Beruflich Dokumente
Kultur Dokumente
LIST OF FIGURES
ACKNOWLEDGEMENTS
ABSTRACT
INTRODUCTION
10
10
11
11
12
12
12
12
13
13
14
14
14
15
16
3.4A Parameters
16
16
3.4.3 Calculations
17
18
20
21
21
21
22
v.-
23
24
25
25
29
30
32
32
34
36
39
39
39
43
43
44
44
6.2.2 Odour
45
46
6.2.2 Biological
46
52
7.0 Recommendations
54
8.0 Conclusion
55
9.0 References
56
ANNEX
57
LIST OF TABLES
Table 1: Summary of legislation and administrative ramework
Table 2: Summary of the climatology of the East of Mauritius
Table 3: Noise levels of equipment
Table 4: Workforce of WWTP
Table 5: Employees working at the WWTP
Table 6: Standard for particulate matter
Table 7: Standard for onsite substances discharge
Table 8: Noise exposure limits
Table 9: Pollutant Exposure limits
Table 10: Permissible limits for wastewater parameters
LIST OF FIGURES
Figure 1: General map of the proposed waste water treatment plant at Bassin Requins
Figure 2: Layout of the proposed facilities
Figure 3: Air Quality Standards
Figure 4: Map showing the B62 road
ACKNOWLEDGEMENTS
We would like to show our gratitude and heartfelt thanks to our lecturer, Mrs. Rana, who guided
/
ABSTRACT
This report contains a detailed Environmental Impact Assessment for a wastewater
treatment plant based at Bassin Requins, situated in the East of Mauritius.
The areas that will be beneiting rom this service is the East region comprising of only the
major
villages.
The wastewater treatment will comprise of primary to tertiary method of treatment so the
treated efluent can be used for irrigation purposes for the golf courses around Belle Mare.
^'
INTRODUCTION
Water is a fundamental ingredient of life. Houses, commercial buildings, educational institutions,
industries and in the agricultural sector consume water and produce waste water.
Sanitary
sewage is of domestic origin and its quantity depends on the number of people living in an
area.
Storm water comes rom catchments particularly rom roofs and roads and directly depends
on
the intensity and duration of rainfall. Industrial wastewater is the effluent delivered
out
of
particular industries. Its quality depends upon nature of industry, raw materials
used;
manufacturing process .Wastewater is generally composed of water, pathogen, organic
and
inorganic materials, big debris, emulsions and dissolved minerals.
Wastewater is treated irst before it is disposed in rivers and seas. It is usually done in a
waste water treatment plant. The objective of a waste water treatment plant is to
reduce the concentration of specific pollutants to the level at which the discharge effluent
will not adversely affect the environment or pose health threat. In Mauritius, we have 19
treatment plants, the main one being at St Martin, Grand Baie, Baie Du Tombeau and
Montagne Jacquot.
Most oten, before the construction a treatment plant or any project, the promoters
require an environment impact assessment (EIA) permit. The EIA is an assessment of the
possible impacts that a proposed project may have on the environment, consisting of
environment, social and economic aspects. It ensures that decision makers whether or not to
proceed with the project. The EIA is reinforced by the Environment Protection Act 2002
which helps in the protection of the environment assets of Mauritius and Sustainable
development.
LITERATURE
REVIEW
Sewage treatment
Sewage treatment is a process where contaminant rom wastewater and household sewage is
removed by chemical and biological processes. Its objective is to produce an environmentally
safe effluent and solid waste (sludge) that is safe for disposal or reuse. Using advanced
technology it is now possible to treat wastewater back to drinking water standards.
Note: Singapore is the only country to re-use sewage efluent for drinking purposes
Process Overview
Sewage is collected and transported by a network of pipes to the treatment plant. Sewage
treatment is typically subject to federal regulations and standards.
Sewage treatment generally involves three main stages:
Primary treatment involves temporarily in a quiescent basin where large particle can
settle to the bottom and are removed
Secondary treatment include removal of dissolved and suspended biological matter using
indigenous micro-organism in a supervised environment
Tertiary treatment can be defined as anything beyond primary and secondary treatment
s
prior to disposal into a ragile and sensitive environment or or drinking purposes
*i
When a site for a waste water treatment plant is to be set up, it is preferable to choose a site
which is considerably away from residential areas. Even if most of the treatment plant
components are odor tight, in an aesthetical point of view these kinds of sites are chosen
Besides it is usually chosen at low-level grounds. With a treatment plant at low-level most of the
water is likely to low to the treatment plant by gravity. This means that less pumping will be
necessary making the project more economical.
7|
Moreover location of the site with respect to the eluent disposal must also be considered. There are
two main method of eluent disposal:
Land disposal
Disposal in sea or ivers
Satisfactory disposal of wastewater is dependent on its treatment prior to disposal
^ /
Environmental impacts
Any development irrespective of the nature of the type of work, scale and scope will generate
impacts. They can be either direct or indirect impacts both qualitatively and quantitatively in
terms of the physical aspects of the environment, namely land use, soil and geology, lora, fauna,
air quality, water quality, noise, visual aesthetics and the landscape. The impacts could also be
positive or negative or a mixture of both depending on the nature and complexity of the project.
