When estimating this type of work the preliminaries need specific attention. The pricing
schedule broke down the preliminaries into headings. In order to price these, the headings
need to be assessed for the works required.
Preliminaries
716,720.00
3,600.00
Hoisting/lifting/craneage
96,000.00
Temporary services
47,900.00
Communications
20,060.00
Safety
173,800.00
Rubbish removal
34,200.00
45,000.00
Plant
123,840.00
Page 1.
Copyright 2015 isurv
http://www.isurv.com
12,000.00
82,663.20
Total preliminaries
1,460,383.20
The associated measured works came to 5,804,186.49, which meant the preliminaries
elements came to 25.16% of the measured works. It is only in understanding the nature of the
works being carried out is it possible to develop up a version of the preliminaries rather than
relying on a typical percentage addition. This is particularly prevalent in atypical projects.
In the context of this pre-tender estimate the measured works included the following concrete
works:
Item
Description
Qty
Unit
Rate
Total
36
wks
2500
90,000.00
Preliminaries
Project
manager
Page 2.
Copyright 2015 isurv
http://www.isurv.com
Foreman
36
wks
2500
72,000.00
Senior
engineer
20
wks
1800
36,000.00
Site engineers 80
wks
1400
120,000.00
Assistant site
engineers
80
wks
1000
80,000.00
Logistics
manager
36
wks
1500
54,000.00
QA engineer
36
wks
1500
54,000.00
IT/document
controller
36
wks
1200
43,200.00
Construction
support
36
wks
900
32,400.00
Reinforcement 20
engineer
wks
1500
30,000.00
wks
1800
25,920.00
Senior
surveyor
(40%)
14.4
wks
2000
28,800.00
Assistant
surveyor
36
wks
1400
50,400.00
wks
50
3,600.00
Stores (2Nr)
72
Hoisting/lifting/craneage
Erect
Page 3.
Copyright 2015 isurv
http://www.isurv.com
hoists to
cores
B
Driver and
hire
36
wks
2000
72,000.00
Temporary services
Electrical
connection
item
500.00
Trailing leads
item
2,000.00
Lighting
tripods
item
1,000.00
Equipment
item
10,000.00
Slip cables
and wiring
item
15,000.00
Standby
generators
Temp
plumbing hose
18
wks
800
item
14,400.00
5,000.00
Communications
Calls
36
wks
100
3,600.00
Fax
36
wks
35
1,260.00
Copier
36
wks
25
900.00
Stationery
36
wks
25
900.00
216
wks
25
5,400.00
Page 4.
Copyright 2015 isurv
http://www.isurv.com
(6Nr)
IT equipment
item
8,000.00
Safety
Supervisor
36
wks
1300
46,800.00
Equipment
36
wks
750
27,000.00
Protective
screens
item
50,000.00
Safety netting
item
50,000.00
Rubbish removal
Labour cleaning
36
wks
27,000.00
Skips
36
wks
7,200.00
item
45,000.00
Allowance
Plant
Concrete
pumps
72
wks
86,400.00
Setting out
equipment
108
wks
14,040.00
Small tools
36
wks
14,040.00
Page 5.
Copyright 2015 isurv
http://www.isurv.com
Consumables 36
wks
9,000.00
General
access
item
10,000.00
Scaffolders labour
wks
39,600.00
Haki stairs
item
25,000.00
Handrails and
the like
item
30,000.00
item
12,000.00
Scaffolding
36
Allowance
OHP on
preliminaries
6%
82,663.20
Page 6.