Beruflich Dokumente
Kultur Dokumente
Issued to
Client Representative
Project Director
Project Authorised Delegate
Table of Contents
1.
2.
3.
4.
5.
Introduction ...................................................................................................................... 4
1.1.
Background .............................................................................................................. 4
1.2.
Purpose and Scope ................................................................................................... 4
1.3.
Project Overview ...................................................................................................... 4
1.4.
Construction phases ................................................................................................. 6
1.4.1. Site Establishment .................................................................................................... 6
1.4.2. Main Construction Works ........................................................................................ 6
1.5.
Construction Staging ................................................................................................ 6
Construction Environmental Management System Overview ......................................... 7
2.1.
Environmental Policy ............................................................................................... 7
2.2.
Construction Environmental Management Plan...................................................... 8
2.3.
Issue Specific Sub-Plans............................................................................................ 8
2.4.
Environmental Work Method Statements ............................................................... 9
2.5.
Internal Permit System............................................................................................. 9
Planning .......................................................................................................................... 10
3.1.
Environmental Aspects and Impacts ...................................................................... 10
3.2.
Statutory Requirements ......................................................................................... 10
3.2.1. Ministers Conditions of Approval (MCoA) ............................................................ 10
3.2.2. Commonwealth Consent........................................................................................ 11
3.2.3. The Development Deed ......................................................................................... 11
3.2.4. Green Port Guidelines ............................................................................................ 12
3.2.5. Port Development Code ......................................................................................... 12
3.2.6. Knuckle Management Plan .................................................................................... 12
3.3.
Environmental Objectives and Targets .................................................................. 13
Implementation and Operation ...................................................................................... 14
4.1.
Resources, Roles, Responsibilities and Authority .................................................. 14
4.2.
Competence, Training and Awareness .................................................................. 15
4.2.1. Site Induction ......................................................................................................... 15
4.2.2. Environmental Awareness Training ....................................................................... 16
4.2.3. Toolbox Talks.......................................................................................................... 16
4.3.
Communication and Consultation ......................................................................... 17
4.3.1. Liaison with Patrick ................................................................................................ 17
4.3.2. Community and Stakeholder Management ........................................................... 17
4.3.3. Managing Cumulative Impacts From Multiple Construction Works ...................... 18
4.3.4. Authority Liaison .................................................................................................... 18
4.3.5. Hours of Work ........................................................................................................ 19
4.4.
Emergency Preparedness and Incident Management ........................................... 19
Checking Performance .................................................................................................... 20
5.1.
Environmental Inspections..................................................................................... 20
5.2.
Environmental Monitoring ..................................................................................... 20
5.3.
Environmental Nonconformities ............................................................................ 20
5.4.
Audits & Reporting ................................................................................................. 20
Revised: 3/07/2013
Page 2 of 60
Revised: 3/07/2013
Page 3 of 60
1. Introduction
1.1.
Background
Patrick Stevedores Operations Pty Ltd (Patrick) operates an international shipping container terminal
(Terminal) on the land leased from NSW Ports at Brotherson Dock, Port Botany.
The Terminal loads and unloads containers from ships berthed at the dock and provides a container
stacking area for its clients. All containers are in-transit and the Terminal facilitates the transfer of goods
between the land and sea as well as using trucks and trains to transport containers to customer sites.
The objective of the Port Botany Redevelopment Project (PBRP) is to deliver the infrastructure, change
management and associated works to enable transition from a manual terminal operation to a state of the
art AutoStrad Terminal achieving best practice safety, productivity, energy efficiency and environmental
benefits. The PBRP will be completed in two construction stages as follows:
Stage 1
expansion of the existing container handling facility on reclaimed land, the Knuckle, adjacent to the
Patricks existing container terminal, and
construction of Ramp D which extends from the existing Grade Separation Works undertaken by SPC.
Stage 2
upgrading the existing terminal with new truck grids, additional rail and new road access,
construction of new administration offices, a control tower and workshop buildings, and
procurement of more ecoefficient, less noisy plant with reduced lighting requirements for night time
operation while being amenable for optimal operation as a result of terminal automation.
The NSW Minister for Planning granted staged development consent in 2005 and 2006 under the
Environmental Planning and Assessment Act 1979, subject to a number of Conditions of Approval. This
consent has since been subject to thirteen (13) modifications. In addition, the Commonwealth granted
consent in 2006 under the Environment Protection and Biodiversity Conservation Act 1999, for aspects of
the project relating to migratory birds, such as enhancement of Penrhyn Estuary.
1.2.
This Construction Environmental Management Plan (CEMP) is prepared to cover the construction of Ramp
D only (the Project). The CEMP describes the environmental management processes and controls that
Fulton Hogan will apply during construction of the Project.
Fulton Hogan recognises that the project construction activities will result in some adverse impacts on the
environment. The purpose of this CEMP is to ensure that such activities are undertaken in an
environmentally responsible manner and that any unavoidable adverse impacts on the environment are
minimised.
It is designed to satisfy the requirements of Fulton Hogans Integrated Management System (IMS) and
AS/NZS ISO 14001:2004. This CEMP will be used as a working document to ensure that commitments and
obligations included in the Ministers Conditions of Approval (MCoA) and Environmental Impact Statement
(EIS) obligations are understood and implemented by all construction staff, including sub-contractors.
1.3.
Project Overview
The Project involves the construction of Ramp D which will complement the overall Terminal
redevelopment by providing a main entry and exit point to the Patrick container handling facility.
Revised: 03/07/13
Page 4 of 60
Ramp D is a new ramp and bridge structure that will adjoin the recently constructed Penrhyn Road elevated
roundabout (part of the Grade Separation Works), and traverse the existing rail line that services the
Patrick area of the Port.
The scope of works includes:
Ramp A
Existing Elevated
Roundabout
Limit of Works
Ramp D Construction
Envelope (Indicative)
Limit of Works
Proposed
Ramp D
Revised: 03/07/13
Page 5 of 60
1.4.
Construction phases
Works associated with the construction of Ramp D involve the following phases.
1.4.1.
Site Establishment
1.4.2.
Main construction works will commence immediately after completion of site establishment works and will
include:
1.5.
Construction Staging
Work on Ramp D is expected to commence in July 2013 and will take approximately ten months to
complete. Indicative construction schedule is shown in Figure 1-2 below.
Revised: 03/07/13
Page 6 of 60
2.
The Construction Environmental Management System (CEMS), consistent with the requirements of AS/NZS
ISO 14001:2004 Environmental management systems requirements with guidance for use, has been
developed by Fulton Hogan for the Project. The CEMS consists of this Construction Environmental
Management Plan (CEMP), issue specific sub-plans and other supporting documentation. The structure of
the CEMS is shown in Figure 2-1 below.
Ministers Conditions of
Approval
Dewatering
Works in Waterways
Environmental
Inspections Reports
NCR Reports
Audit Reports
Management Reviews
2.1.
Environmental Policy
The Commitment to Sustainability in combination with Fulton Hogans Mission and General Principles fulfils
the requirement of AS/NZ ISO 14001 and defines the Companys environmental policy.
A copy of Fulton Hogans Commitment to Sustainability, and Mission and General Principles, is included in
Attachment A.
Revised: 03/07/13
Page 7 of 60
2.2.
This CEMP is a key component of the project-specific CEMS. It describes its main elements and provides
references to other relevant plans, procedures and work method statements that together form a
systematic approach to managing environmental risks associated with the works.
The CEMP has been prepared to meet the required standards of environmental management during the
project implementation. It is a live document that will be regularly reviewed and updated to ensure its
continuing suitability, adequacy and effectiveness.
The objectives of this CEMP are as follows:
To provide a framework for achieving the requirements of the EIS and MCoA
To describe the systems and processes that will ensure compliance with relevant legal and other
requirements
To detail environmental monitoring, reporting and auditing requirements
To outline environmental roles and responsibilities, and
To provide a basis for project induction and environmental awareness training.
This CEMP interfaces with other associated Plans, which together describe the overall management system
for the Project.
The CEMP will be forwarded to the Client Representative and relevant authorities for review and comment
or approval prior to commencement of construction.
2.3.
The CEMP includes issue specific sub-plans addressing the key environmental aspects and risks and how
they will be managed during construction.
The sub-plans will be forwarded to the Client Representative and relevant authorities for review and
comment or approval prior to commencement of construction.
The sub-plans required for the project are shown in the diagram below.
Construction
EMP
Revised: 03/07/13
Page 8 of 60
2.4.
Environmental Work Method Statements (EWMSs) will be prepared for all high-risk activities, which include
but are not limited to:
Fulton Hogan will develop EWMSs for the construction phase progressively. Each EWMS will involve a
detailed assessment of the environmental risks associated with the proposed activity and may also contain
information derived from site specific technical assessments undertaken by expert consultants.
EWMSs will be forwarded to the Client Representative for review prior to commencement of construction.
A register of all EWMSs will be maintained.
2.5.
An internal permits system will be maintained for all high-risk activities to ensure all required approvals are
in place and all notification and consultation obligations are met prior to activities commencing.
Each permit will include details of proposed works, justification for the works, measures to reduce impacts,
consultation with the Principals Authorised Representative (if needed), and signoffs on the permit before
release.
The list of internal permits is provided below.
Table 2-1. Internal permits
Type of activity requiring Internal Permit
Permit Title
Dewatering
Discharge/Dewatering Permit
Permit to Enter
Revised: 03/07/13
Page 9 of 60
3.
Planning
3.1.
The environmental aspects and impacts associated with the works were initially identified and assessed in
the Environmental Impact Statement (EIS) and include:
A summary of the MCOA requirements is included in Attachment C. A summary of the EIS requirements is
included in Attachment D.