Apart rom the impact on the physical environment development will have a significant impact
related to the socio-economic aspects, which include the effects on employment and traic. An
assessment of the likely impact of the project on these environmental components has been
carried and elaborated in subsequent sections
Mitigations
Mitigation in legislative terms is the principle that a party who has suffered or caused any
adverse impact has to take reasonable actions to minimize the amount of the loss suffered. For
the development of a wastewater treatment plant, we shall take into account the concerns which
have been expressed rom the developments in recent years. Subsequently substantial
investments shall be expected in the mitigation of the general hostile impacts such as odour
mitigation, noise mitigation, reduction of landscape use, visual impact mitigation and traic
disruption. The adoption of a good management practices and speciic environmental control
measures will mitigate these impacts.
V.
ENVIRONMENTAL
IMPACT
ASSESMENT
FOR
SEWAGE
1.0 Introduction
The Republic of Mauritius intends to construct a new waste water treatment plant in the region of
Flacq, under the National Sewerage Master Plan. As part of this regime, the Government of
Mauritius is planning to modernize the system of treatment of waste water and provide the
inhabitants with the facility of sewerage for the major villages governing the district of Flacq.
In regard of this matter, an Environmental Impact Assessment (EIA) will consider all the laws and
guidelines that can be applied for the construction of a new waste water treatment plant. EIAs
are important to consider prior to approval and design phase, so as to ensure that all the
conditions regarding the protection of the environment are met and that the construction of the
project will not cause any damage to the surroundings.
The proposed site is called Bassin Requins and is found near the coastal region of Poste de Flacq and
is a location whereby no activities are conducted except for pig-rearing. The fact this region has,
since many years, been used for pig rearing, no urban expansion and no tourism activities have
been developed.
Near the proposed site is found Belle Mare Golf club and Le Prince Maurice hotels, and Riviere
du Poste de Flacq river.
10
approval, the Board can also appoint a planning committee that shall furnish the board with
information concerning the future planning needs and nature of development.
23 Noise Prevention Act 1938
Noise is one of our major environmental problems which is giving rise to lots of public
complaints, due mainly to juxtaposition of residential, religious, commercial and industrial
activities. The Act declares that noisy activities related to construction such as demolition of a
building, excavation or illing of land and use of heavy machines require prior authorisation from
the local authority if such activities are carried out before 7 am or ater 7 pm on any day.
2.4 The Waste Water Management Authority Act of 2000
The Waste Water Management Authority Act of 2000, explicitly, provides the ruling classes of
the Waste Water Management Authority (WMA) as an institution responsible of the wastewater
sector in Mauritius. These codes provide guidelines about the power of the authority over the
design and installation of the water system and septic tanks.
The Board is responsible for:
Carrying out, monitoring, supervising, maintaining,
wastewater work.
Promoting treatment and reuse of wastewater.
Handling researches and studies on the wastewater sector
Safeguarding resources to inance operations and maintenance
Monitoring pollutions due to wastewater treatment
x/
unlimited contracts, the law has specified the speciic conditions for each. According to
labour law, it is not allowed to employ any foreigner workers without prior consent rom
the Ministry of Labour. The work permit should not exceed one year and can be renewed
for extra years.
2.7 Maritime Zone Act Of 2005
The Maritime act was introduced in 2005 in order to make necessary controls in thecontiguous
zone to prevent and punish infringement of the customs, fiscal, immigration or sanitary
laws
within Mauritius, its archipelagic waters, internal waters and territorial sea. The Act also
states
that solely the Prime Minister has the right to make regulations to provide for the
authorization
for any construction, operation or the laying of pipelines or cables in the exclusive
economic
zone
2.8 Legal Register
A summary of legislation and administrative ramework applicable during both phases
(construction and operation) is shown in the Table below:
Legislation
Responsible Authority
Ministry Of Environment
Ministry Of Environment
Ministry Of Environment
of2000
Public Health Act 2008
Ministry Of Environment
Ministry Of Labour
Ministry of Fisheries
13
14
Secondary treatment- The secondary treatment process aims to reduce the BOD exerted by
reducing organic matter. This is mediated, primarily, by a mixed population of
heterotrophic bacteria that utilize the organic constituent for energy and growth.
A large number of biological unit operations are available to achieve the aerobic oxidation of
BOD. All operations can be classified on the basis of their microbial population, into either ixed ilm
or dispersed growth processes. Fixed ilm reactors have bioilms attached to a ixed surface where
organic compounds are adsorbed into the bio ilm and aerobically degraded. In suspended (e.g.
activated sludge) growth reactors the microorganisms mix reely with the wastewater and are kept in
suspension by mechanical agitation or mixing by air diffusers.
