Record the measured value and
reconnect the cable. The two measured values should be the
same. If the value of each is R ohms, the resistance will be
R/ 4
INSULATION TESTING
43
44
45
46
47
48
49
INSPECTION RECORDS
50
51
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NO
S:\c-series\c-55\DC5531Dr0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
of
AREA
MANUFACTURER
TYPE
PANEL / CABINET
SPECIFICATION
PANEL / CABINET G.A. NO.
INTERNAL LAYOUT
PANEL / CABINET DWG
SCHEMATIC
PANEL / CABINET DWG
PANEL / CABINET
TERMINATION DWG NO.
AREA CLASSIFICATION
DWG
ITEM NO.
SYSTEM
LOCATION
ITEM
SHEET
HAZARDOUS AREA
ZONE 2
N/A
IP RATING
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
10
11
12
13
14
15
16
17
18
correct IP protection
equipment earthed properly
access
specification
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5532Ar0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
of
ITEM NO.
SYSTEM
LOCATION
AREA
MANUFACTURER
TYPE
PANEL / CABINET
SPECIFICATION
PANEL / CABINET G.A. NO.
INTERNAL LAYOUT
PANEL / CABINET DWG
SCHEMATIC
PANEL / CABINET DWG
PANEL / CABINET
TERMINATION DWG NO.
AREA CLASSIFICATION
DWG
ITEM
SHEET
HAZARDOUS AREA
ZONE 2
N/A
IP RATING
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5532Br0.xls
CLIENT
PLANT
LOCATION
SERVICE
VENDOR / CONTRACTOR
of
ITEM NO.
SYSTEM
LOCATION
AREA
MANUFACTURER
TYPE
PANEL / CABINET
SPECIFICATION
PANEL / CABINET G.A. NO.
INTERNAL LAYOUT
PANEL / CABINET DWG
SCHEMATIC
PANEL / CABINET DWG
PANEL / CABINET
TERMINATION DWG NO.
AREA CLASSIFICATION
DWG
ITEM
SHEET
ZONE 1
ZONE 2
N/A
IP RATING
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5532Cr0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
of
PROJECT
LOCATION
AREA SYSTEM
TYPE
ITEM
DESCRIPTION OF CHECK
YES
NO
N/A
10
11
12
13
14
15
16
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5533r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SYSTEM
CABINET NO.
DESCRIPTION
CARD NO.
of
PORT NO.
LINK TYPE
TOPIC
DATA
TOPIC
No.)
2 Data destination device (Model
16 Baud rate
DATA
No.)
3 Transmission media
4
5
6
7
8
9
10
11
12
13
Length of message
Buffer size
Double buffing required
Type of handshake
Source / target registers
14 Database I.D.
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5535r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
TAG NO.
DESCRIPTION
SYSTEM
HAZARDOUS AREA
MANUFACTURER
TYPE
of
ZONE 1
MODEL NO.
DRAWING NO.
SERIAL NO.
LOCATION
ZONE 2
N/A
DESCRIPTION OF CHECK
YES
NO
N/A
COMMENTS
1 Type
2 Model No.
3 Serial Nio.
4 Manufacturer
5 Data Sheet No.
6 General Condition
7 Flange Correct
8 Signal Correct
9 Supply Correct
10 Ancillary Equipment Correct
11 Calibration
Date
12 Tested - Bench / Insitu
13 Test Equipment Used
14 Electrical Supply Details
15 Test Medium
16 Test Pressure
17 Alarm Trip Setting (Initial) Rising
Falling
18 Alarm Trip Setting (Final) Rising
Falling
19 Alarm Legend Correct
20 Installed Correctly
21 Instrument Supported Correctly
22 Hook-Up Drawing No.
23 Continuity Checked
24 Cable Nos.
25 JB Nos.
26 Loop Drawing No.
27 Connection Diagram No.
28 Vendor Drawing No.
29 Panel No.
30 Instrument Tag Visible & Easily Readable
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5536r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5537r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
AREA
TEST EQUIPMENT
SERIAL NO.
