Sie sind auf Seite 1von 60

Construction Environmental Management Plan

PROJECT: PORT BOTANY REDEVELOPMENT STAGE 1


CONSTRUCTION OF RAMP D
CONTRACT No.:
CONTROLLED COPY NO: e-copy
DISTRIBUTION LIST OF CONTROLLED COPIES
Copy
No.

Issued to

Fulton Hogan Construction

Client Representative

Project Director
Project Authorised Delegate

Construction Environmental Management Plan

Table of Contents
1.

2.

3.

4.

5.

Introduction ...................................................................................................................... 4
1.1.
Background .............................................................................................................. 4
1.2.
Purpose and Scope ................................................................................................... 4
1.3.
Project Overview ...................................................................................................... 4
1.4.
Construction phases ................................................................................................. 6
1.4.1. Site Establishment .................................................................................................... 6
1.4.2. Main Construction Works ........................................................................................ 6
1.5.
Construction Staging ................................................................................................ 6
Construction Environmental Management System Overview ......................................... 7
2.1.
Environmental Policy ............................................................................................... 7
2.2.
Construction Environmental Management Plan...................................................... 8
2.3.
Issue Specific Sub-Plans............................................................................................ 8
2.4.
Environmental Work Method Statements ............................................................... 9
2.5.
Internal Permit System............................................................................................. 9
Planning .......................................................................................................................... 10
3.1.
Environmental Aspects and Impacts ...................................................................... 10
3.2.
Statutory Requirements ......................................................................................... 10
3.2.1. Ministers Conditions of Approval (MCoA) ............................................................ 10
3.2.2. Commonwealth Consent........................................................................................ 11
3.2.3. The Development Deed ......................................................................................... 11
3.2.4. Green Port Guidelines ............................................................................................ 12
3.2.5. Port Development Code ......................................................................................... 12
3.2.6. Knuckle Management Plan .................................................................................... 12
3.3.
Environmental Objectives and Targets .................................................................. 13
Implementation and Operation ...................................................................................... 14
4.1.
Resources, Roles, Responsibilities and Authority .................................................. 14
4.2.
Competence, Training and Awareness .................................................................. 15
4.2.1. Site Induction ......................................................................................................... 15
4.2.2. Environmental Awareness Training ....................................................................... 16
4.2.3. Toolbox Talks.......................................................................................................... 16
4.3.
Communication and Consultation ......................................................................... 17
4.3.1. Liaison with Patrick ................................................................................................ 17
4.3.2. Community and Stakeholder Management ........................................................... 17
4.3.3. Managing Cumulative Impacts From Multiple Construction Works ...................... 18
4.3.4. Authority Liaison .................................................................................................... 18
4.3.5. Hours of Work ........................................................................................................ 19
4.4.
Emergency Preparedness and Incident Management ........................................... 19
Checking Performance .................................................................................................... 20
5.1.
Environmental Inspections..................................................................................... 20
5.2.
Environmental Monitoring ..................................................................................... 20
5.3.
Environmental Nonconformities ............................................................................ 20
5.4.
Audits & Reporting ................................................................................................. 20

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 3/07/2013
Page 2 of 60

Construction Environmental Management Plan

6. Document Control and Records Management .............................................................. 21


7. Review and Improvement of the CEMP.......................................................................... 21
Attachments ............................................................................................................................ 22
Attachment A.
Environmental Policy ............................................................................ 22
Attachment B.
Environmental Risk Register ................................................................. 24
Attachment C.
Summary of MCOA Requirements........................................................ 25
Attachment D.
Summary of EIS Requirements ............................................................. 38
Attachment E.
Register of Relevant Legislation............................................................ 46
Attachment F.
Environmental Inspection Report ......................................................... 51
Attachment G.
Consultation Register ........................................................................... 56

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 3/07/2013
Page 3 of 60

Construction Environmental Management Plan

1. Introduction
1.1.

Background

Patrick Stevedores Operations Pty Ltd (Patrick) operates an international shipping container terminal
(Terminal) on the land leased from NSW Ports at Brotherson Dock, Port Botany.
The Terminal loads and unloads containers from ships berthed at the dock and provides a container
stacking area for its clients. All containers are in-transit and the Terminal facilitates the transfer of goods
between the land and sea as well as using trucks and trains to transport containers to customer sites.
The objective of the Port Botany Redevelopment Project (PBRP) is to deliver the infrastructure, change
management and associated works to enable transition from a manual terminal operation to a state of the
art AutoStrad Terminal achieving best practice safety, productivity, energy efficiency and environmental
benefits. The PBRP will be completed in two construction stages as follows:
Stage 1

expansion of the existing container handling facility on reclaimed land, the Knuckle, adjacent to the
Patricks existing container terminal, and
construction of Ramp D which extends from the existing Grade Separation Works undertaken by SPC.

Stage 2

upgrading the existing terminal with new truck grids, additional rail and new road access,
construction of new administration offices, a control tower and workshop buildings, and
procurement of more ecoefficient, less noisy plant with reduced lighting requirements for night time
operation while being amenable for optimal operation as a result of terminal automation.

The NSW Minister for Planning granted staged development consent in 2005 and 2006 under the
Environmental Planning and Assessment Act 1979, subject to a number of Conditions of Approval. This
consent has since been subject to thirteen (13) modifications. In addition, the Commonwealth granted
consent in 2006 under the Environment Protection and Biodiversity Conservation Act 1999, for aspects of
the project relating to migratory birds, such as enhancement of Penrhyn Estuary.

1.2.

Purpose and Scope

This Construction Environmental Management Plan (CEMP) is prepared to cover the construction of Ramp
D only (the Project). The CEMP describes the environmental management processes and controls that
Fulton Hogan will apply during construction of the Project.
Fulton Hogan recognises that the project construction activities will result in some adverse impacts on the
environment. The purpose of this CEMP is to ensure that such activities are undertaken in an
environmentally responsible manner and that any unavoidable adverse impacts on the environment are
minimised.
It is designed to satisfy the requirements of Fulton Hogans Integrated Management System (IMS) and
AS/NZS ISO 14001:2004. This CEMP will be used as a working document to ensure that commitments and
obligations included in the Ministers Conditions of Approval (MCoA) and Environmental Impact Statement
(EIS) obligations are understood and implemented by all construction staff, including sub-contractors.

1.3.

Project Overview

The Project involves the construction of Ramp D which will complement the overall Terminal
redevelopment by providing a main entry and exit point to the Patrick container handling facility.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 4 of 60

Construction Environmental Management Plan

Ramp D is a new ramp and bridge structure that will adjoin the recently constructed Penrhyn Road elevated
roundabout (part of the Grade Separation Works), and traverse the existing rail line that services the
Patrick area of the Port.
The scope of works includes:

demolition of existing buildings and structures, including RCOS building


relocation and modification of underground services such as water, electrical and communications
installation of new services for the new ramp access such as storm water drainage and electrical for
street lighting
drilling and constructing piles to provide foundation for the bridge structure
construction of reinforced earth wall embankment and bridge abutment
construction of bridge piers and bridge deck
removal and modification of existing lighting, fencing and barriers on the existing elevated roundabout;
placement of pavement material
installation of traffic islands and kerb and gutter
installation of traffic signage, barriers, fencing and safety screening, and
placement of asphalt pavement and line marking.

Figure 1-1 below shows the project layout and location.

Ramp A
Existing Elevated
Roundabout
Limit of Works

Ramp D Construction
Envelope (Indicative)

Limit of Works

Proposed
Ramp D

Figure 1-1. Project Layout & Location

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 5 of 60

Construction Environmental Management Plan

1.4.

Construction phases

Works associated with the construction of Ramp D involve the following phases.
1.4.1.

Site Establishment

Site establishment activities will include:

assembly of site offices and facilities


temporary utility connections to services, and
installation of drainage, and sediment and erosion controls.

1.4.2.

Main Construction Works

Main construction works will commence immediately after completion of site establishment works and will
include:

services identification relocation, protection and installation


demolition of existing building and pavements
drainage works including construction of drains and protection works
construction of piling platform and piling works
earthworks and construction of the reinforced earth wall embankment
structural concrete works for bridge pier and deck construction
installation of bridge girders
construction of pavement drainage and installation of services
placement of pavement, kerb and gutter and asphalt works, and
Installation of barriers, road furniture, street lighting, line marking and signage.

1.5.

Construction Staging

Work on Ramp D is expected to commence in July 2013 and will take approximately ten months to
complete. Indicative construction schedule is shown in Figure 1-2 below.

Figure 1-2: Indicative construction schedule summary


Construction Environmental Management Plan | Ramp D Works |
Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 6 of 60

Construction Environmental Management Plan

2.

Construction Environmental Management System Overview

The Construction Environmental Management System (CEMS), consistent with the requirements of AS/NZS
ISO 14001:2004 Environmental management systems requirements with guidance for use, has been
developed by Fulton Hogan for the Project. The CEMS consists of this Construction Environmental
Management Plan (CEMP), issue specific sub-plans and other supporting documentation. The structure of
the CEMS is shown in Figure 2-1 below.
Ministers Conditions of
Approval

EIS Obligations and Other


Requirements

Corporate Environmental Management System

Construction Environmental Management Plan

Issue-specific Sub Plans

Soil and Water Management Sub-Plan

Acid Sulfate Soils Management Sub-Plan

Construction Noise Management Sub-Plan

Dust Management Sub-Plan

Waste Management Sub-Plan

Environmental Work Method Statements

Clearing and Grubbing

Dewatering

Works in Waterways

Environmental
Inspections Reports

NCR Reports

Audit Reports

Management Reviews

Figure 2-1. Project CEMS structure.

2.1.

Environmental Policy

The Commitment to Sustainability in combination with Fulton Hogans Mission and General Principles fulfils
the requirement of AS/NZ ISO 14001 and defines the Companys environmental policy.
A copy of Fulton Hogans Commitment to Sustainability, and Mission and General Principles, is included in
Attachment A.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 7 of 60

Construction Environmental Management Plan

2.2.

Construction Environmental Management Plan

This CEMP is a key component of the project-specific CEMS. It describes its main elements and provides
references to other relevant plans, procedures and work method statements that together form a
systematic approach to managing environmental risks associated with the works.
The CEMP has been prepared to meet the required standards of environmental management during the
project implementation. It is a live document that will be regularly reviewed and updated to ensure its
continuing suitability, adequacy and effectiveness.
The objectives of this CEMP are as follows:

To provide a framework for achieving the requirements of the EIS and MCoA
To describe the systems and processes that will ensure compliance with relevant legal and other
requirements
To detail environmental monitoring, reporting and auditing requirements
To outline environmental roles and responsibilities, and
To provide a basis for project induction and environmental awareness training.

This CEMP interfaces with other associated Plans, which together describe the overall management system
for the Project.
The CEMP will be forwarded to the Client Representative and relevant authorities for review and comment
or approval prior to commencement of construction.

2.3.

Issue Specific Sub-Plans

The CEMP includes issue specific sub-plans addressing the key environmental aspects and risks and how
they will be managed during construction.
The sub-plans will be forwarded to the Client Representative and relevant authorities for review and
comment or approval prior to commencement of construction.
The sub-plans required for the project are shown in the diagram below.

Construction
EMP

Fulton Hogan Construction


Environmental Management System

ASS Management Sub-Plan


Dust & Air Quality Management Sub-Plan
Noise & Vibration Management Sub-Plan
Soil & Water Management Sub-Plan
Waste & Spoil Management Sub-Plan

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 8 of 60

Construction Environmental Management Plan

2.4.

Environmental Work Method Statements

Environmental Work Method Statements (EWMSs) will be prepared for all high-risk activities, which include
but are not limited to:

Clearing and grubbing


Works in waterways
Dewatering
Management of Acid Sulphate Soils, and
Handling and disposal of contaminated material.

Fulton Hogan will develop EWMSs for the construction phase progressively. Each EWMS will involve a
detailed assessment of the environmental risks associated with the proposed activity and may also contain
information derived from site specific technical assessments undertaken by expert consultants.
EWMSs will be forwarded to the Client Representative for review prior to commencement of construction.
A register of all EWMSs will be maintained.

2.5.

Internal Permit System

An internal permits system will be maintained for all high-risk activities to ensure all required approvals are
in place and all notification and consultation obligations are met prior to activities commencing.
Each permit will include details of proposed works, justification for the works, measures to reduce impacts,
consultation with the Principals Authorised Representative (if needed), and signoffs on the permit before
release.
The list of internal permits is provided below.
Table 2-1. Internal permits
Type of activity requiring Internal Permit

Permit Title

Works in or near waterways

Works in Waterways Permit

Dewatering

Discharge/Dewatering Permit

Clearing and grubbing

Clearing and Grubbing Permit

Works in or near environmentally sensitive areas

Permit to Enter

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 9 of 60

Construction Environmental Management Plan

3.

Planning

3.1.

Environmental Aspects and Impacts

The environmental aspects and impacts associated with the works were initially identified and assessed in
the Environmental Impact Statement (EIS) and include:

water quality, erosion and sedimentation


acid sulfate soils, and contaminated soils
noise
dust
vegetation and weeds, and
waste disposal.

A summary of the MCOA requirements is included in Attachment C. A summary of the EIS requirements is
included in Attachment D.
Fulton Hogan has undertaken a risk assessment of all potential environmental impacts in accordance with
its Risk Management Procedure. The results of this risk assessment are recorded in the Environmental Risk
Register included in Attachment B.

3.2.

Statutory Requirements

A detailed list of legal and other requirements relevant to the Project is included in Attachment E. Any
changes to the existing legislation during construction will be noted and this CEMP will be reviewed and
amended accordingly.
3.2.1. Ministers Conditions of Approval (MCoA)
MCoA have been issued as part of the development consent for the entire Port Botany Expansion Project.
The consent is currently subject to 13 modifications; however, only three are applicable to the construction
of Ramp D. These are shown in Table 3-1 below.
A further modification (number 14) is currently being reviewed by DP&I, and is included in Table 3-1 below.
Table 3-1. List of modifications granted to the original development consent.
Modification

Description

Modification 5 MOD-60-92008 approved 21 September


2008

Specifies the work times allowable for construction activities that would result in
audible noise at any residential premise. Construction outside the specified hours
needs to be approved on a case by case basis.

Modification 6 MOD-68-122008 approved 12 December


2008

Repeals the conditions contained in Modification 5 provided the construction


activities are subject to an environment protection licence issued by the EPA
under the POEO Act and the EPA has approved activities to be conducted outside
the permitted hours.

Modification 13 (MOD 13)


approved 8 February 2013,

Modified the stormwater system for the Patrick knuckle area.

Modification 14 (MOD 14)


subject to DP&I approval.

