PUBLIC WORKS DEPARTMENT,

HIMACHAL PRADESH
QUALITY MANAGEMENT SYSTEMS
(ISO 9001: 2008)
(HPPWD Project Reference No.: - PW-SRC/RIDC/Procurement-ISO/2008)

CONSTRUCTION MANUAL
(WORK INSTRUCTIONS)
ROAD CONSTRUCTION
HIMACHAL PRADESH ROADS & INFRASTRUCTURE DEVELOPMENT
CORPORATION LTD (HPRIDC)
States Roads Project, Nirman Bhawan
Nigam Vihar, Shimla 171002
Tel No.: 0177-2627602

Issue No: 01
Review & Issue By:

Rev No. 00
Approved By:

Project Director(MR)

MD/ Secretary

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

TABLE OF CONTENTS
Title

Page No.

Chapters
AMENDMENT SHEET .......................................................................................................... i
1. INTRODUCTION ...........................................................................................................1-1
2. CONSTRUCTION MANAGEMENT ..............................................................................2-1
2.1. Supervision - Process and Product........................................................................2-1
2.2. Original Construction ..............................................................................................2-1
2.3. Steps involved - Planning and investigation ..........................................................2-2
2.4. Submission of Project Report.................................................................................2-4
2.5. Tendering................................................................................................................2-4
3. PROCESS FLOW..........................................................................................................3-1
4. QUALITY ASSURANCE PLAN FOR ROAD.................................................................4-1
4.1. Background.............................................................................................................4-1
4.2. References..............................................................................................................4-1
4.3. Scope ......................................................................................................................4-1
4.4. Abbreviations and Definitions.................................................................................4-1
4.5. Planning of Road Projects ......................................................................................4-3
4.6. Original Works / Maintenance ................................................................................4-3
5. QUALITY ASSURANCE REQUIREMENTS FOR ROADS ..........................................5-1
5.1. Project Report Preparation.....................................................................................5-1
5.2. Material Controls.....................................................................................................5-1
5.3. Process Controls ....................................................................................................5-1
5.4. Typical Quality Plan for Road and Bridge Construction ........................................5-2
5.5. Quality Assurance for Maintenance of Roads........................................................5-3
5.6. Planning QA Programme........................................................................................5-4
6. NON-CONFORMANCE (NC) AND CORRECTIVE ACTIONS.....................................6-1
6.1. Typical NCs with Product .......................................................................................6-1
7. TEST PLANS AND CHECKLISTS ................................................................................7-1
7.1. Test Plan for Soil ....................................................................................................7-1
7.2. Test Plan for Granular Sub-Base Material .............................................................7-2
7.3. Test Plan for Coarse and Fine Aggregates (Over Size / Size Metal)....................7-3
7.4. Test Plan for Water.................................................................................................7-5
7.5. Test Plan for Stone Rubble ....................................................................................7-6
7.6. Test Plan for Cement..............................................................................................7-7
7.7. Test Plan for Admixture ..........................................................................................7-8
7.8. Test Plan for Reinforcement Steel .........................................................................7-9
7.9. Test Plan for Bitumen ...........................................................................................7-10
7.10. Test Plan for CC/RCC Pipes and Collars ............................................................7-11
7.11. Test Plan for A.C. Pipes .......................................................................................7-12
7.12. Test Plan for CC/RCC Pipes and Collars ............................................................7-13
7.13. Test Plan for CC/RCC Pipes and Collars ............................................................7-14
7.14. Test Plan for Road Furniture ................................................................................7-15
7.15. Test Plan for Geo Synthetics................................................................................7-16
7.16. Checklist for General Inspection of Site ...............................................................7-17
7.17. Checklist for Calibration of Inspection, Measuring and Test Equipment.............7-19
7.18. Checklist for Surveying and Setting Out ..............................................................7-20
7.19. Checklist for Surveying and Setting Out ..............................................................7-22
Procedure No.: QMS/WI/RC/Table of Contents
Controlled Document

Issue 01, Rev 00


Page No.: RC/i

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.20. Checklist for Publicity Utility Services ..................................................................7-23