CABLE NO.
of
SYSTEM
TYPE
N/A
SIZE kcmil(mm)
VOLTAGE
MANUFACTURER
OUTER COLOUR
GLANDING CORRECT
SEGREGATION CORRECT
4. INSULATION TESTS:
MIN VALUE
SEE SHEET 2
(>10 M 500 V)
SEE SHEET 2
(>10 M 500 V)
SEE SHEET 2
(>10 M 500 V)
SEE SHEET 2
(>500 K )
SEE SHEET 2
(>10 M 500 V)
SEE SHEET 2
(>10 M 500 V)
5. CONTINUITY TESTS
CORE CONTINUITY
NOTE 2 (<10 )
SCREEN CONTINUITY
(<10 )
ARMOUR CONTINU
(<10 )
(<10)
THIS SHEET TO BE PROVIDED FOR DRUM CHECK, COMPLETE ITEMS 2, 4 & 5 ONLY.
DRUM CHECK ABOVE TO BE CROSS-REFERENCED IN DOSSIER FOR INSTALLATION CHECK.
USUALLY INDIVIDUAL CONDUCTORS IN A CABLE WILL HAVE A SIMILAR VALUE OF INSULATION RESISTANCE (ABOUT 10 MEGAOHMS).
HOWEVER, WHERE THEY DIFFER THE VALUE STATED SHOULD BE THE LOWEST. IF THESE DIFFER BY A SIGNIFICANT AMOUNT
THIS COULD BE AN INDICATION OF DAMAGED OR POOR WORKMANSHIP AND IS TO BE INVESTIGATED.
ALL MULITCORE FIELD CABLING AND WIRING SHALL BE COMPLETELY DISCONNECTED FROM EQUIPMENT FOR TESTING.
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5538Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
AREA
TEST EQUIPMENT
SERIAL NO.
CABLE NO.
TYPE
N/A
SIZE kcmil(mm)
of
SYSTEM
VOLTAGE
MANUFACTURER
OUTER COLOUR
CORE/PAIR
NUMBER
26
27
28
29
30
31
32
33
34
10
35
11
36
12
37
13
38
14
39
15
40
16
41
17
42
18
43
19
44
20
45
21
46
22
47
23
48
24
49
25
50
COMMENTS
SCREEN
CORE/
CORE/
SCR'N/
SCR'N/
SCR'N/
CORE
EARTH
CORE
ARM'R
SCR'N
EARTH
ARM'R
CONT'Y
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5538Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5539r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5540r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5541r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
Protect and store orifice plate until ready for installation after
hydrotest and just prior to commissioning.
COMMENTS
S:\c-series\c-55\DC5542r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
Check that internal parts are clean and check for free rotation.
10
COMMENTS
S:\c-series\c-55\DC5543r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
Check that the meter is installed so that the meter is not subject
to piping strain and the meter is always full of liquid.
10
11
COMMENTS
S:\c-series\c-55\DC5544r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5545r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
1
CHECK LIST
Check valve package installation conforms to P & ID installation
details and specifications.
COMMENTS
S:\c-series\c-55\DC5546r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5547r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5548r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
10
COMMENTS
S:\c-series\c-55\DC5549r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5550r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5551r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
SUB-SYSTEM
of
TAG NUMBERS
EQUIPMENT NO.
LOCATION
ITEM
CHECK LIST
COMMENTS
S:\c-series\c-55\DC5552r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL BE EXPLICITLY
FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC REQUIREMENTS I.E. MANUFACTURER'S
RECOMMENDATIONS.
USE THIS CHECK LIST WITH SPECIFIC TYPE OF FIRE DETECTOR E.G. SMOKE, HEAT, FLAME.
GENERAL CHECKS
YES
NO
N/A
REMARKS
10
11
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5553Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL BE EXPLICITLY
FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC REQUIREMENTS I.E. MANUFACTURER'S
RECOMMENDATIONS.
USE THIS CHECK LIST WITH SPECIFIC TYPE OF FIRE DETECTOR E.G. SMOKE, HEAT, FLAME.
PRE-COMMISSIONING CHECKS
YES
12
13
14
15
16
17
18
19
20
21
22
NO
N/A
REMARKS
24
Labeling correct
25
26
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5553Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
For other checks refer to Sheet Titled 'Fire Detectors (General)'
YES
1
NO
N/A
REMARKS
10
11
12
13
Glass Sealed
classification
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5554r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL
BE EXPLICITLY FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC
REQUIREMENTS I.E. MANUFACTURER'S RECOMMENDATIONS.
YES
1
Supply fuse/MCB
10
NO
N/A
REMARKS
qualification/training
requirement and applicable standard/listing
11
12
13
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5555Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL
BE EXPLICITLY FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC
REQUIREMENTS I.E. MANUFACTURER'S RECOMMENDATIONS.
