Contractor

REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS


PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

1of 8

METHOD STATEMENT FOR FIXING


PLUGS AT INCOMING MANHOLES
OF PS 50

Date

03/05/2014

S.I.D

Prepared By

Deepak Joy
Mech Engr

Checked By

Approved By

L. Advincula
QA/QC Engr.

S.Iskander
Proj. Manager

Approval Status

Method Statement for fixing plugs at incoming manholes of PS 50


Page 1 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

2of 8

Contents

Item

Description

Page No

Objectives

Scope of Work& Location

Responsibility & Site Supervision

Preparation & Pre-Installation Work

Co-ordination with Other Trades

Sequence of Works

Tools & Tackles Required

Inspection

Health & Safety (HSE)

10

Risk Assessment Plan

11

Attachments

S.I.D

Method Statement for fixing plugs at incoming manholes of PS 50


Page 2 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

3of 8

1. Objectives
The objective of this method statement is to establish the necessary guidelines for
the shutdown of PS 50 and to check the existing plugs/put the plugs in the
incoming sewer lines of MH 50/2 & 50/1 in order to start demolition of MH 02 &
reconstruction of the same.
This method statements aims to ensure that work quality assurance and quality
control activities are conducted in a systematic manner, works are inspected and
conformance is verified and documented.
2. Scope of Work & Location
This method statement relates to Mechanical and Civil works as per consultant
instruction for the inspection and activities at PS 50 pumping station and its
incoming manholes.
3. Responsibility & Site Supervision
Responsibility for the implementation of the works by this method statement rests
ultimately with the Nass Project Manager. However, authority shall be delegated
to the Construction Manager & through him to the respective trade Site Engineers
and Foremen.
QA/QC & Safety is independent and exercises control with their chain of
command.
4. Preparation & Pre-installation Work

Materials and devices shall be arranged for the inspection.

The concerned safety officer will provide the Tool Box talk prior to start the
work at workplace.

The safety officer will check the H2S impact behavior before going into the
confined space.

S.I.D

Method Statement for fixing plugs at incoming manholes of PS 50


Page 3 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

4of 8

Housekeeping will be maintained during inspection.

All hazards will be discussed before start the work at workplace.

Safety observations will be taken into account.

Workers must secure Confined Space Entry Permit from HSE Officer prior to
making any activity in entering confined space as per Procedure for
Confined Space Entry Permit Document# 725-AA-LS-0311-0030.

All safety procedures and safety measures must be complied

Proper access/egress must be clear during confined space entry activities.

It is very necessary that concerned Safety Officer will take safety measures
and oversee as per activity at site.

Initial site setting out shall be performed, confirming existing conditions, such
as locations of services, flows, invert levels etc.

Materials and Equipments shall be moved to the work area in a safe manner
and shall not block access / egress from the site.

Safeties Method Statement shall be developed in accordance with


procedures, when there is a high risk in works are involved.

An emergency response plan will be generated and all the men who are
included in this works will be well trained to take care of the emergency
situations.

5. Co-ordination with Other Trades

S.I.D

Activity & work precedences & inter relations shall be in accordance with
the program of works

Timely meetings (as necessitated & required) shall be held between all
trades to ensure smooth execution of the works.
Method Statement for fixing plugs at incoming manholes of PS 50
Page 4 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

5of 8

6. Sequence of Works
1. A proper time is selected after discussion with the PARSONS and ASHGAL
for the shutdown as all the incoming sewer lines are gravity lines from the
nearby buildings and households.
2. Introductory meeting will take place introducing our staff to the operational
staff and describing the steps of works and operations which we are going to
do for the inspection.
3. Once the flow is very less so that a man can go inside, the H2S level is
checked and our men with all the PPE required will be going to the manhole
MH 03.
4. The existing Plug shall be checked and if found damaged, an air plug will be
fixed considering the amount of flow coming from the respective side.
5. The air plug once fixed will be supported with the wood and pipe jacks to
prevent movement afterwards.
6. Once the plugging is done for the MH 03 the bypass pumps will be started if
needed and the flow will be maintained from that side.
7. We will move on to the Manhole MH 50/2/1 and for this manhole we are using
a mechanical plug considering a lesser flow from this side gravity sewer.
8. Safety officer will check the H2S level with a calibrated device.
9. Once safety officer confirms the H2S are in safety limits, the person who is
installing the plug will be going inside the manhole.
10. Once the plugs are fixed on both sides a normal bypass operation will be
started and will be monitored frequently.
11. Ladders will be provided for the shutdown work if necessary.
12. Each person will be provided with personnel small H 2S sensing instrument for
any hazard identification.

