HIMACHAL PRADESH
QUALITY MANAGEMENT SYSTEMS
(ISO 9001: 2008)
(HPPWD Project Reference No.: - PW-SRC/RIDC/Procurement-ISO/2008)
CONSTRUCTION MANUAL
(WORK INSTRUCTIONS)
ROAD CONSTRUCTION
HIMACHAL PRADESH ROADS & INFRASTRUCTURE DEVELOPMENT
CORPORATION LTD (HPRIDC)
States Roads Project, Nirman Bhawan
Nigam Vihar, Shimla 171002
Tel No.: 0177-2627602
Issue No: 01
Review & Issue By:
Rev No. 00
Approved By:
Project Director(MR)
MD/ Secretary
TABLE OF CONTENTS
Title
Page No.
Chapters
AMENDMENT SHEET .......................................................................................................... i
1. INTRODUCTION ...........................................................................................................1-1
2. CONSTRUCTION MANAGEMENT ..............................................................................2-1
2.1. Supervision - Process and Product........................................................................2-1
2.2. Original Construction ..............................................................................................2-1
2.3. Steps involved - Planning and investigation ..........................................................2-2
2.4. Submission of Project Report.................................................................................2-4
2.5. Tendering................................................................................................................2-4
3. PROCESS FLOW..........................................................................................................3-1
4. QUALITY ASSURANCE PLAN FOR ROAD.................................................................4-1
4.1. Background.............................................................................................................4-1
4.2. References..............................................................................................................4-1
4.3. Scope ......................................................................................................................4-1
4.4. Abbreviations and Definitions.................................................................................4-1
4.5. Planning of Road Projects ......................................................................................4-3
4.6. Original Works / Maintenance ................................................................................4-3
5. QUALITY ASSURANCE REQUIREMENTS FOR ROADS ..........................................5-1
5.1. Project Report Preparation.....................................................................................5-1
5.2. Material Controls.....................................................................................................5-1
5.3. Process Controls ....................................................................................................5-1
5.4. Typical Quality Plan for Road and Bridge Construction ........................................5-2
5.5. Quality Assurance for Maintenance of Roads........................................................5-3
5.6. Planning QA Programme........................................................................................5-4
6. NON-CONFORMANCE (NC) AND CORRECTIVE ACTIONS.....................................6-1
6.1. Typical NCs with Product .......................................................................................6-1
7. TEST PLANS AND CHECKLISTS ................................................................................7-1
7.1. Test Plan for Soil ....................................................................................................7-1
7.2. Test Plan for Granular Sub-Base Material .............................................................7-2
7.3. Test Plan for Coarse and Fine Aggregates (Over Size / Size Metal)....................7-3
7.4. Test Plan for Water.................................................................................................7-5
7.5. Test Plan for Stone Rubble ....................................................................................7-6
7.6. Test Plan for Cement..............................................................................................7-7
7.7. Test Plan for Admixture ..........................................................................................7-8
7.8. Test Plan for Reinforcement Steel .........................................................................7-9
7.9. Test Plan for Bitumen ...........................................................................................7-10
7.10. Test Plan for CC/RCC Pipes and Collars ............................................................7-11
7.11. Test Plan for A.C. Pipes .......................................................................................7-12
7.12. Test Plan for CC/RCC Pipes and Collars ............................................................7-13
7.13. Test Plan for CC/RCC Pipes and Collars ............................................................7-14
7.14. Test Plan for Road Furniture ................................................................................7-15
7.15. Test Plan for Geo Synthetics................................................................................7-16
7.16. Checklist for General Inspection of Site ...............................................................7-17
7.17. Checklist for Calibration of Inspection, Measuring and Test Equipment.............7-19
7.18. Checklist for Surveying and Setting Out ..............................................................7-20
7.19. Checklist for Surveying and Setting Out ..............................................................7-22
Procedure No.: QMS/WI/RC/Table of Contents
Controlled Document
AMENDMENT SHEET
Sl. No. Document
Description of change
Page/
para.
No.
Rev.
No
Date of
issue
1. INTRODUCTION
This manual intends to provide guidance to the HPPWD engineers in their
functions of investigation, designs, estimation inspection and assurance of quality
of construction and maintenance. It helps in the vendor control and gradation of
contractors and is expected to aid in structured Quality Assurance activities of
HPPWD.
Road construction is dependent on several challenges, right from selection of the
terrain, soil conditions, materials, methods, type and design of construction to
supervision and assurance of quality in construction of new roads and
maintenance of the same after the area acquired.
The enclosures would provide typical process flow of road construction, Quality
Assurance requirements and test plans for Quality checks of materials used in
construction.
The checklists are the Level III documents of an established Quality Management
System (QMS) as per ISO 9001:2008 The Quality Plan drawn up highlights on the
process controls necessary for product realization and improvements.
It is also intended to help the internal auditors while carrying out audits of the
implemented QMS of HPPWD.
This document is an important adjunct to the Procedure Manual (Level II)
document and takes into consideration the existing practices and codal needs of
HPPWD. The formats to be used are the same as necessary for the QMS and the
departmental code.
For easy reference to the contents of the manual the following process has been
adopted:
RCM refers to Road Construction Manual.
TP refers to Test Plan
CL refers to various Check list for process control.
The test plans are identified as RCM/TP XX refers to the Serial No. of Test plan,
similarly RCM/CL XX refers to the Serial No. of checklist as applicable. The test
plan and checklist should be considered as work instructions necessary for
construction and maintenance of building.
The typical tests and test Performa are given in separate chapters for the purpose
of guidance to the site engineer, quality control staff and also the contractors.
2. CONSTRUCTION MANAGEMENT
2.1.
2.1.1. Process
2.1.1.1
2.1.1.2
2.1.2. Product
2.2.
Workmanship
Safety.
Specification
Quality Management System.
Original Construction
Public Representation
o
Upon receiving the amount for detail investigation* to Division, EE instructs the
Division to carry out the activity.
Based on the investigation results, designs are prepared.
On the basis of designs and by referring to current schedule of rates,
applicable to concerned Circle, detailed estimate is prepared.
Detailed Project Report** is submitted by Division to Technical committee
(TC)/Board of Directors (BOD).
TC/BOD scrutinizes all the proposals (completed in all aspects) received from
various Divisions.
TC/BOD prioritizes proposals on the basis of need of the project for inclusion
in the budget.
Upon approval from the Govt. (Appearing in the Budget), TC/BOD intimates the
concerned Division accordingly.
The proposal which does not appear in the budget due to financial reasons, are
stored back by TC/BOD, and are reviewed in the subsequent years.
2.3.
2.3.1. Survey
2.3.1.1
2.3.1.2
Socio-Economic Survey
2.3.1.3
2.3.1.4
Geographical Survey
2.3.1.5
2.3.1.6
2.3.1.8
Soil Survey
2.3.1.7
Riding quality.
Widths of pavement, shoulders, formation.
Vertical profile.
Horizontal and vertical curves.
Drainage Studies.
o Objectives.
o High flood level.
o Low water table.
o Depth of water table.
o Special investigation for cut-sections.
o Surface run-off.
2.3.2. Designs
Geometric designs.
Detailed pavement design.
Cross Drains design.
Side drains design.
2.4.
(a).
(b).
(c).
(d).
(e).
Sub-estimates.
(f).
Rate Analysis.
(g).
Plans.
(h).
Index Map.
(i).
(j).
(k).
2.5.
Tendering
Notification for Inviting Tenders (NIT)
Preparation of Draft Tender Papers
o
o
o
o
Technical specifications.
Commercial conditions.
Dispute resolution methodology.
Scope of Tender.
Eligibility criteria.
Amendment of Tender documents.
3. PROCESS FLOW
Preparation of Designs
and estimates
Project Identification
Detailed Investigation
Proposal
appear in the
Budget
Y
Preparing Plans and Estimates
- Administrative Approval
- Technical sanction
Tendering / Award of
Contract
Handing over
of site
Execution of
works
Completion of
project
Background
A good road network has an important bearing on the economy of a country. In
the changing scenario of globalization and economic liberalization, a great deal of
emphasis is already laid on development of infrastructure through construction of
a dependable road network. Consequently, consistency in the quality has gained
paramount importance. In line with this need, the document is prepared to provide
guidelines for Quality Assurance of Roads.
4.2.
References
4.3.
Scope
These guidelines cover quality system for activities of road construction. These
include steps towards planning and investigation, design and construction,
Tendering, Closing NCs, etc.
4.4.
4.4.1. Abbreviations
IRCM
No.
Number
Ref.
Reference
Const.
Construction
Est.
Detailed Estimate
CSR
NIT
QC
Quality Control
NC
Non-Conformance
4.4.2. Definitions
4.4.2.1
Quality
The totality of features and characteristics of a product or service that relies on its
ability to satisfy stated or implied need.
4.4.2.2
Quality Assurance
All those systematic and planned actions necessary to provide adequate
confidence that a product or service will satisfy given requirements for quality.