15 1 ? g e
16
3.4.3 Calculations
Discharge of sewage Q = 35,000 m3/day
Q 3S000
Plan area of tank A = =
= 700 in2
Assuming L = AB
L x B = 4B2 = 700
B = 13.2 = 14m
But B must not be greater than 6m (scrapping becomes dificult otherwise)
Therefore, 5 PST must be provided.
700
4B2=
B = V35 = 5.92 = 6
Therefore L = 4 x 6 = 24
Length of Weir
Weir Loadinq rate =
a
-of Weir
Length J
Q
35000
L-r=^ = -ioF = 3SOm
350
^ weir for each tank = = 70 m
17 I i
18
": ri
ol
C
CO
3 a
C
O
CO
O
O
4 O
CO
w CO
O
Q- O
-S
<L
>
<-1
*N
-d
.5
C
O
W
3
aa QC O
c <u
t/i
VI a.
-j
v_
CO
(A
m
CO <u
to O
a.
o
a.
-^
-\
(L> T3 C
+
CO
4* <L>
S3 3
-S3
id -4-
to
O -i
O CO
<D i-i
a O
6fJ
Si
2
CO
u-4
o
-.-'
S,J
a
13
5
o
<L>
3j
o
>
^
O
a.
T
J
C
O
t3
CO
O
o
apsejg
\i
.2
55
CO
3
sum bay
CO
"3
a"
Pi
.5
*co CO
a
CO
r^
3
V x. X
*"
PaiUia
^ Control
rump
S*tMi
i
-I*.
.-
OetstTi
A*> t ftwUHmg
WMcMn *
T>-i AS J T
Utility
Bufking
it
***,
*vliV j* ** "*W _^j43C-w>S J 'r r..' - - -caJ^B
x.
E-J*
.
->
^*.,^_ ^^jj^^^
*
i. +> !*"*.H ct.
*t*~ WSS*
"O
.jt^-^
*-';
^W'
.:' -'i," lit-W"05>c*M.^?7j;'
-- -\*: :.i; **
-#
^ f
*f
''ie^
w-*
-**
5"
l
J
*
"
%
,-c^i;
*
:#*?
>!^ V
&
%ir Vf S
3*
v^.
u
-*
1,-.
rr"i^
>
?K?WBEr
VKH
v
^ka
f&*
V
*.
sx
->*,F
=**-*-.
^^r
>-".;A t
tFigure 2: Layout of the proposed facilities
J-BA
Major industrial and commercial activities are located to the east and west of the proposed
treatment plant. The major tourism activities are located at Belle Mare and a few others at Poste
La Fayette. The nearest hotels are Le Prince Maurice and Le Touressrok; each ofthem having
their own waste water treatment plant and discharging the treated effluent into the nearby seas or
used as water for irrigation purposes.
\*S s
20
Month
Mean maximum
Average rainfall
Temperature (C)
(Ka/h)
(mm)
January
28.8
8.0
261.3
February
28.7
9.1
334.1
March
28.6
9.6
231.2
21
- -n r- ^
April
27.6
9.1
240.0
May
26.2
9.3
167.7
June
24.6
10.8
104.0
July
23.7
12.3
102.5
August
23.8
11.7
104.9
September
24.3
11.2
70.1
October
25.4
11.0
62.2
November
27.1
10.1
82.0
December
28.2
9.1
201.8
respectively, dominate the geology of Mauritius. The soil of Bassin Requins mostly belongs to the
Lowland Latosolic Reddish Brown Prairie soils.
The surface drainage pattern of Mauritius has been classiied into major drainage areas with
permanently lowing rivers and minor drainage areas, which lie between the major ones.
The Riviere Francoise North and Riviere du Poste East are fed principally rom groundwater
originating in the Nouvelle Decouverte area. Riviere du Poste, in addition to its natural low,
receives water rom Riviere Francoise (North) via Constance Canal as well as rom G.R.S.E via
Sans Souci canal.
To the east of Riviere du Poste is the minor drainage area, which is similar to the Plaine des
Roches minor catchment.
The next drainage area, Riviere Seche East is also fed rom groundwater originating in Nouvelle
Decouverte and Quartier Militaire, lowing underground between Fayence and Montagne
Blanche, to appear at Clemencia as Riviere Seche.
22
j--
r\
23 j ri r-: -'>
~i -
24 I F a 2 e
During the operation phase, the following environmental and social aspects were identified as
signiicant:
1) Impacts on Physical Environment
Air Quality
Noise
Water
quality
Land Use and Landscape
&
quantity
25 | P a g a
During the operation phase, the following environmental and social aspects were identified as
signiicant:
1) Impacts on Physical Environment
Air Quality
Noise
Water
quality
Land Use and Landscape
&
quantity
25 | P a g a
commercial establishments. Therefore, the noise sensitive receptors to the site are the
houses, commercial premises along roads, schools, and a hospital.
Common construction activities will include truck traffic, heavy machinery
movement
and
area
and rock excavation and use of pneumatic rock breaking equipment will also generate
severe
noise impact.
These higher noise levels may have significant and negative health impacts on staff
working within the construction site.
The
an idea of the
noise
levels
generated by typical
construction equipment.