Re-assesses vehicle traffic based on required activities for construction of terminal


operation infrastructure.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 10 of 60

Construction Environmental Management Plan

3.2.2. Commonwealth Consent


Commonwealth consent was granted for the Port Botany Expansion project under the Environment
Protection and Biodiversity Conservation Act 1999. The consent relates to migratory birds that inhabit the
Penrhyn Estuary and was granted on 3 January 2006. The approval conditions were modified on 7
December 2012.
SPC prepared a Habitat Enhancement Plan and is responsible for all measures in the consent. Whilst SPC is
responsible for all measures in the Commonwealth consent, as defined in the Schedule 10 of the
Development Deed, the construction works will be carried out in a manner that will minimise potential
impacts from noise and lighting on shorebirds at Penrhyn Estuary.
3.2.3. The Development Deed
The Development Deed between SPC and Patrick comprises the agreed terms under which work can be
carried out on the Project. Ramp D works can be carried out within the scope of the original consent so long
as the requirements under the Development Deed are satisfied. SPC have confirmed that no additional
approvals are required for Ramp D related works. A summary of the environmental-related obligations in
the Deed relevant to the construction phase is included in Table 3-2 below.
Table 3-2. Summary of environmental obligations.
Summary of Environment-Related Deed Obligations

Where addressed

Requirement to comply with the Dust Management Plan

Dust & Air Quality Mgmt Sub Plan

3.1 (h)

EMP is required to be prepared as per clause 30.18

CEMP

3.1 (m)

Condition B1.4 of SPC Existing Development Approval

CEMP s4.3.3

5.1 (xi)

Project to accept management, control and responsibility for


the Site and for risk in connection with Dust Management Plan

Dust & Air Quality Mgmt Sub Plan

Requirement to carry all development in accordance with the


Applicable Development Approval only

CEMP s3.2.1, Appendix C

Compliance with obligation in each Project Document including


the CEMP

CEMP s5

10.2

Conditions relating to communication with general public and


to participate in community consultation meetings regarding
project

CEMP s4.3.2

15.5

Obligations relating to Nuisance, Noise (s.15.5), Rubble (s.15.6)

Construction Noise Mgmt Sub-Plan

Section
2(g)

Waste & Spoil Mgmt Sub Plan


29

Applications to relevant authorities to obtain all approvals


necessary to lawfully construct works and in compliance with
the CEMP

CEMP s4.3.3

30.1

Duration to determine consent by SPC

CEMP s4.3.3

30.8

Consultation with Sydney Ports and address comments or


suggestions raised by SPC

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 11 of 60

Construction Environmental Management Plan

Section
30.16

Summary of Environment-Related Deed Obligations

Where addressed

Operator must comply with all approvals

30.18(i)

CEMP to be consistent with Compliance Schedule, SPC EMP and


shall provide details of legal compliance and management of
site to minimising environmental impact

31.1

Carry out, construct and complete the works in accordance


with the CEMP and Dust Management Plan and in conformity
with approvals and requirements of government agencies, NSW
and Australian Law and relevant Australian Standards

CEMP s5

Environmental Obligations including compliance with


Environmental Laws, approval conditions, minimising harm,
notification and clean up of pollution incidents, provide reports,
comply with CEMP, liability for pre-existing contamination.

CEMP

Sch. 2

Sections 10-14 & 18 specify the minimum standards for the


works relating to Stormwater, Water, Sewer, Lighting and Plant
& Equipment

NA - relates to operational
requirements

Sch. 10

Compliance Schedule in 4 parts as follows:

37

Sch.14

Dust & Air Quality Mgmt Sub Plan

Emergency Response & Incident


Mgmt Plan

Part 1: Development Consent Conditions

CEMP Appendix C

Part 2: EIS & Additional Requirements

CEMP Appendix D

Part 3: Content of the Environmental Management Plans

CEMP

Part 4: Incident Reporting Protocol

Emergency Response & Incident


Mgmt Plan

Knuckle Management Plan

Dust & Air Quality Mgmt Sub Plan

3.2.4. Green Port Guidelines


Although Green Port Guidelines primarily relate to operational activities, where applicable to construction
these guidelines will be adapted. To this end, the Green Ports Guideline compliance checklist will be
reviewed and completed prior to commencement of construction to identify the criteria that are relevant
to the construction phase and how relevant criteria have been addressed.
3.2.5. Port Development Code
The Port Development Code sets out the minimum criteria for the developments proposed for Port Botany
after June 2009 and is supported by the Green Port Guidelines. The values espoused in the Code have been
incorporated, where applicable, primarily by Patrick as input to the design consultants.
3.2.6. Knuckle Management Plan
Patrick have prepared a Knuckle Management Plan (April 2012) which contains measures for construction
of the knuckle. Measures relevant to Ramp D will be implemented by Patrick, where they are relevant.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 12 of 60

Construction Environmental Management Plan

3.3.

Environmental Objectives and Targets

When setting environmental objectives and targets for the Project, consideration was given to legal and
other requirements, the Projects potential environmental impacts, available technological options, likely
hazards and risks, operational requirements and the views of key stakeholder groups. The environmental
objectives and targets for the Project are set out in Table 3-3 below.
Table 3-3.

Environmental Objectives and Targets.

Environmental
Aspect

Objective

Target

Noise

To minimise disturbance of residents


caused by construction noise

Noise levels below applicable noise goals and


limits at sensitive receivers

Soil and water


quality

To minimise water pollution caused by


construction activities

No unauthorised discharges to receiving environment

Air quality

To minimise adverse impacts resulting


from dust generation

No instances of dust related complaints from the public

Contaminated
material

To minimise adverse impacts resulting


from contaminated material

Any contaminated material identified during the works


is contained and promptly disposed of to an
appropriately licenced facility

Heritage

To preserve any Aboriginal or nonAboriginal items of significance should


these be discovered during the
construction works

No instances of damage to heritage items

Flora and fauna

To minimise adverse impacts on


threatened flora and fauna should
these be discovered during the
construction works

No instances of damage to threatened flora and fauna

Waste

To minimise generation of waste from


the construction activities and to
maximise reuse and recycling where
appropriate

5% reduction in waste to landfill from forecasted


amount at the start of the project

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 13 of 60

Construction Environmental Management Plan

4. Implementation and Operation


4.1.

Resources, Roles, Responsibilities and Authority

The Project teams organisational structure and overall roles and responsibilities are detailed in the PMP.
The key environmental roles and responsibilities for the Project team are listed in Table 4-1 below.
The Environmental Representative (ER) as required by section B4.3 of the MCOA is to be undertaken by
Patrick. The ER is to ensure that environmental management and monitoring measures are detailed in
plans that comply with all approvals, obligations and commitments, and are implemented throughout
construction. The ER is independent and reports to DP&I and Patricks corporate environmental managers.
Table 4-1. Environmental roles and responsibilities
Role
Environmental
Engineer (EE)

Responsibilities
The Environmental Engineer is responsible for:

Project Manager

being the primary contact point in relation to the environmental performance of the
construction phase of the project
developing management plans and monitoring programs required under this CEMP
considering and advising on matters specified in the conditions of the consent, and
all other licences and approvals relating to the environmental performance and
impacts of the project
managing procedures and practices for receiving and responding to complaints and
inquiries in relation to the environmental performance project
reporting all environmental incidents and near misses to the Patrick HSEQ Manager
and ER immediately
facilitating an induction and training program for relevant persons involved with the
construction phases, and
requiring reasonable steps to be taken to avoid or minimise unintended or adverse
environmental impacts, and failing the effectiveness of such steps, to direct that
relevant actions be ceased immediately should an adverse impact on the
environment is likely to occur.

The Project Manager is responsible for:

the overall control of the Project and the CEMP


reviewing and approving the CEMP
identifying the potential environmental aspects and impacts at the Project launch
providing the necessary resources to ensure the CEMP is properly implemented
ensuring all personnel are inducted into the Project environmental requirements
prior to commencement of works on site
ensuring suppliers are made aware of the environmental objectives pertaining to
them through conditions of contract
providing leadership to the Project in following and supporting the CEMP in a public
manner to help develop a positive environmental culture supporting environmental
policy and review the performance reports and take strategic actions to continuously
improve the CEMP, and
participating in incident investigations.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 14 of 60

Construction Environmental Management Plan

Role
Project/Site Engineer

Responsibilities
The Project / site Engineer is responsible to the Project Manager for:

Foreman

ensuring all workers and subcontractors under their control are properly inducted
and instructed in the requirements of the CEMP pertaining to their part of the work
in consultation with EE and other relevant disciplines, identifying environmental risks
and nominating suitable control measures prior to commencement of construction
activities under their control, and
ensuring all work under their control, including subcontractors, is undertaken in
accordance with this CEMP and statutory environmental requirements.

The Foreman is responsible to the Project Manager for:

All employees and


sub-contractors

supervising construction activities under their control to ensure compliance with the
requirements of this CEMP and the relevant sub-plans
assisting Project/Site Engineer in identifying environmental risks and nominating
suitable control measures for activities under their control
attending environmental emergencies on site
ensuring all work under their control is undertaken in accordance with the CEMP and
statutory environmental requirements.

All Fulton Hogan employees are responsible for undertaking their work in accordance
with this CEMP and Fulton Hogan Environmental Policy as directed at their induction and
as instructed by their supervisor.
All subcontractors and suppliers are responsible for ensuring that their work or product
complies with the CEMP and the relevant sub-plans.

4.2.

Competence, Training and Awareness

The following three main forms of environmental training will be provided on site:

Site environmental induction


Environmental awareness training, and
Toolbox talks.
4.2.1. Site Induction

Prior to commencing work on site, all Project personnel including subcontractors, will attend a site
induction and all visitors will attend a visitor induction.
All Project personnel, subcontractors and consultants will be required to undertake a site induction which
will, as a minimum, address the following environmental topics:

The CEMP and consequences of non-compliance with the CEMP


The requirements of due diligence and duty of care
Conditions of environmental approvals, permits and notifications
Requirements associated with community consultation
Incident notification and reporting procedures and procedures for dealing with damage and
maintenance of erosion and sediment controls

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 15 of 60

Construction Environmental Management Plan

Boundaries for vegetation clearing and location of restricted access areas, as well as controls in regard
to clearing and/or trimming of vegetation
Erosion and sediment controls, water quality controls and sediment basin management
Hours of work
Obligations to prevent the spread of noxious weeds during construction, and
Environmental emergency response procedures.

Records of training, competency and qualifications including dates, names and trainer details, will be
registered in the Inductions Register and kept with the Project Safety Manager.
4.2.2. Environmental Awareness Training
Targeted environmental awareness training will be provided to individuals or groups of workers with a
specific authority or responsibility for environmental management or those undertaking a high risk activity.
This training will aim to achieve the level of awareness and competence appropriate to their assigned tasks.
The target groups and suggested topics are shown in Table 4-2 below.
Table 4-2. Environmental awareness training by topic and target group.
Target Group

Topic

Project Managers and


Engineers

Content and requirements of the CEMP, the sub-plans and the EWMSs

Earthworks crews

Erosion and sediment control


Management of Acid Sulfate Soils
Working in and/or near waterways
Dust control
Stockpile management

Structures Crews

Management of high noise generating activities


Works in waterways or in riparian zones
Concrete works

4.2.3. Toolbox Talks


A toolbox talk involves the dissemination of information to Project personnel at the field level. Generally
toolbox talks generally focus on safety aspects with reference to certain Project jobs or tasks. They will also
be used to disseminate environmental information. Environmental toolbox talks will cover aspects such as:

Working in or near environmentally sensitive areas


Working in waterways
Dust control
Noise management, and
Works outside standard hours.

Toolbox training will help to ensure that relevant information is communicated to the workforce and will
also provide a forum for feedback on issues of interest or concern. Toolbox training will generally be
prepared and delivered by site Environmental Engineer but may also be delivered by other authorised
persons.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 16 of 60

Construction Environmental Management Plan

4.3.

Communication and Consultation

4.3.1. Liaison with Patrick


The following two Project team members are nominated as 24 hour contacts for environmental regulatory
authorities, with the authority to take immediate action to shut down any activity, or to affect any pollution
control measure:

Irina Kliger (NSW Environmental Manager) - 0488 264 613, and


Michael Terry (Project Manager) 0416 040 587.

Patrick will be notified immediately should a pollution incident occur that causes or likely to cause harm to
the environment. An incident report will be prepared and submitted to Patrick within one working day.
Fulton Hogan will also notify Patrick immediately of any site visits by the EPA, including purpose and
outcome of the visit and any actions taken by Fulton Hogan in response to the visit.
4.3.2. Community Consultation and Complaints Handling
A number of community groups and local residents have been identified as stakeholders in relation to the
construction phase of this project. Communication with these groups, along with NSW Ports relevant
authorities and other groups is managed by Patrick as part of their community engagement for the
Redevelopment Project. Specifically:

Community engagement activities are undertaken to inform and engage relevant stakeholders
including the Port Botany Expansion Community Consultative Committee (CCC) and Port Botany
Neighbourhood Liaison Group.
Where appropriate Patrick will also proactively issue community updates/newsletters, public displays
to ensure the community is aware of potential impacts.
Representatives of the Redevelopment Project will attend and provide construction/community
updates at regular community forum meetings.

More detail is available on the community page of the Redevelopment Project website at
http://www.patrick.com.au/community/w1/i1002943/ along with the monthly community update, Q&As,
relevant construction environmental management plans and monitoring.
There is an established complaints handling process in place to respond to issues raised by stakeholders in
relation to construction. The 24 hour complaints telephone line is available to residents or stakeholders by
telephoning 1800 177 722. The complaints telephone number has been proactively communicated to local
residents and businesses, is on the Project website and has been published by local media.
Complaints received will be investigated and dealt with immediately by Patrick. A database of complaints is
held and managed by Patrick and is shared and reported on monthly to NSW Ports.
Complaints management database will record the date and time of complaint, the method by which the
complaint was made, the contact details of the complainant, the nature of the complaint/enquiry, action
taken in response, who is responsible for the action, the team member that responded to the complainant,
what follow ups (if any are required), if monitoring is required and, if so, when it will occur, the associated
follow-up and, if no action is to be taken, the reasoning why.
Project staff will be available during office hours to visit community members to discuss and investigate
where needed.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 17 of 60

Construction Environmental Management Plan

4.3.3. Managing Cumulative Impacts From Multiple Construction Works


Fulton Hogan acknowledges that multiple contractors will be undertaking construction works on the PBRP
at the same time and the potential for cumulative environmental impacts such as noise, dust, and traffic
during the construction of Ramp D. The management of common environmental issues from multiple
construction works will be coordinated by Patrick through regular meetings with Fulton Hogan and other
contractors. Fulton Hogan will implement any additional control measures agreed upon at these meetings
to minimise the adverse impact on the local communities and businesses.
4.3.4. Authority Liaison
This plan, and all environmental plans, has been designed to address client expectations and requirements,
and adequately address risks and stakeholder concerns.