4.4.2.3
Quality Plan
A document specifying which procedures and associated resources shall be
applied by whom and when to a specific project, process or contract.
4.4.2.4
Non-Conformity
Non-fulfillment of specified requirements.
4.4.2.5
Technical Sanction
The name is given to the order of the competent authority sanctioning a properly
detailed estimate of the cost of a work of construction or repair, to be carried out
by the public works department. Ordinarily, such sanction can only be accorded
by the government in the public works department or by such authorities of the
department to whom the power has been delegated by government. Sanction
accorded to a work by any other department of government is regarded as an
administrative approval of the work.
4.4.2.6
Administrative Approval
This term denotes the formal acceptance, by the administrative department
concerned, of the proposals for incurring any expenditure in the public works
department on a work initiated by or connected with the requirements of such
administrative department. It is in effect, an order to the Public Works Department
to execute certain specified works at a stated sum to meet the administrative
needs of the department requiring the work. .
Administrative Approval
Subject to appearing in the Budget
4.4.2.7
Technical Sanction
For estimate of original work
4.5.
Maintenance
Original
Construction
Annual
Maintenance
4.6.
Periodical
Maintenance
Special / Urgent
Maintenance
5.2.
Material Controls
Testing of materials- Aggregates- coarse, fine, components (base, sub-base,
pavement, shoulders).
Test methods, Acceptance limits.
Sampling and Frequency of testing.
Availability of equipment- Monitoring and measurement.
Reports of test results, calibration.
5.3.
Process Controls
5.3.1. Alignment
Edges, carriageway, horizontal alignment, vertical profile, pavement thickness
5.3.2. Road Embankment
Grade, sub base and fill.
Grain size, Plasticity Index, of materials, moisture content, density.
Sampling and frequency of testing, Test methods, testing equipment,
calibration.
Tests on finished profile.
5.3.3. Granular Base Course Laying
Tests on cores.
Tests on concrete for Cross Drainage.
5.4.
JE/AE /AEE/EE/
SE/CE
Survey,
estimation,
construction,
inspection
sampling, inspection, results
calibration, report preparation,
review and action.
Defect
notification,
nonconformance
reporting,
corrective and preventive
actions,
retesting,
and
procedure
modification
if
required.
PROCESS
Duties and
responsibilities
INPUTS
Effective
controls,
lesser
customer complaints, higher
productivity and safety.
OUTPUT
5.5.
Annual
Maintenance
Periodic
(preventive)
Maintenance
Special repairs
(Corrective
actions)
(b).
(c).
(d).
Keeping the sign boards; km stones and other traffic aids and furniture in
good shape and condition.
5.6.
Planning QA Programme
Strip map.
Surface history.
List of roads - State Highway/ Major District Roads.
GIS data if any.
Traffic census details.
Black spot study details, if applicable.
Safety audit reports, if any.
SH
MDR
Routine
Special
Routine
Special
Routine
Special
Six
monthly
Pre and
Bi monthly
Post
monsoon
Pre and
Post
monsoon
Bi monthly
Weekly
Quarterly
Pre and
Bi monthly
post
monsoon
Bi monthly
During
monsoon
Monthly
Weekly
The required strength and density for concrete should conform the
specified and required strength. In the event of cube tests failures, it
needs to be re-worked and re-verified before approval.
(b).
The causes for such failures shall be identified and measures shall be
taken to rectify the problem.
Issue a notice in writing stating the facts and confirming the failures of
works done to rectify the same at the cost of the contractor. The rectified
work needs to be re-verified before approval
(b).
(c).
(d).
Yours truly,
Enclosure:
1. Performa for New Road / Maintenance (Appendix I).
<Head of account>
Ref.: Public Representation dated Attached herewith, I am hereby submitting a proposal, in the prescribed format
for construction / Improvement / Maintenance of Roads / Bridges / Culverts / Pave
dip / causeway / others.
I hope this proposal will be considered for necessary approval from Government
and work will be taken-up at the earliest.
Thanking you,
Yours truly,
Executive Engineer
Sub- Division
Enclosure:
1. Checklist for Road (Appendix II).
2. District Map
3. Tehshil Map
4. Copy of Representatives Letter, if any
3.
4.
5.
6.
7.
Status of
components
Side drain
Shoulder and
Slope
Camber.
Pot holes.
Erosion.
Drain washouts.
Carriageway
Fill Patches.
Fill Pot holes.
Grit.
Cross Drain
Details
Encroachment
details
Road Accessories
Missing boards.
Km Stones.
Pavement.
Other markings.
KM
KM
KM
KM
KM
Safety history
Remarks:
Nature of actions:
Inspected by:
Approved by:
2.
3.
4.
5.
6.
7.
8.
9.
10.
Items
Jan-Mar
Repairs of Road
berms
including
jungle clearance.
Repairs
to
longitudinal, side
shoulder and catch
drains.
Collection of patch
repairs material for
WBM roads.
Collection of patch
repairs material for
BT roads.
Patch
repairs
material for WBM
roads.
Patch
repairs
material for BT
roads.
Repairs
and
repainting
of
signage boards.
Painting
of
hectometer / km /
5km/ guard stones.
Maintenance
of
roadside trees by
pruning
Removal
of
encroachment and
unauthorized
hoardings.
Apr-Jun
Jul-Sept
Oct-Dec
Remarks
Sl.
No.
1.
2.
Name of District
3.
Name of Tehshil
4.
Name of constituency
5.
6.
Category of Road
7.
8.
11.
12.
Population benefited
13.
Surface
existing
Drain
9.
10.
Particulars
Project 1
condition
of
WBM
Bridge/Cross
From To
14.
Proposed improvements
15.
16.
17.
Priority level *
18.
Justification
19.
Remarks
Project 2
Project 3
BT
WBM
BT
WBM
BT
From To
From To
From To
From To
From To
Top priority
(b).
Medium priority
(c).
Low priority
Estimated Cost :
Sanction No. and date:
Test/Parameter
Acceptance Standard
Sample size
Acceptance Criteria
MOSRTH 305-2
IS2720 Part-8
IS2720 Part-7 Part-8
IS2720 Part-8
IS2720 Part-5
BS1377 Test-9
Visual
As per IS
As per IS
As per IS
As per IS
As per BS
7.2.
The GSB material could be natural sand. Murrum, Gravel, Crushed Stone, Quarry Spoils, Oversize metal or combination of these
depending upon grading required.
RCM/TP 02
Name of Work :
Agreement No.:
Sl.
No.
1.
2.
Estimated Cost :
Sanction No. and date:
Test/Parameter
Acceptance Standard
Sample size
Acceptance Criteria
Sieve analysis
Water absorption value of coarse.
Aggregate = 2%
If more than 2% soundness test.
As per standard
Conformance
IS2886 (Part-3)
IS383
As per standard
As per standard
Conformance
Conformance
SO/JE
7.3.
Test Plan for Coarse and Fine Aggregates (Over Size / Size Metal)
RCM/TP 03
Name of Work :
Agreement No.:
Estimated Cost :
Sanction No. and date:
Sl. Test/Parameter
No.
1.
Pre-qualification of Source
2.
Alkali Reactivity
Acceptance / Performance
Standard
IS 383
IS 383/IS 2386
Sampling
One sample
One Sample / Week
Lot wise
New source or change in
quality
One Sample / Week
3.
MOSRTH-2001
- Section 900 IS 2386
4.
Deleterious Material
MOSRTH-2001
- Section 900 IS 2386
5.
Crushing Value
MOSRTH-2001
- Section 900 IS 2386 Part-I
6.
Abrasion (Optical)
MOSRTH-2001
- Section 900 IS 2386 Part-IV
7.
Impact Value
MOSRTH-2001
- Section 900 IS 2386 Part-IV
8.
Soundless Value
MOSRTH-2001
- Section 900, IS 2386 Part-V
9.
MOSRTH-2001
- Section 900 IS 2386 Part-V
Name of Work :
Agreement No.:
Estimated Cost :
Sanction No. and date:
Sl. Test/Parameter
No.
10. Flakiness / Elongation
Acceptance / Performance
Standard
MOSRTH-2001
- section-900 IS 2386 Part-1
Sampling
11.
MOSRTH-2001
- section-900 IS 2386 Part-1
12.
MOSRTH-2001
- section-900 IS 2386 Part-III
13.
MOSRTH-2001
- section-900 IS 2386 Part-III
14.
MOSRTH-2001
- section-900 IS 2386 Part-III
7.4.
Name of Work :
Agreement No.:
Estimated Cost :
Sanction No. and date:
Sl. Test/Parameter
No.
1.
Pre-qualification
Acceptance / Performance
Standard
IS456, IS SP-23
Sampling
Acceptance Criteria
New Source
New Source
2.
7.5.
Name of Work :
Agreement No.:
Sl.
No.
1.
Test/Parameter
2.
Physical Properties
Water absorption
Estimated Cost :
Sanction No. and date:
Acceptance / Performance
Standard
IS 1124
MOSRTH 1004
IS 1124
MOSRTH 1004
Sampling
One Sample
Weekly
One Sample
Weekly
7.6.