Fulton Hogan has undertaken a risk assessment of all potential environmental impacts in accordance with
its Risk Management Procedure. The results of this risk assessment are recorded in the Environmental Risk
Register included in Attachment B.
3.2.
Statutory Requirements
A detailed list of legal and other requirements relevant to the Project is included in Attachment E. Any
changes to the existing legislation during construction will be noted and this CEMP will be reviewed and
amended accordingly.
3.2.1. Ministers Conditions of Approval (MCoA)
MCoA have been issued as part of the development consent for the entire Port Botany Expansion Project.
The consent is currently subject to 13 modifications; however, only three are applicable to the construction
of Ramp D. These are shown in Table 3-1 below.
A further modification (number 14) is currently being reviewed by DP&I, and is included in Table 3-1 below.
Table 3-1. List of modifications granted to the original development consent.
Modification
Description
Specifies the work times allowable for construction activities that would result in
audible noise at any residential premise. Construction outside the specified hours
needs to be approved on a case by case basis.
Revised: 03/07/13
Page 10 of 60
Where addressed
3.1 (h)
CEMP
3.1 (m)
CEMP s4.3.3
5.1 (xi)
CEMP s5
10.2
CEMP s4.3.2
15.5
Section
2(g)
CEMP s4.3.3
30.1
CEMP s4.3.3
30.8
Revised: 03/07/13
Page 11 of 60
Section
30.16
Where addressed
30.18(i)
31.1
CEMP s5
CEMP
Sch. 2
NA - relates to operational
requirements
Sch. 10
37
Sch.14
CEMP Appendix C
CEMP Appendix D
CEMP
Revised: 03/07/13
Page 12 of 60
3.3.
When setting environmental objectives and targets for the Project, consideration was given to legal and
other requirements, the Projects potential environmental impacts, available technological options, likely
hazards and risks, operational requirements and the views of key stakeholder groups. The environmental
objectives and targets for the Project are set out in Table 3-3 below.
Table 3-3.
Environmental
Aspect
Objective
Target
Noise
Air quality
Contaminated
material
Heritage
Waste
Revised: 03/07/13
Page 13 of 60
The Project teams organisational structure and overall roles and responsibilities are detailed in the PMP.
The key environmental roles and responsibilities for the Project team are listed in Table 4-1 below.
The Environmental Representative (ER) as required by section B4.3 of the MCOA is to be undertaken by
Patrick. The ER is to ensure that environmental management and monitoring measures are detailed in
plans that comply with all approvals, obligations and commitments, and are implemented throughout
construction. The ER is independent and reports to DP&I and Patricks corporate environmental managers.
Table 4-1. Environmental roles and responsibilities
Role
Environmental
Engineer (EE)
Responsibilities
The Environmental Engineer is responsible for:
Project Manager
being the primary contact point in relation to the environmental performance of the
construction phase of the project
developing management plans and monitoring programs required under this CEMP
considering and advising on matters specified in the conditions of the consent, and
all other licences and approvals relating to the environmental performance and
impacts of the project
managing procedures and practices for receiving and responding to complaints and
inquiries in relation to the environmental performance project
reporting all environmental incidents and near misses to the Patrick HSEQ Manager
and ER immediately
facilitating an induction and training program for relevant persons involved with the
construction phases, and
requiring reasonable steps to be taken to avoid or minimise unintended or adverse
environmental impacts, and failing the effectiveness of such steps, to direct that
relevant actions be ceased immediately should an adverse impact on the
environment is likely to occur.
Revised: 03/07/13
Page 14 of 60
Role
Project/Site Engineer
Responsibilities
The Project / site Engineer is responsible to the Project Manager for:
Foreman
ensuring all workers and subcontractors under their control are properly inducted
and instructed in the requirements of the CEMP pertaining to their part of the work
in consultation with EE and other relevant disciplines, identifying environmental risks
and nominating suitable control measures prior to commencement of construction
activities under their control, and
ensuring all work under their control, including subcontractors, is undertaken in
accordance with this CEMP and statutory environmental requirements.
supervising construction activities under their control to ensure compliance with the
requirements of this CEMP and the relevant sub-plans
assisting Project/Site Engineer in identifying environmental risks and nominating
suitable control measures for activities under their control
attending environmental emergencies on site
ensuring all work under their control is undertaken in accordance with the CEMP and
statutory environmental requirements.
All Fulton Hogan employees are responsible for undertaking their work in accordance
with this CEMP and Fulton Hogan Environmental Policy as directed at their induction and
as instructed by their supervisor.
All subcontractors and suppliers are responsible for ensuring that their work or product
complies with the CEMP and the relevant sub-plans.
4.2.
The following three main forms of environmental training will be provided on site:
Prior to commencing work on site, all Project personnel including subcontractors, will attend a site
induction and all visitors will attend a visitor induction.
All Project personnel, subcontractors and consultants will be required to undertake a site induction which
will, as a minimum, address the following environmental topics:
Revised: 03/07/13
Page 15 of 60
Boundaries for vegetation clearing and location of restricted access areas, as well as controls in regard
to clearing and/or trimming of vegetation
Erosion and sediment controls, water quality controls and sediment basin management
Hours of work
Obligations to prevent the spread of noxious weeds during construction, and
Environmental emergency response procedures.
Records of training, competency and qualifications including dates, names and trainer details, will be
registered in the Inductions Register and kept with the Project Safety Manager.
4.2.2. Environmental Awareness Training
Targeted environmental awareness training will be provided to individuals or groups of workers with a
specific authority or responsibility for environmental management or those undertaking a high risk activity.
This training will aim to achieve the level of awareness and competence appropriate to their assigned tasks.
The target groups and suggested topics are shown in Table 4-2 below.
Table 4-2. Environmental awareness training by topic and target group.
Target Group
Topic
Content and requirements of the CEMP, the sub-plans and the EWMSs
Earthworks crews
Structures Crews
Toolbox training will help to ensure that relevant information is communicated to the workforce and will
also provide a forum for feedback on issues of interest or concern. Toolbox training will generally be
prepared and delivered by site Environmental Engineer but may also be delivered by other authorised
persons.
Revised: 03/07/13
Page 16 of 60
4.3.
Patrick will be notified immediately should a pollution incident occur that causes or likely to cause harm to
the environment. An incident report will be prepared and submitted to Patrick within one working day.
Fulton Hogan will also notify Patrick immediately of any site visits by the EPA, including purpose and
outcome of the visit and any actions taken by Fulton Hogan in response to the visit.
4.3.2. Community Consultation and Complaints Handling
A number of community groups and local residents have been identified as stakeholders in relation to the
construction phase of this project. Communication with these groups, along with NSW Ports relevant
authorities and other groups is managed by Patrick as part of their community engagement for the
Redevelopment Project. Specifically:
Community engagement activities are undertaken to inform and engage relevant stakeholders
including the Port Botany Expansion Community Consultative Committee (CCC) and Port Botany
Neighbourhood Liaison Group.
Where appropriate Patrick will also proactively issue community updates/newsletters, public displays
to ensure the community is aware of potential impacts.
Representatives of the Redevelopment Project will attend and provide construction/community
updates at regular community forum meetings.
More detail is available on the community page of the Redevelopment Project website at
http://www.patrick.com.au/community/w1/i1002943/ along with the monthly community update, Q&As,
relevant construction environmental management plans and monitoring.
There is an established complaints handling process in place to respond to issues raised by stakeholders in
relation to construction. The 24 hour complaints telephone line is available to residents or stakeholders by
telephoning 1800 177 722. The complaints telephone number has been proactively communicated to local
residents and businesses, is on the Project website and has been published by local media.
Complaints received will be investigated and dealt with immediately by Patrick. A database of complaints is
held and managed by Patrick and is shared and reported on monthly to NSW Ports.
Complaints management database will record the date and time of complaint, the method by which the
complaint was made, the contact details of the complainant, the nature of the complaint/enquiry, action
taken in response, who is responsible for the action, the team member that responded to the complainant,
what follow ups (if any are required), if monitoring is required and, if so, when it will occur, the associated
follow-up and, if no action is to be taken, the reasoning why.
Project staff will be available during office hours to visit community members to discuss and investigate
where needed.
Revised: 03/07/13
Page 17 of 60
MCoA B2.6
MCoA B2.20
MCoA B2.4
MCoA B2.5
MCoA B2.33
MCoA B2.43
MCoA B2.14
MCoA B2.41
SSROC
CCC
Primary
Industries
MCoA B1.3
Randwick
EPA
CEMP
Botany
Primarily
required by
RMS
Plan
DP&I
The MCOA requires Patrick and Fulton Hogan to consult with specific authorities and stakeholders in the
preparation of this plan and sub-plans. The table below indicates approval (A) and consultation (C) required
by the MCOA for each plan. These stakeholders have been consulted during the finalisation of this plan and
related plans.
C
C
The final draft CEMP will be submitted to DP&I, EPA, Primary Industries, Botany Council and the CCC for
comment. Relevant sub-plans will be submitted to these organisations, plus RMS, Randwick Council and the
CCC.
After comments from these organisations, the draft final CEMP and sub-plans will be updated to account
for comments. The final CEMP and relevant sub-plans will be issued to DP&I for approval and compliance
certification by the DP&I. Documentation as to how Patrick and Fulton Hogan addressed stakeholder
comments during consultation is available. The final CEMP will be issued to EPA, Primary Industries and
Botany Council for information, as per the requirements of MCOA B1.3.
Fulton Hogan will not commence any work on-site until:
Revised: 03/07/13
Page 18 of 60
The procedure for notifying Patrick and relevant authorities in advance of any proposed extension to hours
of work is included in the Construction Noise & Vibration Management Sub-Plan.
Some out of hours activities are likely to be required throughout the construction period. These activities
are permitted by the MCOA and may be required to be undertaken out of hours work to:
undertake works for safety reasons for protection of workers and the public;
reduce disruption to traffic and the community;
satisfy operational requirements of government agencies or authorities; or
due to unforeseen circumstances.