7.21. Checklist for Curst Design Of Flexible Pavement................................................7-24
7.22. Checklist for Excavation For Road Work (Utility related)....................................7-25
7.23. Checklist for Excavation for Road Work (Tree related) .......................................7-26
7.24. Checklist for Excavation for Road Work ..............................................................7-27
7.25. Checklist for 95% PD Earth Work (To be Completed for each Layer) ................7-29
7.26. Checklist for 95% PD Earth Work (To be Completed for each Layer) ................7-32
7.27. Checklist for 95% PD Earth Work (To be Completed for each Layer) ................7-34
7.28. Checklist for 95% PD Earth Work (To be Completed for each Layer) ................7-35
7.29. Checklist for 100% PD Earth Work ......................................................................7-36
7.30. Checklist for Hard Murrum for Side Shoulder ......................................................7-38
7.31. Checklist for Granular Sub Base ..........................................................................7-39
7.32. Checklist for Water Bound Macadam (Gr.1) In Layers ........................................7-41
7.33. Checklist for Water Bound Macadam (Gr.II) In Layers ........................................7-44
7.34. Checklist for Water Bound Macadam (Gr.III) In Layers.......................................7-47
7.35. Checklist for Road Side Gutter in Cement Concrete ...........................................7-50
7.36. Checklist for Tack Coat ........................................................................................7-53
7.37. Checklist for Bitumen Bound Macadam...............................................................7-55
7.38. Checklist for Surface Dressing .............................................................................7-57
7.39. Checklist for Surface Dressing .............................................................................7-58
7.40. Checklist for Bitumen Macadam...........................................................................7-60
7.41. Checklist for Bitumen Macadam...........................................................................7-63
7.42. Checklist for Bitumen Macadam...........................................................................7-64
7.43. Checklist for Bitumen Macadam...........................................................................7-65
7.44. Checklist for Mix Seal Surface .............................................................................7-66
7.45. Checklist for Pre-Mix Carpet ................................................................................7-68
7.46. Checklist for Dense Bituminous Macadam ..........................................................7-70
7.47. Checklist for Dense Bituminous Macadam ..........................................................7-73
7.48. Checklist for Asphaltic Concrete ..........................................................................7-75
7.49. Checklist for Asphaltic Concrete ..........................................................................7-78
7.50. Checklist for Mastic Concrete...............................................................................7-80
7.51. Checklist for Mastic Concrete...............................................................................7-83
7.52. Checklist for Concrete Pavement.........................................................................7-84
7.53. Checklist for Road Marking Paint - Thermoplastic Plant .....................................7-87
7.54. Checklist for Kerb Stone for Central Verge..........................................................7-89
7.55. Checklist for Kilometre Stone and 200 metre Stones ..........................................7-91
7.56. Checklist for Cast Iron Pipe Railing and Parapets.............................................7-93
7.57. Checklist for Guard Stones ..................................................................................7-95
7.58. Checklist for Boundary Stones .............................................................................7-97
7.59. Checklist for Cross Drainage Works (Hume Pipe Drain).....................................7-99
7.60. Checklist for Road Signs ....................................................................................7-103
7.61. Checklist for Slab Drain ......................................................................................7-105
8. TESTS AND TEST PROFORMAE................................................................................8-1
8.1. Tests to be Conducted by Construction Division ...................................................8-1
8.2. Tests to be Conducted by Quality Control Division ...............................................8-1
8.3. Test report on aggregate characteristics of Grade 2 metal for WBM Work ..........8-3
8.4. Test Report on Cement Concrete Cubes...............................................................8-4
8.5. Test Report of Sand Sample ..................................................................................8-5
8.6. Test Report of Brick Sample ..................................................................................8-6
8.7. Test Report of Coarse Aggregate (40mm and less / 20mm and less) ..................8-7
Procedure No.: QMS/WI/RC/Table of Contents
Controlled Document

Issue 01, Rev 00


Page No.: RC/ii

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.8. Test Report of Cement Sample..............................................................................8-8


8.9. Test Report on Aggregate Characteristics of Single Coat Surface Dressing........8-9
8.10. Test Report on Aggregate Characteristics of 20mm Thick Open Graded Premix
Carpet / Seal Coat ................................................................................................8-10
8.11. Test Report on Aggregate of Built-up Spray Grout..............................................8-11
8.12. Test Report on Coarse Aggregate for Bituminous Concrete ...............................8-12
8.13. Test Report on Aggregates Characteristic for SDBC ..........................................8-13
8.14. Test Report on Aggregate Characteristics of Bituminous Macadam ..................8-14
8.15. Test Report on Aggregates Characteristic for Dense Graded Bituminous
Macadam ..............................................................................................................8-15
Annexures
Annexure I. : Typical Letter for Public Representation ......................................................I-1
Annexure II. : Typical Covering Letter from Division to Division.......................................II-1
Annexure III. : Typical Routine Inspection Proforma for Maintenance of Road ..............III-1
Annexure IV. : Annual Calendar for QA Checks for Road Maintenance........................ IV-1
Appendixes
Appendix I. : Proforma for New Road / Maintenance ........................................................I-1
Appendix II. : Checklist for Proposal Preparation of Road ...............................................II-1

Procedure No.: QMS/WI/RC/Table of Contents


Controlled Document

Issue 01, Rev 00


Page No.: RC/iii

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

AMENDMENT SHEET
Sl. No. Document

Description of change

Page/
para.
No.