Name of Work :
Agreement No.:
Sl.
No.
1.
Test/Parameter
Estimated Cost :
Sanction No. and date:
Sampling Criteria
Acceptance Criteria
Acceptance / Performance
Standard
IS 4031
Every consignment.
Conformance to specification
2.
IS 269
Every consignment.
Conformance to specification
3.
IS 445
Every consignment.
Conformance to specification
4.
IS 1489
Every consignment.
Conformance to specification
5.
IS 8041
Every consignment.
Conformance to specification
6.
IS 8112
Every consignment.
Conformance to specification
7.
IS 12269
Every consignment.
Conformance to specification
8.
IS 12330
Every consignment.
Conformance to specification
Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.
7.7.
Name of Work :
Agreement No.:
Sl.
No.
1.
Test/Parameter
2.
Test.
Pre-qualification and
recommendation.
i. Chemical Analysis
ii. Physical Analysis.
iii. Performance
Estimated Cost :
Sanction No. and date:
Acceptance / Performance
Standard
IS 9103/ASTMC 494
Sampling Criteria
Acceptance Criteria
Before commencement of
work and change of
source
IS SP 23
IS 9103
IS SP 23
IS 9103
ASTMC-494
Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.
7.8.
Name of Work:
Agreement No.:
Sl.
No.
1.
2.
Test/Parameter
Physical test / Chemical composition
Mild Steel
Grade Designation S240
Estimated Cost:
Sanction No. and date:
Acceptance / Performance
Standard
IS 432 Part 1
Sampling Criteria
Acceptance Criteria
Physical Test.
For each consignment
Chemical test.
Once at the beginning /
every source change.
Conformance to specification
IS 1786
Physical Test.
For each consignment
Chemical test.
Once at the beginning /
every source change.
Conformance to specification
Note: Additional tests may be carried out, whenever there is any change of source or in case of any disputes.
7.9.
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl.
No.
1.
Test/Parameter
Pre-qualification of source
Acceptance / Performance
Standard
Project Specification IS 73
2.
Test.
a) Physical
b) Chemical
Project Specification IS 73
Project Specification IS 73
Sampling Criteria
Acceptance Criteria
Each lot
New source / as per
requirement
Once in week
New source / as per
requirement
Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.
Test/Parameter
Estimated Cost:
Sanction No. and date:
Sampling Criteria
Acceptance Criteria
Classification
Acceptance / Performance
Standard
MOSRTH 10/ IS 458
Each Lot
Conformance
2.
Dimensional Check
IS 458
Each Lot
Conformance
3.
Visual Inspection
IS 458
Each Lot
Conformance
4.
Strength
IS 458
Each Lot
Conformance
Note : Additional tests may be carried out whenever there is any change of source or in case of any disputes
Test/Parameter
2.
Estimated Cost:
Sanction No. and date:
Sampling Criteria
Acceptance Criteria
Visual Inspection
Acceptance / Performance
Standard
MOSRTH 2706
Each lot
Conformance
Hydraulic Check
MOSRTH 2706
Each lot
Conformance
Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.
Test/Parameter
Estimated Cost:
Sanction No. and date:
Sampling Criteria
Ordinary Paint
Acceptance / Performance
Standard
IS 164
Acceptance Criteria
(a)
One/ batch/lot
Conformance to spec.
2.
IS 164
One/ batch/lot
Conformance to spec.
(a)
One/ batch/lot
Conformance to spec.
3.
Reflectors paint
One/ batch/lot
Conformance to spec.
4.
Gradation.
MOSRTH 803.4.3
One/ batch/lot
Conformance to spec.
5.
Roundness
MOSRTH 803.4.3
One/ batch/lot
Conformance to spec.
6.
Refractive index
MOSRTH 803.4.3
One/ batch/lot
Conformance to spec.
7.
MOSRTH 803.4.3
One/ batch/lot
Conformance to spec.
One/ batch/lot
Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.
Estimated Cost:
Sanction No. and date:
Sl. Test/Parameter
No.
1.
Concrete
Acceptance Standard
Sampling Criteria
Acceptance Criteria
IS 456
As per IS
Conformance to IS
2.
Reinforcing steel
IS 1786
As per IS
Conformance to IS
3.
IS 1367
As per IS
Conformance to IS
(a)
IS 1367
As per IS
Conformance to IS
(b)
IS 1364
As per IS
Conformance to IS
4.
IS 2062
As per IS
Conformance to IS
(a)
Plates
IS 2062
As per IS
Conformance to IS
(b)
Supports
IS 2062
As per IS
Conformance to IS
5.
Aluminum sheets
As per IS
Conformance to IS
6.
As per IS
Conformance to IS
7.
Massage borders
As per IS
Conformance to IS
Estimated Cost:
Sanction No. and date:
Sl.
No.
1.
Test/Parameter
Acceptance Standard
Sampling Criteria
Acceptance Criteria
IRCM-26 MOSRTH-804
As per Standard
Conformance
2.
Kilometre Stones.
IRCM-8 MOSRTH-804
As per Standard
Conformance
3.
Road Delineators.
IRCM-79 MOSRTH-805
As per Standard
Conformance
4.
Boundary Stones.
IRCM-25 MOSRTH-800
As per Standard
Conformance
5.
Fencing.
As per Standard
Conformance
6.
As per Standard
Conformance
7.
MOSRTH 810
As per Standard
Conformance
8.
IRCM-93 IS7537
MOSRTH 11-811
As per Standard
Conformance
Synthetic Material: Geo Textile, Geo Grid, Geo net, Geo membrane, Geo Composite.
RCM/TP 15
Name of Work:
Agreement No.:
Sl.
No.
1.
2.
Estimated Cost:
Sanction No. and date:
Test/Parameter
Acceptance Standard
Sampling Criteria
Acceptance Criteria
Pre-qualification
As per Standard
Conformance
As per Standard
Conformance
3.
As per Standard
Conformance
4.
Geo grid.
As per Standard
Conformance
5.
Geo net.
As per Standard
Conformance
6.
Geo membrane.
As per Standard
Conformance
7.
Geo composite.
As per Standard
Conformance
Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item
2.
Pre execution checks have been completed
date and reference.
3.
The site office, laboratory, godown and
labour camp are maintained in good
conditions.
4.
The first aid box is having with all the
necessary medicines.
5.
The furniture and equipments in site office
and laboratory are maintained in good
condition.
6.
The machinerys provided in laboratory are
maintained properly in good conditions.
7.
Insurance of technical staff, supervisory staff
and labour is updated.
8.
Approved copy of tender, plans and work
order book is available and maintained in
good condition.
9.
Various Performa required for testing of
materials are available on site and are being
filled up regularly.
10. There is no stagnation of wastewater.
11. Adequate traffic safety arrangement up to
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
date.
12. Labour registers are maintained up to date.
13. CAR insurance policy is updated.
14. Additional observation if any:
15. Conclusion by inspecting officer:The execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. ..
If not satisfactory the contractors to report
the corrective action taken and inform for the
re-inspection.
16. Contractor / Authorized representative
name:
Designation and Signature.
17. Inspecting Officer Name
Designation and Signature
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
All Surveying and Measuring Instruments
are uniquely identified.
3.
All Sand M Instruments are calibrated.
4.
All S and M instrument calibrations have
tractability to national standard.
5.
Range,
accuracy,
correction,
factor,
acceptance criteria, user details of all S and
M instruments have been recorded.
6.
Due dates of next calibration have been
identified and recorded on labels.
7.
Additional observations if any.
8.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reinspection.
9.
Contractor / authorized representative name,
designation, signature.
10. Inspecting officer, name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
The leveling instrument like dumpy levels /
theodolites etc, are calibrated (refer
calibration status of the instrument).
3.
The instruments and tripod are in good
working condition (visual inspection).
4.
Required numbers of ranging roads and
wooden
pegs
are
available
(refer
requirement submitted by JE).
5.
Required quantity of cord, lime, paint etc,, is
available for marking lettering etc,.. (refer
requirement submitted by JE).
6.
Steel tapes of length 30 m and 15m are
available in good condition, (visual
inspection).
7.
Required quantity of red flags, traffic, cones
etc,. are prepared for traffic safety (refer
requirement submitted by JE/AE).
8.
Adequate trained labours are available.
9.
Level books, field books are available on
site (refer requirement submitted by JE/AE).
10. Minimum two aluminum leveling staffs are
available.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
11. Benchmark is established at required
intervals with respect to GTS benchmark.
12. The benchmarks are established on
permanent structures or built up in masonry
etc,. so that the same are available in good
condition till finalization of work.
13. Additional observation if any.
14. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reinspection.
15. Contractor / authorized representative name,
designation, signature.
16. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Value of GTS Bench Mark
Value of permanent
bench mark on site
Remarks
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
The execution check share completed date
and reference.
3.
Representative
of
concerned
utilities
services is present during extension of work.