Where there is a requirement for out of hours activities that are not previously authorised by the MCOA,
and would be audible, Patrick is required to submit relevant information to DP&I for consideration under
Condition B2.19A of the MCOA.
This would include justification of varied construction hours, appropriate notification to sensitive receivers,
and noise reduction measures to be put in place. Appropriate community notification would be required, as
per the Community Consultation Plan.
4.4.
Environmental incidents and emergencies and management controls for dealing with these are addressed
in detail in the Incident and Emergency Response Plan (IERP).
The IERP includes:
All incidents will be recorded in Fulton Hogans Case and Action Management System (CAMs) in accordance
to Fulton Hogans Case and Action Management Procedure and Incident Investigation, Reporting &
Notification Procedure.
Revised: 03/07/13
Page 19 of 60
5. Checking Performance
5.1.
Environmental Inspections
The effectiveness of site environmental controls will be assessed on a regular basis. To document this, a
number of checklists, registers and forms will be completed. These may include (but not necessarily be
limited to) the following:
These will provide a means to evaluate and verify compliance with the relevant regulatory requirements
and the contractual environmental requirements.
Site Environmental Engineer will conduct weekly site inspections and document the results of these
inspections in an Environmental Inspection Report (refer to Appendix F).
Any non-conformances identified during site inspections or through monitoring results will be investigated
to determine the cause and to ascertain the necessary corrective actions.
5.2.
Environmental Monitoring
Project environmental monitoring will comprise collection and interpretation of quantitative data to
evaluate compliance and to verify the effectiveness of the environmental controls on site.
Environmental monitoring will include:
Noise monitoring
Water quality monitoring, and
Weather monitoring.
The methodology, location and frequency of environmental monitoring are further described in issuespecific sub-plans. The environmental sampling and testing equipment used on the project will be
calibrated in accordance with the manufacturers specifications and results recorded on the Calibration
Equipment Register.
5.3.
Environmental Nonconformities
Written responses to any nonconformities raised by Patrick or the relevant authorities will be provided
within the agreed timeframes or as required by the relevant contract environmental specifications.
5.4.
The CEMP compliance audits will be undertaken by suitably qualified and experienced Fulton Hogan
personnel not directly associated with the project every six months, with the first audit occurring no longer
than three months after commencement of construction.
The scope of internal audits may include but is not limited to:
Revised: 03/07/13
Page 20 of 60
Any deficiencies identified in the audit will be promptly rectified according to the level of risk.The outcomes
of internal audits may also trigger the requirement to update the CEMP and/or the sub-plans.
Patrick will undertake the Annual Independent Environmental Audit as required by section B4.5 of the
MCOA. Patrick will also undertake the Annual Environmental Management Report as required by section
B4.2 of the MCOA.
Any revisions to the CEMP as a result of management review will be issued as per Section 4.3.3 of this Plan
and the Documents and Records Management Plan.
Revision History
Rev
Revised By
Date
Description/Summary of Changes
I. Kliger
P. Nadanapatham
8/07/2013
Issued to Client
Revised: 03/07/13
Page 21 of 60
Attachments
Attachment A.Environmental Policy
The Commitment to Sustainability in combination with Fulton Hogans Mission and General Principles fulfils
the requirement of AS/NZ ISO 14001 and defines Fulton Hogans environmental policy.
Revised: 03/07/13
Page 22 of 60
Revised: 03/07/13
Page 23 of 60
Environmental Aspect
Description of Risk
Dust
Emissions
Low 2
Contamination
Med 8
Asbestos
High 21
Control Measures
Responsible
Person
Environmental
Engineer
Foreman
Environmental
Engineer
High 18
Environmental
Engineer
High 17
Environmental
Engineer/Foreman
Unexpected finds
Med 13
Environmental
Engineer
Vegetation
Med 13
Environmental
Engineer
Vegetation
High 17
Environmental
Engineer
Project Manager
Vegetation
High 17
Environmental
Engineer
Project Manager
High 23
Environmental
Engineer
High 21
Environmental
Engineer
High 23
Environmental
Engineer
High 17
Environmental
Engineer
Fuel/Oil spills
High 17
Environmental
Engineer
Noise
Med 13
Environmental
Engineer
Revised: 03/07/2013
Page 24 of 60
Only items related to the Fulton Hogan scope of works has been included in the following schedules.
Items shaded in grey are assumed to be SPC and/or Patrick responsibility
A1.
Condition
Implementation
CEMP Reference
All
GENERAL
Scope of Development
A1.1
The approved aspects of the development shall be carried out generally in accordance with:
a) Development Application DA-494-11-2003-i, lodged with Department on 26 November 2003.
b) Port Botany Expansion: Environmental Impact Statement (ten volumes), prepared by URS and dated Nov 2003;
c) Port Botany Expansion Commission of Inquiry Primary Submission (two volumes), prepared by URS dated May 2004
d) Port Botany Expansion Commission of Inquiry Supplementary Submission to EIS, prepared by URS and dated August 2004
e) Port Botany Expansion Environmental Impact Statement Supplementary Submission (two volumes), prepared by URS and dated October
2004;
f) modification application MOD-107-9-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Application: Modification of Consent
Conditions, prepared by SPC and dated September 2006;
g) modification application MOD-134-11-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Modification Wharf Structure Design,
prepared by SPC and dated November 2006;
h) modification application MOD-149-12-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Modification Application to Modify
Conditions B2.9 and B2.22 of the Port Botany Consent, prepared by SPC and dated 1 December 2006;
i) modification application MOD-78-9-2007-i, accompanied by Port Botany Expansion Modification of Conditions C2.20 & C2.25, prepared by SPC,
dated July 2007;
j) modification application MOD-60-9-2008, accompanied by Port Botany Expansion Modification of Conditions B2.46 & C2.25, prepared by SPC,
dated 27 August 2008;
k) modification application MOD-68-12-2008, accompanied by a letter from SPC dated December 2008;
l) modification application MOD-08-03-2009, accompanied by a letter from NSW Ports dated 16 February 2009 and assessment report titled Port
Botany Expansion Rail Operations Section 96(1A) Modification dated February 2009;
m) modification application 494-11-2003-I MOD 8, accompanied by an assessment report titled Port Botany Expansion Ship Turning Area
Revised: 03/07/2013
Page 25 of 60
No
Condition
Implementation
CEMP Reference
N/A
N/A
All
a) the conditions of this consent and any document listed from condition A.1.1(a) to (r) inclusive, the conditions of this consent shall prevail to the
extent of the inconsistency; and
b) any document listed from condition A1.1(a) to (r) inclusive, the most recent document shall prevail to the extent of the inconsistency.
Statutory Requirements
A1.3
All licences, permits and approvals shall be obtained and maintained as required throughout the life of the development. No condition of this
consent removes the obligation to obtain, renew or comply with such licences, permits or approvals.
Revised: 03/07/2013
Page 26 of 60
SCHEDULE B - CONSTRUCTION WORKS AND ONGOING ENVIRONMENTAL MANAGEMENT OF THE NON-OPERATIONAL ASPECTS OF THE TERMINAL
No
Condition
B1.
GENERAL REQUIREMENTS
Implementation
CEMP Reference
Application of Schedule
B1.1
The conditions in this Schedule of the consent relate the following aspects of the development:
a) development activities and works associated with the construction phase(s) of terminal footprint infrastructure including transportation and
delivery of materials and construction personnel to/from the site;
c) on-going management, mitigation and monitoring associated with the development, excluding direct terminal operation matters subject to the
conditions in Schedule C.
B1.2
The conditions in this Schedule of the consent must be complied with by the Applicant, or any party undertaking the activities and works referred
to under condition B1.1 on behalf of the Applicant.
N/A
The Applicant shall prepare a Construction Environmental Management Plan (CEMP) which, must be approved by the Director-General prior to the
commencement of any site preparation or construction works. The CEMP must:
Patrick / Fulton
Hogan
CEMP:
-Describe all activities to be undertaken on the site during site establishment and construction;
-clearly outline stages/phases of construction that require on-going environmental management monitoring and reporting up to and beyond the
commencement of operations of the terminal;
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
-detail statutory and other obligations that the Applicant is required to fulfil during site establishment and construction, including all approvals,
consultations and agreements required from authorities and other stakeholders, and key legislation and policies;
Patrick / Fulton
Hogan
Section 3
-include specific consideration of measures to address any requirements of the Department, DEC, DNR and the Council during site establishment
and construction;
Patrick / Fulton
Hogan
Section 4.3.3
-describe roles and responsibilities for all relevant employees involved in site establishment or construction;
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
-Describe relevant stages/phases of construction, including a work program outlining relevant timeframes for each stage/phase.
-detail how environmental performance of the site preparation and construction works will be monitored, and what actions will be taken to
address identified adverse environmental impacts;
Section 1.4
Section 1.5
Section 1.4
Section 4.1
Section 5
Revised: 03/07/2013
Page 27 of 60
No
Condition
Implementation
CEMP Reference
-include all Management Plans/Studies and Monitoring Programs required in this schedule;
Patrick / Fulton
Hogan
Sections 2.3, 5
-include arrangements for community consultation and complaints handling procedures during construction;
Patrick
Section 4.3.2
-be made available for public inspection after approval of the Director General.
Patrick / Fulton
Hogan
- Separate CEMPs may be prepared and submitted for works associated with the construction of the terminal footprint.
