Beruflich Dokumente
Kultur Dokumente
CHARU KANDPAL
THDC INSTITUTE OF HYDROPOWER
ENGINEERING AND TECHNOLOGY
Summer Training Report
Table of Contents
Serial
Number
Topics
Page Number
Submission Details
Acknowledgement
Introduction
11
Power Generation
15
Excitation System
16
Braking System
18
Governor System
19
21
23
References
25
Epilogue
26
1|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Submission Details
Duration of Training-
Title of Report-
Submitted To-
Name-
Charu Kandpal
CollegeUniversityBranchRoll No. -
110970105019
Guides:
1)
2)
3)
4)
5)
Er. D. P. Kothiyal
Er. P. C. Pandey
Er. Rakesh Panwar
Er. Sachin Vyas
Er. Arpan Kumar
2|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Acknowledgement
I would like to whole heartedly thank all the guides for their true
effort they put in to make us understand principles behind working
of all sections in brief.
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
Uttarakhand Technical University
3|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
ntroduction
Tehri DamThe Tehri Dam is a multi-purpose rock and earth-fill embankment dam at
the confluence of Bhagirathi and Bhilangna River at Tehri in Uttarakhand, India. Tehri Hydro
Power Projects comprises of three phases.
Phase 1.
Phase 2.
4|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Coal dominates the energy mix in India, contributing to 55% of the total primary energy
production. Over the years, there has been a marked increase in the share of natural gas in
primary energy production from 10% in 1994 to 13% in 1999. There has been a decline in the
share of oil in primary energy production from 20% to 17% during the same period.
Coal Power:
India has huge coal reserves, at least 84,396 million tons of proven recoverable reserves
(at the end of 2003). These amounts to almost 8.6% of the world reserves and it may last for
about 230 years at the current Reserve to Production (R/P) ratio. In contrast, the world's
proven coal reserves are expected to last only for 192 years at the current R/P ratio.
Natural Gas:
Natural gas accounts for about 8.9 per cent of energy consumption in the
country. The current demand for natural gas is about 96 million cubic meters per day (mcmd) as
against availability of 67 mcmd. By 2007, the demand is expected to be around 200 mcmd.
Natural gas reserves are estimated at 660 billion cubic meters.
Hydro Power:
India is endowed with a vast and viable hydro potential for power generation of
which only 15% has been harnessed so far. The share of hydropower in the country's total
generated units has steadily decreased and it presently stands at 25% as on 31st May 2004. It is
assessed that exploitable potential at 60% load factor is 84,000 MW.
5|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Nuclear Power:
Nuclear Power contributes to about 2.4 per cent of electricity generated in India.
India has ten nuclear power reactors at five different nuclear power stations. More nuclear
reactors have also been approved for construction.
6|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Power Plant:
A power plant or a power generating station is basically an industrial location
that is utilized for the generation and distribution of electric power in mass scale. Since for the
purpose of bulk power generation, only thermal, nuclear and hydro power comes handy,
therefore a power generating station can be broadly classified in the 3 below mentioned types.
7|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
This power is utilized for rotating the alternator shaft, to convert it to equivalent electrical
energy.
An important point to be noted is that, the hydro-electric plants are of much lower capacity
compared to their thermal or nuclear counterpart. For this reason hydro plants are generally
used in scheduling with thermal stations, to serve the load during peak hours. They in a way
assist the thermal or the nuclear plant to deliver power efficiently during periods of peak hours.