YES
22
23
24
25
26
NO
N/A
REMARKS
mount detector
See Note 1
e.g. heaters
27
28
29
30
31
32
Labeling correct
33
34
See Note 2
COMMENTS:
NOTE 1 : Any damaged detectors must be replaced. This applies to detectors with paint, grease, oil, etc. built up.
NOTE 2 : Typically using heat source to simulate the flow of heated air beneath the ceiling across the detector surface
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5555Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOOP No.
SYSTEM
TAG No.'s
P & ID
EQUIPMENT No.
TYPE / MODEL
SERIAL No.
10
DETECTOR CHECK
1
MOUNTING FIRM
ORIENTATION CORRECT
PRE-CHECK COMPLETE
MULTICORES
FIELD CABLES
LOOP CHECK
1
10
11
12
of
YES
NO
N/A
REMARKS
YES
NO
N/A
REMARKS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5556r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL BE EXPLICITLY
FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC REQUIREMENTS I.E. MANUFACTURER'S
RECOMMENDATIONS.
FOR OTHER CHECKS REFER TO SHEET TITLED "FIRE DETECTORS (GENERAL)"
INSTALLATION CHECKS
YES
10
11
12
13
14
15
16
17
18
NO
N/A
REMARKS
Interlocking Acoustic
tiles not suitable
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5557Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL BE EXPLICITLY
FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC REQUIREMENTS I.E. MANUFACTURER'S
RECOMMENDATIONS.
FOR OTHER CHECKS REFER TO SHEET TITLED "FIRE DETECTORS (GENERAL)"
PRE-COMMISSIONING CHECKS
YES
All tag plates (including those outside the duct) - duty description checked
Detector protected against dust, paint, etc. (or not installed) until
NO
N/A
REMARKS
recommendations
with manufacturer's instructions
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5557Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST SHALL BE COMPLETED USING THE SPECIFIC INFORMATION SUPPLIED BY THE GAS DETECTOR
MANUFACTURER
SOME TYPE E.G. BEAM TYPE REQUIRE SPECIFIC CHECKING TECHNIQUES I.E. USE OF OPAQUE GLASS
YES
1
NO
N/A
REMARKS
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5558r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
SYSTEM
TAG NO.
P & ID No.
of
ZONE
GAS DETECTOR MODULE
EQUIPMENT No.
EQUIPMENT No.
LOCATION
TYPE / MODEL
MANUFACTURER
INPUT RANGE
RANGE
GAS DETECTOR MODULE
YES
NO
N/A
REMARKS
YES
NO
N/A
REMARKS
10
11
12
13
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5559Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
SYSTEM
TAG NO.
P & ID No.
of
ZONE
GAS DETECTOR MODULE
EQUIPMENT No.
EQUIPMENT No.
LOCATION
TYPE / MODEL
MANUFACTURER
INPUT RANGE
RANGE
FIELD MOUNTED GAS DETECTOR
TEST / CHECKS
1
YES
NO
N/A
REMARKS
YES
NO
N/A
REMARKS
ATTACHED
GENERAL
TEST / CHECKS
1
10
11
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5559Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
FOR OTHER CHECKS REFER TO SHEET TITLED "FIRE DETECTORS (GENERAL)"
YES
Instrument to air line feeding the tubing made out of correct material
NO
N/A
REMARKS
Element re-installed
F(C)
6
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5560Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
FOR OTHER CHECKS REFER TO SHEET TITLED "FIRE DETECTORS (GENERAL)"
YES
JB location correct
10
11
Loop resistance =
12
NO
N/A
REMARKS
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5560Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
YES
1
10
11
12
13
14
15
16
17
18
19
20
21
22
23
NO
N/A
REMARKS
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5561r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL BE EXPLICITLY
FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC REQUIREMENTS I.E. MANUFACTURER'S
RECOMMENDATIONS.
YES
10
11
12
NO
N/A
REMARKS
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5562Ar0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
NOTE:
THIS CHECK LIST IS A GENERIC ONE AND THE DETECTOR MANUFACTURER'S RECOMMENDATIONS SHALL BE EXPLICITLY
FOLLOWED. THIS CHECK LIST SHALL BE AMENDED TO THE PROJECT SPECIFIC REQUIREMENTS I.E. MANUFACTURER'S
RECOMMENDATIONS.
YES
13
14
15
16
17
18
NO
N/A
REMARKS
location of detectors.