NA
NA
Patrick / Fulton
Hogan
CEMP, section
4.3.3
As above
As above
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Compliance Certification
B1.4
Prior to each of the events listed from a) to c) below, or within such period otherwise agreed by the Director-General, documentation certifying
that all conditions of this consent applicable prior to that event have been complied with shall be submitted to the satisfaction of the DirectorGeneral. Where an event is to be undertaken in stages, submission of compliance certification may be staged consistent with the staging of
activities relating to that event, subject to the prior agreement of the Director-General.
a) commencement of construction works associated with the development;
b) commencement of each phase of construction works established under the program required under condition B1.3; and
c) completion of each phase of construction works established under the program required by condition B1.3.
The certifying documentation shall clearly outline any on-going environmental management, monitoring or reporting requirements associated
with the concluded construction works phase.
B1.5
Notwithstanding condition B1.4, the Director-General may require an update report on compliance with all, or any part, of the conditions of this
consent. Any such update shall meet the requirements of the Director-General and be submitted within such period as the Director-General may
agree.
B2.
B2.1
Unless otherwise permitted by an Environment Protection Licence applicable to the development, the Applicant shall ensure that construction
works are undertaken in compliance with section 129 of the protection of the Environment Operations Act 1997. [S129 prohibits odour emission
without a licence]
Dust Management Plan
B2.4
The Applicant shall prepare a Dust Management Plan in consultation with DEC, RTA, DOP, Botany and Randwick Councils. The Applicant shall
address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative Committee in
Revised: 03/07/2013
Page 28 of 60
No
Condition
Implementation
CEMP Reference
preparation of the Plan. Plan must include, but not be limited to strategies in which the construction shall:
-minimise or prevent the emission of dust from the site;
-ensure that all trafficable areas and vehicle manoeuvring areas in or on the premises shall be maintained, at times, in a condition that will
minimise the generation, or emission from the premises, of wind-blown or traffic generated dust;
-ensure that all vehicles entering and leaving the site and carrying a load that may generate dust are covered at all times, except during loading
and unloading. Any such vehicles shall be covered or enclosed in a manner that will prevent emissions of dust from the vehicle at all times; and
-ensure that all dust source surfaces are sealed.
The Plan shall be approved by the Director-General prior to commencement of construction.
Soil And Water Management
Soil and Water Management Plan
B2.5
The Applicant shall prepare a Soil and Water Management Plan in consultation with DEC, RTA, DOP, DNR, Botany and Randwick Councils. The
Applicant shall address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative
Committee in preparation of the Plan. The Plan must detail erosion and sediment controls, prepared in accordance with Managing Urban
Stormwater: Soils and Construction (available from the Department of Housing) and must:
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Acid Sulphate
Soils Mgmt SubPlan
-identify the management responses to activities that could cause soil erosion or result in the discharge of sediments and/or other pollutants
from the site;
-specify standards/performance criteria for erosion, sediment, and pollution control including water sediment basin locations and discharge
points, for example parameters, frequency, duration location and method; and
-describe what actions and measures will be implemented, the effectiveness these actions and measures and how they will be monitored during
the works, clearly indicating who will conduct the monitoring, how the results of this monitoring would be recorded; and, if any non-compliance
is detected.
The Plan shall be approved by the Director-General prior to commencement of construction.
Acid Sulphate Soils
B2.6
Prior to the commencement of construction activities, the Applicant must prepare an Acid Sulphate Soils Management Plan to assess and manage
any Acid Sulphate Soils (ASS) or potential ASS (PASS). The Plan shall be prepared in accordance with the Acid Sulphate Soils Manual 1998
published by the NSW Acid Sulphate Soil Management Advisory Committee. In the event that ASS are encountered during the works, the
Applicant shall notify the NSW Maritime Authority immediately.
Pollution Prevention
Revised: 03/07/2013
Page 29 of 60
No
B2.7
Condition
Implementation
Unless permitted through an environment protection licence applicable to the development, the Applicant must comply with section 120 of the
Protection of the Environment Operations Act 1997, which prohibits the pollution of waters. [S120 prohibits pollution without a licence.]
CEMP Reference
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Construction Plan
Patrick / Fulton
Hogan
Traffic
Management Plan
Patrick / Fulton
Hogan
Traffic
Management Plan
Patrick / Fulton
Hogan
Traffic
Management Plan
Prior to commencement of construction, the Applicant is required to consult with Sydney Water regarding the likely requirements from Sydney
Water for a section 73 Compliance Certificate.
Traffic, Transport and Infrastructure Management
Construction Traffic Management Plan
B2.14
Prior to the commencement of any construction works, the applicant must prepare a Construction Traffic Management Plan in consultation with
RTA, DOP, Botany and Randwick Councils and SSROC. The Applicant shall address the requirements of these organisations in the Plan. The
Applicant shall also consult with the Community Consultative Committee in preparation of the Plan. Plan must include, but not be confined to,
mitigation measures identified in EIS such as:
-identification of preferred haulage routes;
-access routes and, signage and access arrangements on site;
-measures to limit the impact on Foreshore Rd. and Botany Rd.;
-need for restrictions on delivery hours and/or routes; and,
-development of traffic management measures during construction works to ensure minimal traffic disruptions
The plan must be submitted and approved by the Director-General prior to the commencement of construction.
Safety Audit
B2.15
The Applicant must undertake safety audit in accordance with RTA guidelines upon completion of works but prior to operation to ensure the
safety of any road works, traffic management facilities, cycling and pedestrian provisions undertaken as part of the proposed works.
Port Traffic Handbook
B2.16
Prior to construction the Applicant must prepare a handbook and distribute it to drivers of construction related vehicles providing information on
accepted routes, constraints to traffic and preferred hours of use and amenities on such routes to ensure that the impact of traffic growth on
local traffic is minimised.
Rail Access to New Terminal
B2.18
The Applicant shall ensure that Grade separation of Penrhyn Road over the rail access to the new berth includes the grade separation of the
inter-terminal road over the rail access to Patricks terminal. This is required to ensure efficient operation of both road and rail access to all
NSW PORTS
Revised: 03/07/2013
Page 30 of 60
No
Condition
Implementation
CEMP Reference
Patrick / Fulton
Hogan
The Applicant shall only undertake construction activities associated with the project (with the exception of dredging construction activities) that
would generate an audible noise at any residential premises during the following hours:
a)
b)
c)
Audible noise is defined as noise that can be heard at the receiver. This condition does not apply in the event of a direction from police or other
relevant authority for safety or emergency reasons. Note: safety or emergency reasons refers to emergency works which may need to be
undertaken to avoid loss of life, property loss and/or to prevent environmental harm.
B2.19A
The Applicant must seek the Director-Generals approval to conduct construction activities audible at residential premises (with the exception of
dredging construction activities) outside the hours specified under condition B2.19 on a case-by-case basis. In seeking the Director-Generals
approval, the Applicant shall demonstrate a need for activities to be conducted during varied hours and how local acoustic amenity will be
protected, as well as details of how the EPAs requirements with respect to the variation of hours have been addressed.
Patrick / Fulton
Hogan
B2.19B
For activities subject to an environmental protection licence issued by the EPA under the Protection of the Environment Operations Act 1997,
conditions B2.19 and B2.19A do not apply if the EPA has approved activities to be conducted outside the hours permitted by condition B2.19.
Patrick / Fulton
Hogan
NA
Patrick / Fulton
Hogan
Prior to the commencement of construction, the Applicant must prepare a Construction Noise Management Plan in consultation with DEC, DOP,
Botany and Randwick Councils. The Plan shall include noise mitigation for piling works for diesel powered machinery, provision of training to
ensure that construction workers are aware of the noise created during construction and are appropriately trained to minimise noise where
possible. In addition, the Construction Noise Management Plan must:
-identify general activities that will be carried out and associated noise sources;
-assess construction noise impacts at the relevant receivers;
-provide details of overall management methods and procedures that will be implemented to control noise during the construction stage;
- identification of all feasible and reasonable measures to minimise noise and vibration, including but not limited to:
- using least noisy construction methods, vehicles, plant and equipment;
Revised: 03/07/2013
Page 31 of 60
No
Condition
Implementation
CEMP Reference
Patrick / Fulton
Hogan
Construction Noise
Mgmt Sub-Plan
Patrick / Fulton
Hogan
- positioning and orientating noisy plant and equipment so as to minimise noise impacts on noise sensitive receivers and wildlife in Penrhyn
Estuary;
- positioning items of noisy plant and equipment as far apart as is practicable from each other;
- minimising noisy activities by adopting alternative construction measures;
- carrying out above ground loading and unloading activities as far away as is practicable from noise sensitive receivers and wildlife in Penrhyn
Estuary;
- designing each work site to minimise the need for truck reversing movements;
- ensuring all vehicles and self-propelled plant and equipment enter and leave the premises in a forward direction unless unforeseen accidents or
other unforeseeable circumstances arise that may require reversing movements, in which case minimising any such reversing movements;
- taking all practicable steps to avoid reversing movements on the surface within the premises, and where it is impracticable to avoid reversing
movements, taking all necessary steps to minimise reversing movements;
- preventing vehicle, plant and equipment queuing and idling outside the hours of construction prescribed by this consent.
-include a pro-active and reactive strategy for dealing with complaints including achieving the construction noise goals, particularly with regard to
verbal and written responses;
-detail noise monitoring, reporting and response procedures consistent with DEC requirements;
-provide for internal audits of compliance of all plant and equipment;
-indicate site establishment timetabling to minimise noise impacts;
-procedures for notifying residents of construction activities likely to affect noise amenity;
-address the requirements of DEC; and
-be approved by the Director-General prior to the commencement of any works on the site.
Construction Noise Goals
B2.21
The goal for noise from construction activities as the LA10 (15 minute) should not exceed the Rating Background Level (RBL) plus 5dB(A) at
sensitive receivers.
Other Construction Noise Matters
B2.24
The Applicant is required to identify measures to be implemented to ensure that where movement alarms are fitted to vehicles, plant or
equipment entering or operating on the site, such alarms are of a type that minimises noise at noise sensitive receivers.