8|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Reservoir
Full Reservoir Level (F.R.L)
Maximum Level During Design Flood
Dead Storage Level (D.S.L)
Water Spread at F.R.L
Water Spread at D.S.L
Dam
Type
Top Level
Height
Width at Riverbed
Length at Top
Spillway
Chute Spillway
Crest Level
Waterways
Type and No. Of Gates
Right Bank Shaft Spillway
Type and No. of Gates
Crest Level
Diameter of Shaft
Left Bank Shaft Spillway
Type and No. Of Gates
Crest Level
Diameter of Shaft
Intermediate Level Outlet
Number
Size (Diameter)
EL 830 M
EL 835 M
EL 740 M
42 Sq. KM
18 Sq. KM
Earth and Rock Fill Dam
839.5 M
260.5 M
1125 M
592 M
EL 815 M
3 bays of 10.5 M each
Radial Gates, 3 Nos
Ungated, 2 Nos
830.2 M
12 M
Radial Gated, 2 Nos
EL 815 M
12 M
One
8.5 M
9|Page
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Penstocks
Numbers
Size
Total Length
Power House
Machine Hall
Type
Location
Number & Units
Head
Transformer Hall
Type
Size
Step Up Transformer
Capacity
Number
Voltage Ratio
Switchyard
Type
Tail Race Works
Number and Size of Tail Race Tunnel
Length of Tunnels
Insert Level of Outlet
Installed Capacity
Total
Tehri- I
Tehri- II
Koteshwar
4
5.75 M dia. Each
1040 M
Underground
Left Bank, Underground
4, 250 MW each
Maximum: 231.5 M
Minimum: 127.5 M
Designed: 188.0 M
Underground
16118.529 M
306 MVA
4
15.75/420 KV
Indoor SF-6 Switchgear
2 Nos, 9.0 M dia. Each
862.5 M, 747.5 M
EL 598 M
2400 MW
1000 MW
1000 MW
400 MW
10 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Head Race TunnelThere are 04 Numbers of HRTs on the Right Bank of the reservoir having
circular shape, 8.5 m diameter. The lengths of HRTs are 779 m, 855 m, 997 m &1033 m. It takes
water from reservoir and supplies it to power house machines for generation. HRT-1 and
HRT-2 carry the later to Hydro power plant (HPP). HRT-3 and HRT-4 carry the water to the
pump storage plant (PSP) which is still an ongoing project and is not functional right now.
11 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Penstocks:
Water enters through the different penstocks to the different generating units.
Each penstock comprises upper horizontal, vertical & lower horizontal reach including upper &
lower bend. The diameter of penstock is 5.75 m.
Inlet Valves:
One Butterfly Inlet Valve (BIV) at mouth of the each penstock and one machine inlet
valve (MIV) before the spiral casing are installed. The valve remains close in case of unit
shutdown.
When the unit is started then after sensing the starting command, MIV opens first to build up
the pressure in spiral casing and roll the turbine.
Turbine:
Four Vertical Francis turbines are installed having net head of 188 meter.
Water from the spiral casing enters through the 28 guide vanes and strikes the 14 blades of the
runner, which is coupled to the main shaft. The shaft is coupled to the rotor of the generator at
the other end. The opening of guide vanes depends upon the generation requirement. Water
strikes the blades of the runner and fall axially in the draft tube. For keeping shaft vertically,
Turbine guide bearing is installed which is of rotating sump self-cooled type.
Generator:
It is 278 MVA, 0.9pf, 50HZ, 3 Phase generator which generates power at a
voltage of 15.75 KV. A generator has two parts, Stator and Rotor. Power generated is
transmitted through isolated phase bus duct to transformer gallery from where it is stepped up
to 400 KV by GSU transformers. Two bearings named as Thrust bearing and upper guide
bearing are installed for sustaining the outward thrust of rotor and keeping shaft verticality.
Both the bearings are of water cooled type. The direction of rotation is anticlockwise when
viewed from the top.
13 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Transformer Gallery:
Eight in numbers, 306 MVA, 15.75/ 400KV GSU 3 Phase transformers are
installed in transformer gallery (TG) for the four units. Other four set of transformers are
installed for upcoming Pumped Storage Plant (PSP). 15.75 KV is generated from the each unit
and this power is stepped up to 400 KV here and sent to switchyard through oil filled cables.
These generating transformers are provided with makeup valve which is filled with water that
cools the oil that is being used to cool the transformer. These transformers are also equipped
with micro wave detector which detects the microwave that generated In case of some spark
and raises the alarm. Transformer oil conditioner is used to purify the oil which is used to cool
the transformer and eliminates different gases from the oil that got mixed during the cooling
process.