4.
Proper case is taken during excavation.
5.
If there is any damage for utility service, the
same is informed to the concerned authority.
6.
Additional observation if any.
7.
Conclusion by inspecting officer
The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
8.
Contractor / authorized representative name,
designation, signature.
9.
Inspecting officer, name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Ref. and Date of
sending sample for
testing
Name of
laboratory
Unsoaked
Remarks
Estimated Cost:
Sanction No. and date:
Estimated Cost:
Sanction No. and date:
Sl. Location
of No. of affected trees
No. trees Chainage
to Chainage
Date and Ref Date of joint Date of receipt Completion date Remarks
intimation
to inspection with of approval of of
removal
/
tree authority
tree authority
tree authority
shifting of trees
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
The execution inspection checks have been
completed - date and reference.
3.
The
traffic
diversion
and
safety
arrangements have been made as per the
approved plan.
(Refer traffic diversion plan).
4.
Equipment as verified in The execution
check are available in good working
condition.
5.
Required depth of excavation is achieved as
per cross-sections.
(Refer cross section).
6.
Camber, profile and gradient is maintained
as per approved drawing
7.
Usable material is stacked at specified
dumping location.
8.
Usable material is tested and approved as
per test plan no
If yes, date and reference.
9.
Care is taken to see that no portion of
existing pavement designated for retention is
loosened or disturbed.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. All utilities / trees / poles / drains / sewers
etc,. found during excavation are protected.
11. The finalized sub grade is protected from
movement of vehicular traffic and conforms
to approved c-section and l-sections.
12. The final levels of excavation are taken with
reference to GTS.
Field Book No. Page No:
13. The supervision of contractors is adequate
(refer QA Plan).
14. Additional observation if any:
15. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
16. Contractor / authorized representative name,
designation, signature.
17. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
7.25. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 10
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
Site is clean (visual inspection).
3.
Line out is approved
If yes, date of approval ..
4.
Initial ground levels are taken with reference
to GTS and recorded in field book.
If yes, Filed Book No:
Page No:
5.
Ground is leveled and compacted to
facilitate the first layer of earthwork (visual
inspection).
6.
7.
8.
9.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. If height less than 3.0m minimum dry unit
weight is 15.2 kN/Cum when tested as per
IS 2720 (Part-8)
11. Earthwork is required for sub grade / earth
side shoulders / verges / back fill if yes, then
dry unit weight.
(should be minimum 17.5 kN/Cum. When
tested as per IS2720 (Part-8)]
12. Borrowed material tested and proved if yes,
date and reference.
(test report shall be received 7 days before
the date of commencement).
13.
14.
15.
16.
17.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
18. Adequate traffic safety devices are procured
as per traffic safety plan approved by
engineer-in-charge
(refer approved traffic safety plan)
19. Trees / utility services etc, are removed /
shifted.
20.
21.
22.
23.
/ / 200
/ / 200
7.26. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 11
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks have been
completed date and reference.
3.
Graph of density against moisture content
submitted by contractor (refer graph).
4.
Relationship between density moisture
content and C.B.R. for light / heavy
compactive efforts submitted by contractors.
5.
Laying of embankment material is in uniform
thickness of 300 mm over entire width of
embankment.
6.
7.
8.
9.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. The field density least are carried out as per
IS2720 (Part 28) (should be at least 95%
PD).
11. The cross fall of surface of the embankment
/ sub-grade is maintained as specified (Refer
approved C/S and L/S).
12. Traffic safety arrangements have been
made and maintained in good conditions.
(Refer approved traffic diversion plan).
13. Contractors supervision is adequate. (Refer
QA Plan).
14. Contractors supervision is adequate.
15. Additional observation if any.
16. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
17. Contractor / authorized representative name,
designation, signature.
18. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
7.27. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 12
Name of Work:
Agreement No.:
Sl.
No.
1
Particulars of
Item
2
Estimated Cost:
Sanction No. and date:
Location
Layer
Signature of -Contractor
Type of roller
and weight
8
No. of
passes
9
Remarks
10
Signature of Engineer
No of passes required shall be decided by the Engineer-in-charge after ascertaining the required field density.
7.28. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 13
Name of Work:
Agreement No.:
Sl.
No.
Particulars
of Item
Estimated Cost:
Sanction No. and date:
Location
/ layer of
test
Moisture content
test (2720 Part 2)
Quantum
Executed
Quantum
Executed
Quantum
Executed
Value
Value
Value
Soaked
Un-marked
10
Signature of Contractor
Results
acceptable
/ not
acceptable
Remarks
11
12
Signature of Engineer
*One test per 250 Cum. of work ** One test per 1000 Sq.m. of work ***One test per 3000 Cum. of work.
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks have been
completed date and reference.
3.
Graph of density against moisture content
submitted by contractor (refer graph).
4.
Relationship between density moisture
content and C.B.R. for light / heavy
compactive efforts submitted by contractors.
5.
Laying of embankment material is in uniform
thickness of 300 mm over entire width of
embankment.
6.
Earthwork laid is as per specified grade and
camber.
Refer field book no.. page no.
7.
The moisture content is as per IS2720
(Part-2) at the site of placement prior to
compaction
8.
The static weight of vibratory roller used for
compaction is within 80 to 100 KN (refer
weigh bridge challan).
9.
The each layer thoroughly compacted to
achieve least 95% of PD
10. The field density least are carried out as per
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
IS2720 (Part 28) (should be at least 95%
PD).
11. The cross fall of surface of the embankment
/ sub-grade is maintained as specified (refer
approved C/S and L/S).
12. Traffic safety arrangements have been
made and maintained in good conditions.
(refer approved traffic diversion plan)
13. Contractors supervision is adequate. (Refer
QA Plan).
14. Additional observation if any.
15. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for rre-inspection.
16. Contractor / authorized representative name,
designation, signature.
17. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre execution inspection checks are
completed date and reference.
3.
Adequate safety devices are provided.
4.
Spreading of hard murum is done as per
clause 305.3.5.1. of MOSRTH5.
Compaction is carried out as per the clause
305.3.6. of MOSRTH.
6.
Necessary surface drawing arrangement is
provided The execution.
7.
The finishing operations are carried out as
per the clause of 305.3.9 of MOSRTH.
8.
Additional observations if any.
9.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
10. Contractor / authorized representative name,
designation, signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre execution inspection checks have been
completed date and reference.
3.
Mixing any ingredients of GSB is done as
per MOSRTH clause 401.2.1.
4.
Is there any deficiency of moisture in mix?
(refer from GSBF)
If Yes, additional water sprinkled.
5.
The static weight of vibratory roller used for
compaction is within 80 to 100 KN when
thickness exceeds 100 mm (refer weigh
bridges challan).
6.
Rolling being done from lower edges
forwards upper edges.
(Visual inspection).
7.
The field density tested as per IS 2720
(should be 98% of dry density) refer form
GSBF).
8.
Traffic safety arrangements have been
made and maintained in good condition
(refer approved traffic diversion plan).
9.
Contractors supervision adequate (refer QA
Plan).
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. Final grade and camber of the GSB layer is
as per approved C/S and L/S (refer field
book no page no.).
11. Additional observations if any.
12. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
13. Contractor / authorized representative name,
designation, signature.
14. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference..
3.
The grade-1 metal is uniformly spread on
prepared sub-grade / sub-base to proper
profiles by using template placed across the
road at 6m apart
4.
The grade-1 metal laid is of required
thickness to get compacted layer of 0.115m
after compaction.
5.
The segregation of metal is controlled while
spreading to avoid any pocket of the
material.
6.
The rolling is done with vibratory roller of 80
to 100 kN static weight.
(Refer weigh bridge challan and form)
7.
Rolling is done from lower edges towards
Centro and from inner edge to the outer
edges for super elevation portion.
8.
Polled surface is checked transversely and
longitudinally with templates.
9.
The shoulders are built up simultaneously
along with WBM
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. The surface is applied over rolled surface in
dry condition.
11. Dry rolling is done after application of
screenings.
12. Brooming and spreading is done during dry
rolling till all the voids are filled.
13. The water is sprinkled, swept and rolled after
dry rolling.
14. The sprinkling, sweeping and rolling
operation is continued till the coarse
aggregate are thoroughly keyed, well
bonded and firmly set in its full depth.
15. After final compaction the surface is allowed
to dry over night.
16. The hungry spots are filled with screening
after next day.
17. Adequate machinery and equipment are
available on site.
(refer QA Plan)
18. Adequate traffic safety arrangements are
provided.
(refer approved traffic safety
diversion plan).
19. Required field tests namely, aggregate
impact value, grading, flakiness index and
elongation index, Atterberg limit of binding
materials have been taken and record
maintained in the form WBMF-2.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reinspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference..
3.
The grade-II metal is uniformly spread on
prepared sub-grade / sub-base to proper
profiles by using template placed across the
road at 6m apart.
4.
The grade-II metal laid is of required
thickness to get compacted layer of 0.115m
after compaction.