Revised: 03/07/2013
Page 32 of 60
No
Condition
Implementation
CEMP Reference
B2.25
The Applicant must install all physical noise management measures as early as is practicable during construction of the Port Botany Expansion
project.
Patrick / Fulton
Hogan
B2.26
Patrick / Fulton
Hogan
No blasting
Patrick / Fulton
Hogan
Waste Management
Construction Waste Management Plan
B2.33
Prior to the commencement of construction, the Applicant is required to prepare a Construction Waste Management Plan in consultation with
Botany Council and DEC. The Plan must provide details of proposed waste management measures to minimise production and impact of wastes
generated at the site including but not limited to:
-identification of the type and quantities of waste that would be generated, a description of how the waste would be handled, stored, re-used,
recycled, and if necessary, appropriately treated;
-identification of a designated area for the storage and collection of waste and recyclable materials top be provided on the site;
-description of how the effectiveness of these measures would be monitored and, if non-compliance detected, actions to be required;
-measures to involve and encourage employees and contractors to minimise domestic waste production on site and to reuse/recycle where
possible.
Waste Management On-site
B2.34
Management of waste must be in accordance with the environment protection licence issued by EPA under the Protection of the Environment
Operations Act 1997.
Patrick / Fulton
Hogan
NA
B2.35
All wastes and material generated on the site during construction and operation shall be classified in accordance with the DECs Environmental
Guidelines: Assessment, Classification and Management of Liquid and Non-Liquid Wastes prior to transporting the waste off site and be disposed
of to a facility that may lawfully accept the waste.
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Except as expressly permitted by a licence issued by the EPA under the Protection of the Environment Operations Act 1997, only the hazardous
and/or industrial and/or Group A waste listed below may be generated and/or stored at the premises: -waste oil/water, hydrocarbons/water
mixtures or emulsions; and -grease trap waste.
Heritage Management
Potential for Discovery of Aboriginal Heritage Objects
Revised: 03/07/2013
Page 33 of 60
No
Condition
Implementation
CEMP Reference
B2.39
If an Aboriginal object is discovered during the construction of the development, works should cease in the subject area and the Applicant shall
notify DEC immediately.
Patrick / Fulton
Hogan
Patrick / Fulton
Hogan
Construction Safety
Study
Patrick
Patrick / Fulton
Hogan
Incident and
Emergency Response
Plan
Patrick / Fulton
Hogan
Construction Plan
The Applicant shall prepare a Construction Safety Study prior to commencement of construction of terminal operations infrastructure, accordance
with Hazardous Industry Planning Advisory Paper No.7 Construction Safety Study Guidelines (DoP, 1992). The commissioning portion of the
Construction Safety Study may be submitted 2 months prior to commencement of commissioning. The study shall be submitted for the approval of
Director-General prior to the commencement of construction of the terminal operations infrastructure.
Fire Safety Study
B2.42
The Applicant shall prepare a Fire Safety Study prior to the commencement of construction of the terminal operations infrastructure in accordance
with Hazardous Industry Planning Advisory Paper No.2 Fire Safety Study Guidelines (DoP, 1992). The study shall be submitted for the approval of
the Director-General and the Commissioner of the NSW Fire Brigades prior to the commencement of construction of the terminal operations
infrastructure.
Emergency Incident Management
Emergency Response and Incident Management Plan
B2.43
The Applicant shall develop an Emergency Response and Incident Management Plan in consultation with DEC, DOP, Council and the Community
Consultative Committee. The Plan must be approved by the Director-General prior to the commencement of construction and shall detail:
-terminal security and public safety issues;
-effective spill containment and management;
-effective fire fighting capabilities;
-effective response to emergencies and critical incidents; and
-a single set of emergency procedures, consistent with the existing Port Botany Emergency Plan, should be developed that can be scaled as
appropriate for any incident or emergency.
Aviation Construction Management
Impact on Aviation Operations at Sydney Airport
B2.44
The Applicant shall ensure that all aspects associated with construction considers the required lateral separation distances to minimise the
interference to Sydney Airport radar and navigational systems.
Revised: 03/07/2013
Page 34 of 60
No
Condition
Implementation
CEMP Reference
The Applicant shall ensure that all construction equipment is below obstacle limitation surface, unless otherwise permitted by an approval under
the Airports (Protection of Airspace) Regulation 1996 and following consultation with the Department of Infrastructure, Transport, Regional
Development and Local Government, Civil Aviation Safety Authority and Sydney Airport Corporation Limited.
Patrick / Fulton
Hogan
Construction Plan
Patrick / Fulton
Hogan
Construction Plan
The Applicant must meet the following requirements in relation to community consultation and complaints management:
Patrick
Community
Consultation Plan
-all monitoring, management and reporting documents required under the development consent shall be made publicly available;
Patrick
-provide means by which public comments, inquiries and complaints can be received, and ensure that those means are adequately publicised; and
Patrick
-includes details of a register to be kept of all comments, inquiries and complaints received by the above means, including the following register
fields:
Patrick
-the date and time, where relevant, of the comment, inquiry or complaint;
Patrick
-means by which comment, inquiry, complaint was made (telephone, fax, mail, email, person);
Patrick
-any personal details of the commenter, inquirer or complainant that were provided, or if no details were provided, a note to that effect;
Patrick
Patrick
-any action(s) taken by the Applicant in relation to the comment, inquiry or complaint, including any follow-up contact with the commenter,
inquirer or complainant; and
Patrick
-if no action was taken by the Applicant in relation to the comment, inquiry or complaint, the reason(s) why no action was taken.
Patrick
-Provide quarterly reports to the Department and DEC, where relevant, outlining details of complaints received.
The Applicant shall ensure design specifications of any construction lighting conform to the requirements of Regulation 94 of the Civil Aviation
Regulations 1988.
B3.
B3.1
B4.
B4.1
The Director-General shall be notified of any incident with actual or potential significant off-site impacts on people or biophysical environment
Patricks / Fulton
Revised: 03/07/2013
Page 35 of 60
No
Condition
Implementation
CEMP Reference
within 12 hours of Applicant, or other relevant party undertaking the development, becoming aware of the incident. Full written detail of the
Hogan
incident shall be provided to the D-G within seven days of the date on which the incident occurred. The D-G may require additional measures to be
implemented to address the cause or impact of any incident, as it relates to this consent, reported in accordance with this condition, within such
period as the D-G may require.
Annual Environmental Management Report (AEMR)
B4.2
The Applicant must prepare an Annual Environmental Management Report for the development. The Annual Environmental Management Report
must:
Patricks
Prior to the commencement of construction, a suitably qualified and experienced Environmental Representative(s) shall be nominated and
Patricks
approved by the D-G. The Environmental Representative(s) shall be employed for the duration of the construction and the on-going management,
mitigation and monitoring associated with the development, excluding direct terminal operation matters subject to the conditions in Schedule C, or
as otherwise agreed by the D-G. The Environmental Representative shall be:
Revised: 03/07/2013
Page 36 of 60
No
Condition
Implementation
CEMP Reference
Fulton Hogan
Patricks
d) responsible for the management of procedures and practices for receiving and responding to complaints & inquiries in relation to the
environmental performance of construction phases;
e) required to facilitate an induction/training program for relevant persons involved with construction phases;
f) given the authority and independence to require reasonable steps be taken to avoid or minimise unintended or adverse environmental impacts,
and failing the effectiveness of such steps, to direct that relevant actions be ceased immediately should an adverse impact on environment be
likely to occur.
Environmental Training
B4.4
Prior to commencement of any dredging, reclamation and construction an Environmental Training Program shall be developed and implemented
to establish a framework in which relevant employees will be trained in environmental management and operation of plant and equipment,
including pollution control equipment, where relevant. Program shall include, but not necessarily limited to:
a) identification of relevant employment positions associated with the development that have an operational or management role related to
environmental performance;
b) details of appropriate training requirements for relevant employees;
c) program for training relevant employees in operational and/ or management issues associated with environmental performance;
d) program to confirm/update environmental training and knowledge during employment of relevant persons.
Environmental Auditing
B4.5
Within one year of the commencement of construction and every year thereafter for the duration of construction a full independent
environmental audit shall be undertaken by a suitably qualified person/team approved by the Director-General. Audits would be made publicly
available and would:
-be carried out in accordance with ISO 14010 and ISO 14011 Procedures for Environmental Auditing;
-assess compliance with requirements of this consent, other licences/approvals;
-assess the construction against the predictions made and conclusions drawn in the development application, EIS, additional information and
Commission of Inquiry material; and
-review effectiveness of environmental management, including any environmental impact mitigation works.
Note: An independent and transparent environmental audit can verify compliance (or otherwise) with the Ministers consent and various
approvals. Auditing also provides an opportunity for continued improvement in environmental performance.
Revised: 03/07/2013
Page 37 of 60
Attachment D.
Item
EIS Reference
1.
ES2 Some limited disturbance of potential acid sulphate soils may occur as a result of construction of the new
2
terminal, however, any potential acid sulphate soils within the dredged area would be contained within the
reclamation, or kept below the water level to prevent oxidisation.
2.
ES3 An Environmental Management and Monitoring Plan (EMMP) would be developed and implemented in
0
accordance with management and monitoring measures set out in this EIS, statutory requirements and
conditions of approval for the project. Construction and Operation EMPs would form an integral part of the
project EMMP and would be prepared in accordance with ISO 9001:2000 and ISO 14001:1996.
CEMP
3.