S.I.D

Method Statement for fixing plugs at incoming manholes of PS 50


Page 5 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

6of 8

13. Persons who are meant to touch the sewerage medium during the shutdown
will be provided with hand gloves and other PPE needed if necessary.
14. Complete observation will be there till the pumping station gets to a normal
bypass operation.
15. Advance communication and notification to the Ashghal, assigned pumping
station in charge and operator before the shutdown and associated works
shall not proceed until the required sewage blocking and complete Diversion
of the flow.
7. Tools & Tackles required
Following Tools & Tackles will be made available during Construction period
1.
2.
3.
4.
5.
6.
7.
8.

Measuring Tape
H2S Sensor.
Loader
Wire sling
Chain Block
Hand Pallet Trucks
Lever chain Hoists
All Hand tools like Hammers, spanners, screw drivers, Allen Keys
shall be provided to each fitter in his Tool Box
9. Dewatering pump
10. Temporary tank for disposing of surplus fluids
11. Earthwork supports
12. Air blowers
13. Potable water
14. Vehicle for removal of pipe work, mobilization of work
15. Lights
16. Generator
17. Traffic barriers
18. Gas Detector
19. Cable Detector
20. SCBA
21. Emergency escape breathing set
22. Emergency light source
23. Lifting Frame Tripod
24. Safety Harness with lifeline attached
S.I.D

Method Statement for fixing plugs at incoming manholes of PS 50


Page 6 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

7of 8

25. Other safety tools.


8. Inspection

All the works shall be monitored for quality of workmanship against


approved method statement by the relevant Mechanical Engineer and the
Consultant.

9. Health & Safety(HSE)

ONE (1) Safety officer shall be on site during all times.

First Aid facility shall be available

Before start of work, conduct Tool Box talk to the team, explaining the
Hazards in their work during the day

Proper PPE shall be provided to all employees & visitors on site

Proper training shall be imparted to employees according to their tasks

Standard Health and Safety facilities will be provided.

Safety Rules To be implemented


Hazardous Atmospheres
Ventilation
Where there is reason to suspect oxygen deficiency or the presence of a
hazardous atmosphere, gas tests must be carried out by a qualified person.
Where necessary, mechanical ventilation shall be used, or other appropriate
precautions shall be taken before men enter. Note: Toxic, oxygen and
flammable gas tests are to be conducted before entering Restricted Areas.
Hazardous Atmospheres

S.I.D

Method Statement for fixing plugs at incoming manholes of PS 50


Page 7 of 8
Rev 00

Contractor
REFURBISHMENT AND UPGRADING WORKS FOR VARIOUS
PUMPING STATIONS PHASE 7
Project Title: :

Consultant:

PARSONS INTERNATIONAL LTD.

Document No:

725-GEN-DOC-0267

Client:

Public Works Authority (PWA)


Document Title:

METHOD STATEMENT FOR THE FIXING PLUGS AT


INCOMING MANHOLES OF PS 50

Revision No :

00

Dated :

03/05/2014

Pages :

8of 8

Prior to entry into confined spaces, a work permit shall be issued. Gas tests
shall verify that the oxygen level is 21%, combustible gases 0.0 LEL, and H2S
is 0 PPM. Additional safety measures shall be taken if the gas levels are
different and devices such as SCBA shall be used. Corrective measures may
include use of air movers, identification and isolation of sources from fuel
lines, sewers, open tanks or other measures to return the breathing
atmosphere to normal readings. Subsequent testing is required to monitor
the area during the work so appropriate precautions can be taken as
necessary.
Emergency Rescue Equipment
Emergency rescue equipment, such as breathing apparatus, a safety harness
and line, or a basket stretcher, shall be readily available where hazardous
atmospheric conditions exist or may develop during work. A standby man
outside the trench when in use will attend this equipment.
10. Risk Assessment Plan

A detailed risk assessment plan will be submitted before starting the work,.

11. Attachments
Risk assessment table.
Drawings.

S.I.D

Method Statement for fixing plugs at incoming manholes of PS 50


Page 8 of 8
Rev 00