Procedure No.: QMS/WI/RC/Amendment Sheet


Controlled Document

Rev.
No

Date of
issue

Issue 01, Rev 00


Page No.: RC/i

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

1. INTRODUCTION
This manual intends to provide guidance to the HPPWD engineers in their
functions of investigation, designs, estimation inspection and assurance of quality
of construction and maintenance. It helps in the vendor control and gradation of
contractors and is expected to aid in structured Quality Assurance activities of
HPPWD.
Road construction is dependent on several challenges, right from selection of the
terrain, soil conditions, materials, methods, type and design of construction to
supervision and assurance of quality in construction of new roads and
maintenance of the same after the area acquired.
The enclosures would provide typical process flow of road construction, Quality
Assurance requirements and test plans for Quality checks of materials used in
construction.
The checklists are the Level III documents of an established Quality Management
System (QMS) as per ISO 9001:2008 The Quality Plan drawn up highlights on the
process controls necessary for product realization and improvements.
It is also intended to help the internal auditors while carrying out audits of the
implemented QMS of HPPWD.
This document is an important adjunct to the Procedure Manual (Level II)
document and takes into consideration the existing practices and codal needs of
HPPWD. The formats to be used are the same as necessary for the QMS and the
departmental code.
For easy reference to the contents of the manual the following process has been
adopted:
RCM refers to Road Construction Manual.
TP refers to Test Plan
CL refers to various Check list for process control.
The test plans are identified as RCM/TP XX refers to the Serial No. of Test plan,
similarly RCM/CL XX refers to the Serial No. of checklist as applicable. The test
plan and checklist should be considered as work instructions necessary for
construction and maintenance of building.
The typical tests and test Performa are given in separate chapters for the purpose
of guidance to the site engineer, quality control staff and also the contractors.

Procedure No.: QMS/WI/RC-01/Introduction


Controlled Document

Issue 01, Rev 00


Page No.: RC/1-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

2. CONSTRUCTION MANAGEMENT
2.1.

Supervision - Process and Product

2.1.1. Process
2.1.1.1

Monitoring Measuring Devices

2.1.1.2

Test frequencies and calibration schedule


Handling by skilled men.

Quality control of materials (QC)

Inspection and certification of materials, on receipt at site


Sampling of materials to be tested.
Testing of materials during construction
Methodology of construction as per standards/codes.
Competency of workers

2.1.2. Product

2.2.

Workmanship
Safety.
Specification
Quality Management System.

Original Construction
Public Representation
o

Letter from Public / Elected Public representative to Division (Annexure I).

Feasibility study by Division


o
o
o
o
o
o
o
o

Economic profile and analysis.


Traffic survey.
Preliminary Topographical survey.
Soil survey and drainage studies.
Initial pavement designs.
Land acquisition estimate.
Traffic analysis and projection.
Line estimate for detail investigation.

Typical Covering Letter from Division to Division (Annexure II).


Proposal verified and recommended (or rejected) by EE and submitted to SE.
Proposal verified and recommended (or rejected) by SE and submitted to CE.
(Submission to SE / CE depends upon the amount involved and financial
powers delegated).
EE/SE/CE submits proposal to Govt. for sanctioning the amount towards detail
investigation.
Procedure No.: QMS/WI/RC-02/Construction Management
Controlled Document

Page No.: RC/2-1

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Upon receiving the amount for detail investigation* to Division, EE instructs the
Division to carry out the activity.
Based on the investigation results, designs are prepared.
On the basis of designs and by referring to current schedule of rates,
applicable to concerned Circle, detailed estimate is prepared.
Detailed Project Report** is submitted by Division to Technical committee
(TC)/Board of Directors (BOD).
TC/BOD scrutinizes all the proposals (completed in all aspects) received from
various Divisions.
TC/BOD prioritizes proposals on the basis of need of the project for inclusion
in the budget.
Upon approval from the Govt. (Appearing in the Budget), TC/BOD intimates the
concerned Division accordingly.
The proposal which does not appear in the budget due to financial reasons, are
stored back by TC/BOD, and are reviewed in the subsequent years.

2.3.

Steps involved - Planning and investigation

2.3.1. Survey
2.3.1.1

Detailed Topographical Survey

2.3.1.2

Socio-Economic Survey

2.3.1.3

Re-alignment, alternate alignment and Final alignment of Road.


Detailed soil survey.
Visibility / sight distance in horizontal and vertical profile.
Carriageway shoulder width and formation width.
Cross Drainage structures.
Drainage system.
Safety features.

Land availability and acquisition.


Economic profile data.
Socio-economic status of the road influence area.
Growth trends.

Traffic Surveys and Analysis

Classified traffic volume survey.


Origin-destination studies.
Speed and delay studies.
Survey for design of road junctions, road over/under bridges, etc.
Axle load studies.
Accident records.
Traffic projection.

Procedure No.: QMS/WI/RC-02/Construction Management


Controlled Document

Page No.: RC/2-2

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

2.3.1.4

Geographical Survey

2.3.1.5

Environmental Impact Studies

2.3.1.6

Study of secondary data.


Soil investigation for low embankments.
Special investigation for high embankments.
Soil investigation for cut sections.
Special investigation for land-slide-prone area.
Detailed investigation for flexible pavement design.