1622
Aside from turbidity control, the following mitigation measures would be implemented to minimise the impact Soil & Water Management Sub-Plan
of the construction on surface water flow and water quality:
construction activities would be conducted in a manner that minimises the potential for spills or leaks,
including the regular inspection and maintenance of plant and equipment, and providing bunding or similar
spill containment structures for onsite fuel and oil storage;
any spills or leaks would be contained/cleaned up as quickly as possible;
resealing and revegetation of all exposed surfaces as soon as practical to prevent extended exposure to
erosion;
erosion and sediment control planning and implementation would apply to all areas which may be
disturbed. Regular inspection of all structures would occur after heavy rain and during periods of prolonged
rainfall;
a Soil and Water Management Plan (SWMP) would be prepared in accordance with the guidelines
contained in Managing Urban Stormwater - Soils and Construction Manual and incorporated into the CEMP
for the project. Details of erosion and sediment control measures would include:
temporary structures such as sedimentation ponds and silt fences surrounding stockpiles to prevent
offsite movement of sediment;
control of drainage from areas adjacent to construction areas using earth bunds and diverting structures
such as earth drains;
minimisation of traffic in construction zones and provision of dedicated parking areas; and
removal of soil from vehicle wheels and undercarriages before departing the site to reduce soil carried
offsite.
4.
1714
The SWMP for construction would be based on the Managing Urban Stormwater- Soils and Construction
Manual and incorporated in the CEMP. All work would be carried out to avoid contamination of site and the
Revised: 03/07/2013
Page 38 of 60
Item
EIS Reference
points 6,17,21
storage and handling of all dangerous goods in accordance with AS, NSW Dangerous Goods (General)
Regulations 1999 and NSW EPA guidelines;
an emergency response plan to control fuel, oil and chemical spills;
machinery would be inspected regularly to identify any leaks;
provision of spill containment equipment (e.g. spill kits) located around the construction site; and
training of staff in spill clean-up procedures and use of spill kits.
5.
Chapter 18.5.1
Paragraph 8
1811
The SWMP for construction would be based on the Managing Urban Stormwater- Soils and Construction
Manual and would be incorporated in the Construction EMP. All work would be carried out to avoid erosion
and sedimentation of the site and the surrounding areas. Erosion and sediment control measures would
include:
temporary structures to prevent offsite movement of sediment such as sedimentation ponds and silt fences
surrounding stockpiles;
control of drainage from areas adjacent to construction areas using earth bunds and diverting structures
such as earth drains;
dust minimisation using collected stormwater where possible;
cessation of work, or implementation of further suppression measures if excessive fugitive dust emissions
are observed;
minimisation of traffic in construction zones and a dedicated parking area;
removal of soil from vehicle wheels and undercarriages; and
sealing and revegetation of all disturbed surfaces as soon as practical to prevent extended exposure to
erosion.
Erosion and sediment control planning and implementation would apply to all areas which may be disturbed.
Regular inspections would occur after heavy rain & during periods of prolonged rainfall.
6.
Chapter 21.9.1
Paragraph 1
2126
A detailed Construction Traffic Management Plan would be developed and incorporated into Construction EMP Traffic Management Plan
for the project. The plan would include detailed consideration of:
identification of preferred haulage routes;
access routes and signage, and access arrangements at the site;
measures to ensure that Foreshore Road would not be affected by:
loading/unloading from the carriageway;
queuing; and
Revised: 03/07/2013
Page 39 of 60
Item
EIS Reference
Chapter 22.5.9
Paragraph 1
2224
A Noise Management Plan would be developed and incorporated into the CEMP, including:
8.
Chapter 23.8.1
2317
apply water, through the use of water trucks, to active earthwork areas, stockpiles, gravel roads and loads
of soil being transported to reduce wind blown dust emissions;
site roads to consist of coarse gravel and to be kept wet to minimize wheel generated dust emissions;
The DMP would also include safeguard measures such as:
keep the working face and areas of open excavation to a minimum;
vegetate stockpiles where material is to remain on site for long periods;
cease work if excess dust is observed, or phase down while the source is being actively investigated and
suppression measures are implemented;
restrict construction traffic to defined roads and implement a speed limit;
remove soil adhering to the wheels and undercarriage of vehicles prior to departure from the site; and
progressively landscape and vegetate areas as the construction activities proceed, where practical.
9.
Chapter 23.9.1
2318
Prior to and during construction, monitoring in areas considered most likely to receive dust impacts during
construction would be undertaken. All monitoring would be undertaken in accordance with the NSW EPA
Approved Methods for the Sampling and Analysis of Air Pollutants in NSW (2001). All monitoring devices
Revised: 03/07/2013
Page 40 of 60
Item
EIS Reference
would be located in accordance with AS 2922-1987 Ambient Air Guide for Siting of Sampling Units.
In particular, one high-volume air sampler would be installed within the residential area to the north of
Foreshore Road, preferably to the south of Botany Road. This location is shown by dispersion modelling to
receive the greatest dust impacts during construction. This high-volume air sampler would monitor PM10
on a six-day cycle in accordance with AS 3580.9.6-1990 Particulate matter PM10 high-volume sampler
with size-selective inlet.
Three dust deposition gauges would also be installed within residential areas two in the residential area
north of Foreshore Road, and one in the Matraville residential area immediately east of Amcor (Botany Road,
Matraville). An additional dust deposition gauge would also be located in Penrhyn Estuary.
10.
Chapter 28.10.3
Paragraph 1
2820
Pursuant to and in accordance with SEPP 33 guidelines, following project approval NSW PORTS would conduct Construction Safety Study
a construction safety study, incorporating comprehensive identification of potentially hazardous incidents that
could arise during the construction of the Port Botany Expansion and setting out the organisational and
operational safeguards proposed to address such incidents.
11.
29-6 Temporary construction lighting would use tinted lights where possible to minimise the attraction of insects on Construction Plan
which birds are likely to feed.
12.
29-8 Should birds be attracted to the site, attempts would be made to discourage them from feeding or roosting by Waste & Spoil Management Sub-Plan
using flagging material or other deterrent methods as described [in EIS section 29.4.2 paragraph 2].
13.
Chapter 30.5.2
14.
Chapter 35.4.1
Paragraph 1
Lighting during construction and operation would be carefully selected to ensure they would not infringe the
Construction Plan
provision of Regulation 94 of the Civil Aviation Regulations 1988. During the detailed design stage, CASA would
be consulted for detailed guidance and appropriate restrictive controls.
35-4 The following mitigation measures would be undertaken during construction works and detailed in the
Construction EMP:
efficient work scheduling and methods that minimize equipment idle time and double handling of material;
throttling down and switching off construction equipment when not in use;
switching off truck engines while they are waiting to access the site and while they are waiting to be loaded
and unloaded;
switching off site office equipment and lights and using optimum lighting intensity for security and safety
purposes;
careful design of temporary roads to reduce transportation distances;
regular equipment maintenance to ensure optimum ops & fuel efficiency;
the specification of energy efficient construction equipment.
Revised: 03/07/2013
Page 41 of 60
Item
EIS Reference
15.
37-3 Develop a SWMP, as part of the Construction EMP, to ensure an adequate standard is applied to control of
contaminants which could impact groundwater quality during the construction of the Port Botany Expansion.
16.
37-3 Prepare and implement a SWMP as part of the Construction EMP to control erosion and sedimentation (as
described above).
17.
Chapter 37.2
18.
37-5 Reduce noise levels from piling hammers by placing resilient dollies in between pile and hammer, where practical.
The hammer would be shrouded to provide acoustic attenuation.
19.
37-5 Reduce noise levels from diesel powered machinery by fitting noise control kits to machinery, where practical.
20.
37-5 Conduct training to ensure construction workers are aware of noise issues and act to minimise noise where
possible.
CEMP Section 5
21.
37-6 Keep the working face and areas of open excavation to a minimum.
22.
37-6 Apply water, through the use of water trucks, to active earthwork areas, stockpiles, gravel roads and loads of soil
being transported to reduce wind blown dust emissions.
23.
37-6 Ensure site roads consist of coarse gravel and are kept wet to minimise wheel generated dust emissions.
24.
37-6 Vegetate stockpiles where material is to remain on site for a long period of time.
25.
37-6 Cease or phase down work if excess fugitive dust is observed while the source is being actively investigated and
suppression measures are implemented.
26.
Revised: 03/07/2013
Page 42 of 60
Item
EIS Reference
27.
37-6 Remove soil adhering to the wheels and undercarriage of vehicles prior to departure from the site.
28.
37-6 Progressively landscape and vegetate areas as the construction activities proceed.
29.
Construction Plan
30.
3711
Empty portable toilet facilities on a regular basis by an appropriately licensed waste management contractor
3711
Develop and implement a WMP for the construction and operational phase in accordance with the requirements of Waste & Spoil Management Sub-Plan
the Waste Avoidance and Resource Recovery Act 2001, the Protection of the Environment Operations Act 1997, the
EPA's Environmental Guidelines: Assessment, Classification & Management of Liquid & Non-Liquid Wastes (1999),
the Botany Bay DCP 29 and the National Minimisation and Recycling Strategy.
The Construction WMP would require that all contractors carrying out construction works record the types,
quantities and destinations of all waste material taken offsite. In addition, any licensing requirements for the
management and disposal of waste from the site would be identified in the Construction WMP. All personnel
would be advised of waste management and disposal procedures described in the Construction WMP prior to
commencing work.
32.
3711
Minimise construction waste that requires disposal by accurately calculating materials brought to the site and
limiting materials packaging.
3711
Return excess construction materials which are suitable for reuse to the supplier or store for future use.
3711
Store construction wastes which are not suitable for reuse, but are able to be recycled, in dedicated and secure
skips prior to recycling.
3711
Store, in separate skips, construction wastes which cannot be recycled. The skips would be collected by a licensed
waste contractor on a regular basis and transported for disposal to a licensed landfill or recycling facility.
34.
35.
Chapter 37.2
Point 134
Table 37.1
Revised: 03/07/2013
Page 43 of 60
Item
EIS Reference
3711
Process or shred vegetation waste (trees and shrubs) into wood chip or mulch, which would then be used in the
rehabilitation of areas disturbed during construction and for landscaping.
