Beruflich Dokumente
Kultur Dokumente
Select one:
a. cost and decision making
b. time and cost
c. uncertainty and damage
d. quality and time
a. Responses
b. Expectations
c. Uncertainities
d. Contingencies
You have an activity where the early start is week 6, the early finish is week 10, the latest
start is week 14, and the latest finish is week 18. The slack in this activity is
Select one:
a. 6 weeks
b. 8 weeks
c. 4 weeks
d. 18 weeks
The amount of time a job can be delayed without affecting the early start time of any other
job is called
Select one:
a. Independent Slack
b. Interfering Slack
c. Total Slack
d. Free Slack
In which life cycle phase would the financial risks of a project be the greatest
Select one:
a. Delivery
b. Conceptual
c. Planning
d. Execution
a. Retaining Risk
b. Mitigating Risk
c. Transferring Risk
d. Avoiding Risk
Which of the following cannot be identified after performing a forward pass and backward
pass
Select one:
a. Dummy activities
b. Slack time
c. How much overtime is planned
d. Critical path activities
A risk response strategy that generally reduces the probability or impact of the event without
altering the project's objectives is called
Select one:
a. Acceptance
b. Transfer
c. Mitigation
d. Avoidance
A network based schedule has four paths, namely, 7,8,9 and 10 weeks. If the 10 week path
is compressed to 8 weeks, then
Select one:
a. We now have two critical paths
b. Only the 7-week path has slack
c. The 9 week path is now the critical path
d. Not enough information is provided to make a determination
The main disadvantage of using the bar charts to manage a project is that bar charts
Select one:
a. do not show dependencies between activities
b. are ineffective for projects under 1 million dollar in size
c. are ineffective for projects under one year in length
d. do not identify start and end dates of a schedule
Reducing the peaks and valleys in manpower assignments in order to obtain a relatively
smooth manpower curve is called
Select one:
a. Manpower allocation
b. Manpower leveling
c. Manpower scheduling
d. Manpower loading
b. Beta Distribution
c. Binomial Distribution
d. Poisson Distribution
The shortest time necessary to complete all of the activities in a network is called the
Select one:
a. Activity duration lenght
b. Compression path
c. Critical Path
d. Maximum slack path
The program that allocates resources to project activities to find the shortest project
schedule conditions with fixed resource limits is called
Select one:
a. Resource Scheduling
b. Resource Allocation
c. Resource Loading
d. Resource leveling
Which of the following is not a commonly used technique for scheduling compression
Select one:
a. Resource reduction
b. Fast tracking activities
c. Use of overtime
d. Reducing scope
Identifying a risk as high, moderate or low would be an example of which risk assessment
Select one:
a. Go for broke
b. Quantitative
c. Qualitative
d. Adverse