Road Construction Materials Survey

2.3.1.8

Environmental impact assessment.


Environmental management action plan.
Resettlement and rehabilitation action plan.

Soil Survey

2.3.1.7

Study of maps and survey sheets.


Study of GIS information.

Naturally available aggregates for pavement layers.


Manufactured aggregates.
Water for construction purpose.

Road Inventory and Condition Survey

Riding quality.
Widths of pavement, shoulders, formation.
Vertical profile.
Horizontal and vertical curves.
Drainage Studies.
o Objectives.
o High flood level.
o Low water table.
o Depth of water table.
o Special investigation for cut-sections.
o Surface run-off.

2.3.2. Designs

Geometric designs.
Detailed pavement design.
Cross Drains design.
Side drains design.

Procedure No.: QMS/WI/RC-02/Construction Management


Controlled Document

Page No.: RC/2-3

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

2.3.3. Detailed Project Report (DPR) Preparation


DPR verified and submitted to EE / SE / CE / TC/BOD.
(Depending upon the amount involved and financial powers delegated).
DPR consists of:
Survey details (including land acquisition needs).
Design details.
Detailed estimate:
It is based on Current Schedule of Rates (CSR) applicable for respective Circles.
It includes-

2.4.

(a).

General report detailing about present condition of the road, connectivity,


proposed improvements.

(b).

Inspection Certificate by EE and EE.

(c).

Abstract - Detailing name of the work and estimated cost.

(d).

Detailed Estimate describing items, units, quantity, rate amount, etc.

(e).

Sub-estimates.

(f).

Rate Analysis.

(g).

Plans.

(h).

Index Map.

(i).

Bar chart for existing Road condition.

(j).

Bar chart for proposed improvements.

(k).

Data rate for non-CSR items.

Submission of Project Report


Submission of the DPR for Administrative Approval from Division to Division
and in turn to competent authorities in accordance with the Delegation of
financial powers for administrative approval.
After administrative approval, Technical Sanction is accorded by competent
authorities.
Upon accord of technical sanction by competent authority, Division initiates the
next activity of tendering. The Division prepares Draft Tender Schedule (DTS)
and seeks approval from competent authorities

2.5.

Tendering
Notification for Inviting Tenders (NIT)
Preparation of Draft Tender Papers
o
o
o
o

Pre-qualification of Contractor, if applicable.


Preparation of Draft Tender Schedules (DTS).
Preparation of schedule B.
Competent Authority approval for Draft Tender Papers.

Procedure No.: QMS/WI/RC-02/Construction Management


Controlled Document

Page No.: RC/2-4

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Preparation of Tender Documents, It Shall Contain:


o
o
o

Technical specifications.
Commercial conditions.
Dispute resolution methodology.

Supply of Tender Documents


Clarification of Tender Documents
o
o
o

Scope of Tender.
Eligibility criteria.
Amendment of Tender documents.

Receipt of Tenders and Tender Opening


Tender Evaluation to be in Accordance with Evaluation Criteria
Preparation of Evaluation Report and Award of Contract

Procedure No.: QMS/WI/RC-02/Construction Management


Controlled Document

Page No.: RC/2-5

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

3. PROCESS FLOW
Preparation of Designs
and estimates

Project Identification

Detailed Investigation

Scrutiny and approval by


competent authority

Scrutiny and Prioritization


by Technical Cell
(Shelf of Project)

Proposal
appear in the
Budget

Y
Preparing Plans and Estimates

- Administrative Approval
- Technical sanction

Tendering / Award of
Contract

Handing over
of site

Execution of
works

Completion of
project

Procedure No.: QMS/WI/RC-03/Process Flow


Controlled Document

Issue 01, Rev 00


Page No.: RC/3-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

4. QUALITY ASSURANCE PLAN FOR ROAD


4.1.

Background
A good road network has an important bearing on the economy of a country. In
the changing scenario of globalization and economic liberalization, a great deal of
emphasis is already laid on development of infrastructure through construction of
a dependable road network. Consequently, consistency in the quality has gained
paramount importance. In line with this need, the document is prepared to provide
guidelines for Quality Assurance of Roads.

4.2.

References

4.3.

ISO 9000:2005 Fundamentals and Vocabulary.


Indian Roads Congress (IRC).
Ministry of Shipping, Road Transport and Highways (MOSRTH).
Quality Manual, Procedure Manual, Manual of Forms and Formats.
Bureau of Indian Standards (BIS).

Scope
These guidelines cover quality system for activities of road construction. These
include steps towards planning and investigation, design and construction,
Tendering, Closing NCs, etc.

4.4.

Abbreviations and Definitions

4.4.1. Abbreviations
IRCM

Indian Road Congress

No.

Number

Ref.

Reference

Const.

Construction

Est.

