Beruflich Dokumente
Kultur Dokumente
APPENDIX 1
1.1
1.1.1
General
General conditions of the ship
56
Bureau Veritas
Pt B, Ch 3, App 1
Pendulums
The use of three pendulums is recommended but a minimum of two are to be used to allow identification of bad
readings at any one pendulum station. However, for ships of
a length equal to or less than 30 m, only one pendulum can
be accepted. They are each to be located in an area protected from the wind. The pendulums are to be long
enough to give a measured deflection, to each side of
upright, of at least 15 cm. To ensure recordings from individual instruments are kept separate, it is suggested that the
pendulums be physically located as far apart as practical.
The use of an inclinometer or U-tube is to be considered in
each separate case. It is recommended that inclinometers or
other measuring devices only be used in conjunction with at
least one pendulum.
1.1.5
Means of communications
Documentation
lines plan
capacity plan showing capacities and vertical and longitudinal centres of gravity of cargo spaces, tanks, etc.
When water ballast is used as inclining weights, the
transverse and vertical centres of gravity for the applicable tanks, for each angle of inclination, must be available
docking drawing with keel profile and draught mark corrections (if available).
1.1.8
Bureau Veritas
57
Pt B, Ch 3, App 1
The plot is to be run during the test to ensure that acceptable data are being obtained.
The pendulum deflection is to be read when the ship has
reached a final position after each weight shifting.
For ships with a length equal to or less than 30 m, six distinct weight movements may be accepted.
Figure 1 : Weight shift procedure
Initial position
1
all double bottoms, as well as all tanks and compartments which can contain liquids, are to be checked,
paying particular attention to air pockets which may
accumulate due to the ships trim and the position of air
pipes, and also taking into account the provisions of
[1.1.1]
2
3
4
1 shift
it is to be checked that the bilge is dry, and an evaluation of the liquids which cannot be pumped, remaining
in the pipes, boilers, condenser, etc., is to be carried out
the entire ship is to be surveyed in order to identify all
items which need to be added, removed or relocated to
bring the ship to the lightship condition. Each item is to
be clearly identified by weight and location of the centre of gravity
6 shift
7 shift
8 shift
4
5 shift
1
2
3
4
2
3
4
The incline
Movement No.8, a recheck of the zero point, may be omitted if a straight line plot is achieved after movement No.7. If
a straight line plot is achieved after the initial zero and six
weight movements, the inclining test is complete and the
second check at zero may be omitted. If a straight line plot
is not achieved, those weight movements that did not yield
acceptable plotted points should be repeated or explained.
After each weight shifting, the new position of the transverse centre of gravity of the weights is to be accurately
determined.
The weights are to be transversely shifted, so as not to modify the ships trim and vertical position of the centre of gravity.
58
4 shift
3 shift
1.1.9
2 shift
Bureau Veritas