Equipment
Bulldozers
80
Backhoe
82
Bobcat
75
Crane
76
Dump Truck
88
Jack Hammer
90
Table 3: Noise levels of equipment
Given that the nearest receptors are at least1 km away rom the construction site, the noise
pressure levels are within acceptable levels during day and night. The overall noise level will be
higher during the day time compared with the night
time.
Mitigation measures
accordingly.
will
have
to
be
\1
i
applied - V/ ^ I.. M-
the
atmosphere. A region's air quality is inluenced by many factors including the type and
amount
of pollutants
emitted
into
the
atmosphere
and
the
prevailing
meteorological
conditions.
r\
During the construction phase, the harmful agent affecting air quality will mainly be dust and
vehicular emissions arising rom construction activities.
Construction activities at the different sites will inevitably generate dust, particularly during
excavation, and earth moving operations. Vehicle movements along the roads will also generate
dust, which is likely to have a slight temporary effect on neighboring properties.
Also some of the construction equipment and vehicles may result in emission of gases like:
Sulphur dioxide [SO2 ]
Nitrogen oxides [NOx]
Carbon monoxide [ CO ]
The general guidelines for air quality standards for Mauritius and as recommended by the
World Health Organisation (WHO) are listed in the table below.
POLLUTANT
MAURITIUS
PM10
150 ug m3 50 ug m3
S02
1 000 ug m3 200
HgJm3 50 ug m3
N02
200 uc'ui
CO
40 000 uam,"1
OO
70 Mg ni3
350 u;g/m3 125
ugm3 50 M8-P13
400pgm3 150
Mgm3
30 000 ng m3
Averaging Time
1-h 24-h Annual
1-h 3-h 24-h Annual
i -h 24-h
1-h
Solid Waste
Pre-construction activities such as site clearance will cause the generation of some forms of solid
waste.
During the construction phase, solid wastes would include concrete waste, glass, scrap metals,
some wooden strips, as well as domestic waste like remnants of foods, plastics, paper and
27 n r\-
r
aluminum cans. These waste if not properly disposed would not only cause eyesore and attract
rodents but would also pose as health and safety hazards.
Thus, it is important that ater construction, the site is free rom any form of waste that could
cause land pollution.
The pre-construction and construction phase will not generate hazardous wastes that have toxic,
reactive and corrosive characteristics.
Domestic waste
The proposed construction site will accommodate a temporary site oice, equipped with toilet
facilities.
Wrongful disposal of the domestic wastewater will result in land degradation and emission of
offensive odors. This will in turn prevent a healthy atmosphere rom prevailing on the
construction site.
Appropriate mitigation measures will have to be implemented.
5.1.1.4 Visual
Landscape and visual impacts associated with the construction and operation phases of the
project are important to assess the land use, regarding the Waste Water Treatment Plant.
The proposed site is bordered on the residential side by mature trees, which will not be disturbed by
construction activities.
It is anticipated that the WWTP will be visible to travelers on the B62 Road. The mature trees
that are present provide a natural buffer. Where possible, additional trees will be planted at the
outskirts of the site to provide additional buffer between the newly planted trees will serve as a
carbon sink.
iS
28 I ? 3 s e
Additional electrical cables in the vicinity of the proposed Treatment Plant are expected
following the completion of construction.
There will be no post-construction impacts on the surrounding community since disturbed areas will
be restored to their original condition.
Short-term, minor, adverse impacts to local visual aesthetics are expected due to construction
equipment and excavation work.
5.1.2.1 Flora
Bassin Requin's lora consists mainly of grasses and herbaceous vegetation. Rows of eucalyptus and
Pine trees also form part of the vegetative decor. Therefore, there would be limited impacts on
terrestrial
ecology
as
the
habitat
lost
is
not
of
nature
conservation
value.
Site clearing activities for the implementation of the project would necessitate the felling of these
trees and the removal of invasive exotic shrubs.
Proposed sewer pipe work extends through forested area and would have minimal impact on
vegetation.
The removal of mature trees will have a short term impacts on the surrounding landscape.
5.1.2.2 Fauna
The construction site consists of no endangered species. Certain species, particularly bird
species, could lee to nearby habitat during the construction phase of projects when their habitat
will be disrupted. However, given the temporary nature of construction-related impacts to
29 ^
::
'< *.:
wildlife and the likely separations in implementation timerames, there is little potential for
cumulative impact to resident wildlife rom construction activities associated with the proposed
action.
Therefore, there would be no significant impacts to wildlife rom the construction phase.
5.1.2.3 Pest nuisance
Construction activities will not have any impact on pest nuisance as the inluence comes rom
operation activities.
Direct employment
The table below gives a general breakdown of the workforce that will be employed by the
contractor during the construction of the wastewater treatment plant at Bassin Requins.
30 | PC
Category
Number
Manual workers
40
12
15
There will be a temporary intensification of traic going in and out of Bassin Requins because of
the transport of workers, construction materials and equipment. Workers will access the site
either by private cars or by buses, construction materials and equipment will be transported by
trucks.