Detailed Estimate

CSR

Current Schedule of Rate

NIT

Notification Inviting Tenders

QC

Quality Control

NC

Non-Conformance

4.4.2. Definitions
4.4.2.1

Quality
The totality of features and characteristics of a product or service that relies on its
ability to satisfy stated or implied need.

Procedure No.: QMS/WI/RC-04/Quality Assurance Plan for Road


Controlled Document

Page No.: RC/4-1

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

4.4.2.2

Quality Assurance
All those systematic and planned actions necessary to provide adequate
confidence that a product or service will satisfy given requirements for quality.

4.4.2.3

Quality Plan
A document specifying which procedures and associated resources shall be
applied by whom and when to a specific project, process or contract.

4.4.2.4

Non-Conformity
Non-fulfillment of specified requirements.

4.4.2.5

Technical Sanction
The name is given to the order of the competent authority sanctioning a properly
detailed estimate of the cost of a work of construction or repair, to be carried out
by the public works department. Ordinarily, such sanction can only be accorded
by the government in the public works department or by such authorities of the
department to whom the power has been delegated by government. Sanction
accorded to a work by any other department of government is regarded as an
administrative approval of the work.

4.4.2.6

Administrative Approval
This term denotes the formal acceptance, by the administrative department
concerned, of the proposals for incurring any expenditure in the public works
department on a work initiated by or connected with the requirements of such
administrative department. It is in effect, an order to the Public Works Department
to execute certain specified works at a stated sum to meet the administrative
needs of the department requiring the work. .
Administrative Approval
Subject to appearing in the Budget

4.4.2.7

Technical Sanction
For estimate of original work

For Lump-sum Contract Architectural, Acoustic, Landscaping, electrical etc.

Procedure No.: QMS/WI/RC-04/Quality Assurance Plan for Road


Controlled Document

Page No.: RC/4-2

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

4.5.

Planning of Road Projects


ROAD

Maintenance

Original
Construction

Annual
Maintenance

4.6.

Periodical
Maintenance

Special / Urgent
Maintenance

Original Works / Maintenance


The term original works indicates new constructions whether of entirely new
works or of additions and alterations to existing works.
When a portion of an existing structure or other work not being a road surface,
road bridge, causeway, embankment, ferry approach, protective or training work
in connection with a road, is to be replaced or remodeled (whether or not change
involves any dismantlement) and the cost of the change represents a genuine
increase in the value of the property, the work of replacement remodeling, as the
case may be shall be classified as original works.

Procedure No.: QMS/WI/RC-04/Quality Assurance Plan for Road


Controlled Document

Page No.: RC/4-3

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

5. QUALITY ASSURANCE REQUIREMENTS FOR ROADS


5.1.

Project Report Preparation


Design and drawings, Contracts and contractors, Materials, quantity estimation,
requirements of human resources, execution, inspection and testing, acceptance /
reworking and asset acquisition

5.2.

Material Controls
Testing of materials- Aggregates- coarse, fine, components (base, sub-base,
pavement, shoulders).
Test methods, Acceptance limits.
Sampling and Frequency of testing.
Availability of equipment- Monitoring and measurement.
Reports of test results, calibration.

5.3.

Process Controls

5.3.1. Alignment
Edges, carriageway, horizontal alignment, vertical profile, pavement thickness
5.3.2. Road Embankment
Grade, sub base and fill.
Grain size, Plasticity Index, of materials, moisture content, density.
Sampling and frequency of testing, Test methods, testing equipment,
calibration.
Tests on finished profile.
5.3.3. Granular Base Course Laying

Material testing (Gradation, sizing, aggregate impact values, density).


Frequency and sampling.
Test equipment and test methods.
Tests on surface profile (slope and evenness).

5.3.4. Bituminous Pavement Laying

Tests on aggregates, bitumen, mix grading.


Temperature and rate of application of prime and tack coating.
Temperature for mixing, laying and compaction of bitumen mix.
Core sampling, assess for density, voids.
Tests on surface profiles, evenness, slope of the finished pavement.

5.3.5. Cement Concrete Pavements


Tests on aggregates, (for the base and paving).
Tests on cement.
Tests on CC mix, (both in situ and laboratory).
Procedure No.: QMS/WI/RC-05/Quality Assurance Requirements for Roads
Controlled Document

Page No.: RC/5-1

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Tests on cores.
Tests on concrete for Cross Drainage.

5.4.

Typical Quality Plan for Road and Bridge Construction

JE/AE /AEE/EE/
SE/CE

Survey,
estimation,
construction,
inspection
sampling, inspection, results
calibration, report preparation,
review and action.

Defect
notification,
nonconformance
reporting,
corrective and preventive
actions,
retesting,
and
procedure
modification
if
required.

PROCESS

Duties and
responsibilities

Quality Planning- Relevant


documents,
Flowcharts,
Statement of duties and
responsibilities,
Scheduling
and controls

INPUTS

Statement of policy and Objectives

Effective
controls,
lesser
customer complaints, higher
productivity and safety.