5.
The segregation of metal is controlled while
spreading to avoid any pocket of the
material.
6.
The rolling is done with vibratory roller of 80
to 100 kN static weight.
(refer weigh bridge challan and form )
7.
Rolling is done from lower edges towards
Centro and from inner edge to the outer
edges for super elevation portion.
8.
Polled surface is checked transversely and
longitudinally with templates.
9.
The shoulders are built up simultaneously
along with WBM
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. The surface is applied over rolled surface in
dry condition.
11. Dry rolling is done after application of
screenings.
12. Brooming and spreading is done during dry
rolling till all the voids are filled.
13. The water is sprinkled, swept and rolled after
dry rolling.
14. The sprinkling, sweeping and rolling
operation is continued till the coarse
aggregate are thoroughly keyed, well
bonded and firmly set in its full depth.
15. After final compaction the surface is allowed
to dry over night.
16. The hungry spots are filled with screening
after next day.
17. Adequate machinery and equipment are
available on site.
(refer QA Plan)
18. Adequate traffic safety arrangements are
provided. (Refer approved traffic safety
diversion plan).
19. Required field tests for, aggregate impact
value, grading, flakiness index and
elongation index, Atterberg limit of binding
materials have been taken and record
maintained.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference..
3.
The grade-III metal is uniformly spread on
prepared sub-grade / sub-base to proper
profiles by using template placed across the
road @ 6M apart (refer WBMF-1)
4.
The grade-III metal laid is of required
thickness to get compacted layer of 0.115m
after compaction.
5.
The segregation of metal is controlled while
spreading to avoid any pocket of the
material.
6.
The rolling is done with vibratory roller of 80
to 100 KN static weight.
(refer weigh bridge challan and form WBMF1)
7.
Rolling is done from lower edges towards
Centro and from inner edge to the outer
edges for super elevation portion.
8.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
9.
The shoulders are built up simultaneously
along with WBM
10. The surface is applied over rolled surface in
dry condition.
11. Dry rolling is done after application of
screenings.
12. Brooming and spreading is done during dry
rolling till all the voids are filled.
13. The water is sprinkled, swept and rolled after
dry rolling.
14. The sprinkling, sweeping and rolling
operation is continued till the coarse
aggregate are thoroughly keyed, well
bonded and firmly set in its full depth.
15. After final compaction the surface is allowed
to dry over night.
16. The spots are filled with screening after next
day.
17. Adequate machinery and equipment are
available on site.
(refer QA Plan)
18. Adequate traffic safety arrangements are
provided.
(refer approved traffic safety
diversion plan).
19. Required field tests for aggregate impact
value, grading, flakiness index and
elongation index, atterberg limit of binding
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
materials have been taken and record
maintained.
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre execution activities are complete date
and reference.
3.
Adequate safety arrangements is provided
on site.
4.
Excavation is done as per the approved
drawing.
5.
Excavated material is stacked properly or
disposed of as directed by Engineer incharge
6.
Bed level are taken after excavation and
approved by engineer-in-charge.
If yes, date and reference.
7.
Sand and boulder filling is done in
foundation as per approval drawing.
8.
Sand and boulder filling is well compacted
normally or by any other approved method.
9.
Top level of Sand and boulder filling is taken
for verification .If yes, date and reference.
10. Mixing of bed concrete is done for grade of
concrete specified in agreement.
11. The bed concrete is well completed by plate
vibrator / manually.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
12. Top levels bed concrete is taken if yes, date
and reference.
13. Proper curing of bed concrete is done for
required period.
14. Concrete for foundation is checked
15. Centring for walls and gutter is approved by
engineer-in-charge.
If yes, date and reference.
16. Top level of wall is marked on centering if
yes, date and reference.
17. Mixing of concrete for walls of gutter is of
grade specified in concrete.
18. Concrete for walls of gutter is checked as
per test plan no:
If yes, Date and reference.
19. Ghani register is maintained for concrete
work, if yes, date and reference.
20. Cement consumption register is maintained
for concrete work. If yes date and reference.
21. Mixer operating register for duration of
mixing of maintained.
22. Concrete laying is not done for more than
60 Cubic Meter at a time.
23. Proper bonding is provided between
subsequent lift of walls.
24. AC Pressure relief pipe use at interval
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
specified in agreement / drawing or as
directed by engineer-in-charge.
25. Additional observations, if any.
26. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
27. Contractor / authorized representative name,
designation, signature.
28. Inspecting Officer, name,
Designation and Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre-extension checks have been completed
date and reference.
3.
The spraying temperature of bituminous
emulsion is in the range of 20 Degree to 60
Degree.
4.
Binder is applied with self propelled or towed
bitumen pressure sprayer with self-heating
arrangements.
5.
The rate of application of binder is
maintained as per Table 500.2:MOSRTH/or as specified on the item of
tender.
6.
The application of binder quantity is as
specified. In tender (to be ascertained by
weighing it).
7.
Contractors supervision is adequate.
8.
Adequate safety measures have bee taken.
9.
Additional observations if any.
10. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
11. Contractor / authorized representative name,
designation, signature.
12. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Receiving
surface
is
clean
(visual
inspection).
3.
The 40mm size metal is uniformly spread.
4.
Tack coat at 50Kg / 100 sq.m applied the
surface.
5.
The metal laid is of required thickness to get
compacted layer of 0.075 m after
compacted.
6.
The 20mm key aggregates shall evenly
spread at the rate of 1.50 m3 / 100m2.
7.
The segregation of avoid any pocket of fine
material.
8.
The rolling is done with vibratory roller of so
to 100KN state weight.
9.
Rolling is done from lower edges to censer
and from inner edges to the outer edges for
super-elevation portion.
10. Bitumen of IS Grade S-35 having 30/40 or
S-65 having 60/70 penetration heated to
through a pressure sprayed (browzer)
uniformly at the rate of 250 Kg / 100m2.
11. 12mm chips are uniformly spread over the
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
surface as blindage at the rate of 1.80 m 3 /
100m2 and are broomed immediately to
ensure uniform thicken.
12. The surface is again rolled to obtain full
compaction and the farce the blindage chips
in to the interstices of course aggregate.
13. The
contractor
provides
adequate
supervisory staff.
14. Adequate safety measures are taken The
execution of work.
15. Additional observation if any.
16. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
17. Contractor / authorized representative name,
designation, signature.
18. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Per execution check carried out date and
reference.
3.
Stone chipping is spread uniformly as per
MOSRTH table 500.13. requirement.
4.
Bitumen is sprayed uniformly as per
MOSRTH table 500.13 requirement.
5.
Rolling is done as per MOSRTH 1995
clause No. 508.1.3.5.
6.
Adequate supervisory and technical staff are
employed by the contractor.
7.
Additional observations, if any.
8.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
9.
Contractor / authorized representative name,
designation, signature.
10. Inspecting officer, name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
The temperature of bitumen is 150 degree to
163 degree.
4.
Adequate traffic safety devices are provided.
5.
The bitumen is spread as per the clause
508.1.3.3. of MOSRTH-1995.
6.
The stone chipping / aggregate is spread as
per the clause 512.2.2. of MOSRTH-1995.
7.
Rolling is carried out by 80-100 KN smooth
wheeled wheel roller or 80-100 KN static
weight vibratory roller.
8.
Rolling is commenced at edge and progress
towards the top.
9.
Supervision of contractor is adequate.
10. All test on materials required to be carried
out as per test plans If yes, date and
reference.
11. Additional observation, if any.
12. Conclusion by inspecting officer The
execution activities are satisfactory / not
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
13. Contractor / authorized representative name,
designation, signature.
14. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Tack coat is properly sprayed as required to
the surface where B.M. is to be laid. If yes
date and reference of checklist for tack coat.
3.
Equipments as verified in The execution
check are available in good working
condition.
4.
The mix is prepared in drum mix plant or any
other specified item.
5.
6.
/ / 200
/ / 200
7.
8.
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
9.
The mix is tested for
Bitumen content.
Gradatiion..
10. Proper offsets have been provided in
longitudinal joints of each layer)
11.
12.
13.
14.
15.
16.
17.
18.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
19. Additional observation if any.
20. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
21. Contractor / authorized representative name,
designation, signature.
22. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl.
No.
Date
and
Time
Vehicle
No.
Type of
Mix
Agg.
Impact
value
Flakiness
index
value
Elongation
index value
Grading of aggregate
(Two tests per day per plant)
Metal-1 Metal-2 Combined
10
Bitumen
content
Grade of
bitumen
Remarks
11
12
13
Date
Estimated Cost:
Sanction No. and date:
Location Ch.
.to Ch /
Site / Layer
No.
Lane no /
width
Time
Vehicle
Weight
Gross Tear
Net
Temp. at
time of
laying
10
Passes of
Initial
or Final rolling
intermediate
by 60-80KN
rolling
by Static roller
100KN
vibratory roller
11
12
Remarks
13
Date
Location
Ch to
Ch./
Side
3
Estimated Cost:
Sanction No. and date:
Line No/
width
Time
Vech.
