Sie sind auf Seite 1von 9

2.

2 Construction
General

Site Leveling for the Site. (100%)


Transport Palm trees outside the site (100%)
Constructing the wooden fences for the site (100%)
Prepare site office (100 %)
Prepare the site layout facilities (100%)
Operation for the Dewatering System (100%)

Transformer boxes (2 No)


Install the earthing cable (100%)
Back filling the earthing trench (100%)
Pouring Concrete grade 40 for base slab (100 %)
Pouring concrete for Internal & External Walls till +4.2 (100%)
Grinding & Repair for Internal Wall (100%)
Grinding & Repair for External Wall (100%)
Internal Painting (80%)
Backfilling (85%)
Pouring screed for floor (100%)
Installing Transformers (100%)
Pouring Concrete for Cable Ducts (100%)
Water proofing for cable ducts (100%)
External painting (80%)
Transformer boxes (6 No)
Install the earthing cable (100%)
Back filling the earthing trench (100%)
Pouring Concrete grade 40 for base slab (100 %)
Pouring concrete for Internal & External Walls till +4.2 (100%)
Grinding & Repair for Internal Wall (100%)
Grinding & Repair for External Wall (100%)
Internal Painting (80%)
Backfilling (95%)
Pouring screed for floor (100%)
Installing transformers (100%)
Pouring Concrete for Cable Ducts (100%)
Waterproofing for Cable Ducts (100%)
External painting (90%)

Electrical & Control Building


Install the earthing cable (100%)
Pouring RC base slab (100%)
Pouring concrete for basement Walls & columns (100%)
Pouring Concrete for ground floor slab (100%)
Pouring Columns ground floor columns (100%)
Pouring roof slab from axis 1E to axis 17E (100%)
Water proofing for walls & columns (95%)
Basement Wall, Column & Ceiling Surface finishing from axis 1E to
axis 17E (100%)
Pouring screed inside the basement (100%)
Pouring Concrete for Parapet from axis 1E to axis 17E (100%)
Installation for angles of the drain channel & Frame of the drain pit
(100%)
Oil Paint for basement Walls from axis 1E to axis 17E (85%)
Block work for internal walls (100%)
Block work for external walls (50%)
Plaster work (98%)
Pouring AC Supports on Roof (100%)
Backfilling (80%)
Pouring light weight concrete for roof (100%)
Paint for ground floor Walls & Ceiling (90%)
Finishing of Roof Slab (100%)
Pouring Ground floor Screed (95%)
Tiling Work (100%)
Anti-Fungus Coating (100%)
False ceiling installation (80%)
Painting of external walls (20%)
Pump House

Install the Earthing Cable (100%)


Pouring concrete for RC Foundation (100%)
Install Sylomer for PG1 & PG2 (100%)
Pouring concrete for RC foundation for pump footings (100%)
Pouring Concrete for Walls & Columns (100%)
Installing Pumps (100%)
Pouring Concrete for laydown area (100%)

Water proofing for walls & columns (100%)


Backfilling (90%)
Installing Steel Structure (98%)
Internal Block work for Walls (100%)
Pouring Concrete for Pipe Supports (100%)
Plastering for Internal Walls (100%)
Painting for Internal Walls (95%)
Screed for floor (100%)

Utility Building

Pouring RC isolated footings (100%)


Pouring Concrete for columns & ground beams (100%)
Pouring Concrete for Roof slab (100%)
Water proofing of footing, columns & ground beam (100%)
Backfilling (90%)
Block work for internal walls (100%)
Block work for external walls (25%)
Installing Steel Structure (99%)
Blinding Concrete for Internal Cable Trench and Ground floor Slab
(100%)
Waterproofing for Internal Cable Trench and Ground floor Slab
(100%)
Pouring Concrete for Internal Cable Trench and Ground floor Slab
(100%)
Plaster work (98%)
Pump & pipe supports concrete (100%)

Surge Vessel (For PG1)

Pouring concrete for foundation (100%)


Pouring concrete for pipe & surge supports (100%)
Finishing & Repair for surface foundation (100%)
Backfilling (100%)
Base Grout (100%)

Surge Vessel (For PG2)

Pouring concrete for foundation (100%)


Pouring concrete for pipe & surge supports (100%)
Finishing & Repair for surface foundation (100%)
Backfilling (100%)