Acid Sulphate Soils Management Sub-Plan

MCoA B2.6

Construction Noise & Vibration Management Sub-Plan

MCoA B2.20

Dust & Air Quality Management Sub-Plan

MCoA B2.4

Soil & Water Management Sub-Plan

MCoA B2.5

Waste & Spoil Management Sub-Plan

MCoA B2.33

Emergency Response & Incident Management Plan

MCoA B2.43

Traffic Management Plan (incl. Port Traffic Handbook)

MCoA B2.14

Construction Safety Study

MCoA B2.41

SSROC

CCC

Primary
Industries

MCoA B1.3

Randwick

EPA

CEMP

Botany

Primarily
required by

RMS

Plan

DP&I

The MCOA requires Patrick and Fulton Hogan to consult with specific authorities and stakeholders in the
preparation of this plan and sub-plans. The table below indicates approval (A) and consultation (C) required
by the MCOA for each plan. These stakeholders have been consulted during the finalisation of this plan and
related plans.

C
C

The final draft CEMP will be submitted to DP&I, EPA, Primary Industries, Botany Council and the CCC for
comment. Relevant sub-plans will be submitted to these organisations, plus RMS, Randwick Council and the
CCC.
After comments from these organisations, the draft final CEMP and sub-plans will be updated to account
for comments. The final CEMP and relevant sub-plans will be issued to DP&I for approval and compliance
certification by the DP&I. Documentation as to how Patrick and Fulton Hogan addressed stakeholder
comments during consultation is available. The final CEMP will be issued to EPA, Primary Industries and
Botany Council for information, as per the requirements of MCOA B1.3.
Fulton Hogan will not commence any work on-site until:

the CEMP and related documents are approved by DP&I;


a Compliance Certificate is issued by DP&I under MCOA B1.4.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 18 of 60

Construction Environmental Management Plan

4.3.5. Hours of Work


Construction hours are:

7am to 6pm on weekdays


8am to 1pm on Saturdays, and
No works on Sundays or public holidays.

The procedure for notifying Patrick and relevant authorities in advance of any proposed extension to hours
of work is included in the Construction Noise & Vibration Management Sub-Plan.
Some out of hours activities are likely to be required throughout the construction period. These activities
are permitted by the MCOA and may be required to be undertaken out of hours work to:

undertake works for safety reasons for protection of workers and the public;
reduce disruption to traffic and the community;
satisfy operational requirements of government agencies or authorities; or
due to unforeseen circumstances.

Where there is a requirement for out of hours activities that are not previously authorised by the MCOA,
and would be audible, Patrick is required to submit relevant information to DP&I for consideration under
Condition B2.19A of the MCOA.
This would include justification of varied construction hours, appropriate notification to sensitive receivers,
and noise reduction measures to be put in place. Appropriate community notification would be required, as
per the Community Consultation Plan.

4.4.

Emergency Preparedness and Incident Management

Environmental incidents and emergencies and management controls for dealing with these are addressed
in detail in the Incident and Emergency Response Plan (IERP).
The IERP includes:

Identification of potential environmental hazards


Risk assessment of potential environmental emergencies
Emergency response procedures for different emergency scenarios
Notification requirements and emergency contacts
Roles and responsibilities during environmental emergencies, and
Periodic testing of the emergency response procedures.

All incidents will be recorded in Fulton Hogans Case and Action Management System (CAMs) in accordance
to Fulton Hogans Case and Action Management Procedure and Incident Investigation, Reporting &
Notification Procedure.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 19 of 60

Construction Environmental Management Plan

5. Checking Performance
5.1.

Environmental Inspections

The effectiveness of site environmental controls will be assessed on a regular basis. To document this, a
number of checklists, registers and forms will be completed. These may include (but not necessarily be
limited to) the following:

Environmental inspection checklists


Audit reports, and
Nonconformities (NCRs).

These will provide a means to evaluate and verify compliance with the relevant regulatory requirements
and the contractual environmental requirements.
Site Environmental Engineer will conduct weekly site inspections and document the results of these
inspections in an Environmental Inspection Report (refer to Appendix F).
Any non-conformances identified during site inspections or through monitoring results will be investigated
to determine the cause and to ascertain the necessary corrective actions.

5.2.

Environmental Monitoring

Project environmental monitoring will comprise collection and interpretation of quantitative data to
evaluate compliance and to verify the effectiveness of the environmental controls on site.
Environmental monitoring will include:

Noise monitoring
Water quality monitoring, and
Weather monitoring.

The methodology, location and frequency of environmental monitoring are further described in issuespecific sub-plans. The environmental sampling and testing equipment used on the project will be
calibrated in accordance with the manufacturers specifications and results recorded on the Calibration
Equipment Register.

5.3.

Environmental Nonconformities

The process for managing any environmental nonconformities will be as follows:

All nonconformities will be raised through QAntrol and CAMs systems


All nonconformities will be recorded in the Environmental Actions Register
The status of NCRs will be recorded and monitored to ensure timely closure, and
The negative trends will be identified and analysed and preventive actions initiated and implemented
to prevent recurrence.

Written responses to any nonconformities raised by Patrick or the relevant authorities will be provided
within the agreed timeframes or as required by the relevant contract environmental specifications.

5.4.

Audits & Reporting

The CEMP compliance audits will be undertaken by suitably qualified and experienced Fulton Hogan
personnel not directly associated with the project every six months, with the first audit occurring no longer
than three months after commencement of construction.
The scope of internal audits may include but is not limited to:

Compliance with legislation, license, permit and approval obligations;

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 20 of 60

Construction Environmental Management Plan

Compliance with the mitigation measures in the CEMP and sub-plans;


Management of environmental nonconformities and incidents
Subcontractor management, and
Management of the environmental incidents.

Any deficiencies identified in the audit will be promptly rectified according to the level of risk.The outcomes
of internal audits may also trigger the requirement to update the CEMP and/or the sub-plans.
Patrick will undertake the Annual Independent Environmental Audit as required by section B4.5 of the
MCOA. Patrick will also undertake the Annual Environmental Management Report as required by section
B4.2 of the MCOA.

6. Document Control and Records Management


The system used for document control and records management is detailed in the Documents and Records
Management Plan. This enables the complete management of all documents, including the identification of
document or drawing lists, author and recipient management and ensuring that documents remain legible
and readily identifiable.

7. Review and Improvement of the CEMP


The CEMP will be reviewed at least annually to ensure compliance with legislative requirements and its
suitability and effectiveness for the project and other requirements. The CEMP may be reviewed more
regularly due to a change in construction activities, where targets are not achieved or in response to audit
findings.
The review may be in a form of:

formal management review


second party audit, and/or
inclusion as a separate item at site meetings.

Any revisions to the CEMP as a result of management review will be issued as per Section 4.3.3 of this Plan
and the Documents and Records Management Plan.

Revision History
Rev

Revised By

Reviewed & Approved By

Date

Description/Summary of Changes

I. Kliger

P. Nadanapatham

8/07/2013

Issued to Client

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 21 of 60

Construction Environmental Management Plan

Attachments
Attachment A.Environmental Policy
The Commitment to Sustainability in combination with Fulton Hogans Mission and General Principles fulfils
the requirement of AS/NZ ISO 14001 and defines Fulton Hogans environmental policy.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 22 of 60

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 23 of 60

Construction Environmental Management Plan

Attachment B. Environmental Risk Register


Risk
Score

Environmental Aspect

Description of Risk

Dust

Dust and particulate matter reducing air quality and


affecting local amenity

Emissions

Vehicle emmissions from plant and equipment

Low 2

Contamination

Unexpected contamination uncovered on site during


excavation or in imported fill material

Med 8

Acid Sulfate Soils (ASS)

ASS uncovered during earthworks

Asbestos

High 21

Control Measures

Responsible
Person

Dust Management Sub-Plan

Environmental
Engineer

Prestart Plant and Equipment Check

Foreman

Waste Management Sub-Plan

Environmental
Engineer

High 18

Acid Sulfate Management Sub-Plan

Environmental
Engineer

Exposure to friable asbestos fibres

High 17

Asbestos Management Procedure


Waste Management Sub-Plan

Environmental
Engineer/Foreman

Unexpected finds

Unexpected discovery of Aboriginal or Non-Aboriginal


heritage items

Med 13

Unexpected Finds Procedure

Environmental
Engineer

Vegetation

Clearing outsideclearing limits

Med 13

Clearing and Grubbing EWMS

Environmental
Engineer

Vegetation

Inadequate rehabilitation /revegetation of disturbed areas


following construction causing loss of habitat and erosion
and sediment issues

High 17

Clearing and Grubbing EWMS

Environmental
Engineer
Project Manager

Vegetation

Inadequate control of noxious weeds leading to spread of


weeds

High 17

Clearing and Grubbing EWMS

Environmental
Engineer
Project Manager

Erosion and sedimentation

Inadequate ERSED controls resulting in off site


discharges of sediment laden water

High 23

Erosion and Sedimentation Management Plan

Environmental
Engineer

Erosion and sedimentation

Inadequate management of stockpiled materials

High 21

Soil and Water Management Sub-Plan

Environmental
Engineer

Erosion and sedimentation

Mud tracking on public roads

High 23

Soil and Water Management Sub-Plan

Environmental
Engineer

Fuel and Chemical Storage

Storage of fuels, chemcials and hazardous materials


causing soil and groundwater contamination

High 17

Hazardous Chemicals Storage and Handling Procedure

Environmental
Engineer

Fuel and Chemical Storage

Fuel/Oil spills

High 17

Spills Response Procedure

Environmental
Engineer

Noise

Causing disturbace to local residents and businesses

Med 13

Noise Management Sub-Plan

Environmental
Engineer

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 24 of 60

Construction Environmental Management Plan

Attachment C. Summary of MCOA Requirements


Notes:

Only items related to the Fulton Hogan scope of works has been included in the following schedules.
Items shaded in grey are assumed to be SPC and/or Patrick responsibility

SCHEDULE A: OVERALL SCOPE OF DEVELOPMENT WORKS AND GENERAL PROVISIONS


No

A1.

Condition

Implementation

CEMP Reference

All

CEMP, section 3.2.1

GENERAL
Scope of Development

A1.1

The approved aspects of the development shall be carried out generally in accordance with:
a) Development Application DA-494-11-2003-i, lodged with Department on 26 November 2003.
b) Port Botany Expansion: Environmental Impact Statement (ten volumes), prepared by URS and dated Nov 2003;
c) Port Botany Expansion Commission of Inquiry Primary Submission (two volumes), prepared by URS dated May 2004
d) Port Botany Expansion Commission of Inquiry Supplementary Submission to EIS, prepared by URS and dated August 2004
e) Port Botany Expansion Environmental Impact Statement Supplementary Submission (two volumes), prepared by URS and dated October
2004;
f) modification application MOD-107-9-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Application: Modification of Consent
Conditions, prepared by SPC and dated September 2006;
g) modification application MOD-134-11-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Modification Wharf Structure Design,
prepared by SPC and dated November 2006;
h) modification application MOD-149-12-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Modification Application to Modify
Conditions B2.9 and B2.22 of the Port Botany Consent, prepared by SPC and dated 1 December 2006;
i) modification application MOD-78-9-2007-i, accompanied by Port Botany Expansion Modification of Conditions C2.20 & C2.25, prepared by SPC,
dated July 2007;
j) modification application MOD-60-9-2008, accompanied by Port Botany Expansion Modification of Conditions B2.46 & C2.25, prepared by SPC,
dated 27 August 2008;
k) modification application MOD-68-12-2008, accompanied by a letter from SPC dated December 2008;
l) modification application MOD-08-03-2009, accompanied by a letter from NSW Ports dated 16 February 2009 and assessment report titled Port
Botany Expansion Rail Operations Section 96(1A) Modification dated February 2009;
m) modification application 494-11-2003-I MOD 8, accompanied by an assessment report titled Port Botany Expansion Ship Turning Area

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 25 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

Dredging Section 96(1A) Modification dated May 2009;


n) modification application DA-494-11-2003-i MOD 9, accompanied by an assessment report titled Port Botany Expansion Additional High Spot
Dredging off Molineux Point Section 96(1A) Modification dated May 2009;
o) modification application DA-494-11-2003-i MOD 10, accompanied by an assessment within letter titled Port Botany Expansion Section 96(1A)
Modification - Additional Ship Turning Area Dredging dated 8 July 2009;
p) modification application DA-494-11-2003-i MOD 11, accompanied by an assessment report titled Sydney Port Botany Terminal No. 3 PKG-17.1
Planning Section 75W Modification Operations Building and Maintenance Building dated 14 September 2011;
q) modification application DA-494-11-2003-i MOD 12, accompanied by an assessment report titled Sydney Port Botany Terminal No. 3 PKG-17.1
Planning Section 75W Modification to Stormwater First Flush System dated 15 February 2012 and supplementary advice provided on 6 June 2012
in relation to other proprietary SQID devices;
r) modification application DA-494-11-2003-i MOD 13, accompanied by an assessment report titled Project No. 231658 Section 75W Modification
to Stormwater System for Southern Expansion Area dated 31 October 2012; and
s) the conditions of this consent.
Insofar as they relate to the approved development.
A1.2

In the event of an inconsistency between:

N/A

N/A

All

CEMP, section 3.2

a) the conditions of this consent and any document listed from condition A.1.1(a) to (r) inclusive, the conditions of this consent shall prevail to the
extent of the inconsistency; and
b) any document listed from condition A1.1(a) to (r) inclusive, the most recent document shall prevail to the extent of the inconsistency.
Statutory Requirements
A1.3

All licences, permits and approvals shall be obtained and maintained as required throughout the life of the development. No condition of this
consent removes the obligation to obtain, renew or comply with such licences, permits or approvals.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 26 of 60

Construction Environmental Management Plan

SCHEDULE B - CONSTRUCTION WORKS AND ONGOING ENVIRONMENTAL MANAGEMENT OF THE NON-OPERATIONAL ASPECTS OF THE TERMINAL
No

Condition

B1.

GENERAL REQUIREMENTS

Implementation

CEMP Reference

Application of Schedule
B1.1

The conditions in this Schedule of the consent relate the following aspects of the development:
a) development activities and works associated with the construction phase(s) of terminal footprint infrastructure including transportation and
delivery of materials and construction personnel to/from the site;

a) NSW PORTS &


Patrick

b) development activities associated with the construction of terminal operations infrastructure;

b) NSW PORTS &


Patrick

c) on-going management, mitigation and monitoring associated with the development, excluding direct terminal operation matters subject to the
conditions in Schedule C.
B1.2

The conditions in this Schedule of the consent must be complied with by the Applicant, or any party undertaking the activities and works referred
to under condition B1.1 on behalf of the Applicant.

CEMP, section 3.1

c) NSW PORTS &


Patrick
As above

N/A

The Applicant shall prepare a Construction Environmental Management Plan (CEMP) which, must be approved by the Director-General prior to the
commencement of any site preparation or construction works. The CEMP must:

Patrick / Fulton
Hogan

CEMP:

-Describe all activities to be undertaken on the site during site establishment and construction;

-clearly outline stages/phases of construction that require on-going environmental management monitoring and reporting up to and beyond the
commencement of operations of the terminal;

Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan

-detail statutory and other obligations that the Applicant is required to fulfil during site establishment and construction, including all approvals,
consultations and agreements required from authorities and other stakeholders, and key legislation and policies;

Patrick / Fulton
Hogan

Section 3

-include specific consideration of measures to address any requirements of the Department, DEC, DNR and the Council during site establishment
and construction;

Patrick / Fulton
Hogan

Section 4.3.3

-describe roles and responsibilities for all relevant employees involved in site establishment or construction;

Patrick / Fulton
Hogan
Patrick / Fulton
Hogan

Construction Environmental Management Plan (CEMP)


B1.3

-Describe relevant stages/phases of construction, including a work program outlining relevant timeframes for each stage/phase.