14 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
ower Generation
Water enters from reservoir through HRT-1 and HRT-2. Each HRT further divides
into two penstocks which are equipped with a butterfly valve. Hence four penstocks
lead to four turbines. This water rotates the turbine blades and turbine rotates the
excited rotor. This leads to change in flux and according to faradays law electricity is
generated.
Water from turbine enters the draft tubes and there after tail race tunnel TRT-1
and TRT-2. These TRTs takes the water to mainstream.
15 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
xcitation System
The basic principle of power generation is when a magnetic field is moved across a
stationary conductor, voltage is induced in the conductor. Voltage will be induced even if
conductor is rotated and magnetic field is kept stationary, Generators consist of two circuits an
electric circuit and a magnetic circuit; one is rotating with respect to other. The magnetic circuit
of a generator is called exciter.
In modern generators magnetic field is produced by an electromagnet. The
intensity of magnetic field can be varied by varying the amount of DC current
applied to electromagnet. Generator output voltage is affected by the following
factors:
1) Intensity of the flux in the rotating magnetic excitation field. This can be
varied by varying the DC current applied to the electromagnets.
2) Rate at which flux lines cut by the conductor. This is not variable since the
generators operator at the rated constant speed.
3) Length of the conductor (Not variable).
The excitation system is intended for providing the following functions:
Start up, field flashing and switching to the system by precise synchronizing.
Operation of the generator at loads varying from no load to maximum load for the
generator.
Operation in the synchronous condenser mode both with inductive and capacitive load.
Field forcing at the set voltage response and de excitation at disturbances in the power
grid causing voltage rise or drop in the system.
16 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Rotor field suppression by the field circuit breaker at protection operation with
simultaneous inversion of the rectifying unit.
Operation on joint control maintaining even distribution of the reactive load between
machines.
Limiting the ratio of ceiling field current to nominal field current by two (2) per unit
without time delay as well limiting of over load by the time-inverse characteristics.
Limiting minimum field current with set point depending on generator active power in
the mode of VAR load demand from the grid.
Protection of the generator for loss of excitation/asynchronous run.
Protection of generator transformer from damage at frequency drops under no load
conditions by lowering the voltage regulator setting suitably.
Compensation for step-up transformer impedance.
Startup of pumped storage units by back-to-back method and for electrical braking
operation of the units.
17 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
raking System
Figure 8: Mechanical
Brake
18 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
Governor System:
The main purpose of governor system is to maintain the rotational speed of the
rotor within permissible limits. It consist of Electrohydraulic Transducers, which takes
input from electronic transducers installed in unit control boards and performs desirable
action by sending it to servomotor. It also takes signals from servomotor and in case of
any malfunctioning, it sends signal to electronic transducer to take mandatory action
according to the scenario.
For controlling the speed of a turbine a signal proportional to the speed is to be fed to
the control system. The pressure is maintained constant by a separate unit called as oil
pressure unit.
For achieving automatic control, a portion of the system output is fed back to the
system and this signal is called feedback. The governor then automatically adjusts the
flow to control the prime movers power.
20 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
as Insulated Switchyard
21 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
In GIS red cylinder contains Nitrogen whereas blue cylinders contain SF6. Nitrogen is used here
to take vacant space created by motor whenever breaks are applied. As breakers are removed or
applied by a motor and Nitrogen fills it very fast and it is cheap.
22 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
It uses SCADA i.e. Supervisory Control and Data Acquisition system. It has full control on
starting, running and stopping of a machine. Amount of energy produced, Shutdown of a
machine, starting of a machine etc. is ensured by SCADA system of ALSTOM installed in
CCR.
Start Sequence:
START
1)
2)
3)
4)
5)
MIV open
Gen. Cooling Water ON
Gen. Space Heaters OFF
Field Beaker ON
Governor Start
23 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
If Speed> 95%
Excitation ON
If Voltage>80%
Spinning Mode
Check
Synchronization
and close circuit
breaker
END
24 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
eferences
25 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15
pilogue
26 | P a g e
Charu Kandpal
THDC Institute of Hydropower Engineering and Technology
2014-15