No
Temp. at
time of
laying
Bitumen
content (one
test per day on
site)
8
Rate of spread
weight of BM
Area
9
Field density
(one test per
500 Sqmt.
Area)
10
ThickNess
of spread =
Density rate
of spread
11
Remarks
12
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution check carried out date and
reference.
3.
Tack coat is anticorrosive applied uniformly
anticorrosive the rate specified in the
agreement.
4.
Mix is spread uniformly with paver.
5.
The thickness is as per requirements.
6.
The rolling is done with static roller followed
by vibratory roller.
7.
The rolling is done from lower edge to higher
edge and from miner edge to outer edge for
super elevation portion.
8.
Adequate supervisory / technical staff is
provided by the contractor.
9.
Additional observation if any.
10. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reProcedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
inspection.
11. Contractor / authorized representative name,
designation, signature.
12. Inspecting officer,
Name.
Designation and Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed, date and reference.
3.
The temperature of bitumen is 130 degree to
160 degree.
4.
Tack coat is applied uniformly at the rate
specified in tender.
5.
Tack coat is applied of binder used for tack
coat is as per clause 503.3.2.
6.
The mix is tested as per the table no. 500.16
of MOSRTH .
7.
Adequate safety measures are provided The
execution.
8.
The mix is spread in uniform thickness
specified in tender.
9.
Rolling is done by 80-100 KN roller smooth
wheel tandem type.
10. Rolling is begun from lower edge to upper
edge.
11. Surface finish of the construction conforms
to requirement of clause 902 of MOSRTH.
12. The seal coat is applied as per clause 513 of
MOSRTH.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
13. Additional observation if any.
14. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
15. Contractor / authorized representative name,
designation, signature.
16. Inspecting officer, Name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Tack coat is properly sprayed as required to
the surface where BM is to be laid. If yes
date and reference of checklist for tack coat.
4.
Equipment are available in good working
condition.
5.
The mix is prepared in drum mix plant or any
other specified item.
6.
7.
/ / 200
/ / 200
8.
9.
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
No.
Date
is in between 120 to 160 degree
10. The mix is tested for Bitumen content.
Gradation.
11.
12.
13.
14.
15.
16.
17.
18.
/ / 200
/ / 200
/ / 200
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
19. The supervision of contractor is adequate
(refer QA Plan).
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
/ / 200
Name of Work:
Agreement No.:
Sl.No. Particulars
Date
Signature.
Estimated Cost:
Sanction No. and date:
Remarks (Y / N / NA / Observation if any)
/ / 200
/ / 200 / / 200
/ / 200
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Tack coat is properly sprayed as required to
the surface where B.M. is to be laid. If yes
date and reference of checklist for tack coat.
4.
Equipment as verified during execution
check are available in good working
condition.
5.
The mix is prepared in drum mix plant or any
other specified item.
6.
7.
8.
9.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
is in between 120 to 160 degree
10. The mix is tested for
Bitumen content.
Gradation..
11. Proper offsets have been provided in
longitudinal joints of each layer)
12. The initial or intermediate rolling is followed
by vibratory roller of 80 to 100 KN capacity.
13.
14.
15.
16.
17.
18.
19.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Random one set of three Marshall specimen
sample of DBM is collected for verifying
stability of mix.
If Yes,
Dumper No.
Date: Time:
3.
The samples are sealed, labeled and signed
in presence of contractor
If yes, details
4.
5.
6.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
re-inspection.
7.
Contractor / authorized representative name,
designation, signature.
8.
Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Tack coat is properly sprayed as required to
the surface where BM is to be laid. If yes,
date and reference of checklist for tack coat.
4.
Equipment as verified in The execution
check are available in good working
condition.
5.
The mix is prepared in drum mix plant or any
other specified item..
6.
The temperature of binder and aggregate is
maintained in the range between 150 to 163
degree and 155 to 163 degree respectively
at the time of mixing
7.
The discharge temperature of mix is in
between 130 to 160 degree.
8.
9.
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
No.
Date
is in between 120 to 160 degree
10. The mix is tested for
Bitumen content.
Gradation
11.
12.
13.
14.
15.
16.
17.
/ / 200
/ / 200
/ / 200
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
18. Adequate traffic safety arrangements are
provided (refer QA Plan)
19. The supervision of contractor is adequate
(refer QA Plan)
20. Additional observations ,if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
One sample of each for bitumen coarse
aggregate fine aggregate, filler is collected
at random for verifying its properties.
If Yes, Location No.
Date: Time:
3.
Random sample for mastic asphalt is
collected for verifying hardness number.
If yes, No: .
Date Time..
4.
The samples are sealed, labeled and signed
in presence of contractor
If yes, No. Date:
5.
The samples are sent to the laboratory
If Yes,
Name of Laboratory.
Date and Ref..
6.
Additional observations if any.
7.
Signature.
Designation.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
complete if yes, date and reference.
3.
The formwork is as per approved drawings
and designs (refer approved form work
drawing).
4.
The dowel bars are adequate and are as per
required length and diameter.
5.
Openings are made for dowel bars in the
shuttering.
6.
Adequate arrangements for compaction are
made to the shuttering.
7.
Equipments on like skid vibrator, needle
vibrator, plate vibrators are available and are
in good working conditions.
8.
Separation membrane is laid on the sub
base as per clause 602.5. of MOSRTH.
9.
Dowel Bars are as per clause 602.3.5. of
MOSRTH.
10. Tie bars are as per clause 602.6.6. of
MOSRTH.
11. Batching, mixing, transportation, placing of
concrete, surface texture, curing are as per
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
clause 602.9. of MOSRTH
12. Joints are as per clause 602.10.5.2. of
MOSRTH.
13. Preparation and sealing of joint grooves.
14. Tolerance for surface regularity, level,
thickness and strength are according to
clause 903.5. of MOSRTH.
15. Concrete cubes and beams in required
numbers are taken as per clause 602.3.3.2.
of MOSRTH.
16. Slump tests are taken.
17. Field tests required are taken as per the
frequency mentioned in clause no. 903.5. of
MOSRTH
18. Exposed surface of concrete pavement is
kept continuously in a damp or wet condition
by pounding jute gunny bags kept constantly
wet for a period of not less than 14 days
from the date of placing of concrete.
19. When steam curing is adopted, it is ensured
that it is done in a suitable enclosure to
minimize moisture and heat losses.
20. Permission for using curing compound is
accorded by engineer.
21.
The
honeycombing,
broken
edges
/ / 200
/ / 200
or
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
corners and other defects if observed, are
thoroughly cleaned, saturated with water
and carefully pointed with mortar of cement
and fine aggregate mixed in the same
proportions used in the grade of concrete.
22. All construction and expansion joints in the
completed work are left carefully tooled and
free from any mortar concrete.
23. Expansion joint filler is left exposed for its full
length with clean and true edges.
24. Immediately on removal of forms, the
engineer examines the concrete work before
any defects are made good.
25. Additional observations, if any.
26. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
27. Contractor / authorized representative name,
designation, signature.
28. Inspecting officer, name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks are completed date
and reference.
3.
Adequate traffic safety measures are
provided.
4.
Line out is marked and approved.
5.
Painting is being done by machine /
approved manual method.
6.
The temperature of the receiving surface is
more then 10% and the paint is as specified
by the manufacturer.
7.
The thickness of paint is 2.5 mm.
8.
The glass beads are applied at the rate of
250gm / sq.mt area on hot paint surface in
quick succession of paint by spraying
operator.
9.
Traffic shall be open after setting of
thermoplastic paint surface.
10. Additional observations if any.
11. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
12. Contractor / authorized representative name,
designation, signature.
13. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
Adequate safety arrangement is provided.
4.
Soling is done in foundation is well
compacted with plate vibrator / power roller /
manually.
5.
The thickness of soling is as per approved
drawing.
6.
Proper mixing for grade of cement concrete
is done as specified in agreement for
foundation.
7.
Thickness of foundation oriented over the
foundation concrete is as per approved
drawing.
8.
The pre-cast kerb stones oriented over the
foundation concrete is as per approved
drawing.
9.
The vertical and horizontal tolerance is equal
to 6mm with respect to line and level shown
in approved drawing.
10. The gap between road and kerbstone is
tilled with cement concrete of grade
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
specified in agreement.
11. Kerb on drainage ends in super elevated
portions shall be cast as per approval
drawing.
12. Portion on back side of kerb is tilled with the
approved material specified in agreement /
drawing.
13. The filled material is compacted with plate
vibrator / material specified in agreement.
14. Adequate supervisory staff is provided by
the contractor.
15. Pointing is done in cement mortar of
proportion specified in agreement.
16. Additional observations, if any.
17. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
18. Contractor / authorized representative name,
designation, signature.
19. Inspecting officer name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed ; date and reference.
3.
Proper safety arrangements are provided.
4.
Pits excavated are as per size specified in
drawing.
5.