19
20
21
22
23
24
25
26
27
28
29
30
31
32
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5562Br0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
YES
1
NO
N/A
REMARKS
classification
6
10
11
12
Circuit checked for unwanted voltages between circuit conductors and ground
13
14
be damaged
15
Resistance measured and recorded for any circuit pair which is short-circuited
Resistance =
16
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5563r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
YES
1
10
11
12
13
14
15
16
17
18
19
20
21
22
NO
N/A
REMARKS
dBA
dBA
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5564r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
ITEM NO.
LOCATION
TAG NUMBER
SYSTEM NO.
P & ID NO.
MANUFACTURER
MODEL NO.
of
SERIAL NO.
YES
NO
N/A
REMARKS
Resistance =
Ohms
Resistance =
Ohms
Flow switch function tested on rig floor flowrate for s/w differential
Flow switch function tested in-situ using alarm by pass connection specifically
Integral time delay (to eliminate contact bounce effect) tested (if applicable)
10
12
13
14
COMMENTS:
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5565r0.xls
CLIENT
PLANT
LOCATION
SHEET
SERVICE
VENDOR / CONTRACTOR
of
ITEM No.
SYSTEM
P & ID No.
PIPE I.D.
INSTALLATION CORRECT
ISOLATING VALVES CORRECT
TAPINGS POSITION CORRECT
LOCATION CORRECT
MATERIALS CORRECT
ORIFICE DIAMETER
IMPULSE CONNECTIONS:
CORRECT TO HOOK-UP
PRESSURE TESTED
STEAM / ELECT. TRACED
MATERIALS CORRECT
TEST PRESSURE
LAGGED
FIELD INSTRUMENT(S):
INSTALLATION CORRECT
WEATHER PROTECTED
PANEL INSTRUMENT(S):
INSTALLATION CORRECT
SCALE / CHART CORRECT
CONTROL VALVE(S):
AIR SUPPLIES:
TEMPERATURE LOOPS:
CABLE TO SPECIFICATION
LOOP IMPEDANCE CHECKED
GENERAL:
SUPPORTS CORRECT
TAGGING CORRECT
TRANSMISSION
PNEU:
ELECT:
DATE:
LOOP TEST:
TRANSMITTER
TRANSMITTER
LOCAL INST.
PANEL INST.
OUTPUT
OUTPUT
READING
READING
CONTROL
MEASUREMENT
CHECKED:
WITNESSED BY:
DATE:
0
50%
100%
CONTROLLER
TRANSDUCER
VALVE
CONTROL
INPUT
OUTPUT
POSITIONER
OUTPUT
VALVE
POSITION
0
50%
100%
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5566r0.xls
CLIENT
PLANT
LOCATION
SERVICE
ITEM
SHEET
VENDOR / CONTRACTOR
CHECK LIST
of
ITEM No.
YES
N/A
DATE
REMARKS
SIGNED
1
2
7
8
10
11
12
13
14
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5567Ar0.xls
CLIENT
PLANT
LOCATION
SERVICE
ITEM
SHEET
VENDOR / CONTRACTOR
CHECK LIST
of
ITEM No.
YES
N/A
DATE
REMARKS
SIGNED
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5567Br0.xls
CLIENT
PLANT
LOCATION
SERVICE
ITEM
SHEET
VENDOR / CONTRACTOR
CHECK LIST
of
ITEM No.
YES
N/A
DATE
REMARKS
SIGNED
30
32
33
34
35
31
36
37
38
39
40
41
42
43
44
45
46
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5567Cr0.xls
CLIENT
PLANT
LOCATION
SERVICE
SHEET
VENDOR / CONTRACTOR
ITEM
CHECK LIST
of
ITEM No.
YES
N/A
DATE
REMARKS
SIGNED
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5567Dr0.xls
CLIENT
PLANT
LOCATION
SERVICE
ITEM
SHEET
VENDOR / CONTRACTOR
CHECK LIST
of
ITEM No.
YES
N/A
DATE
REMARKS
SIGNED
63
64
65
66
67
68
Authority having
jurisdiction may be the
Owner or the Insurance
company
COMMENTS
PRINT NAME
SIGNATURE
DATE
TESTED BY
ACCEPTED BY
VENDOR / CONTRACTOR
OWNER
COMMISSIONING TEAM
CERTIFYING AUTHORITY
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
S:\c-series\c-55\DC5567Er0.xls