-detail how environmental performance of the site preparation and construction works will be monitored, and what actions will be taken to
address identified adverse environmental impacts;

Section 1.4
Section 1.5
Section 1.4

Section 4.1
Section 5

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 27 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

-include all Management Plans/Studies and Monitoring Programs required in this schedule;

Patrick / Fulton
Hogan

Sections 2.3, 5

-include arrangements for community consultation and complaints handling procedures during construction;

Patrick

Section 4.3.2

-be made available for public inspection after approval of the Director General.

Patrick / Fulton
Hogan

- Separate CEMPs may be prepared and submitted for works associated with the construction of the terminal footprint.

NA

NA

Patrick / Fulton
Hogan

CEMP, section
4.3.3

As above

As above

Patrick / Fulton
Hogan

Waste & Spoil


Mgmt Sub-Plan

Patrick / Fulton
Hogan

Dust & Air Quality


Mgmt Sub-Plan

Compliance Certification
B1.4

Prior to each of the events listed from a) to c) below, or within such period otherwise agreed by the Director-General, documentation certifying
that all conditions of this consent applicable prior to that event have been complied with shall be submitted to the satisfaction of the DirectorGeneral. Where an event is to be undertaken in stages, submission of compliance certification may be staged consistent with the staging of
activities relating to that event, subject to the prior agreement of the Director-General.
a) commencement of construction works associated with the development;
b) commencement of each phase of construction works established under the program required under condition B1.3; and
c) completion of each phase of construction works established under the program required by condition B1.3.
The certifying documentation shall clearly outline any on-going environmental management, monitoring or reporting requirements associated
with the concluded construction works phase.

B1.5

Notwithstanding condition B1.4, the Director-General may require an update report on compliance with all, or any part, of the conditions of this
consent. Any such update shall meet the requirements of the Director-General and be submitted within such period as the Director-General may
agree.

B2.

CONSTRUCTION ENVIRONMENTAL PERFORMANCE


Air Quality Management
Odour Impacts and Sediment Sampling

B2.1

Unless otherwise permitted by an Environment Protection Licence applicable to the development, the Applicant shall ensure that construction
works are undertaken in compliance with section 129 of the protection of the Environment Operations Act 1997. [S129 prohibits odour emission
without a licence]
Dust Management Plan

B2.4

The Applicant shall prepare a Dust Management Plan in consultation with DEC, RTA, DOP, Botany and Randwick Councils. The Applicant shall
address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative Committee in

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 28 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

preparation of the Plan. Plan must include, but not be limited to strategies in which the construction shall:
-minimise or prevent the emission of dust from the site;
-ensure that all trafficable areas and vehicle manoeuvring areas in or on the premises shall be maintained, at times, in a condition that will
minimise the generation, or emission from the premises, of wind-blown or traffic generated dust;
-ensure that all vehicles entering and leaving the site and carrying a load that may generate dust are covered at all times, except during loading
and unloading. Any such vehicles shall be covered or enclosed in a manner that will prevent emissions of dust from the vehicle at all times; and
-ensure that all dust source surfaces are sealed.
The Plan shall be approved by the Director-General prior to commencement of construction.
Soil And Water Management
Soil and Water Management Plan
B2.5

The Applicant shall prepare a Soil and Water Management Plan in consultation with DEC, RTA, DOP, DNR, Botany and Randwick Councils. The
Applicant shall address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative
Committee in preparation of the Plan. The Plan must detail erosion and sediment controls, prepared in accordance with Managing Urban
Stormwater: Soils and Construction (available from the Department of Housing) and must:

Patrick / Fulton
Hogan

Soil & Water


Mgmt Sub-Plan

Patrick / Fulton
Hogan

Acid Sulphate
Soils Mgmt SubPlan

-identify the management responses to activities that could cause soil erosion or result in the discharge of sediments and/or other pollutants
from the site;
-specify standards/performance criteria for erosion, sediment, and pollution control including water sediment basin locations and discharge
points, for example parameters, frequency, duration location and method; and
-describe what actions and measures will be implemented, the effectiveness these actions and measures and how they will be monitored during
the works, clearly indicating who will conduct the monitoring, how the results of this monitoring would be recorded; and, if any non-compliance
is detected.
The Plan shall be approved by the Director-General prior to commencement of construction.
Acid Sulphate Soils
B2.6

Prior to the commencement of construction activities, the Applicant must prepare an Acid Sulphate Soils Management Plan to assess and manage
any Acid Sulphate Soils (ASS) or potential ASS (PASS). The Plan shall be prepared in accordance with the Acid Sulphate Soils Manual 1998
published by the NSW Acid Sulphate Soil Management Advisory Committee. In the event that ASS are encountered during the works, the
Applicant shall notify the NSW Maritime Authority immediately.
Pollution Prevention

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 29 of 60

Construction Environmental Management Plan

No
B2.7

Condition

Implementation

Unless permitted through an environment protection licence applicable to the development, the Applicant must comply with section 120 of the
Protection of the Environment Operations Act 1997, which prohibits the pollution of waters. [S120 prohibits pollution without a licence.]

CEMP Reference

Patrick / Fulton
Hogan

Soil & Water


Mgmt Sub-Plan

Patrick / Fulton
Hogan

Construction Plan

Patrick / Fulton
Hogan

Traffic
Management Plan

Patrick / Fulton
Hogan

Traffic
Management Plan

Patrick / Fulton
Hogan

Traffic
Management Plan

Consultation with Sydney Water


B2.13

Prior to commencement of construction, the Applicant is required to consult with Sydney Water regarding the likely requirements from Sydney
Water for a section 73 Compliance Certificate.
Traffic, Transport and Infrastructure Management
Construction Traffic Management Plan

B2.14

Prior to the commencement of any construction works, the applicant must prepare a Construction Traffic Management Plan in consultation with
RTA, DOP, Botany and Randwick Councils and SSROC. The Applicant shall address the requirements of these organisations in the Plan. The
Applicant shall also consult with the Community Consultative Committee in preparation of the Plan. Plan must include, but not be confined to,
mitigation measures identified in EIS such as:
-identification of preferred haulage routes;
-access routes and, signage and access arrangements on site;
-measures to limit the impact on Foreshore Rd. and Botany Rd.;
-need for restrictions on delivery hours and/or routes; and,
-development of traffic management measures during construction works to ensure minimal traffic disruptions
The plan must be submitted and approved by the Director-General prior to the commencement of construction.
Safety Audit

B2.15

The Applicant must undertake safety audit in accordance with RTA guidelines upon completion of works but prior to operation to ensure the
safety of any road works, traffic management facilities, cycling and pedestrian provisions undertaken as part of the proposed works.
Port Traffic Handbook

B2.16

Prior to construction the Applicant must prepare a handbook and distribute it to drivers of construction related vehicles providing information on
accepted routes, constraints to traffic and preferred hours of use and amenities on such routes to ensure that the impact of traffic growth on
local traffic is minimised.
Rail Access to New Terminal

B2.18

The Applicant shall ensure that Grade separation of Penrhyn Road over the rail access to the new berth includes the grade separation of the
inter-terminal road over the rail access to Patricks terminal. This is required to ensure efficient operation of both road and rail access to all

NSW PORTS

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 30 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

Patrick / Fulton
Hogan

Construction Noise &


Vibration Mgmt SubPlan

existing and proposed new berths.


Noise and Vibration Management
Restrictions to Hours
B2.19

The Applicant shall only undertake construction activities associated with the project (with the exception of dredging construction activities) that
would generate an audible noise at any residential premises during the following hours:
a)

7:00 am to 6:00 pm, Mondays to Fridays, inclusive;

b)

8:00 am to 1:00 pm on Saturdays; and

c)

at no time on Sundays or public holidays.

Audible noise is defined as noise that can be heard at the receiver. This condition does not apply in the event of a direction from police or other
relevant authority for safety or emergency reasons. Note: safety or emergency reasons refers to emergency works which may need to be
undertaken to avoid loss of life, property loss and/or to prevent environmental harm.
B2.19A

The Applicant must seek the Director-Generals approval to conduct construction activities audible at residential premises (with the exception of
dredging construction activities) outside the hours specified under condition B2.19 on a case-by-case basis. In seeking the Director-Generals
approval, the Applicant shall demonstrate a need for activities to be conducted during varied hours and how local acoustic amenity will be
protected, as well as details of how the EPAs requirements with respect to the variation of hours have been addressed.

Patrick / Fulton
Hogan

Construction Noise &


Vibration Mgmt SubPlan

B2.19B

For activities subject to an environmental protection licence issued by the EPA under the Protection of the Environment Operations Act 1997,
conditions B2.19 and B2.19A do not apply if the EPA has approved activities to be conducted outside the hours permitted by condition B2.19.

Patrick / Fulton
Hogan

NA

Patrick / Fulton
Hogan

Construction Noise &


Vibration Mgmt SubPlan

Construction Noise Management Plan


B2.20

Prior to the commencement of construction, the Applicant must prepare a Construction Noise Management Plan in consultation with DEC, DOP,
Botany and Randwick Councils. The Plan shall include noise mitigation for piling works for diesel powered machinery, provision of training to
ensure that construction workers are aware of the noise created during construction and are appropriately trained to minimise noise where
possible. In addition, the Construction Noise Management Plan must:
-identify general activities that will be carried out and associated noise sources;
-assess construction noise impacts at the relevant receivers;
-provide details of overall management methods and procedures that will be implemented to control noise during the construction stage;
- identification of all feasible and reasonable measures to minimise noise and vibration, including but not limited to:
- using least noisy construction methods, vehicles, plant and equipment;

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 31 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

Patrick / Fulton
Hogan

Construction Noise
Mgmt Sub-Plan

Patrick / Fulton
Hogan

Construction Noise &


Vibration Mgmt SubPlan

- positioning and orientating noisy plant and equipment so as to minimise noise impacts on noise sensitive receivers and wildlife in Penrhyn
Estuary;
- positioning items of noisy plant and equipment as far apart as is practicable from each other;
- minimising noisy activities by adopting alternative construction measures;
- carrying out above ground loading and unloading activities as far away as is practicable from noise sensitive receivers and wildlife in Penrhyn
Estuary;
- designing each work site to minimise the need for truck reversing movements;
- ensuring all vehicles and self-propelled plant and equipment enter and leave the premises in a forward direction unless unforeseen accidents or
other unforeseeable circumstances arise that may require reversing movements, in which case minimising any such reversing movements;
- taking all practicable steps to avoid reversing movements on the surface within the premises, and where it is impracticable to avoid reversing
movements, taking all necessary steps to minimise reversing movements;
- preventing vehicle, plant and equipment queuing and idling outside the hours of construction prescribed by this consent.
-include a pro-active and reactive strategy for dealing with complaints including achieving the construction noise goals, particularly with regard to
verbal and written responses;
-detail noise monitoring, reporting and response procedures consistent with DEC requirements;
-provide for internal audits of compliance of all plant and equipment;
-indicate site establishment timetabling to minimise noise impacts;
-procedures for notifying residents of construction activities likely to affect noise amenity;
-address the requirements of DEC; and
-be approved by the Director-General prior to the commencement of any works on the site.
Construction Noise Goals
B2.21

The goal for noise from construction activities as the LA10 (15 minute) should not exceed the Rating Background Level (RBL) plus 5dB(A) at
sensitive receivers.
Other Construction Noise Matters

B2.24

The Applicant is required to identify measures to be implemented to ensure that where movement alarms are fitted to vehicles, plant or
equipment entering or operating on the site, such alarms are of a type that minimises noise at noise sensitive receivers.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 32 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

B2.25

The Applicant must install all physical noise management measures as early as is practicable during construction of the Port Botany Expansion
project.

Patrick / Fulton
Hogan

Construction Noise &


Vibration Mgmt SubPlan

B2.26

The Applicant must not undertake any blasting on the premises

Patrick / Fulton
Hogan

No blasting

Patrick / Fulton
Hogan

Waste & Spoil Mgmt


Sub-Plan

Waste Management
Construction Waste Management Plan
B2.33

Prior to the commencement of construction, the Applicant is required to prepare a Construction Waste Management Plan in consultation with
Botany Council and DEC. The Plan must provide details of proposed waste management measures to minimise production and impact of wastes
generated at the site including but not limited to:
-identification of the type and quantities of waste that would be generated, a description of how the waste would be handled, stored, re-used,
recycled, and if necessary, appropriately treated;
-identification of a designated area for the storage and collection of waste and recyclable materials top be provided on the site;
-description of how the effectiveness of these measures would be monitored and, if non-compliance detected, actions to be required;
-measures to involve and encourage employees and contractors to minimise domestic waste production on site and to reuse/recycle where
possible.
Waste Management On-site

B2.34

Management of waste must be in accordance with the environment protection licence issued by EPA under the Protection of the Environment
Operations Act 1997.

Patrick / Fulton
Hogan

NA

B2.35

All wastes and material generated on the site during construction and operation shall be classified in accordance with the DECs Environmental
Guidelines: Assessment, Classification and Management of Liquid and Non-Liquid Wastes prior to transporting the waste off site and be disposed
of to a facility that may lawfully accept the waste.

Patrick / Fulton
Hogan

Waste & Spoil Mgmt


Sub-Plan

Patrick / Fulton
Hogan

Waste & Spoil Mgmt


Sub-Plan

Hazardous and Industrial Waste


B2.36

Except as expressly permitted by a licence issued by the EPA under the Protection of the Environment Operations Act 1997, only the hazardous
and/or industrial and/or Group A waste listed below may be generated and/or stored at the premises: -waste oil/water, hydrocarbons/water
mixtures or emulsions; and -grease trap waste.
Heritage Management
Potential for Discovery of Aboriginal Heritage Objects

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 33 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

B2.39

If an Aboriginal object is discovered during the construction of the development, works should cease in the subject area and the Applicant shall
notify DEC immediately.