Procedure No.: QMS/WI/RC-05/Quality Assurance Requirements for Roads


Controlled Document

Page No.: RC/5-2

OUTPUT

Quality Audits- Scheduling,


conduct,
verification
of
compliance, reporting, noncompliance closing, safety
audits, management review
Corrective preventive actions
taken, review for continual
improvement.

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

5.5.

Quality Assurance for Maintenance of Roads


The basic objective of QA in maintenance activity is to ensure safety and meeting
customer requirements. The Quality Assurance activities assure that the
maintenance activities are performed as per plans. Towards this, a calendar is
drawn up at the beginning of the year for both preventive and annual maintenance
of all assets- roads, buildings and bridges. Atypical maintenance plan is given
below:
Maintenance

Annual
Maintenance

Periodic
(preventive)
Maintenance

Special repairs
(Corrective
actions)

5.5.1. Ordinary Repairs / Routine Maintenance/ Annual Maintenance


Maintenance includes following nature of works:
(a).

Upkeep of road pavements and side shoulders.

(b).

Upkeep of roadside drainage system.

(c).

Upkeep of culverts and bridges, and earth retaining structures and


parapets.

(d).

Keeping the sign boards; km stones and other traffic aids and furniture in
good shape and condition.

5.5.2. Periodic Maintenance


It covers periodic renewals to carriageway of graveled metalled or black topped
roads. It is maintained to ensure adequate level of serviceability. Typical Routine
Inspection Performa for Maintenance of Road is given in (Annexure III).
5.5.3. Special Repairs
It covers damages occurred due to unforeseen / natures calamity.
The process maintenance of road needs a system approach involving a series of
sequential operations.
Detailed assessment of the present road condition.
Diagnosis of the problem occurred.
Selection of the most appropriate treatment.
This systematic approach enables a clear understanding of determination of
priorities more objectively and allotment of available resources where they are
most needed.
Procedure No.: QMS/WI/RC-05/Quality Assurance Requirements for Roads
Controlled Document

Page No.: RC/5-3

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

5.6.

Planning QA Programme

5.6.1. Inventory of Road


The first step in planning a maintenance operation is to know the existing road in
terms of physical condition, structural capacity, surface profile, etc. The following
data are required to be collected. The various inputs are:

Strip map.
Surface history.
List of roads - State Highway/ Major District Roads.
GIS data if any.
Traffic census details.
Black spot study details, if applicable.
Safety audit reports, if any.

5.6.2. Condition Survey


Condition surveys at fixed frequency are necessary for determining periodic
renewal requirements and long-term maintenance strategy.
Type of Maintenance
Type of
Road

SH

MDR

Routine

Special

Routine

Special

Routine

Special

Six
monthly

Pre and
Bi monthly
Post
monsoon

Pre and
Post
monsoon

Bi monthly

Weekly

Quarterly

Pre and
Bi monthly
post
monsoon

Bi monthly
During
monsoon

Monthly

Weekly

It can be carried out by


Visual inspection.
Evaluation testing.
The findings are recorded in the prescribed format
5.6.3. Calendar of QA Planning for Maintenance
The calendar is drawn up for the year, keeping in mind the best time for
maintenance activity ,such as, pre monsoon, post monsoon, winter (for hill roads)
etc. A typical calendar is shown for purpose of reference (Annexure IV).

Procedure No.: QMS/WI/RC-05/Quality Assurance Requirements for Roads


Controlled Document

Page No.: RC/5-4

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

6. NON-CONFORMANCE (NC) AND CORRECTIVE ACTIONS


6.1.

Typical NCs with Product

6.1.1. Non-Conformance with Strength Requirements


(a).

The required strength and density for concrete should conform the
specified and required strength. In the event of cube tests failures, it
needs to be re-worked and re-verified before approval.

(b).

The causes for such failures shall be identified and measures shall be
taken to rectify the problem.

6.1.2. Even for Non-Conformity Other than the Strength


(a).

Issue a notice in writing stating the facts and confirming the failures of
works done to rectify the same at the cost of the contractor. The rectified
work needs to be re-verified before approval

6.1.3. Non-Conformance with Required Finish


Where the required finish is not attained to, then:
(a).

Approval of similar work shall be withheld.

(b).

All aspects of work shall be reviewed.

(c).

The cause of poor finish shall be identified.

(d).

Revised specifications/instructions to avoid further reoccurrence of nonconformance shall be issued.

Procedure No.: QMS/WI/RC-06/Non-Conformance (NC) and Corrective Actions


Controlled Document

Page No.: RC/6-1

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Annexure I. : Typical Letter for Public Representation


Date:
To
The Executive Engineer
<Tehshil> Division,
Pin No.Sir,
Sub: Submission of proposal (Tick mark the applicable)
Ref.:
I am /We are submitting a proposal in the prescribed format attached herewith for
construction / Improvement / Maintenance of Roads / Buildings / Bridges /
Culverts / Pave dip / causeway / others.
I / We hope this proposal will be considered for obtaining necessary approval from
Government and work will be taken-up at the earliest.
Thanking you.