Soling is done as per drawing.
6.
Proper mixing of bed concrete is done as
specified in agreement.
7.
Thickness of bed concrete is as shown in
drawing.
8.
The kilometer / 200 meter stones is provided
over bed concrete and oriented as shown in
drawing.
9.
The gaps around kilometer / 200 meter
stones are filled by cement concrete and
compacted.
10. The colours, arrangement of letters and
script of kilometer / 200 meter stones is as
per approved drawing and agreement.
11. Adequate supervisory staff is provided by
the contractor.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
12. Additional observations, if any.
13. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
14. Contractor / authorized representative name,
designation, signature.
15. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Proper safety arrangement is provided.
4.
Excavated material for back filling is
classified and stacked properly as approved
by engineer-in-charge.
5.
The unusable material is disposed of from
site.
6.
The bed of foundation is properly leveled
and rammed.
7.
Bed concrete is provided as per the mix and
dimension shown on approved drawing.
8.
Curing is done at least for Seven days.
9.
Hole and drilled in the posts at the distance
specified in the approved drawing.
10. Posts are erected vertically to its line, level
and alignment as required as per the
approval drawing.
11. Horizontal pipes are properly places and
jointed.
12. Painting for structural work is done in three
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
coats on primer coat or as specified in the
contract.
13. The post to be embedded in bed concrete is
coated with coal tar.
14. Additional observations, if any.
15. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
16. Contractor / authorized representative name,
designation, signature.
17. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
Adequate safety arrangements are provided.
4.
Pits excavated are as per size specified in
drawing.
5.
Soling is done as per drawing.
6.
Proper mixing of bed concrete is as shown
in drawing.
7.
Thickness of bed concrete is as shown in
drawing.
8.
The guard stones is provided over bed
concrete and oriented as shown in drawing.
9.
The gaps around guard stones are filled by
cement concrete and compacted.
10. White washing is done in required number of
coats specified in agreement.
11. Adequate supervisory staff is provided by
the contractor.
12. Additional observations if any.
13. Conclusion by inspecting officer The
execution activities are satisfactory / not
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
14. Contractor / authorized representative name,
designation, signature.
15. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Particulars
Date
Location / chainage / description of item.
/ / 200
/ / 200
/ / 200
/ / 200
/ / 200
/ / 200
Name of Work:
Agreement No.:
Sl.
No.
12.
13.
14.
Estimated Cost:
Sanction No. and date:
Particulars
Date
Additional observations, if any.
/ / 200
/ / 200
/ / 200
/ / 200
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
Adequate traffic safety arrangements are
provided.
4.
Excavation for pipe laying is done to the
lines and grade as shown on the approved
drawing or as directed by the engineer-incharge.
5.
Strata classification is done and approved by
the engineer-in-charge.
6.
Excavated material required for back fill
stacked properly.
7.
Unusable material is disposed of as directed
by engineer-in-charge.
8.
It is ensured that the ground where pipe is to
be placed is reasonably firm.
9.
Soling / approved granular material layer is
suitable laid as shown in approval drawing
and well compacted.
10. Concrete bedding is suitably provided as per
the dimensions shown in the approved
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
drawing.
11. The mix for the concrete is not leaner than
M-15 and cured for at least 7 days and the
constituents are tested as per the .
Test plan no for cement.
If yes, date and reference.
Test plan no for fine aggregate
If yes, date and reference.
Test plan no for coarse aggregate.
If yes, date and reference.
12. Pipes have been laid before the setting of
the concrete.
13. It is ensured that pipes are in good
conditions before and after laying.
14. The minimum distance between outer
surface of two pipes is half the diameter of
pipe or minimum 450 mm.
15. The arrangement for lifting, loading,
unloading, and laying of pipe in the bed is
approved by the engineer-in-charge.
16. Pipe laying started from proceeding from
outlet to inlet.
17. Invert level of the pipes are as per the
required grade.
18. There is no defective pipe.
19. If yes, it is removed by the contractor at his
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
own cost.
20. The caulking space of the joints is between
13mm to 20 mm or as shown in the drawing.
21. Caulking material is wet mix CM in
proportion of 1:2 mixed with caulking irons.
22. There is even annular space at the joints.
23. Joint space is filled properly with 1:2 cement
mortar.
24. Joints are properly finished.
25. Curing is done at least for four days.
26. Back filling is done after the joining material
is hardened.
27. Back fill soil is clean, free from boulders,
large roots and excessive amounts of sods
or other vegetable materials and logs.
28. The back fill material is approved by
engineer-in-charge.
29. The back filling is compacted in the layers
not exceeding 150MM with the help of
approved equipment.
30. Back filling is done simultaneously on both
sides of the pipe.
31. Head walls, wing walls, apron and other
ancillary
works
are
carried
out
simultaneously in accordance with the
approved drawing.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
32. Contractor supervisor is trained to supervise
the work.
33. The masonry work for the wall is carried out
confirming to section 1400 MOSRTH - and
aprons conforming to section 2500 of
MOSRTH .
34. It is ensured that height of filling about the
pipe is more than 600 mm.
35. Additional observations if any.
36. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
37. Contractor / authorized representative name,
designation, signature.
38. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been competed
date and reference.
3.
Adequate safety arrangement is provided.
4.
Excavation is done as per approved
drawing.
5.
Excavation material is stacked / disposed
properly.
6.
Cement concrete of required grade as
specified in agreement /drawing is provided
in foundation.
7.
The board oriented over bed concrete is
checked by engineer-in-charge.
8.
The supports of the boards are fixed in
cement concrete of required grade as
specified in agreement.
9.
The frame embedded in soil is provided with
approved anti-corrosive treatment.
10. The frame and border is painted in approved
oil paint.
11. Additional observations, if any.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
12. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
13. Contractor / authorized representative name,
designation, signature.
14. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre-excavation
checks
have
been
completed date and reference.
3.
Excavation for foundation is done to the
lines and grade as shown on the approved
drawing or as directed by the engineer-incharge.
4.
Strata classification is done and approved by
the engineer-in-charge.
5.
Excavated material required for back fill
stacked properly.
6.
Unusable material is disposed as directed by
engineer-in-charge.
7.
It is ensured that the starta on which
foundation is to be places is reasonably firm
to take the load of slab drain and vehicular
traffic.
8.
Soling / approved granular material layer is
suitably laid as shown in approval drawing
and well compacted.
9.
Concrete bedding is suitably provided as per
the dimensions shown in the approved
drawing.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. Curing of the concrete beading is carried out
for not less than Seven days.
11. De-watering is carried out and recorded in
maintained.
12. Centering for walls of slab drain is erected
and dimensions are verified as per the
approved drawing.
13. Concrete for walls is done in layer for height
not more than 90 cm.
14. Metal pins for proper bonding of subsequent
layers are provided as directed by the
engineer-in-charge.
15. Cement consumption register and gunny
register are maintained.
16. Minimum seven days curing is done for
walls.
17. Centering for slab is done and dimensions
are verified as per the approved plan.
18. Reinforcement are placed and verified as
per the approved drawing.
19. Cover for reinforcement at bottom, top and
sides are as per requirement.
20. Proper care is taken while placing the
concrete so that there is no suggestion.
21. Stem is as per requirement.
22. Required number of cubes are cast for
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document
/ / 200
/ / 200
Name of Work:
Agreement No.:
Estimated Cost:
Sanction No. and date:
Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
testing.
23. Additional observations, if any.
24. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
25. Contractor / authorized representative name,
designation, signature.
26. Inspecting officer name, Designation and
Signature.
/ / 200
/ / 200
5.
6.
7.
8.
9.
Item
Test to be conducted
Embankment
8.2.
Item
Embankment
2.
GSB
3.
WBM
4.
Bituminous Works
5.
Sand
Test to be Conducted
Density, Atterberg limits, Moisture Content
(Suitability before and The execution).
Gradation / Atterberg Limits / Moisture Content /
Density, CBR*.
Impact Value, Gradation, Flakiness and Elongation,
Abrasion Test*.
Temperature (Binder / Mix) Rate of Spread of
Bitumen.
Gradation, Impact, Flakiness and Elongation for
Aggregates.
Binder Content, Stripping value, Marshall Stability
Analysis ( Mixture Design) Penetration value,
Softening Point, Viscosity, Density, Ductility*.
Gradation
Silt / Clay / Deleterious Materials.
Sl.
No.
6.
Item
Bricks
7.
Coarse Aggregate
8.
Concrete
9.
Soil
10.
Cement
11.
Tiles
Test to be Conducted
Size and Shape, Compressive strength, water
Absorption*.
Gradation, Water Absorption, Impact, Flakiness
and Elongation, Abrasion Test*.
Slump, Compressive strength, Mix Design of
Concrete*.
SBC Test, Grain size analysis, Classification of
Soils, Density, Moisture Content, Atterberg
limits, Direct Shear Test, Triaxial shear test
CBR*.
Normal Consistency, Initial and Final setting
time, Fineness, Strength of Cement (3 days, 7
days, 28 days)*.