3711
Stockpile excavated soil generated during site preparation activities for reuse in landscaping activities. Any soil
which cannot be disposed of in this manner would be transported off site to a licensed landfill, after appropriate
classification for the material is carried out in accordance with NSW EPA requirements.
3712
Provide recycling facilities to maximise recycling of waste materials such as plastic and glass bottles/containers,
Waste & Spoil Management Sub-Plan
aluminium cans and paper/cardboard. Separate bins would be provided for food waste. Collect all domestic waste
on a regular basis and transported off site for disposal to a licensed landfill or recycling facility.
38.
39.
3712
Recycle scrap metal, used parts, components and machinery where practicable.
40.
3712
Waste oils and fluids from maintenance activities would be collected and stored and would either be reused on site Waste & Spoil Management Sub-Plan
or removed by a licensed waste contractor.
41.
Chapter 38.2
CEMP
42.
Chapter 38.2
38-3 Prepare Emergency Response & Incident Management Plan for construction.
43.
38-4 Monitor compliance of the construction activities with the Construction EMP, including EPA requirements and
MCOA, on an ongoing basis.
CEMP
44.
38-5 Monitor erosion and sediment control structures in accordance with the SWMP prepared in accordance with the
guidelines contained in Managing Urban Stormwater - Soils and Construction Manual and incorporated into the
CEMP.
CEMP
45.
CEMP
46.
38-5 Monitor the extent of construction areas to ensure they do not extend beyond the defined construction zone
CEMP
47.
38-6 Visual inspection of construction zones to ensure construction vehicles are using defined roads and access points.
Revised: 03/07/2013
Page 44 of 60
Item
EIS Reference
48.
38-6 Check that on site trucks are not overloaded, that they adhere to speed limits, that their trays are covered and that Traffic Management Plan, CEMP
materials are loaded and unloaded carefully.
49.
38-6 Check that trucks arriving at the site before it opens are parked in designated holding areas and not on adjacent
streets.
50.
51.
38-6 Conduct noise monitoring in the vicinity of residential areas and sensitive receiver locations for each stage of
construction prior to construction of infrastructure and facilities on the new terminal itself
52.
38-6 Visually monitor dust generation from work zones to ensure that excessive dust is not being produced.
53.
38-6 Inspect sites to ensure that adequate dust controls are being used such as regularly watering unsealed areas.
54.
38-6 Monitor dust impacts using a high-volume air sampler, dust deposition gauges and onsite meteorological station in Dust Management Plan, CEMP
accordance with the EPA Approved Methods for the Sampling & Analysis of Air Pollutants (2001). Locate
monitoring devices in accordance with AS 2922-1987 - Ambient Air - Guide for Siting of Sampling Units.
55.
38-6 Report any heritage relics discovered during construction activities to NPWS for Aboriginal relics or Heritage Office
for items of European heritage. Cease works pending their consideration.
56.
38-6 Inspect waste receptacles to ensure that they are not being overfilled and are being collected on a regular basis.
57.
38-6 Inspect construction zones to monitor for any unauthorised waste disposal activity.
58.
38-6 Inspect the construction site to evaluate the effectiveness of waste storage and collection practices.
59.
38-6 Inspect any portable toilet facilities to ensure they are being emptied on a regular basis.
60.
38-6 Monitor waste recycling and disposal procedures to ensure they are being complied with.
Revised: 03/07/2013
Page 45 of 60
Key Requirements
The main objective of this Act is to establish a process for investigating and remediating land areas where
contamination presents a significant risk of harm to human health or some other aspect of the environment.
Under this act EPA has the power to:
Environmentally
Hazardous Chemicals
Act 1985
The purpose of this Act is to control chemicals that are environmentally hazardous. EPA may make chemical
control orders (CCOs) with respect to assessed chemicals or declared chemical wastes. The CCOs may regulate
the manufacture, processing, conveying, buying, selling or disposal of chemical or declared waste. A CCO may
prohibit activities in relation to declared chemical wastes, except under the authority of a licence issued by EPA.
Environmental
Planning and
Assessment Act 1979
(EP&A Act)
The main objective of the EP&A Act is to ensure that proper management and development of land is
undertaken incorporating the ecologically sustainable development principles. To achieve this the EP&A Act:
Conditions to the
development approval
(Ministers Conditions of
Approval) are tracked via
CEMP Appendix 2A.
Aboriginal heritage
measures are in the Waste
& Spoil Management SubPlan.
Ensures compliance with planning consents and conditions associated with the consent;
Ensures environmental assessment is undertaken prior to development consent;
Has provision for penalties to be issued should development conditions be breached.
Under this Act, NPWS is responsible for the care, control and management of all national parks, historic sites,
nature reserves, reserves, Aboriginal areas and state game reserves. The Act governs various activities
including:
Protection of the
The POEO Act is the key piece of environment protection legislation, and is administered by the EPA. The
Revised: 03/07/2013
Page 46 of 60
Legislation
Environment
Operations Act 1997
(POEO Act)
Key Requirements
objective of the Act is to protect restore and enhance the quality of the environment in NSW with a need to
maintain ecologically sustainable development. To achieve this the following tools are employed:
The Regulation:
sets out how to calculate fees for environment protection licences, environment protection notices and
noise control notices, and makes provision for adjustment or refunds of those fees;
makes provisions for load reduction agreements (load reduction agreements allow for fee rebates in return
for measures taken to reduce pollution in the future);
sets out matters to be included by the EPA for the grant or refusal of a licence application;
makes it an offence to provide false or misleading information in relation to a licence application;
requires licensees to retain records used to calculate licence fees;
gives effect to the National Environment Protection (National Pollutant Inventory) Measure by requiring
occupiers of certain facilities to submit data relating to the emission of certain substances;
prescribes certain matter when placed into water to be water pollution, and the methodology for testing
matter in waters;
exempts certain water pollution from the water pollution offence under the Protection of the Environment
Operations Act 1997;
prescribes certain forms to be used with respect to warrants relating to noise abatement directions;
declares certain bodies to be the appropriate regulatory authority in relation to certain activities for the
purposes of the Protection of the Environment Operations Act 1997;
This Regulation repeals and remakes, with minor amendments, the provisions of the Protection of the
Revised: 03/07/2013
Page 47 of 60
Legislation
Regulation 2008
Key Requirements
the sounding of sirens and similar devices and the use of sound systems on vessels,
the emission of noise from the engines or exhausts of motor vehicles and vessels,
the maintenance of noise control equipment on motor vehicles and vessels,
the issue of defective vehicle notices and defective vessel notices,
the times during which it is not permissible to use certain articles if they emit noise that can be heard in any
residential premises,
the inspection and testing procedures for the purpose of determining noise emission levels of certain motor
vehicles, motor vehicle accessories, vessels, articles or equipment.
POEO (Penalty
Notices) Regulation
2004
This Regulation:
sets out the offences under the Protection of the Environment Operations Act 1997 and related Acts and
regulations for which penalty notices may be issued, and the amount of such fines;
specifies the organisations authorised to issue penalty notices for particular offences; and
authorises the service of a penalty notice relating to an offence, applying to an owner of a motor vehicle or
vessel, on the owner without naming the address of the owner and by leaving the penalty notice on that
vehicle or vessel.
Environmental protection
offences and penalties, and a
duty to notify of environmental
harm, apply to all personnel
working on the project.
POEO (Waste)
Regulation 2005
Schedule 1 of the regulation sets out the types of waste to which waste tracking requirements apply.
Protection of the
Environment
Operations
Amendment (Schedul
ed Activities and
Waste) Regulation
2008
This framework uses a mix of legislative, policy, educative and economic tools to encourage waste avoidance
and the further recovery of resources. This new framework includes:
Waste Avoidance
and Resource
New resource recovery licensing categories and resource recovery exemptions; and
Revised: 03/07/2013
Page 48 of 60
Legislation
Recovery Act 2001
Key Requirements
Ensuring industry has a responsibility for reducing and dealing with waste;
Providing penalties for breaches of this Act.
An Act consolidating water rights, water and drainage and artesian wells. Provisions include a licence
requirement to sink or alter an artesian bore, not to waste water taken from dams, lakes, artesian wells and
bores, and not to unlawfully interfere with sub-surface water or obstruct its flow.
N/A
Water Management
Act 2000 and
Water Management
(General) Regulation
2004
The Water Management Act 2000 is the main piece of water legislation in NSW and governs:
N/A
Works involving the removal of obstructions from the improvement of rivers and foreshores and the
prevention of erosion of lands by tidal and non-tidal waters
Permits are required to excavate protected land, remove material from protected land or do anything to
detrimentally affect the flow of waters.
Commonwealth
Environment
Protection and
Biodiversity
Conservation Act
1999
(EPBC Act)
This Act aims to protect the environment, particularly matters of National Environmental Significance (NES).
Approval is required for actions that are likely to have a significant impact on:
Revised: 03/07/2013
Page 49 of 60
Legislation
Key Requirements
This Act regulates export and import of hazardous waste to ensure that hazardous waste is disposed of safely.
The Act requires that a permit be obtained before hazardous waste is exported from Australia or imported into
Australia.
N/A
SEPP 33 -Hazardous
and Offensive
Development
Provides new definitions for 'hazardous industry', 'hazardous storage establishment', 'offensive industry' and
'offensive storage establishment'. These enable decisions to approve or refuse a development to be based on
the merit of proposal. The policy also requires specified matters to be considered for proposals that are
'potentially hazardous' or 'potentially offensive'. The policy does not change the role of councils as consent
authorities, land zoning, or designated development provisions of the EP&A Act.
No relevance.