Yours truly,
Enclosure:
1. Performa for New Road / Maintenance (Appendix I).

Procedure No.: QMS/WI/RC/Annexure


Controlled Document

Issue 01, Rev 00


Page No.: RC/AN.I-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Annexure II. : Typical Covering Letter from Division to Division


No./EE- <Sub-div>/Case worker/ Subject / File No. / Year / Dispatch No. /
Dispatch Date
Date:
To
The Executive Engineer
<>District>
Pin. No.
Sir,
Sub:

Proposal for (Strike out the non applicable product)


Road / Bridge under

<Head of account>

Ref.: Public Representation dated Attached herewith, I am hereby submitting a proposal, in the prescribed format
for construction / Improvement / Maintenance of Roads / Bridges / Culverts / Pave
dip / causeway / others.
I hope this proposal will be considered for necessary approval from Government
and work will be taken-up at the earliest.
Thanking you,
Yours truly,

Executive Engineer
Sub- Division
Enclosure:
1. Checklist for Road (Appendix II).
2. District Map
3. Tehshil Map
4. Copy of Representatives Letter, if any

Procedure No.: QMS/WI/RC/Annexure


Controlled Document

Issue 01, Rev 00


Page No.: RC/AN.II-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Annexure III. : Typical Routine Inspection Proforma for Maintenance of Road


SH / MDR No:
Date of inspection:
Place:
Sl.
No.
1.
2.

3.

4.
5.
6.

7.

Status of
components
Side drain
Shoulder and
Slope
Camber.
Pot holes.
Erosion.
Drain washouts.
Carriageway
Fill Patches.
Fill Pot holes.
Grit.
Cross Drain
Details
Encroachment
details
Road Accessories
Missing boards.
Km Stones.
Pavement.
Other markings.

KM

KM

KM

KM

KM

Safety history
Remarks:

Actions on the following are required:

Nature of actions:

Immediate/ In due course

Inspected by:

Approved by:

Procedure No.: QMS/WI/RC/Annexure


Controlled Document

Issue 01, Rev 00


Page No.: RC/AN.III-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Annexure IV. : Annual Calendar for QA Checks for Road Maintenance


Sl.
No.
1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

Items

Jan-Mar

Repairs of Road
berms
including
jungle clearance.
Repairs
to
longitudinal, side
shoulder and catch
drains.
Collection of patch
repairs material for
WBM roads.
Collection of patch
repairs material for
BT roads.
Patch
repairs
material for WBM
roads.
Patch
repairs
material for BT
roads.
Repairs
and
repainting
of
signage boards.
Painting
of
hectometer / km /
5km/ guard stones.
Maintenance
of
roadside trees by
pruning
Removal
of
encroachment and
unauthorized
hoardings.

Apr-Jun

Jul-Sept

Oct-Dec

Remarks

X - Recommended period of activity

Procedure No.: QMS/WI/RC/Annexure


Controlled Document

Issue 01, Rev 00


Page No.: RC/AN.IV-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Appendix I. : Performa for New Road / Maintenance


1. Proposal for a New Road :
o Connectivity.
o Traffic Density.
o Population benefited.
o Location of School, Colleges, Hospitals etc.
2. Name of the Road:
3. Location :
o Name of Village
o Name of Taluka
o Name of District
4. Present condition of Road:
5. Improvements required:

Procedure No.: QMS/WI/RC/Appendixes


Controlled Document

Issue 01, Rev 00


Page No.: RC/AP.I-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Appendix II. : Checklist for Proposal Preparation of Road

Sl.
No.
1.

Name of the work:

2.

Name of District

3.

Name of Tehshil

4.

Name of constituency

5.

Name of proposed Road

6.

Category of Road

7.

Total length of Road

8.

11.

Length of the Road


proposed for improvement
Estimated cost Rs. in
Lakhs.
Based on S.R. for the
year.
Estimated cost for detailed
investigation
Villages benefited

12.

Population benefited

13.

Surface
existing
Drain

9.

10.

Particulars

Project 1

condition
of
WBM
Bridge/Cross

From To

14.

Proposed improvements

15.

Traffic census and year

16.

Name of the representative

17.

Priority level *

18.

Justification

19.

Remarks

Project 2

Project 3

BT

WBM

BT

WBM

BT

From To

From To

From To

From To

From To

Note: Priority Levels


(a).

Top priority

(b).

Roads which are badly damaged and having WBM surface.

Medium priority

Roads which are asphalted but badly damaged

Procedure No.: QMS/WI/RC/Appendixes


Controlled Document

Issue 01, Rev 00


Page No.: RC/AP.II-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

(c).

Low priority

Roads which are asphalted but requires minimum improvements.


Bridge/Cross Drains, which are asphalted but require minimum
improvements.
MDR but traffic intensity low.
Minor District Road and traffic intensity low.