Patrick / Fulton
Hogan

Waste & Spoil Mgmt


Sub-Plan

Patrick / Fulton
Hogan

Construction Safety
Study

Patrick

Fire Safety Study

Patrick / Fulton
Hogan

Incident and
Emergency Response
Plan

Patrick / Fulton
Hogan

Construction Plan

Hazard & Risk Management


Construction Safety Study
B2.41

The Applicant shall prepare a Construction Safety Study prior to commencement of construction of terminal operations infrastructure, accordance
with Hazardous Industry Planning Advisory Paper No.7 Construction Safety Study Guidelines (DoP, 1992). The commissioning portion of the
Construction Safety Study may be submitted 2 months prior to commencement of commissioning. The study shall be submitted for the approval of
Director-General prior to the commencement of construction of the terminal operations infrastructure.
Fire Safety Study

B2.42

The Applicant shall prepare a Fire Safety Study prior to the commencement of construction of the terminal operations infrastructure in accordance
with Hazardous Industry Planning Advisory Paper No.2 Fire Safety Study Guidelines (DoP, 1992). The study shall be submitted for the approval of
the Director-General and the Commissioner of the NSW Fire Brigades prior to the commencement of construction of the terminal operations
infrastructure.
Emergency Incident Management
Emergency Response and Incident Management Plan

B2.43

The Applicant shall develop an Emergency Response and Incident Management Plan in consultation with DEC, DOP, Council and the Community
Consultative Committee. The Plan must be approved by the Director-General prior to the commencement of construction and shall detail:
-terminal security and public safety issues;
-effective spill containment and management;
-effective fire fighting capabilities;
-effective response to emergencies and critical incidents; and
-a single set of emergency procedures, consistent with the existing Port Botany Emergency Plan, should be developed that can be scaled as
appropriate for any incident or emergency.
Aviation Construction Management
Impact on Aviation Operations at Sydney Airport

B2.44

The Applicant shall ensure that all aspects associated with construction considers the required lateral separation distances to minimise the
interference to Sydney Airport radar and navigational systems.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 34 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

Obstacle limitation Surface


B2.46

The Applicant shall ensure that all construction equipment is below obstacle limitation surface, unless otherwise permitted by an approval under
the Airports (Protection of Airspace) Regulation 1996 and following consultation with the Department of Infrastructure, Transport, Regional
Development and Local Government, Civil Aviation Safety Authority and Sydney Airport Corporation Limited.

Patrick / Fulton
Hogan

Construction Plan

Patrick / Fulton
Hogan

Construction Plan

The Applicant must meet the following requirements in relation to community consultation and complaints management:

Patrick

Community
Consultation Plan

-all monitoring, management and reporting documents required under the development consent shall be made publicly available;

Patrick

-provide means by which public comments, inquiries and complaints can be received, and ensure that those means are adequately publicised; and

Patrick

-includes details of a register to be kept of all comments, inquiries and complaints received by the above means, including the following register
fields:

Patrick

-the date and time, where relevant, of the comment, inquiry or complaint;

Patrick

-means by which comment, inquiry, complaint was made (telephone, fax, mail, email, person);

Patrick

-any personal details of the commenter, inquirer or complainant that were provided, or if no details were provided, a note to that effect;

Patrick

-the nature of the complaint;

Patrick

-any action(s) taken by the Applicant in relation to the comment, inquiry or complaint, including any follow-up contact with the commenter,
inquirer or complainant; and

Patrick

-if no action was taken by the Applicant in relation to the comment, inquiry or complaint, the reason(s) why no action was taken.

Patrick

-Provide quarterly reports to the Department and DEC, where relevant, outlining details of complaints received.

NSW PORTS & Patrick

Terminal Construction Lighting Design


B2.47

The Applicant shall ensure design specifications of any construction lighting conform to the requirements of Regulation 94 of the Civil Aviation
Regulations 1988.

B3.

COMMUNITY INFORMATION, INVOLVEMENT AND CONSULTATION


Community Information and Complaints Handling

B3.1

B4.

ENVIRONMENTAL MANAGEMENT, REPORTING AND AUDITING


Incident Reporting

B4.1

The Director-General shall be notified of any incident with actual or potential significant off-site impacts on people or biophysical environment

Patricks / Fulton

CEMP, Section 4.3.1

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 35 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

within 12 hours of Applicant, or other relevant party undertaking the development, becoming aware of the incident. Full written detail of the
Hogan
incident shall be provided to the D-G within seven days of the date on which the incident occurred. The D-G may require additional measures to be
implemented to address the cause or impact of any incident, as it relates to this consent, reported in accordance with this condition, within such
period as the D-G may require.
Annual Environmental Management Report (AEMR)
B4.2

The Applicant must prepare an Annual Environmental Management Report for the development. The Annual Environmental Management Report
must:

Patricks

CEMP, Section 5.4

Prior to the commencement of construction, a suitably qualified and experienced Environmental Representative(s) shall be nominated and
Patricks
approved by the D-G. The Environmental Representative(s) shall be employed for the duration of the construction and the on-going management,
mitigation and monitoring associated with the development, excluding direct terminal operation matters subject to the conditions in Schedule C, or
as otherwise agreed by the D-G. The Environmental Representative shall be:

CEMP, section 4.1

-detail compliance with the conditions of this consent;


-contain a copy of the Complaints Register (for the preceding twelve-month period, exclusive of personal details) and details of how these
complaints were addressed and resolved;
-include a comparison of the environmental impacts and performance predicted in the EIS and additional information documents provided to the
Department and Commission of Inquiry;
-detail results of all environmental monitoring required under the development consent and other approvals, including interpretations and
discussion by a suitably qualified person;
-contain a list of all occasions in the preceding twelve-month period when environmental performance goals have not been achieved, indicating the
reason for failure to meet the goals and the action taken to prevent recurrence of that type of incident;
-be prepared within twelve months of commencement of construction, and every twelve months thereafter;
-be approved by the Director-General; and
-be made available for public inspection.
Environmental Representative
B4.3

a) the primary contact point in relation to environmental performance of construction phases;


b) responsible for all Management Plans and Monitoring Programs required under this consent, in relation to construction phases;
c) responsible for considering/advising on matters specified in the conditions of this consent, and all other licences and approvals relating to the
environmental performance and impacts of the construction phases;
Construction Environmental Management Plan | Ramp D Works |
Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 36 of 60

Construction Environmental Management Plan

No

Condition

Implementation

CEMP Reference

Fulton Hogan

CEMP, section 4.2

Patricks

CEMP, Section 5.4

d) responsible for the management of procedures and practices for receiving and responding to complaints & inquiries in relation to the
environmental performance of construction phases;
e) required to facilitate an induction/training program for relevant persons involved with construction phases;
f) given the authority and independence to require reasonable steps be taken to avoid or minimise unintended or adverse environmental impacts,
and failing the effectiveness of such steps, to direct that relevant actions be ceased immediately should an adverse impact on environment be
likely to occur.
Environmental Training
B4.4

Prior to commencement of any dredging, reclamation and construction an Environmental Training Program shall be developed and implemented
to establish a framework in which relevant employees will be trained in environmental management and operation of plant and equipment,
including pollution control equipment, where relevant. Program shall include, but not necessarily limited to:
a) identification of relevant employment positions associated with the development that have an operational or management role related to
environmental performance;
b) details of appropriate training requirements for relevant employees;
c) program for training relevant employees in operational and/ or management issues associated with environmental performance;
d) program to confirm/update environmental training and knowledge during employment of relevant persons.
Environmental Auditing

B4.5

Within one year of the commencement of construction and every year thereafter for the duration of construction a full independent
environmental audit shall be undertaken by a suitably qualified person/team approved by the Director-General. Audits would be made publicly
available and would:
-be carried out in accordance with ISO 14010 and ISO 14011 Procedures for Environmental Auditing;
-assess compliance with requirements of this consent, other licences/approvals;
-assess the construction against the predictions made and conclusions drawn in the development application, EIS, additional information and
Commission of Inquiry material; and
-review effectiveness of environmental management, including any environmental impact mitigation works.
Note: An independent and transparent environmental audit can verify compliance (or otherwise) with the Ministers consent and various
approvals. Auditing also provides an opportunity for continued improvement in environmental performance.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 37 of 60

Construction Environmental Management Plan

Attachment D.

Summary of EIS Requirements

Item

EIS Reference

1.

Executive Summary ES11.5


Paragraph 3

ES2 Some limited disturbance of potential acid sulphate soils may occur as a result of construction of the new
2
terminal, however, any potential acid sulphate soils within the dredged area would be contained within the
reclamation, or kept below the water level to prevent oxidisation.

Acid Sulfate Soil Management Sub-Plan

2.

Executive Summary ES12


Paragraph 1

ES3 An Environmental Management and Monitoring Plan (EMMP) would be developed and implemented in
0
accordance with management and monitoring measures set out in this EIS, statutory requirements and
conditions of approval for the project. Construction and Operation EMPs would form an integral part of the
project EMMP and would be prepared in accordance with ISO 9001:2000 and ISO 14001:1996.

CEMP

3.

Chapter 16.8.1 Paragraph 5

1622

Chapter 37.2 Table 37.1,


point 12

Page No Relevant Text

Responsibility / Actions to address

Aside from turbidity control, the following mitigation measures would be implemented to minimise the impact Soil & Water Management Sub-Plan
of the construction on surface water flow and water quality:
construction activities would be conducted in a manner that minimises the potential for spills or leaks,
including the regular inspection and maintenance of plant and equipment, and providing bunding or similar
spill containment structures for onsite fuel and oil storage;
any spills or leaks would be contained/cleaned up as quickly as possible;
resealing and revegetation of all exposed surfaces as soon as practical to prevent extended exposure to
erosion;
erosion and sediment control planning and implementation would apply to all areas which may be
disturbed. Regular inspection of all structures would occur after heavy rain and during periods of prolonged
rainfall;
a Soil and Water Management Plan (SWMP) would be prepared in accordance with the guidelines
contained in Managing Urban Stormwater - Soils and Construction Manual and incorporated into the CEMP
for the project. Details of erosion and sediment control measures would include:
temporary structures such as sedimentation ponds and silt fences surrounding stockpiles to prevent
offsite movement of sediment;
control of drainage from areas adjacent to construction areas using earth bunds and diverting structures
such as earth drains;
minimisation of traffic in construction zones and provision of dedicated parking areas; and
removal of soil from vehicle wheels and undercarriages before departing the site to reduce soil carried
offsite.

4.

Chapter 17.6.2 Paragraph 2


Chapter 37.2 Table 37.1,

1714

The SWMP for construction would be based on the Managing Urban Stormwater- Soils and Construction
Manual and incorporated in the CEMP. All work would be carried out to avoid contamination of site and the

Soil & Water Management Sub-Plan


Emergency Response & Incident Management

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 38 of 60

Construction Environmental Management Plan

Item

EIS Reference

Page No Relevant Text

points 6,17,21

surrounding areas. Contamination control measures would include:

Responsibility / Actions to address


Plan

storage and handling of all dangerous goods in accordance with AS, NSW Dangerous Goods (General)
Regulations 1999 and NSW EPA guidelines;
an emergency response plan to control fuel, oil and chemical spills;
machinery would be inspected regularly to identify any leaks;
provision of spill containment equipment (e.g. spill kits) located around the construction site; and
training of staff in spill clean-up procedures and use of spill kits.
5.

Chapter 18.5.1
Paragraph 8

1811

The SWMP for construction would be based on the Managing Urban Stormwater- Soils and Construction
Manual and would be incorporated in the Construction EMP. All work would be carried out to avoid erosion
and sedimentation of the site and the surrounding areas. Erosion and sediment control measures would
include:

Soil & Water Management Sub-Plan

temporary structures to prevent offsite movement of sediment such as sedimentation ponds and silt fences
surrounding stockpiles;
control of drainage from areas adjacent to construction areas using earth bunds and diverting structures
such as earth drains;
dust minimisation using collected stormwater where possible;
cessation of work, or implementation of further suppression measures if excessive fugitive dust emissions
are observed;
minimisation of traffic in construction zones and a dedicated parking area;
removal of soil from vehicle wheels and undercarriages; and
sealing and revegetation of all disturbed surfaces as soon as practical to prevent extended exposure to
erosion.
Erosion and sediment control planning and implementation would apply to all areas which may be disturbed.
Regular inspections would occur after heavy rain & during periods of prolonged rainfall.
6.

Chapter 21.9.1
Paragraph 1

2126

A detailed Construction Traffic Management Plan would be developed and incorporated into Construction EMP Traffic Management Plan
for the project. The plan would include detailed consideration of:
identification of preferred haulage routes;
access routes and signage, and access arrangements at the site;
measures to ensure that Foreshore Road would not be affected by:
loading/unloading from the carriageway;
queuing; and

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 39 of 60

Construction Environmental Management Plan

Item

EIS Reference

Page No Relevant Text

Responsibility / Actions to address

reversing manoeuvres during construction;


the need for restrictions on delivery hours and/or routes; and
the need for measures to protect pedestrians, cyclists and other motorists in the vicinity of the site.
provision of cleaning facilities for vehicles exiting the site.
7.

Chapter 22.5.9
Paragraph 1

2224

A Noise Management Plan would be developed and incorporated into the CEMP, including:

Construction Noise & Vibration Management


Piling noise - Where impact piling cannot be avoided, all efforts would be made to reduce noise levels from Sub-Plan
the piling hammers. Resilient dollies would be placed in between the pile and the hammer. The hammer
CEMP Section 6 and Appendix 8a
would also be shrouded to provide acoustic attenuation where practical. The exact degree of attenuation
depends on hammer design and therefore cannot be predicted accurately at this stage.
Machinery noise control Where practical, noise levels from diesel powered machinery would be reduced
by fitting noise control kits to machinery.
Awareness and training Provision of training to ensure that construction workers are aware of the noise
created during construction and are appropriately trained to minimise noise where possible.
Complaints Complaints would be assessed and responded to in a quick and effective manner.
Noise monitoring Noise monitoring would be conducted to assess impacts from construction noise at
monthly intervals and in response to any complaints which may be received.

8.

Chapter 23.8.1

2317

Dust Management Plan for construction:

Dust & Air Quality Management Sub-Plan

apply water, through the use of water trucks, to active earthwork areas, stockpiles, gravel roads and loads
of soil being transported to reduce wind blown dust emissions;
site roads to consist of coarse gravel and to be kept wet to minimize wheel generated dust emissions;
The DMP would also include safeguard measures such as:
keep the working face and areas of open excavation to a minimum;
vegetate stockpiles where material is to remain on site for long periods;
cease work if excess dust is observed, or phase down while the source is being actively investigated and
suppression measures are implemented;
restrict construction traffic to defined roads and implement a speed limit;
remove soil adhering to the wheels and undercarriage of vehicles prior to departure from the site; and
progressively landscape and vegetate areas as the construction activities proceed, where practical.

9.

Chapter 23.9.1

2318

Prior to and during construction, monitoring in areas considered most likely to receive dust impacts during
construction would be undertaken. All monitoring would be undertaken in accordance with the NSW EPA
Approved Methods for the Sampling and Analysis of Air Pollutants in NSW (2001). All monitoring devices

Dust & Air Quality Management Sub-Plan

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 40 of 60

Construction Environmental Management Plan

Item

EIS Reference

Page No Relevant Text

Responsibility / Actions to address

would be located in accordance with AS 2922-1987 Ambient Air Guide for Siting of Sampling Units.
In particular, one high-volume air sampler would be installed within the residential area to the north of
Foreshore Road, preferably to the south of Botany Road. This location is shown by dispersion modelling to
receive the greatest dust impacts during construction. This high-volume air sampler would monitor PM10
on a six-day cycle in accordance with AS 3580.9.6-1990 Particulate matter PM10 high-volume sampler
with size-selective inlet.
Three dust deposition gauges would also be installed within residential areas two in the residential area
north of Foreshore Road, and one in the Matraville residential area immediately east of Amcor (Botany Road,
Matraville). An additional dust deposition gauge would also be located in Penrhyn Estuary.
10.