Introduces state-wide planning controls for remediation of contaminated land. Land must not be developed if it
is unsuitable for a proposed use because it is contaminated. If the land is unsuitable, remediation must take
place before the land is developed. The policy makes remediation permissible across the State, defines when
consent is required, requires all remediation to comply with standards, ensures land is investigated if
contamination is suspected, and requires councils to be notified of all remediation proposals. To assist councils
and developers, the Department, in conjunction with the Environment Protection Authority, has prepared
Managing Land Contamination: Planning Guidelines.
SEPP (Infrastructure)
2007
Provides a consistent planning regime for infrastructure and the provision of services across NSW, along with
providing for consultation with relevant public authorities during the assessment process. The SEPP supports
greater flexibility in the location of infrastructure and service facilities along with improved regulatory certainty
and efficiency.
No relevance.
to provide planning controls for the local government area of Botany Bay City which update and consolidate
into a single local environmental plan the various local planning controls that currently apply to the local
government area of Botany Bay City;
Key Policies
to give the Council greater responsibility in environmental planning by creating broad controls;
Revised: 03/07/2013
Page 50 of 60
Sunny
Issue
Scattered clouds
Action Required
Light showers
Rain
Thunderstorm
By Whom
By When
Completion
Sign Off
Windy
Revised: 03/07/13
Page 51 of 60
Yes No
Foreman
Earthworks Manager
Structures Manager
Project Director
Revised: 03/07/13
Page 52 of 60
Revised: 03/07/13
Page 53 of 60
Check dams are used within diversion drains where required to slow flows down and minimise erosion within the drains
Geotextile linings (or similar) is used to provide temporary surface protection in areas where appropriate (e.g. batter drains, culvert construction)
Stockpile Management
Stockpiles are sited in low-hazard areas clear of watercourses and flood prone lands
Cut-off drains on the upslope side and sediment fencing on the downslope side are in place for all stockpile areas within the site
Stockpiles are less than 2m in height
Sediment Control
Sediment control measures are constructed as close to the potential source of sediment as possible
Shakers, rubble pads or wash down areas have been installed and used to minimise the tracking of mud and soil material onto local roads
There is no mud on the roads outside of the project boundary
Sediment fencing or equivalent is provided downslope of disturbed areas that cant be directed into a designated sediment basin
Sediment Basins and Traps
The volume markers intact and clearly visible
The inlets and outlets are stable
Accumulated sediment is below 30% of the sediment storage zone
The basins been emptied since the last rain event and restored to their design capacity (if not, explanation must be provided)
Revised: 03/07/13
Page 54 of 60
Revised: 03/07/13
Page 55 of 60
Contact address
Ingrid Ilias
Department of Planning & Infrastructure
Major Projects Assessments
Contact email
Ingrid.Ilias@planning.nsw.gov.au
9228 6411
GPO Box 39
Sydney
NSW 2001
EPA
sarah.deards@epa.nsw.gov.au
9995-5000
Documents Sent
CEMP
Acid Sulfate Soils Management Sub-Plan
Construction Noise Management Sub-Plan
Second Phone
Call
Package Sent
Confirmation of
Package Received
Feedback
Comment on Feedback
Consultation
Complete
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
12/06/2013
19/06/2013
Yes
Left Message
Left Message
Returned message
extended response
date to 27/6/13
12/06/2013
N/A
N/A
Initial Phone
Call
carla.ganassin@dpi.nsw.gov.au
9527 8552 4254-5527
Yes
Yes
Revised: 03/07/13
Page 56 of 60
Stakeholder
RMS
Botany
Council
Contact address
Contact email
Documents Sent
Nicolas Kocoski
NSW Transport Roads and Maritime
Services
Locked Bag 5100
Camperdown 1450
Nicolas.KOCOSKI@rms.nsw.gov.au
8849-2328
Stephen Poulton
City of Botany Bay Council
PO Box 331
141 Coward Street
MASCOT
NSW 2020
shephenp@botanybay.nsw.gov.a CEMP
u
Construction Noise Management Sub-Plan
9366-3666
Initial Phone
Call
Second Phone
Call
12/06/2013
19/06/2013
Left Message
Package Sent
Confirmation of
Package Received
N/A
Yes
Consultation
Complete
Comment on Feedback
Yes
Feedback
Satisfied that all key criteria for these plans have been incorporated into
the document and at this stage has no issues with the development
12/06/2013
19/06/2013
Spoke to Stephen P
and extended
response date to
28/6/13
N/A
Yes
Yes
None proposed
None proposed
Agreed.
Revised: 03/07/13
Page 57 of 60
Stakeholder
Randwick
Council
Contact address
Bronwyn Englaro
Randwick City Council
30 Frances Street
RANDWICK
NSW 2031
Contact email
Documents Sent
Initial Phone
Call
Second Phone
Call
Package Sent
Confirmation of
Package Received
Feedback
Consultation
Complete
Comment on Feedback
Details on proposed dust suppression measures appears to be limited Noted. Details of dust suppresion mitigation
and the
measures and the equipment to be used are detailed
sub plan provides little details of on site equipment and operational
in Sections 5 and 7 of the AQDMP.
procedures with regard to these activities. Council suggests that this
plan demonstrate how dust suppression activities will be carried out and
to confirm the required equipment for this will be on site and operational
as and when required throughout the project's duration.
As per noise monitoring and reporting Council recommends that dust
monitoring
reports be made accessible to the community via a project website.
Soil and Water Management Sub-Plan
12/06/2013
19/06/2013
Left Message
N/A
Yes
As above
This plan states the use of groundwater for dust suppression activities Agreed. SWMP has been revised accordingly.
whereas the dust management sub plan states the use of rainwater tank
or sea water for dust suppression. Due to potential inhalation risk from
possible volatiles in the groundwater Council suggests that the dust
plan recommendations be utilised to minimise this exposure risk.
Council suggest consideration cumulative traffic impact in this TMP
in conjunction with other
construction activities occurring at terminal 3 and in the vicinity of the
Port.
A project requirement should be that no construction vehicle
stacking, loading
or unloading shall occur on, or in a manner that adversely affects the
flow of traffic along Foreshore Road and Council is pleased to see that
a designated on site truck waiting facility is being provided.
Council also recommends that onsite signage and other
communications
mechanisms be utilised to notify visitors/uers of alternative access
arrangements to roads, cycle ways and footpaths during works.
Yes
Revised: 03/07/13
Page 58 of 60
Stakeholder
Contact address
SSROC
Helen Sloane
Southern Sydney Region of Councils
PO Box 536
HURSTVILLE
NSW 1481
Contact email
rryan@urbis.com.au
Also contact Shane Hobday:
shobday@sydneyports.com.au
8233-9900
hs@ssroc.nsw.gov.au
9330 6455
Documents Sent
CEMP
Acid Sulfate Soils Management Sub-Plan
Construction Noise Management Sub-Plan
Dust & Air Quality Management Sub-Plan
Soil and Water Management Sub-Plan
Waste & Spoil Management Sub-Plan
Emergency Response and Incident
Management Plan
Traffic Management Plan
Construction Safety Study
Traffic Management Plan
CEMP
Initial Phone
Call
Second Phone
Call
12/06/2013
41437
N/A
Package was
returned not known
at address.
Confirmed with
Patricks (Emmanuel
Diacos) that ther is
no need to resend
as Susan Rudland
has a copy of all
plans.
N/A
N/A
N/A
Package Sent
Confirmation of
Package Received
Feedback
Comment on Feedback
N/A
N/A
No Comments received
N/A
Yes
12/06/2013
TMP Section 5.4.2 Access via the Caltex site and across the SICTL rail area is not
permitted, unless specific approval is obtained from both Caltex and
SICTL (as well as NSW Ports). This is highly unlikely in view of the
SICTL rail construction and rail operations in respectively 2013 and
2014.
TMP Section 5.4 Please address the exiting construction traffic from 'southern' site. Will
this exit via the Cargolink facility? Review turning circles.
Consultation
Complete
Yes
Revised: 03/07/13
Page 59 of 60
Stakeholder
Contact address
Contact email
Documents Sent
Initial Phone
Call
Second Phone
Call
Package Sent
Confirmation of
Package Received
Feedback
Access to main 'northern' site is via Ramp C (please correct text in 5.4
that states 'Ramp B').
Review signage based on above required changes.
Address pedestrian access to the construction site.
TMP Section 5
With this proposal and the concurrent construction of the Knuckle and
Ramp D, Patrick will introduce significant construction traffic
movements on the roundabout at the bottom of Ramp C. The
roundabout was not initially designed to cater for the additional entry /
exit lanes. NSW Ports requires Patrick to confirm that Patrick has full
responsibility of the traffic on and the operation of that roundabout. NSW
Ports requires that Patrick confirm the safety of the roundabout by
means of a road safety audit.
Incident and
Reference should be made to the Port Botany Emergency Alarm Radio
Emergency
(PBEAR) which s located at the Patrick Gatehouse and is the primary
Response Plan means for notifying other facilities in the Port that there is an incident on
the Patrick site. A PBEAR unit is also located and monitored at the
Mascot Police Station. The system is routinely tested every Thursday
morning.
CEMP - Section 1 Please include a section acknowledging and addressing the issue of
multiple construction contractors undertaking construction works on the
PBE at the same time and need for coordination and management of
common environmental issues (i.e. noise, dust, complaints, water,
traffic etc)
CEMP - General Please include table of all comments reviewed from stakeholders
identifying all comments, how they have been addressed and where
they have been addressed in the management plans.
CEMP - General
Consultation
Complete
Comment on Feedback
Correction made
Signage ammended accordingly
There will be no pedestrian access to the
construction site. All personnel will arrive by vehicle
Includeded that FH will undertake a road safety audit
once initial traffic control has been implemented to
enable the works. (clause 8.1)
Includeded in plan
Revised: 03/07/13
Page 60 of 60