Therefore, impacts on external and internal (inside the plant boundaries) current traic during
construction phase , that will last 20 months, have to be identified and mitigation measures will
have to be implemented to minimize negative impacts.
5.1.3.3 Cultural Heritage
There is currently no recorded evidence or visible evidence for archaeological remains on the
site. It is possible that objects of ancestral value may be found during excavations. If any
31 3 :: ..j f
archaeological resources are discovered at the various work locations, work must be stopped
immediately in the area of discovery and the concerned authority alerted.
32
r C:
-. - ,- '., ^,
^
All in all, the expected impacts will eventually protect public health, maintain good living
conditions for lora and fauna in the affected areas, decrease pollution of water resources
(surface and ground) and support the already existing agricultural activities. Awareness
campaigns on the proper handling and usage of treated water in agriculture should be conducted for
the farmers in the area.
Thus, all impacts are expected to be significantly positive, both directly and indirectly in the
short and long terms.
33 D p C-O
During the operational phase, there will not be any expected negative or positive impacts on land use
and landscape, as no new land usage or change in landscape will be done. Expansion of the WWTP
is not forecasted before the year 2035.
(flies and
mosquitoes) around Bassin Requins and believed their presence was mainly due to the stagnant
water ponds present there.
The Pig Farm in the vicinity also has a telling effect on the mosquito breed.
The possible sources of lies in the vicinity, as they represent a source of organic food for them,
are:
Agricultural
activities
(resh
manure)
Potential adverse operational impacts include accidental spills of diluted or undiluted sewage or
other waste materials into water bodies if a pipeline leaked, particularly in cases where pipelines
cross streams or pass through water bodies.
35 I F a t e
Such accidental spills are rare and temporary and can be corrected quickly. These spills typically do
not result in specific adverse impacts to biological resources because they are rare and the
receiving water body further dilutes the waste.
5.2.3 Anticipated Signiicant Impacts on Social-Economic condiions
5.2.3.1 Employment
The new treatment plant will create a large number of job opportunities. These will cater for all
skills, ranging rom cleaners to plant operators. The recruitment process will be in line with the
Equal Opportunities Act (2008). Therefore, no part of the recruitment will be subject to
discrimination and every eligible candidate applying for a position will have a fair opportunity.
The following table shows an overview of the overall expected personnel operating the treatment
plant.
Category
Number
Manual (Cleaners)
10
24
scrapers)
Skilled (Engineers & Technicians)
Table 5: Employees working at the WWTP
12
^
36 t- o a
I- *'< *
'^
' '-J**i*J*-.*
A
Potable Water
The potable water demand for the proposed development has been estimated to be approximately
30m3/day.
The National Development Strategy (NDS) recommends the need for judicious use of water
resources on the island while the National Physical Development Policy sets out clearly defined
guidelines for eicient use of water resources:
Policy No U.l: Reduction of losses in water supply systems
Policy No U.3: Water Source Development
Policy No U.5: Augmentation of Service Reservoir Storage Capacity
37
Electricity
The electrical power demand for the proposed development is of significant value. The Central
Electricity Board (CEB) has been informed of the power needs and necessary contributions will be
paid by the promoter.
38 | P a 2 e
39 | ? ? g a
Pollutant
Applicable to
Standard
200 mg/m3
kept
clear
speeds
of
mud
controlled
40 ' - a- -
equipment
eficiently
to
decrease
fuel
consumption
Domestic waste
During the construction phase, the main source of efluent will occur when staff and workers will
be present on site. The amount of sewage generated will obviously depend on the number of staff
present on site. However it is expected that the rate of generation will be at a maximum of 10
m7day.
41 | P a g e
In order to account for the above, the selected contractor will be required to provide an adequate
mobile toilet facility for the duration of works on the proposed site for development. The above
effluents cannot be disposed of in the environment since their bacterial concentrations exceed the
threshold set by the authorities.
The Wastewater Management
standards
regarding
various
Standards
COD
120
TKN
25
NH4 Nitrogen
Nitrate
10
Total Phosphate
10
45
pH
5-9
-\
\V
V
\ > t-
X: ^
V
The following shall be implemented to mitigate domestic waste during the construction phase
Implementation of an onsite disposal facilities, namely a septic tank.
After construction, the toilet facilities will be decommissioned and the resulting sludge
will be pumped at carted away in accordance to the requirements of the local authorities.
The toilet facilities should be kept in a clean and sanitary condition at all times.
Domestic wash water will be channeled to a temporary soakaway pit.
These short-term measures will prevent the occurrence of land degradation and eliminate
emissions of ofensive odours rom the generation of domestic liquid waste.
42 -> '-\
Plans would incorporate existing trees into the project design to the maximum extent
possible
During construction, the contractor will be required to minimize the impact of the
excavation and backfill activities. Disturbed areas will be graded and vegetated with noninvasive native species as quickly as possible following construction to restore the natural
setting.
6.1.2.2 Fauna
The impact upon existing animals will be minimal, as they will relocate to the nearest available
habitats, which will be present near to the WWTP itself.