Chapter 28.10.3
Paragraph 1

2820

Pursuant to and in accordance with SEPP 33 guidelines, following project approval NSW PORTS would conduct Construction Safety Study
a construction safety study, incorporating comprehensive identification of potentially hazardous incidents that
could arise during the construction of the Port Botany Expansion and setting out the organisational and
operational safeguards proposed to address such incidents.

11.

Chapter 29.4.1 Paragraph 3

29-6 Temporary construction lighting would use tinted lights where possible to minimise the attraction of insects on Construction Plan
which birds are likely to feed.

12.

Chapter 29.4.2 Paragraph 1

29-8 Should birds be attracted to the site, attempts would be made to discourage them from feeding or roosting by Waste & Spoil Management Sub-Plan
using flagging material or other deterrent methods as described [in EIS section 29.4.2 paragraph 2].

13.

Chapter 30.5.2

14.

Chapter 35.4.1
Paragraph 1

Lighting during construction and operation would be carefully selected to ensure they would not infringe the
Construction Plan
provision of Regulation 94 of the Civil Aviation Regulations 1988. During the detailed design stage, CASA would
be consulted for detailed guidance and appropriate restrictive controls.
35-4 The following mitigation measures would be undertaken during construction works and detailed in the
Construction EMP:

Dust & Air Quality Management Sub-Plan

efficient work scheduling and methods that minimize equipment idle time and double handling of material;
throttling down and switching off construction equipment when not in use;
switching off truck engines while they are waiting to access the site and while they are waiting to be loaded
and unloaded;
switching off site office equipment and lights and using optimum lighting intensity for security and safety
purposes;
careful design of temporary roads to reduce transportation distances;
regular equipment maintenance to ensure optimum ops & fuel efficiency;
the specification of energy efficient construction equipment.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 41 of 60

Construction Environmental Management Plan

Item

EIS Reference

15.

Chapter 37.2 Table 37.1


Point 17

37-3 Develop a SWMP, as part of the Construction EMP, to ensure an adequate standard is applied to control of
contaminants which could impact groundwater quality during the construction of the Port Botany Expansion.

Soil & Water Management Sub

16.

Chapter 37.2 Table 37.1


Point 21

37-3 Prepare and implement a SWMP as part of the Construction EMP to control erosion and sedimentation (as
described above).

Soil & Water Management Sub

17.

Chapter 37.2

37-5 Develop a Construction Traffic Management Plan with:

Traffic Management Plan

Table 37.1 Point 45

Page No Relevant Text

Responsibility / Actions to address

identification of preferred haulage routes;


access routes and signage, and access arrangements at the site;
measures to ensure that Foreshore Road would not be affected by loading/unloading from the carriageway,
queuing and reversing manoeuvres;
the need for restrictions on delivery hours and/or routes; and
the need for measures to protect pedestrians, cyclists and other motorists.

18.

Chapter 37.2, Table 37.1


Point 50

37-5 Reduce noise levels from piling hammers by placing resilient dollies in between pile and hammer, where practical.
The hammer would be shrouded to provide acoustic attenuation.

Construction Noise & Vibration Management


Sub

19.

Chapter 37.2, Table 37.1


Point 51

37-5 Reduce noise levels from diesel powered machinery by fitting noise control kits to machinery, where practical.

Construction Noise & Vibration Management


Sub

20.

Chapter 37.2, Table 37.1


Point 52

37-5 Conduct training to ensure construction workers are aware of noise issues and act to minimise noise where
possible.

CEMP Section 5

21.

Chapter 37.2 Table 37.1


Point 57

37-6 Keep the working face and areas of open excavation to a minimum.

Dust & Air Quality Management Sub-Plan

22.

Chapter 37.2 Table 37.1


Point 58

37-6 Apply water, through the use of water trucks, to active earthwork areas, stockpiles, gravel roads and loads of soil
being transported to reduce wind blown dust emissions.

Dust & Air Quality Management Sub-Plan

23.

Chapter 37.2 Table 37.1


Point 59

37-6 Ensure site roads consist of coarse gravel and are kept wet to minimise wheel generated dust emissions.

Dust & Air Quality Management Sub-Plan

24.

Chapter 37.2 Table 37.1


Point 60

37-6 Vegetate stockpiles where material is to remain on site for a long period of time.

Dust & Air Quality Management Sub-Plan

25.

Chapter 37.2 Table 37.1


Point 63

37-6 Cease or phase down work if excess fugitive dust is observed while the source is being actively investigated and
suppression measures are implemented.

Dust & Air Quality Management Sub-Plan

26.

Chapter 37.2 Table 37.1


Point 64

37-6 Restrict traffic to defined roads and implement a speed limit.

Dust & Air Quality Management Sub-Plan

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 42 of 60

Construction Environmental Management Plan

Item

EIS Reference

Page No Relevant Text

Responsibility / Actions to address

27.

Chapter 37.2 Table 37.1


Point 65

37-6 Remove soil adhering to the wheels and undercarriage of vehicles prior to departure from the site.

Dust & Air Quality Management Sub-Plan

28.

Chapter 37.2 Table 37.1


Point 66

37-6 Progressively landscape and vegetate areas as the construction activities proceed.

Dust & Air Quality Management Sub-Plan

29.

Chapter 37.2 Table 37.1


Point 104

37-9 All construction and operation equipment to be below the OLS

Construction Plan

30.

Chapter 37.2 Table 37.1


Point 128

3711

Empty portable toilet facilities on a regular basis by an appropriately licensed waste management contractor

Waste & Spoil Management Sub-Plan

3711

Develop and implement a WMP for the construction and operational phase in accordance with the requirements of Waste & Spoil Management Sub-Plan
the Waste Avoidance and Resource Recovery Act 2001, the Protection of the Environment Operations Act 1997, the
EPA's Environmental Guidelines: Assessment, Classification & Management of Liquid & Non-Liquid Wastes (1999),
the Botany Bay DCP 29 and the National Minimisation and Recycling Strategy.

Chapter 34.4.1 Paragraph 9


31.

Chapter 37.2 Table 37.1


Point 130
Chapter 34.4.1 Paragraphs
1,2

The Construction WMP would require that all contractors carrying out construction works record the types,
quantities and destinations of all waste material taken offsite. In addition, any licensing requirements for the
management and disposal of waste from the site would be identified in the Construction WMP. All personnel
would be advised of waste management and disposal procedures described in the Construction WMP prior to
commencing work.
32.

Chapter 37.2 Table 37.1


Point 131

3711

Minimise construction waste that requires disposal by accurately calculating materials brought to the site and
limiting materials packaging.

Waste & Spoil Management Sub-Plan

3711

Return excess construction materials which are suitable for reuse to the supplier or store for future use.

Waste & Spoil Management Sub-Plan

3711

Store construction wastes which are not suitable for reuse, but are able to be recycled, in dedicated and secure
skips prior to recycling.

Waste & Spoil Management Sub-Plan

3711

Store, in separate skips, construction wastes which cannot be recycled. The skips would be collected by a licensed
waste contractor on a regular basis and transported for disposal to a licensed landfill or recycling facility.

Waste & Spoil Management Sub-Plan

Chapter 34.4.1 Paragraph 3


33.

Chapter 37.2 Table 37.1


Point 132
Chapter 34.4.1 Paragraph 4

34.

Chapter 37.2 Table 37.1


Point 133
Chapter 34.4.1 Paragraph 4

35.

Chapter 37.2
Point 134

Table 37.1

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 43 of 60

Construction Environmental Management Plan

Item

EIS Reference

Page No Relevant Text

Responsibility / Actions to address

Chapter 34.4.1 Paragraph 4


36.

Chapter 37.2 Table 37.1


Point 135

3711

Process or shred vegetation waste (trees and shrubs) into wood chip or mulch, which would then be used in the
rehabilitation of areas disturbed during construction and for landscaping.

Waste & Spoil Management Sub-Plan

3711

Stockpile excavated soil generated during site preparation activities for reuse in landscaping activities. Any soil
which cannot be disposed of in this manner would be transported off site to a licensed landfill, after appropriate
classification for the material is carried out in accordance with NSW EPA requirements.

Waste & Spoil Management Sub-Plan

3712

Provide recycling facilities to maximise recycling of waste materials such as plastic and glass bottles/containers,
Waste & Spoil Management Sub-Plan
aluminium cans and paper/cardboard. Separate bins would be provided for food waste. Collect all domestic waste
on a regular basis and transported off site for disposal to a licensed landfill or recycling facility.

Chapter 34.4.1 Paragraph 6


37.

Chapter 37.2 Table 37.1


Point 136
Chapter 34.4.1 Paragraph 7

38.

Chapter 37.2 Table 37.1


Point 137
Chapter 34.4.1 Paragraph 8

39.

Chapter 37.2 Table 37.1


Point 138

3712

Recycle scrap metal, used parts, components and machinery where practicable.

Waste & Spoil Management Sub-Plan

40.

Chapter 37.2 Table 37.1


Point 139

3712

Waste oils and fluids from maintenance activities would be collected and stored and would either be reused on site Waste & Spoil Management Sub-Plan
or removed by a licensed waste contractor.

41.

Chapter 38.2

38-1 Prepare Environmental Management and Monitoring Plan for construction.

CEMP

42.

Chapter 38.2

38-3 Prepare Emergency Response & Incident Management Plan for construction.

Emergency Response & Incident Management


Plan

43.

Chapter 38.5 Table 38.2


Point 1

38-4 Monitor compliance of the construction activities with the Construction EMP, including EPA requirements and
MCOA, on an ongoing basis.

CEMP

44.

Chapter 38.5 Table 38.2


Point 5

38-5 Monitor erosion and sediment control structures in accordance with the SWMP prepared in accordance with the
guidelines contained in Managing Urban Stormwater - Soils and Construction Manual and incorporated into the
CEMP.

CEMP

45.

Chapter 38.5 Table 38.2


Point 7

38-5 Monitor construction activities in accordance with the ASSMP.

CEMP

46.

Chapter 38.5 Table 38.2


Point 8,12

38-5 Monitor the extent of construction areas to ensure they do not extend beyond the defined construction zone

CEMP

47.

Chapter 38.5 Table 38.2


Point 15

38-6 Visual inspection of construction zones to ensure construction vehicles are using defined roads and access points.

Traffic Management Plan, CEMP

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 44 of 60

Construction Environmental Management Plan

Item

EIS Reference

Page No Relevant Text

Responsibility / Actions to address

48.

Chapter 38.5 Table 38.2


Point 16

38-6 Check that on site trucks are not overloaded, that they adhere to speed limits, that their trays are covered and that Traffic Management Plan, CEMP
materials are loaded and unloaded carefully.

49.

Chapter 38.5 Table 38.2


Point 17

38-6 Check that trucks arriving at the site before it opens are parked in designated holding areas and not on adjacent
streets.

Traffic Management Plan, CEMP

50.

Chapter 38.5 Table 38.2


Point 18

38-6 Conduct investigative noise monitoring in response to specific complaints.

Construction Noise & Vibration Management


Plan, CEMP

51.

Chapter 38.5 Table 38.2


Point 19

38-6 Conduct noise monitoring in the vicinity of residential areas and sensitive receiver locations for each stage of
construction prior to construction of infrastructure and facilities on the new terminal itself

Construction Noise Management Plan,

52.

Chapter 38.5 Table 38.2


Point 20

38-6 Visually monitor dust generation from work zones to ensure that excessive dust is not being produced.

Dust Management Plan, CEMP

53.

Chapter 38.5 Table 38.2


Point 21

38-6 Inspect sites to ensure that adequate dust controls are being used such as regularly watering unsealed areas.

Dust Management Plan, CEMP

54.

Chapter 38.5 Table 38.2


Point 22

38-6 Monitor dust impacts using a high-volume air sampler, dust deposition gauges and onsite meteorological station in Dust Management Plan, CEMP
accordance with the EPA Approved Methods for the Sampling & Analysis of Air Pollutants (2001). Locate
monitoring devices in accordance with AS 2922-1987 - Ambient Air - Guide for Siting of Sampling Units.

55.

Chapter 38.5 Table 38.2


Point 24

38-6 Report any heritage relics discovered during construction activities to NPWS for Aboriginal relics or Heritage Office
for items of European heritage. Cease works pending their consideration.

Waste & Spoil Management Sub-Plan

56.

Chapter 38.5 Table 38.2


Point 14

38-6 Inspect waste receptacles to ensure that they are not being overfilled and are being collected on a regular basis.

Waste & Spoil Management Sub-Plan

57.

Chapter 38.5 Table 38.2


Point 14

38-6 Inspect construction zones to monitor for any unauthorised waste disposal activity.

Waste & Spoil Management Sub-Plan

58.

Chapter 38.5 Table 38.2


Point 14

38-6 Inspect the construction site to evaluate the effectiveness of waste storage and collection practices.

Waste & Spoil Management Sub-Plan

59.

Chapter 38.5 Table 38.2


Point 14

38-6 Inspect any portable toilet facilities to ensure they are being emptied on a regular basis.

Waste & Spoil Management Sub-Plan

60.

Chapter 38.5 Table 38.2


Point 14

38-6 Monitor waste recycling and disposal procedures to ensure they are being complied with.

Waste & Spoil Management Sub-Plan

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 45 of 60

Construction Environmental Management Plan

Attachment E. Register of Relevant Legislation


Legislation

Key Requirements

Relevance to the Project

Mechanism for Evaluating


Compliance

New South Wales


Contaminated Land
Management Act
1997

The main objective of this Act is to establish a process for investigating and remediating land areas where
contamination presents a significant risk of harm to human health or some other aspect of the environment.
Under this act EPA has the power to:

Declare an investigation site and order and investigation


Declare a remediation site and order remediation to take place
Agree to a voluntary proposal to investigate or remediate a site

Some spoil may be contaminated


as a result of previous off-site
activities. Where contaminated
material is found, storage and
disposal procedures are to
comply with the Contaminated
Land Management Act 1997.

Measures for testing,


handling and disposing of
contaminated spoil are in
the Waste & Spoil
Management Sub-Plan..
Testing is used to ensure
compliance.

Environmentally
Hazardous Chemicals
Act 1985

The purpose of this Act is to control chemicals that are environmentally hazardous. EPA may make chemical
control orders (CCOs) with respect to assessed chemicals or declared chemical wastes. The CCOs may regulate
the manufacture, processing, conveying, buying, selling or disposal of chemical or declared waste. A CCO may
prohibit activities in relation to declared chemical wastes, except under the authority of a licence issued by EPA.

Certain chemicals used or


generated may be subject to
handling and disposal
requirements in this Act.

Measures for identification,


handling, disposal of
hazardous wastes are in the
Waste & Spoil Management
Sub-Plan.