Base Grout (100%)

Air Compressor

Excavation for Air Compressor (100%)


Install Earthing Cables (100%).
Pouring Concrete for foundation (100%)
Pouring Concrete for enclosure up stand (100%)

Water Quality Monitoring

Excavation (100%)
Pouring Concrete for footing (100%)
Pouring Concrete for Roof Slab & Columns (100%)
Water Proofing for foundation and ground columns (100%)
Backfilling (95%)
Internal Block work (100%)
Plastering for internal Walls (100%)
Painting work (90%)
External blockwork (98%)
Tilling work (98%)

Oil Separator & Drain Storage

Excavation for foundation (100%)


Shoring for excavation sides retaining (100%)
Pouring Base concrete for Storage Tank
Pouring 1st stage Walls for Storage Tank (100%)
Water proofing for walls (100%)
Pouring for foundation of Oil Separator (100%)
Pouring 1st Stage of Oil separator walls (100%)
Backfilling (95%)
Pouring 2nd stage of oil separator walls (100%)

Drain Pipe line

Excavation for Pipeline (80%)


Installing of Pipelines (50%)

Transformers Drain Manholes (4 Nos)

Excavation for manholes

Excavation for Pipeline (100%)


Pouring Blinding Concrete (100%)
Water Proofing (95%)
Pouring Screed (100%)
Pouring Concrete for Foundations (100%)
Pouring Concrete for Walls (100%)

FM-01

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (90%)
Water proofing for walls (90%)
Concrete of pipe supports (100%)
Screed for floor (100%)
Fixing link seal of pipe (100%)

FM-02

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (100%)
Waterproofing for walls (100%)
Backfilling (100%)
Concrete of pipe supports (100%)
Screed for floor (100%)

FM-03

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (100%)
Waterproofing for walls (100%)

Concrete of pipe supports (100%)


Screed for floor (100%)
Backfilling (100%)

Suction Pipe Lines

Excavation for Pipeline (60%)


Bedding Layer (60%)
Backfilling (45%)

VP-01

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (100%)
Waterproofing for walls (90%)
Backfilling (90%)
Concrete of pipe supports (100%)
Screed for floor (100%)

VP-02

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (100%)
Waterproofing for walls (90%)
Concrete of pipe supports (100%)
Backfilling (65%)

VP-04

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (100%)

Waterproofing for walls (90%)


Concrete of pipe supports (100%)
Screed for floor (100%)
Backfilling (65%)

VP-05

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (100%)
Waterproofing for walls (90%)
Backfilling (90%)
Concrete of pipe supports (100%)
Screed for floor (100%)

VP-06

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water proofing & Screed (100%)
Pouring concrete for foundation (100%)
Pouring concrete for walls (100%)
Waterproofing for walls (95%)
Backfilling (75%)

VP-07

Excavation for foundation (100%)


Shoring for sides retaining (100%)
Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring concrete for walls (100%)
Backfilling (10%)
Concrete of pipe supports (100%)
Screed for floor (100%)

VP-08

Excavation for foundation (100%)

Pouring Blinding Concrete (100%)


Water Proofing & Screed (100%)
Pouring Concrete for foundation (100%)
Pouring Concrete for Walls (60%)
Waterproofing for walls (90%)
Backfilling (75%)
Screed for floor (100%)

Boundary walls

Excavation for foundation (50%)


Pouring Blinding Concrete (50%)
Water Proofing & Screed (50%)
R.C footings & columns installation (50%)
Hollow core & panels installation (50%)
Backfilling (30%)
Waterproofing coating under G.L (30%)

Septic tank

Excavation for foundation (100%)


Pouring Blinding Concrete (100%)
Water Proofing & Screed (100%)
Concrete for foundation (100%)
Concrete for walls (100%)
Waterproofing for walls (90%)
Backfilling (90%)

Cable route from QPS1- QPS2

Hollow core (100%)


Block supports for cable tray (90%)

Cable trenches

Excavation (60%)
Blinding (60%)
Water Proofing & Screed (60%)
Concrete pouring for foundation (60%)
Concrete pouring for Walls (50%)

Fire Fighting Pits & Pipelines

Excavation (70%)
Bedding layer (70%)
Concrete pouring for foundation (70%)