Water Absorption, Size and shape, Transverse
Flexural Strength*.
8.3.
Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification Section 400 clause 404 and test conducted as per IS 2386:1963
Test
No.
1.
1.
2.
3.
Details
of
Sample
2.
3.
Water
absorption
value 2%
(max
4.
Flakiness
Index Max
20%
5.
63mm
90-100 %
7.
53mm
25-75%
8.
45mm
0-15%
9.
22.40mm
0-5%
10.
11.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.4.
Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :
Letter No.
Dated :
Test
No.
1.
1.
2.
3.
Details
of
Casting
2.
Date of
Testing
3.
Age of
Cube in
days
4.
Location of
Concreting
5.
Grade /
Proportion
of mix
6.
Wt. of
Specimen
in gms
7.
Compressive
strength of CC
cubes in kg/cm2
8.
9.
Requirement
as per IS
456:2000
Remarks
10. 11.
12.
13.
Compressive
strength of CC
cubes is computed
for 28 days curing
vide
MOSRTH
Table
900-5
Section 900
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.5.
Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Indian Standard Specification for coarse aggregate IS 383:1970 Table 1 and 4 and test carried out as per IS 2386:1963
Sample
No.
1.
1.
2.
3.
Description of
sand sample
tested
Grading limit
for
fine
aggregate as
per IS 383:
1970 Table 1
and
4
for
concrete work
2.
Deleterious material % by Wt
Passing
Coal
Clay
75
and
Others
lumps
Micron
Lignite
IS Sieve
Max
3.00%
3.
Max
Max
1.00% 1.00%
4.
5.
Max
1.00%
6.
10
mm
100%
Max
100%
5.00%
100%
7.
8.
4.75
mm
90-100% 60-95%
90-100% 75-100%
90-100% 85-100%
9.
1.18
mm
0.600
mm
0.300
mm
0.075
mm
Grading
zone of
sand
sample
30-70%
55-90%
75-100%
15-34%
35-59%
60-79%
5-20%
8-30%
12-40%
0-10%
0-10%
0-10%
Gr - I
Gr - II
Gr - III
12.
13.
14.
2.36
mm
10.
11.
15.
Remarks
16.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division
8.6.
Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :
Sl.
No.
Date of
Testing
Class
designation and
Identification
mark on the top
of the brick
1.
2.
3.
1.
2.
3.
Water
absorption
Value in
%
Crushing
strength of
brick
in
kg/cm2
4.
5.
Letter No.
Dated :
Water
absorption
in %
6.
Water
Crushing
absorption
strength of
Value in %
brick
in
20.00%
2
kg/cm
(Max)
7.
8.
Crushing strength
brick in kg/cm2 Remarks
35/50/75
kg/cm2
(min) based on
class of Bricks
9.
10.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.7.
Test Report of Coarse Aggregate (40mm and less / 20mm and less)
Name of work :
Reference : Executive Engineer
Letter No.
Dated :
Date of Testing :
Indian standard specification for coarse aggregate IS 383:1970 Tables -1 and 2 and test carried out as per IS 2386:1963
Size of coarse
Percentage by weight passing the IS Sieve
aggregate
Details of
Test
Aggregate
80mm
40mm
20mm
10mm
4.75mm
Sample
No.
Impact
40mm and less
100%
95-100%
30-70%
10-35%
0-5%
Collected
Remarks
Value Max
20mm and less
100%
95-100%
25-55%
0-10%
30%
1.
2.
3.
4.
5.
6.
7.
8.
9.
1.
2.
3.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.8.
Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :
Letter No.
Dated :
Standard
consistency of
cement in %
1.
1.
2.
3.
2.
3.
Initial setting
time, minimum
Final setting
time, max
3 days
7 days
28 days
30
600
23
33
43
30
600
27
37
53
30
600
16
22
33
30
600
16
22
33
4.
5.
6.
7.
8.
9.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.9.
Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :
No. of
Tests
1.
1.
2.
3.
Letter No.
Dated :
Requirement as per MOSRTH Specification Section 400 clause 404 and test conducted as per IS 2386:1963
Nominal
Grading Requirements for chips for surface dressing
size
Percentage by wt
Details
Impact
Water
Passing
of
value
Absorption 1%
19
13.2
9.5
6.3 2.36 0.075
13.2 mm Remarks
Sample
30%
(Max)
13 mm
mm
mm
mm mm mm
mm
retained on
Tested
(max)
9.5 mm
100 85-100 0-40 0-7
0-2
0-1.5
65% min
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.10. Test Report on Aggregate Characteristics of 20mm Thick Open Graded Premix Carpet / Seal Coat
Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Section 500 clause 511 and 513 and test conducted as per IS: 2386:1963
Grading for 20mm Open
Grading for Seal Coat
Graded Premix Carpet
Aggregate
(Table 500-23)
% Passing by weight
% passing by weight through
through IS Sieve
Required
Required
IS Sieve designation
Water
Details Impact
designation
Bitumen
Bitumen
value Absorption
of
Test
Type A
Type B
Content
in
Content
in
13.20 mm
11.20mm
value 1%
No. Sample 30%
(clause
(clause
%
for
seal
%
for
metal
metal
(max)
Tested (max)
513.2.2)
513.2.3)
coat mix
carpet mix
22.40 11.20 13.20 5.60
11.2 2.36 2.36 0.180
mm
mm
mm mm
mm mm mm
mm
100
0% 100% 0%
100%
0% 100% 0%
%
9
10
11
12
13
14
1.
2.
3.
4.
5.
6.
7.
8.
1.
2.
3.
Remarks
15
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
1.
1.
2.
3.
Details
of
Sample
Tested
Impact
value
30%
Max
2.
3.
Aggregate
Water
Absorption
value 2%
Coarse
Max
4.
IS Sieve Designation
53 mm
26.5mm
22.4mm
13.2mm
5.6mm
2.8mm
100
40-75
0-20
0-5
Key
100
100
100
40-75
0-20
0-5
5.
6.
7.
8.
9.
10.
Remarks
11.
12.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
1.
2.
3.
4.
Test
No.
Details
of
sample
collected
Impact
value
24%
(max)
Water
Absorption
value 2%
(max)
Grade
I
50-65
mm
II
30-45
mm
26.5
mm
0.15
mm
0.075
mm
100
79100
5979
5272
3555
2844
2234
1527
1020
5-13
2-8
--
100
79100
7088
5371
4258
3448
2638
1828
1220
4-10
Remarks
Apart from conformity with the grading and quality requirement for individual ingredients the mixure shall meet the requirements
set out in Table 500-19 (For Mixture Design)
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
Sl.
No.
1.
2.
3.
4.
Test
No.
Details
of
sample
collected
Impact
value
27%
(max)
Water
Absorption
value 2%
(max)
Grade
I
13 mm
II
10 mm
0.075
mm
100
90-100
70-90
35-51
24-39
15-30
9-19
3-8
--
100
90-100
35-51
24-39
15-30
9-19
3-8
Remarks
Apart from conformity with the grading and quality requirement for individual ingredients the mixure shall meet the requirements
set out in Table 500-16 (For Mixture Design).
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
Impact
value
Test
No.
1.
1.
2.
3.
Details
of
sample
Tested
2.
Water
Absorption
value
30%
Max
3.
2% Max
4.
Grade
I
(80-100
mm)
II
(50-75
mm)
5.
Bitumen
Content % by
weight of total
mix
45
mm
37.5
mm
26.5
mm
19
mm
13.2
mm
4.75
mm
2.36
mm
0.3
mm
0.075
mm
100
%
90100
75100
35-61
1322
4-19
2-10
0-8
3.1 - 3.4
100
90100
56-88
1636
4-19
2-10
0-8
3.3 - 3.5
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Remarks
Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification (4th revision) Section 500 clause 504 and test conducted as per IS 2386:1963
16.
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.
Executive Engineer/In-charge
PWD (QC. Division)
8.15. Test Report on Aggregates Characteristic for Dense Graded Bituminous Macadam
Test
No.
1.
2.
3.
4.
Details
of
Sample
Tested
Flakiness
Elongation
Index
(Combined)
Max 30%
AggreWater
gate
absorp
Impact
-tion
value
Max
Max
2%
27%
Nominal
aggregate
size
Grade
45
mm
40 mm
100
25 mm
II
37-5
mm
95100
100
%
Remarks
Name of work :
Reference :
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification Section-500 clause 507 Table 500-10 and test conducted as per IS 2386:1963
Apart from conformity with the grading and quality requirement for individual ingredients the mixure shall meet the requirements
set out in Table 500-16 (For Mixture Design).
Materials to be tested as per frequency of MOSRTH Section 900.
Test samples of aggregates were collected/supplied by the QC Division/supplied by the Concerned EE through field staff.
The Gradation of DBM in the proportion of the aggregate as mentioned above shall be adopted and gradation shall be got
confirmed in the filed by carrying filed gradation test
Executive Engineer/In-charge
PWD (QC. Division)