Environmental
Planning and
Assessment Act 1979
(EP&A Act)

The main objective of the EP&A Act is to ensure that proper management and development of land is
undertaken incorporating the ecologically sustainable development principles. To achieve this the EP&A Act:

NSW PORTS has satisfied the


requirements of the EP&A Act
1979 to date and has obtained
development consent for the
project.
No requirements for further
development consent are
anticipated.

Conditions to the
development approval
(Ministers Conditions of
Approval) are tracked via
CEMP Appendix 2A.

Relates to any Aboriginal heritage


or relics, and protection of flora
and fauna.
No Aboriginal heritage is
anticipated in the project area
due to previous reclamation, and
minimal cutting.

Aboriginal heritage
measures are in the Waste
& Spoil Management SubPlan.

Construction of structures over

Specific requirements for

National Parks and


Wildlife Act 1974

Ensures compliance with planning consents and conditions associated with the consent;
Ensures environmental assessment is undertaken prior to development consent;
Has provision for penalties to be issued should development conditions be breached.

Under this Act, NPWS is responsible for the care, control and management of all national parks, historic sites,
nature reserves, reserves, Aboriginal areas and state game reserves. The Act governs various activities
including:

Protection of the

Ensures that development consent is obtained prior to construction;

Protection of flora and fauna, and Aboriginal heritage;


Licences and approvals to modify or destroy flora, fauna or Aboriginal heritage;
Penalties for breaches of the Act.

The POEO Act is the key piece of environment protection legislation, and is administered by the EPA. The

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 46 of 60

Construction Environmental Management Plan

Legislation
Environment
Operations Act 1997
(POEO Act)

Key Requirements

Relevance to the Project

objective of the Act is to protect restore and enhance the quality of the environment in NSW with a need to
maintain ecologically sustainable development. To achieve this the following tools are employed:

Integrated environment protection licensing;


Regulation of scheduled and non-scheduled activities;
Environmental protection offences and penalties;
Environmental protection notices;

Mechanism for Evaluating


Compliance

railway systems is an activity that


is required to be licenced.
Environmental protection
offences and penalties, and a
duty to notify of environmental
harm, apply to all personnel
working on the project.

compliance are in the CEMP


and sub-plans.
Training on POEO Act
offences and penalties, and
duty to notify, are included
in induction processes.

Construction activities require


environmental protection
licences.

Specific requirements for


compliance are in the CEMP
and sub-plans.

Noise emissions from machinery.

Measures for reducing

Establishment of a general duty to notify of environmental harm;

Powers for authorised officers to investigate actual or potential pollution events.


Schedule 1 of the POEO Act lists activities that are subject to environmental licensing.
In addition to the main objective, the POEO Act assists in achieving the objectives of the Waste Avoidance and
Resource Recovery Act 2001.
POEO (General)
Regulation 1998

The Regulation:
sets out how to calculate fees for environment protection licences, environment protection notices and
noise control notices, and makes provision for adjustment or refunds of those fees;
makes provisions for load reduction agreements (load reduction agreements allow for fee rebates in return
for measures taken to reduce pollution in the future);
sets out matters to be included by the EPA for the grant or refusal of a licence application;
makes it an offence to provide false or misleading information in relation to a licence application;
requires licensees to retain records used to calculate licence fees;
gives effect to the National Environment Protection (National Pollutant Inventory) Measure by requiring
occupiers of certain facilities to submit data relating to the emission of certain substances;
prescribes certain matter when placed into water to be water pollution, and the methodology for testing
matter in waters;
exempts certain water pollution from the water pollution offence under the Protection of the Environment
Operations Act 1997;
prescribes certain forms to be used with respect to warrants relating to noise abatement directions;
declares certain bodies to be the appropriate regulatory authority in relation to certain activities for the
purposes of the Protection of the Environment Operations Act 1997;

POEO (Noise Control)

This Regulation repeals and remakes, with minor amendments, the provisions of the Protection of the

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 47 of 60

Construction Environmental Management Plan

Legislation
Regulation 2008

Key Requirements

Relevance to the Project

Environment Operations (Noise Control) Regulation 2000:

Mechanism for Evaluating


Compliance
noise are in the
Construction Noise &
Vibration Mgmt Sub-Plan.

the sounding of sirens and similar devices and the use of sound systems on vessels,
the emission of noise from the engines or exhausts of motor vehicles and vessels,
the maintenance of noise control equipment on motor vehicles and vessels,
the issue of defective vehicle notices and defective vessel notices,
the times during which it is not permissible to use certain articles if they emit noise that can be heard in any
residential premises,
the inspection and testing procedures for the purpose of determining noise emission levels of certain motor
vehicles, motor vehicle accessories, vessels, articles or equipment.
POEO (Penalty
Notices) Regulation
2004

This Regulation:
sets out the offences under the Protection of the Environment Operations Act 1997 and related Acts and
regulations for which penalty notices may be issued, and the amount of such fines;
specifies the organisations authorised to issue penalty notices for particular offences; and
authorises the service of a penalty notice relating to an offence, applying to an owner of a motor vehicle or
vessel, on the owner without naming the address of the owner and by leaving the penalty notice on that
vehicle or vessel.

Environmental protection
offences and penalties, and a
duty to notify of environmental
harm, apply to all personnel
working on the project.

Training on POEO Act


offences and penalties, and
duty to notify, are included
in induction processes.

POEO (Waste)
Regulation 2005

Schedule 1 of the regulation sets out the types of waste to which waste tracking requirements apply.

Certain chemicals used or


generated may be subject to
tracking requirements in this
regulation.

Measures for tracking


hazardous wastes are in the
Waste & Spoil Management
Sub-Plan.

Protection of the
Environment
Operations
Amendment (Schedul
ed Activities and
Waste) Regulation
2008

This framework uses a mix of legislative, policy, educative and economic tools to encourage waste avoidance
and the further recovery of resources. This new framework includes:

Altered definitions of waste


categories and disposal
requirements.

Changes made by this


amendment regulation
have been included in the
Waste & Spoil Management
Sub-Plan.

Waste Avoidance
and Resource

This Act promotes waste avoidance and resource recovery by:

Waste is generated during


construction. The principles of

Measures for minimising,


handling, recycling and

Fewer and simpler licensing categories for waste;

A streamlined waste classification system;

New resource recovery licensing categories and resource recovery exemptions; and

Clearer requirements for managing asbestos and clinical waste.


The waste regulatory framework is administered under the principal legislation of the Protection of the
Environment Operations Act 1997 and the Waste Avoidance and Resource Recovery Act 2001.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 48 of 60

Construction Environmental Management Plan

Legislation
Recovery Act 2001

Key Requirements

Relevance to the Project

Encouraging efficient use of resources in accord with ecologically sustainable principles;


Promoting the Avoid, reuse, recycle, dispose hierarchy;

Mechanism for Evaluating


Compliance

the Act are applied to all aspects


of construction to reduce impacts
from waste.

disposal of wastes are in


the Waste & Spoil
Management Sub-Plan.

Ensuring industry has a responsibility for reducing and dealing with waste;
Providing penalties for breaches of this Act.

Water Act 1912

An Act consolidating water rights, water and drainage and artesian wells. Provisions include a licence
requirement to sink or alter an artesian bore, not to waste water taken from dams, lakes, artesian wells and
bores, and not to unlawfully interfere with sub-surface water or obstruct its flow.

Construction works are within


the groundwater extraction
exclusion zone regulating bore
use. No bore use is expected.

N/A

Water Management
Act 2000 and
Water Management
(General) Regulation
2004

The Water Management Act 2000 is the main piece of water legislation in NSW and governs:

Groundwater extraction is not


possible, as construction works
are within the groundwater
extraction exclusion zone. No
bore use is expected.
NSW Maritime indicated that
they do not require a Controlled
Activity Application from NSW
PORTS for this project.

N/A

NSW PORTS has obtained


Commonwealth approval, which
involves migratory and
threatened species protected by
the Act.
Many shorebirds within Botany
Bay are directly protected as
listed threatened species and/or
listed migratory species. Many
aquatic fauna species are listed
as protected.

NSW PORTS is responsible


for complying with consent
conditions under the EPBC
Act, as defined by Deed
Schedule 19.
Procedures for protecting
Penrhyn Estuary are
contained in the Penrhyn
Estuary Protection Plan.

Extraction of water from waterways and bores


The construction of water storage and supply structures
Development or building within the proximity of waterways
Licencing to regulate usage of water resources

Works involving the removal of obstructions from the improvement of rivers and foreshores and the
prevention of erosion of lands by tidal and non-tidal waters
Permits are required to excavate protected land, remove material from protected land or do anything to
detrimentally affect the flow of waters.
Commonwealth
Environment
Protection and
Biodiversity
Conservation Act
1999
(EPBC Act)

This Act aims to protect the environment, particularly matters of National Environmental Significance (NES).
Approval is required for actions that are likely to have a significant impact on:

a matter of national environmental significance;

certain activities in Commonwealth reserves;

environment of Commonwealth land (even if taken outside Commonwealth land);

environment anywhere in the world if the action is undertaken by the Commonwealth.


Permits are required under the EPBC Act for:
activities that affect listed species or communities in Commonwealth areas; cetaceans in Commonwealth
waters and outside Australian waters.
The Act contains compliance and enforcement mechanisms such as court injunctions, required environmental
audits, strict civil and criminal penalties, remediation of environmental damage, liability of executive officers,

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 49 of 60

Construction Environmental Management Plan

Legislation

Key Requirements

Relevance to the Project

Mechanism for Evaluating


Compliance

and publicising contraventions.


Hazardous Waste
(Regulation of
Exports and Imports)
Act 1989

This Act regulates export and import of hazardous waste to ensure that hazardous waste is disposed of safely.
The Act requires that a permit be obtained before hazardous waste is exported from Australia or imported into
Australia.

It is not anticipated that any


hazardous wastes will need to be
exported.

N/A

SEPP 33 -Hazardous
and Offensive
Development

Provides new definitions for 'hazardous industry', 'hazardous storage establishment', 'offensive industry' and
'offensive storage establishment'. These enable decisions to approve or refuse a development to be based on
the merit of proposal. The policy also requires specified matters to be considered for proposals that are
'potentially hazardous' or 'potentially offensive'. The policy does not change the role of councils as consent
authorities, land zoning, or designated development provisions of the EP&A Act.

No relevance.

SEPP 55 Remediation of Land

Introduces state-wide planning controls for remediation of contaminated land. Land must not be developed if it
is unsuitable for a proposed use because it is contaminated. If the land is unsuitable, remediation must take
place before the land is developed. The policy makes remediation permissible across the State, defines when
consent is required, requires all remediation to comply with standards, ensures land is investigated if
contamination is suspected, and requires councils to be notified of all remediation proposals. To assist councils
and developers, the Department, in conjunction with the Environment Protection Authority, has prepared
Managing Land Contamination: Planning Guidelines.

If contaminated soil is found,


storage and disposal procedures
are to comply with the
Contaminated Land Management
Act 1997.

SEPP (Infrastructure)
2007

Provides a consistent planning regime for infrastructure and the provision of services across NSW, along with
providing for consultation with relevant public authorities during the assessment process. The SEPP supports
greater flexibility in the location of infrastructure and service facilities along with improved regulatory certainty
and efficiency.

No relevance.

Botany LEP 1995

to provide planning controls for the local government area of Botany Bay City which update and consolidate
into a single local environmental plan the various local planning controls that currently apply to the local
government area of Botany Bay City;

Provides zoning of area in and


adjacent to project boundaries.
Provides items of local heritage
significance.

Key Policies

to give the Council greater responsibility in environmental planning by creating broad controls;

Measures for testing,


handling and disposing of
contaminated soil are in the
Waste & Spoil Management
Sub-Plan.

to rationalise and simplify zoning and development controls; and


to provide direction and guidance to the community concerning desired growth and change in the local
government area of Botany Bay City.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or unsigned.


Copyright 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013
Page 50 of 60

Construction Environmental Management Plan

Attachment F. Environmental Inspection Report


Inspected by:
Inspection date:
Inspection time:
Rain in the last 24hrs
(mm)?
Weather conditions1:
Location/
Chainage

Sunny

Issue

Scattered clouds

Action Required

Light showers

Rain

Thunderstorm

By Whom

By When

Completion
Sign Off

Windy

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 51 of 60

Construction Environmental Management Plan

Additional notes or observations:

Results of the inspection have been discussed at Site Meeting/Toolbox Talk

Yes No

Results of the inspection have been communicated to:

Foreman
Earthworks Manager
Structures Manager
Project Director

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 52 of 60

Construction Environmental Management Plan

Site environmental performance evaluation criteria


The following criteria are to be used when undertaking site environmental inspections:
General
The site is generally in a tidy condition
All materials and equipment are contained within the project boundary
All works are undertaken within the project boundary
Designated impervious bunded concrete wash out facilities are in place and positioned at least 50m away from natural and built drainage lines, where
practicable
Clean Water Diversion
All clean water is being diverted away from the disturbed areas
All clean water diversion drains are stable
Soil Disturbance and Erosion Control
The sediment fence is installed correctly and there are no gaps
All disturbed area where no works are undertaken are properly covered or stabilised
Areas of localised soil erosion have been identified and appropriate preventative measures implemented
There are no areas of potential or actual concentrated flow that do not flow to sediment basins/traps
Slope lengths are maintained at appropriate lengths to slow flows down and minimise erosion

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 53 of 60

Construction Environmental Management Plan

Check dams are used within diversion drains where required to slow flows down and minimise erosion within the drains
Geotextile linings (or similar) is used to provide temporary surface protection in areas where appropriate (e.g. batter drains, culvert construction)
Stockpile Management
Stockpiles are sited in low-hazard areas clear of watercourses and flood prone lands
Cut-off drains on the upslope side and sediment fencing on the downslope side are in place for all stockpile areas within the site
Stockpiles are less than 2m in height
Sediment Control
Sediment control measures are constructed as close to the potential source of sediment as possible
Shakers, rubble pads or wash down areas have been installed and used to minimise the tracking of mud and soil material onto local roads
There is no mud on the roads outside of the project boundary
Sediment fencing or equivalent is provided downslope of disturbed areas that cant be directed into a designated sediment basin
Sediment Basins and Traps
The volume markers intact and clearly visible
The inlets and outlets are stable
Accumulated sediment is below 30% of the sediment storage zone
The basins been emptied since the last rain event and restored to their design capacity (if not, explanation must be provided)

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 54 of 60

Construction Environmental Management Plan

All discharges are undertaken in accordance with Dewatering Permits


Air Quality
No visible dust leaving the sites boundary
Dust suppression, i.e. water cart, is being used to minimise dust emissions
Clearing
Clearing limits and work boundaries are established and well defined
Clearing and Grubbing Permits have been issued for all current clearing works

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 55 of 60

Construction Environmental Management Plan

Attachment G. Consultation Register

PORT BOTANY RAMP D


CONSULTATION REGISTER
Stakeholder
DP&I

Contact address
Ingrid Ilias
Department of Planning & Infrastructure
Major Projects Assessments