The noise and air quality abatement measures mentioned above will mitigate any negative
impact.
6.1.3Mitigation measures on Socio-Economic Environment
6.1.3.1 Employment
For the construction of the WWTP facilities, it is currently planned bring the number of
construction staf to around 100 people, mainly technicians and operators.
Since the overall efect is positive, no mitigation measures are required.
43 I F a - c
Appropriate sign posts set up well before the region of Bassin Requins to indicate
construction and the crossing of heavy trucks ahead.
Presence of policeman to regulate traffic during peak hours.
07.00-21.00
60
21.00-07.00
55
Table 8: Noise exposure limits
The presence of vegetation and green spaces surrounding the proposed site is likely to reduce the
noise experienced.
Buffer zones between the site and closest residential areas will be provided to reduce noise
propagation.
Therefore, no significant noise impacts will be caused by the proposed plant.
44 | P a s e
6.2.2 Odour
During the processing of wastewater hazardous and smelling gases are released into the air,
mainly Hydrogen Sulphide and methane.
In our Mauritian context, The Standard for Air (1998), listed in the Environment
Protect Act (2002) stipulates the following limits for the above-mentioned pollutant.
Pollutant
Hydrogen sulphide
Applicable to
Standard
At Bassin Requins Treatment Plant, an odour control system will be set up to mitigate any
effect of foul air.
The objective of the odour control system is to eliminate the gases contained in the
polluted air prior to discharge in the environment. The odour control system consists
of a polluted air collection system driven by a number of fans at critical process units,
e.g. pre-treatment unit, pimary settling tank, sludge mixing tank and sludge collection
tanks. The air will guided to the odour treatment unit, where the odorous pollutants
contained in the air are neutralized: a desulphurization odour control followed by
biological odour control.
The eficiency of the odour control system is constantly monitored by a network of gas
sensors,
mainly for Hydrogen Sulphide (H2S) and Methane (CH4). The sensors will be placed in
buildings
with high probability of occurrence of gas concentration exceeding the limits to warn the
people
inside the building. The occurrence of gas concentrations will activate an alarm
inside
the
building (siren) and an alarm at the process control centre in the administration building.
Life-saving measures will be initiated if needed and the alarm will be followed by a
number
of
the
45
The Sludge Management Plan will allow for adaptive management of environmental
compliance and improved performance throughout all stages of sludge production,
treatment, drying, storage, and disposal or reuse.
It should address impacts and risks of concern such as ire, odour, insects, groundwater
seepage, and any additional impacts or risks that may be identiied in the future.
The Sludge Management Plan will clearly identify the party responsible or
implementing, monitoring and reporting on the operating and maintenance procedures. It
will establish
6.2.2 Biological
Parameter
Unit
Temperature
T5
Permissible Limits
pH
40
5-9
Floatables
mm
Biochemical Oxygen
mg/1
250
mg/1
750
Suspended Solids
mg/1
300
Cadmium
MS/1
20
Chromium (VI)
Mg/1
100
Chromiura Total
Mg/1
500
Mi/1
100
Lead
mg/1
Nickel
mg/1
Zinc
mg/1
Total Mercury
Mg/1
10
Arsenic
Jig/1
200
Total pesticides
mg/1
mg/1
20
Demand (BOD5)
Chemical Oxygen Demand
(COD)
47
a e c
Ensure that mitigation associated with all phases, construction and operation, of the
proposed project meets or exceeds the water quality standards outlined within the
associated permit.
Ensure that unmitigated impacts of the proposed project do not adversely influence
wastewater and/or marine waters beyond an acceptable level.
All processes that are expected to generate wastewater that will be discharged into a
sewerage system or marine waters and that will be treated for reuse should be described.
The water balance of the proposed project should be described. A water balance identifies all
successive water uses (e.g., sanitary, boiler, cooling, on-site water treatment) and
associated flow direction and flow rates
The structures discharging wastewater into the marine waters and/or sewerage system
should be described. The structure associated with each wastewater outlet should be
identified with the outlet identifier. For discharge of wastewater into marine waters,
48 | P a 9_ e
information on the pipe dimensions, the material(s), and the distance of discharge rom the
shoreline should also be provided.
Any pre-treatment or treatment that wastewater, including storm water, will undergo
prior to discharge or reuse should be described. Details regarding the treatment systems
and processes, as well as the biological, chemical, and physical properties that will be
altered by the treatments should be provided.
If treated wastewater will be reused, identification and description of the fate or final use of
the treated wastewater should be detailed.
The main parameters that will inluence the quality of the effluent are:
The probable pollutants in wastewater, including storm water, discharged into a sewerage
system and/or marine waters or wastewater treated prior to reuse should be described.
The probable pollutants created with dredging and reclamation activity should be
described. This information should provide a detailed account of the locations and
probable amounts of materials that will be dredged and reclaimed.
The pollutants that will be monitored in wastewater discharged into sewerage or marine
systems, marine water (monitored at sampling locations in the marine waters receiving
wastewater and dredged.
