Content
Introduction
Objective
Apparatus & Tools
Safety Precautions
Procedure
Result
Discussion
Conclusion
References
Appendices

Introduction

Pages

For this week practical lab for the subject Electric Machine Fundamentals
(STB24103), we are required to do a practical lab about Delta-wye transformer
connection and Wye-Delta transformer connection. A delta-wye transformer is a type
of three-phase electric power transformer design that used a delta connected
windings on its primary and wye connected windings on its secondary. Delta-wye
transformers are common in commercial, industrial, and high-density residential
locations, to supply three-phase distribution systems. Meanwhile, for the wye-delta,
wye is connected to the primary windings and delta is connected to the secondary
windings.

Objectives
1. Construct a Delta-Wye connection to the transformer.
2. Construct a Wye-Delta connection to the transformer.
3. Measure voltage phase and voltage line at the primary and secondary
windings at both transformer connection.
4. Measure current phase and current line at the primary and secondary
windings at both transformer connections.

Apparatus
1.
2.
3.
4.
5.
6.

Load resistance
Power supply
Transformer
Ammeter
Voltmeter
Multimeter

Load Resistance

Ammeter

Voltmeter

Transfomer

Power Supply

Connecting
cables

Safety Precautions
1. Carefully inspect the apparatus weather it is in a good condition to use before
start using it.
2. Make sure the power supply is switch off before connecting the power supply
cables.
3. Make sure the power supply is switch off before connecting to the transformer
and load resistance.

Procedure

Delta-Wye Connection.
1. The power supply is check to make sure it is in good condition to use.
2. Multimeter is used to check the current line at the load resistance, and the
data is recorded.
3. The power supply is connected to the transformer primary windings 1,2 and 3.
Then delta connection is done by connect input 1 to output 3, input 2 to output
1 and input 3 to output 2.
4. The load resistance is connected to the transformer secondary winding input
1,2 and 3. The the Wye connection is done by connect output 1 to output 2
and output 2 to output 3.
5. Used the multimeter to check the voltage line, voltage phase, current line and
current phase at each primary winding and the data is recorded.
6. The same step is done at the secondary winding and the data is recorded.

Wye-Delta Connection
1. The power supply is check to make sure it is in good condition to use.
2. Multimeter is used to check the current line at the load resistance, and the
data is recorded.
3 The power supply is connected to the transformer primary windings input 1,2
and 3. Then Wye connection is done by connects the output 1 to output 2 and
output 2 to output 3.
4 The load resistance is connected to the transformer secondary winding input
1,2 and 3. Then the Delta connection is done by connect input 1 to output 3,
input 2 to output 1 and input 3 to output 2.
5 Used the multimeter to check the voltage line, voltage phase, current line and
current phase at each primary winding and the data is recorded.
6 The same step is done at the secondary winding and the data is recorded.