Contact email
Ingrid.Ilias@planning.nsw.gov.au
9228 6411

GPO Box 39
Sydney
NSW 2001

EPA

Sarah Deards / Jennifer Sage


Regional Operations Officer
NSW Environment Protection Authority
Level 14 59-61 Goulburn Street
Sydney
NSW 2000

sarah.deards@epa.nsw.gov.au
9995-5000

Documents Sent
CEMP
Acid Sulfate Soils Management Sub-Plan
Construction Noise Management Sub-Plan

Second Phone
Call

Third Phone Call

Package Sent

Confirmation of
Package Received

Feedback

Comment on Feedback

Consultation
Complete

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

12/06/2013

19/06/2013

Spoke to Jennifer Sage and


had refered onto appropriate
department. Will get
department head to call me
27/6/13 or 28/6/13

6/06/2013 (by post)

Yes

Left Message

Left Message
Returned message
extended response
date to 27/6/13

12/06/2013

N/A

N/A

6/06/2013 (by post)


12/06/2013 (by email)

Dust & Air Quality Management Sub-Plan


Soil and Water Management Sub-Plan
Waste & Spoil Management Sub-Plan
Emergency Response and Incident
Management Plan
Traffic Management Plan
Construction Safety Study
CEMP
Acid Sulfate Soils Management Sub-Plan
Construction Noise Management Sub-Plan
Dust & Air Quality Management Sub-Plan

Soil and Water Management Sub-Plan


Waste & Spoil Management Sub-Plan

DPI Fisheries Carla Ganassin


NSW Department of Primary Industries
PO Box 21
CRONULLA
NSW 2230

Initial Phone
Call

carla.ganassin@dpi.nsw.gov.au
9527 8552 4254-5527

Emergency Response and Incident


Management Plan
CEMP
Soil and Water Management Sub-Plan

Thank you for forwarding the environmental management plans in


No comment on documentation provided
regards with the above mentioned project for our records. The
Environmental Protection Authority (EPA) encourages the development
of such plans to ensure that proponents have determined how they will
meet their statutory obligations and designated environmental
objectives. However, we do not approve or endorse these documents
as our role is to set environmental objectives for environmental
management, not to be directly involved in the development of strategies
to achieve those objectives.

Yes

Fisheries NSW has no objections to the mitigation measures proposed in the


attached plans.

Yes

No objection to documentation provided

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 56 of 60

Construction Environmental Management Plan

Stakeholder
RMS

Botany
Council

Contact address

Contact email

Documents Sent

Nicolas Kocoski
NSW Transport Roads and Maritime
Services
Locked Bag 5100
Camperdown 1450

Nicolas.KOCOSKI@rms.nsw.gov.au
8849-2328

Dust & Air Quality Management Sub-Plan


Soil and Water Management Sub-Plan
Traffic Management Plan

Stephen Poulton
City of Botany Bay Council
PO Box 331
141 Coward Street
MASCOT
NSW 2020

shephenp@botanybay.nsw.gov.a CEMP
u
Construction Noise Management Sub-Plan
9366-3666

Initial Phone
Call

Second Phone
Call

12/06/2013

19/06/2013
Left Message

Third Phone Call

Package Sent

Confirmation of
Package Received

N/A

6/06/2013 (by post)

Yes

Emergency Response and Incident


Management Plan
Traffic Management Plan

Consultation
Complete

Comment on Feedback

I have reviewed the traffic management plan you have submitted.


Please note that I can only comment on the Traffic Management Plan,
not the Dust and Air Quality Management sub plan and the Soil and
Water management sub plan.
I have been involved in the Port Botany expansion works since it has
started so I am aware of all the current works and planned works ahead.
Please note that all regulatory signage proposed on the local road
network, even within the ports itself, approval from Botany Council must
be obtained. The Transport Management Centre will be issuing any
Road Occupancy Licenses.
RMS main concern is the operation of Foreshore Rd and Botany Rd
Acknowledged
and in particular the traffic signals at Botany/Foreshore Rd. RMS
will monitor the usage of the right turn bay on Foreshore Rd
into Penrhyn Rd. The existing right turn bay is approx. 135m, if traffic
queues out of the right turn bay onto Foreshore Rd and effect the
through movement, the number of truck movements will be revisited.

Yes

We do not require any additional information or amendments


Satisfied that all key criteria for these plans have been incorporated into
the document and at this stage has no issues with the development

Dust & Air Quality Management Sub-Plan

Soil and Water Management Sub-Plan


Waste & Spoil Management Sub-Plan

Feedback

Satisfied that all key criteria for these plans have been incorporated into
the document and at this stage has no issues with the development
12/06/2013

19/06/2013
Spoke to Stephen P
and extended
response date to
28/6/13

N/A

6/06/2013 (by post)

Yes

We do not require any additional information or amendments


We do not require any additional information or amendments

Any regulatory signposting (e.g. No Stopping, No Parking, Works


Zone) during the
construction period will need to be approved by the City of Botany Bays
(CoBB) Local Traffic Committee as CoBB is the Road Authority of
Penrhyn Road.
Any lane occupancy on Penrhyn Road due to construction activities will
need to be
approved by CoBB.
Construction truck layover in Botany Road or any residential streets
within the LGA
will not be allowed.
Any construction staff parking in any residential streets within the LGA
will not be
allowed.
CoBB will need to be informed should there is any change in the
approved CTMP
(e.g. projected truck routes, number and types of delivery vehicles etc.)

Yes

None proposed

Agreed. ROL will be required to do demolition work


where the new bridge connects to the existing
roundabout. This is now included in the TCP under
clause 6.7.
Acknowledged

None proposed

Agreed.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 57 of 60

Construction Environmental Management Plan

Stakeholder
Randwick
Council

Contact address
Bronwyn Englaro
Randwick City Council
30 Frances Street
RANDWICK
NSW 2031

Contact email

Documents Sent

Initial Phone
Call

Second Phone
Call

Third Phone Call

Package Sent

Confirmation of
Package Received

bronwyn.englaro@randwick.nsw.gov.a Construction Noise Management Sub-Plan


u
9399-0999

Dust & Air Quality Management Sub-Plan

Feedback

Consultation
Complete

Comment on Feedback

Council supports transparency of noise monitoring data. To


demonstrate a which
commitment to transparency Council recommend that these monthly
noise monitoring reports be made accessible to the community via a
project website. Noise monitoring data that has been provided by
SICTL during their construction works via their website have been well
received by the community.
Council receives noise nuisance complaints from the Port related
operations
particularly in streets located on elevated topographies. Subsequently
Council supports Patrick's commitment to notifying the community 1
week in advance of noisy activities as specified in the construction noise
sub plan. As Council understands that the designated community
extends to Randwick LGA, Council recommends that these community
notifications could be most effectively achieved via notifications in the
local community newspaper i.e. the southern courier which would
remove the need for extensive letterboxing/mail outs.

Noise and dust monitoring data will be accessible to


the community via a project website.

Council recommends monitoring measures take into consideration of


cumulative
impacts of Dust from multiple construction activities occurring at the
terminal at the same time especially during periods of high winds.

Cumulative impacts have been addressed in sect


4.3.3 of the CEMP.

Notifications will be done via local community


newspaper as well as by letterbox drops.

Details on proposed dust suppression measures appears to be limited Noted. Details of dust suppresion mitigation
and the
measures and the equipment to be used are detailed
sub plan provides little details of on site equipment and operational
in Sections 5 and 7 of the AQDMP.
procedures with regard to these activities. Council suggests that this
plan demonstrate how dust suppression activities will be carried out and
to confirm the required equipment for this will be on site and operational
as and when required throughout the project's duration.
As per noise monitoring and reporting Council recommends that dust
monitoring
reports be made accessible to the community via a project website.
Soil and Water Management Sub-Plan

Traffic Management Plan

12/06/2013

19/06/2013

Left Message

N/A

6/06/2013 (by post)

Yes

As above

This plan states the use of groundwater for dust suppression activities Agreed. SWMP has been revised accordingly.
whereas the dust management sub plan states the use of rainwater tank
or sea water for dust suppression. Due to potential inhalation risk from
possible volatiles in the groundwater Council suggests that the dust
plan recommendations be utilised to minimise this exposure risk.
Council suggest consideration cumulative traffic impact in this TMP
in conjunction with other
construction activities occurring at terminal 3 and in the vicinity of the
Port.
A project requirement should be that no construction vehicle
stacking, loading
or unloading shall occur on, or in a manner that adversely affects the
flow of traffic along Foreshore Road and Council is pleased to see that
a designated on site truck waiting facility is being provided.
Council also recommends that onsite signage and other
communications
mechanisms be utilised to notify visitors/uers of alternative access
arrangements to roads, cycle ways and footpaths during works.

Yes

Covered under clause 5.4 of the TMP.

TMP includes a truck parking bay (Figure 4) to


mitigate construction traffic impact on operations.

Acknowledged. Traffic control plans will


further detail necessary signage.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 58 of 60

Construction Environmental Management Plan

Stakeholder

Contact address

CCC, via Roberta Ryan / Susan Rudland


CCC chair Urbis JHD Pty Ltd
Level 21, 321 Kent Street
SYDNEY
NSW 2000

SSROC

Helen Sloane
Southern Sydney Region of Councils
PO Box 536
HURSTVILLE
NSW 1481

Contact email
rryan@urbis.com.au
Also contact Shane Hobday:
shobday@sydneyports.com.au
8233-9900

hs@ssroc.nsw.gov.au
9330 6455

Sydney Ports P. Engelen, S. Hobday, P. Jerogin


Corporation

Documents Sent
CEMP
Acid Sulfate Soils Management Sub-Plan
Construction Noise Management Sub-Plan
Dust & Air Quality Management Sub-Plan
Soil and Water Management Sub-Plan
Waste & Spoil Management Sub-Plan
Emergency Response and Incident
Management Plan
Traffic Management Plan
Construction Safety Study
Traffic Management Plan

CEMP

Acid Sulfate Soils Management Sub-Plan

Construction Noise Management Sub-Plan

Initial Phone
Call

Second Phone
Call

12/06/2013

41437

N/A
Package was
returned not known
at address.
Confirmed with
Patricks (Emmanuel
Diacos) that ther is
no need to resend
as Susan Rudland
has a copy of all
plans.
N/A

N/A

N/A

Third Phone Call

Package Sent

Confirmation of
Package Received

Feedback

Comment on Feedback

N/A

6/06/2013 (by post)

N/A

No Comments received

N/A

6/06/2013 (by post)

Yes
12/06/2013

TMP Section 6.3

Confirmed over the phone that no feedback on document provided

Existing pedestrian access (towards Patrick terminal and SPOC


building) via elevated roundabout is impacted by Ramp D works and
Ramp D construction traffic. Patrick propose to separate pedestrian 2m
wide path with concrete barriers. Please provide detail of this proposal:
is there enough space for 2m wide path plus barriers? Also will barriers
be structurally connected to protect against impact from trucks? Please
address in TMP.

TMP Section 5.4.2 Access via the Caltex site and across the SICTL rail area is not
permitted, unless specific approval is obtained from both Caltex and
SICTL (as well as NSW Ports). This is highly unlikely in view of the
SICTL rail construction and rail operations in respectively 2013 and
2014.
TMP Section 5.4 Please address the exiting construction traffic from 'southern' site. Will
this exit via the Cargolink facility? Review turning circles.

Consultation
Complete

Yes

TMP has been modified to show the vehicle


movements and cross section demonstrating that the
proposed 2m wide pedestrian access is feasible and
does not impact port operations. (clause 6.3)
Structural connection is under consideration however
connection to the existing bridge structure may affect
the integrity of the waterproofing in place and also
provide an avenue for water ingress. There is
potential for the durability to be compromised.

Item removed from plan

Revised plan included in new draft under Figure 4


showing construction traffic entering the site with the
site boundary fence moved to eliminate impact on
opertational traffic. Vehicles will be abble to turn right
off the roundabout if front of gate B110 and enter the
site which will be seperate from the Land Restricted
Zone.

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 59 of 60

Construction Environmental Management Plan

Stakeholder

Contact address

Contact email

Documents Sent

Initial Phone
Call

Second Phone
Call

Third Phone Call

Package Sent

Confirmation of
Package Received

Feedback

Dust & Air Quality Management Sub-Plan

TMP Section 5.4

From the diagram it is understood that entering traffic to southern site


See revised plan under Figure 4.
will enter via Cargolink. Please clarify by elaborating in text of TMP. How
will this impact queuing on Ramp B and ensure functioning of the
roundabout at bottom of Ramp B? Address and ensure that all Patrick
bound traffic on Ramp B is using the left lane.

Soil and Water Management Sub-Plan

TMP Section 5.4

Waste & Spoil Management Sub-Plan


Emergency Response and Incident
Management Plan
Traffic Management Plan

TMP Section 5.4


TMP Section 5.4

Access to main 'northern' site is via Ramp C (please correct text in 5.4
that states 'Ramp B').
Review signage based on above required changes.
Address pedestrian access to the construction site.

Construction Safety Study

TMP Section 5

With this proposal and the concurrent construction of the Knuckle and
Ramp D, Patrick will introduce significant construction traffic
movements on the roundabout at the bottom of Ramp C. The
roundabout was not initially designed to cater for the additional entry /
exit lanes. NSW Ports requires Patrick to confirm that Patrick has full
responsibility of the traffic on and the operation of that roundabout. NSW
Ports requires that Patrick confirm the safety of the roundabout by
means of a road safety audit.
Incident and
Reference should be made to the Port Botany Emergency Alarm Radio
Emergency
(PBEAR) which s located at the Patrick Gatehouse and is the primary
Response Plan means for notifying other facilities in the Port that there is an incident on
the Patrick site. A PBEAR unit is also located and monitored at the
Mascot Police Station. The system is routinely tested every Thursday
morning.
CEMP - Section 1 Please include a section acknowledging and addressing the issue of
multiple construction contractors undertaking construction works on the
PBE at the same time and need for coordination and management of
common environmental issues (i.e. noise, dust, complaints, water,
traffic etc)
CEMP - General Please include table of all comments reviewed from stakeholders
identifying all comments, how they have been addressed and where
they have been addressed in the management plans.
CEMP - General

Consultation
Complete

Comment on Feedback

Correction made
Signage ammended accordingly
There will be no pedestrian access to the
construction site. All personnel will arrive by vehicle
Includeded that FH will undertake a road safety audit
once initial traffic control has been implemented to
enable the works. (clause 8.1)

Includeded in plan

Addressed in Sect 4.3.3 of the CEMP

A number of stakeholder have asked for extention of


deadline for submission of comments till next week.
The comments will be collated and included in the
CEMP by 28/06/13.
All references to SPC / Sydney Ports Corporation to be changed to NSW Changed.
Ports

Construction Environmental Management Plan | Ramp D Works |


Content ID: 7ZA-CEMP
Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet.


Copyright 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13
Page 60 of 60

Das könnte Ihnen auch gefallen