The sample collection and handling procedures that will be implemented for wastewater and
marine water quality monitoring should be described.
Sample collection should be conducted in a manner that is representative of the discharge or
monitoring location and depth. In addition, the samples should be handled in a manner that is
standardized and ensures the highest level of analysis precision and accuracy.
49 | F age
6.2.2.2 Pest
The temporary storage of sludge around the Treatment Plant represents a source of breeding for
flies and mosquitoes.
Mosquitoes can act as vectors for many disease-causing viruses and parasites.
Infected
mosquitoes carry these organisms rom person to person, without exhibiting symptoms
themselves.
General maintenance principles:
With the exception of certain treatment control measures designed to hold permanent
water, treatment measures should drain completely within five days to effectively
suppress vector production.
Any circumstances that restrict the low of water rom a system as designed should be
corrected. Debris or silt build-up obstructing an outell structure should be removed.
Under drains and iltration media should be inspected periodically and cleaned out or
replaced as needed.
Conduct maintenance activities regularly, in accordance with a municipality-approved
maintenance plan.
There are a number of wet ponds around Bassin Requins Treatment Plant. The following
measures should be put in place for pest control:
Long-term site maintenance as well as routine monitoring and management of
mosquitoes by a qualified agency
50 | P c=1 e e
Remove grass cuttings, trash and other debris, especially at outlet structures.
51 | P s g e
Ensure no leakage occurs in the potable water distribution network within the Treatment
Plant.
Setting up of a monitoring system to ensure water losses are kept to a minimum.
Storm water will be channeled towards landscaped areas to make eficient use of
rainwater.
52 | P s gr\
Minimize effects of magnetic ields within the internal electrical network of the
Treatment Plant o'reduce electrical power losses.
6.2.3.2 Employment
Employees recruited by the WWTP must be done a fair and non-discriminatory basis. The
following mediators present will ensure this:
Open advertisement in local newspapers
Employment agencies may be contacted to facilitate recruitment. This will also help to
decrease the unemployment rate in the country.
The Equal Opportunity Act will be enforced to ensure no discrimination on basis of race,
colour and sex.
Employees Rights Tribunal, in the case of unfair treatment on the place of work.
A
53 | P aP 9.
7*0 Recommendations
The Project can further be improved by implementation of the following
The Treatment Plant can be upgraded to make provision for the production of drinking
water.
Over time, provision for a larger demand of treated wastewater will be required. Land is
available on the suburbs of the WWTP. Thus, the treatment plant can undergo expansion to
meet future demands of the population.
A better system can be set up for the disposal of sludge. An underground disposal facility
can be constructed. This will eradicate the problem of pest on control on the sludge
disposal site.
Medical follow ups can be carried out on a regular basis on the employees of the WWTP.
These will be under the aegis of the Ministry of Health.
V
54 I P ?
8.0 Conclusion
In the light of the present discussion, we have observed that wastewater treatment is an
increasingly impotant aspect in the society. And among the multiple steps in building a
wastewater treatment plant, writing an Environmental Impact assessment(EIA) is a very
significant phase of it. Furthermore when writing an EIA we must consider the various acts and
regulations, that is relevant to the development we intend to undertake. Moreover a brief
description of the proposed project and identification of the impacts on the environtment is key
to the EIA. On this note, we can conclude that the purpose of an EIA is the process of
identifying, predicting, evaluating and mitigating the biophysical, social, and other pertinent
effects of development prior to major permission being granted for development and the EIA
report assist in ensuring that the authority is considering the appropriate impacts when deciding
whether to proceed or not with a project.
55 | P ag e
9.0 References
ALTEO Ltd. (Dec 2013). Closure of Beau Champs Sugar Milling Operations and
Centralisation at Union Flacq. Available:
http://environment.gov.mu/English/eia/Documents/Reports/res_UEL/eia/annex.pdf
Last
Last
56 | PC.
X_
r
y
o
\
c--
^
u
y
C-*-*\
f
//
NS
/
(_
\ Bois
^
v
Peit&RetikiiteS J
*i^O"fPi
L \Sii
/.
i
s Vs. V
Latapie
/
Gratia
/
Bnsce verdierc
Retrahe
L.
V - - : - *<* _ Bon ATvueiL /
f5'h-itk "\
;v
,a
^.f
.
/J
/o (.
/
^
v
.
-*v
r>
/
r
J>
'k-^n-1-"--::
Stii
;*wa X
<s
A\
^
^
/
(K"n
Ba
VLWl ,,., H,..,,,;, n.
^
sULrt
Z
(rr
J
to
G?
\
uV
^ r
\
&/
\
r^
/ Grand
dans *-
V"N ^
i T
^
Fond J
*s
\-
\ 7'M<
^
y.
-^
O r^
Ss VJ
^
J f
r
\^.
\
s
Y
k
>
^Pon'tW
anc
Ja:
r
(T
_y
i*.
Cnu
Con
st
Jo
^
<<
XJ\-4
s; \ t- -v
*-. (?
