Beruflich Dokumente
Kultur Dokumente
2.10 Assure all required permits are obtained for the projects.
2.11 During construction, advise the Owner regarding the status
of budget, schedule and quality by issuance of a Monthly Project
Report. The Project Manager will advise the Owner, in a timely
manner, of situations which have increased, or may increase the
cost of the projects; may cause a delay in the completion of the
projects; has or may result in the installation of work or material
which is not acceptable in accordance with the plans and
specifications developed for the projects.
2.12 Schedule and conduct on-site bi-weekly progress meetings involving
the Owner and Professionals to review, resolve and plan in areas such as
budget, schedule, and quality. Meeting minutes will be recorded and
distributed, including an Outstanding Action Item log, detailing the status
of key decisions, responsibility and required timing.
2.13 Review request for changes, submit written recommendations to the
Owner and negotiate Change Orders, with final terms and price subject to
approval by the Owner.
2.14 Review schedule of values and applications by the Professionals,
consultants, and General Contractor for progress and final payments.
2.15 Review the Design/Build team and General Contractors
master project schedule and advise the Owner on issues
potentially impacting timely completion.
2.16 Identify, monitor, track, and coordinate with the appropriate
stakeholders the timely resolution of project issues.
2.17 If required, establish an IT platform for the exchange of real-time
project information between the Owner, PM, Design/Build team,
Architect/Engineer, and General Contractor.
2.18 Maintain the project site for the Owner, one PDF electronic copy of
Contracts, Drawings, Specifications, Addenda, Change Orders and other
modifications, in good order, and in addition, approved Shop Drawings,
Product Data, Samples and similar required submittals. The Project
Manager will make such records available to the Owner during the
performance of the work and upon completion of the projects will deliver
them to the Owner in electronic form.
2.19 With the Owners maintenance personnel, consultants, and
commissioning agent, the PM will observe the Design/Build team and
General Contractors final testing and start-up of utilities, operational
systems, and equipment.
2.20 Coordinate all inspections to determine whether the work is
substantially complete, including review and feedback regarding
the Design/Build team and General Contractors punch-list.
2.21 Receive and review the completeness of all manuals, warranty
information, attic stock, and record drawings delivery to the Owner.
2.22 Coordinate and complete all steps required for timely project closeout. If required, provide the Owner with the documentation required to
close-out a project.
2.23 Schedule and facilitate a Lessons Learned meeting at the conclusion
2.
Emergency nozzle
3.
4.
Well ventilation
5.
Passage ways and routs leading to the warehouse should be paved and wide enough for the civil
defense vehicles passage and other security forces
6.
Emergency exits
7.
Do not pile up clothes and special fabrics etc. at the passage way
8.
Storage should leave enough space between product packs (not less than 1m. width) for easy passage
9.
Warehouses should be three meters away from the factory and well arranged
Small Smithery
1.
2.
3.
4.
Big Smithery
1.
2.
3.
4.
Small Carpentry
1.
2.
3.
Face masks
4.
No smoking signs
5.
6.
7.
8.
9.
Big carpentry
1.
2.
Fire alarm
3.
4.
5.
6.