>
J
H
n
.'j
T>
\
\
j
;
N
1
^: >
C
V\
c ^m 5 r
V
en
\
<.'t
tr
Js*
e \
-O
f
S
\
NX
VP
\ <\
^s
^^X
Belle Vu
n
<
;V
Lahmtie V
^iendijj \^
U
^
P
;
N
J
^C ,
S
K
5\
r
V"
''V
\
{/
:e
I
\
C
\
S'V
/
K
i^
V
r
o
j
)
\
I
^
l*> \
\
V
J\
U-, r-J J V
/^<
^
^^
rr
'
ci:
7 y
N
/
c/ '
0 ^
x
/^
"T
A/
Mi
Ht
^ ' X N
v,
^7
is
i^
V
>/
*
A \
x
^V.
VII
r
/
^
r
\ {\
V
^
N^S
r^
,l(; -Haul
de Flacq c-*,- c\/ ' J
H,/f
Hctilih
^
i Cf-M
^.J!
^
\
x
V'H
oe
\
^
M*
*
**
^
J>
U^
>
\n
S?.0
Ct: C
>' ".'.
mon
Flacq
/-"
^ 4 ^
_>
^
jf-IVy
)
N^ACtffri
ra _
\a r7 F-'-i tnt acne-. *-*
X
ro;
>
-- ^-s^1' -J
/
r-"K^
X
,^ /
^ ^'.'
**'.
rQ
/, hm
J
L
'x
*
_/
;
"\
-"f;
\.
qi
-i
V
x
Q S 0
A
yi
/ ' f /V u / >r^
^
^\
X
>
/c
f
J,
\
V
>-S y
r
\
/
s
/
^
^
\
v
vV/ s y
\
DISTRICT OF FLACQ
\
v
3
/
VJ
XV
^\
OX
C^
s\V_
cv>umt**
XV
'*ot
Ck>u-r.c<
i
f
~
j
.-.'-a'
*j.
u-^t
^. ^
%- .j ."" U*nquc _ ' ^
^
\.rvrv
^ -1
elwd
J>,
^O c
Baittrii
/
y
r\
Grvstht
0 ^ / /
ptedux
X
Providence
*.
^nAA
u;
Ptitnj-:;'.^
^JC
-v v a i^ s.
mp
C?
-
^ j~
^
^ ^
S,7jf'i>
s
V
^ co\
^>
Ux
V
O
y^ y -.S
v>**.
u
^ ' Wvu\
xrr
r :: </ A.^.y
f\ tp"j r
/
o
NJ A
'\
a
W
Is ^ ?
T^~ *.^
rw:*,
\J
^v
F-Jir'i *' \.
\
r-J
6
V
t'S
^1
.*,
.\
>
jO
>
X -.u'^.'^C tTri^f,
A*
.
.-.-
H-"
V^
^
a**'
IVP*/tOlwalZ7
Cl/S;j
v\
\-^
^J
Raphia
Krt.M*j
i?
o /> ~P.
s> c
./
/!
^'>>
Pilaff* PJ^
\
-j*
o( SjO/l
\L- ^
o
'>
p -^ PtedesPuits
^^ J
-s
S^c (7 _>
>
^
^J
>/P
Hermitage
C f Hfff dl
Js h->
JS
M:*.- icaritK
O
*>-^
=0
3
^/uv ^ v-J
\'
- \ ^X:
<r
K-.'v
/
s
\
/
i-C'.nh-u'. Cwtnui
\.
o
xn
n
>A
/>
Cin
Bowii/bn
s \.
P Kmj/
\
J
O. X
y
^
o
>__
Sm;:jJ
i>>
-A
^'
W^*
1/
A^j
*j V x^'r^r^li
^ ^
\
P
<n
i*-*S
^
^
7.. /
V Cilr/V.vyr\
N.
Siij
;j
i^
* ^ v.:
a
P
F
? \J
r
CrounJ
V*
i^-'l
a^
iy
r: >
J
-f
^,
Mlre
r- ->y Ck
Camp
*r O Xi, ch
Aau
"%..
*lct Rouge
AICi/:/ft:' ( o^:^
*>
^ c *^
n o--\
ft*/:
(.
--'o
t':
5>.
/
Argy
^6 1 v
S-)
<k
Bramsthan
\
V
^\ \
^
s*
*S>
c
Ciimp
v
Creol
xlamp
e
C j LJf:
kanco
^?
\'\\ --.
.
V
i.,--:C 'ft
{.
lV
>:
JC*Camp
Lolo
tt
*<oL ,i.-^ V
C&a
x.
O ux>?
hidiTcliost
fu <5;
rX a
T
vrv
2)
^
l$odore. Rose
\1tS
: Or j C
^Hollandak Pte
S^ \'-
du
Puits
Belle Mare
^
Mare du Puits
*-
:v
,
k ;>
cXiatre CocysT~\
f^^^
pl
S
V
des
N
\
X
/^
\i
C^! v/
\
^(
^
r^
J
N^ ^
r?
6 o^
)f
+r
Scale 1: 40,000