Procedure No.: QMS/WI/RC/Appendixes


Controlled Document

Issue 01, Rev 00


Page No.: RC/AP.II-2

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7. TEST PLANS AND CHECKLISTS


7.1.

Test Plan for Soil

7.1.1. Material: - Earth / Murrum (Borrow Material)


RCM/TP 01
Name of Work :
Agreement No.:
Sl.
No.
1.
2.
3.
4.
5.
6.

Estimated Cost :
Sanction No. and date:

Test/Parameter

Acceptance Standard

Sample size

Acceptance Criteria

Physical Properties / Requirements.


CBR Test.
Optimum Moisture contents.
Dry Density.
Atterberg limits (L.L. P.L, S.L., P.L.)
Deleterious content tests (Sulphate
Test on water).

MOSRTH 305-2
IS2720 Part-8
IS2720 Part-7 Part-8
IS2720 Part-8
IS2720 Part-5
BS1377 Test-9

Visual
As per IS
As per IS
As per IS
As per IS
As per BS

Freedom from defects


Conformance to limits
Conformance to limits
Conformance to limits
Conformance to limits
Conformance to limits

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-1

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.2.

Test Plan for Granular Sub-Base Material

The GSB material could be natural sand. Murrum, Gravel, Crushed Stone, Quarry Spoils, Oversize metal or combination of these
depending upon grading required.
RCM/TP 02
Name of Work :
Agreement No.:
Sl.
No.
1.
2.

Estimated Cost :
Sanction No. and date:

Test/Parameter

Acceptance Standard

Sample size

Acceptance Criteria

Sieve analysis
Water absorption value of coarse.
Aggregate = 2%
If more than 2% soundness test.

MOSRTH Table 400-2

As per standard

Conformance

IS2886 (Part-3)
IS383

As per standard
As per standard

Conformance
Conformance

SO/JE

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-2

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.3.

Test Plan for Coarse and Fine Aggregates (Over Size / Size Metal)
RCM/TP 03

Name of Work :
Agreement No.:

Estimated Cost :
Sanction No. and date:

Sl. Test/Parameter
No.
1.
Pre-qualification of Source
2.
Alkali Reactivity

Acceptance / Performance
Standard
IS 383
IS 383/IS 2386

Sampling

Test for Assurance

One sample
One Sample / Week

Lot wise
New source or change in
quality
One Sample / Week

3.

Chloride and Sulfide.

MOSRTH-2001
- Section 900 IS 2386

4.

Deleterious Material

MOSRTH-2001
- Section 900 IS 2386

One Sample / Week

One Sample / Week

5.

Crushing Value

MOSRTH-2001
- Section 900 IS 2386 Part-I

New source / as per


requirement

New source / as per


requirement

6.

Abrasion (Optical)

MOSRTH-2001
- Section 900 IS 2386 Part-IV

New source / as per


requirement

New source / as per


requirement

7.

Impact Value

MOSRTH-2001
- Section 900 IS 2386 Part-IV

New source / as per


requirement

New source / as per


requirement

8.

Soundless Value

MOSRTH-2001
- Section 900, IS 2386 Part-V

New source / as per


requirement

New source / as per


requirement

9.

Size and Gradation

MOSRTH-2001
- Section 900 IS 2386 Part-V

New source / as per


requirement

New source / as per


requirement

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-3

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work :
Agreement No.:

Estimated Cost :
Sanction No. and date:

Sl. Test/Parameter
No.
10. Flakiness / Elongation

Acceptance / Performance
Standard
MOSRTH-2001
- section-900 IS 2386 Part-1

Sampling

Test for Assurance

New Source / Per


requirement

New source / as per


requirement

11.

Coating and Supplying of bitumen


aggregate mixtures.

MOSRTH-2001
- section-900 IS 2386 Part-1

New Source / Per


requirement

New Source / Per


requirement

12.

Specific Gravity and absorption


(normal aggregate).

MOSRTH-2001
- section-900 IS 2386 Part-III

New Source / Per


requirement

New Source / Per


requirement

13.

Specific Gravity and absorption


(Heavy Ore)

MOSRTH-2001
- section-900 IS 2386 Part-III

New Source / Per


requirement

New Source / Per


requirement

14.

Density / Moisture Content.

MOSRTH-2001
- section-900 IS 2386 Part-III

New Source / Per


requirement

New Source / Per


requirement

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-4

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.4.

Test Plan for Water


RCM/TP 04

Name of Work :
Agreement No.:

Estimated Cost :
Sanction No. and date:

Sl. Test/Parameter
No.
1.
Pre-qualification

Acceptance / Performance
Standard
IS456, IS SP-23

Sampling

Acceptance Criteria

New Source

New Source

2.

Project Specification IS456, IS


(Chemical Test).

New Source / Thrice


in a year

New Source / Thrice in Year

Physical and Chemical Tests.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-5

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.5.

Test Plan for Stone Rubble


RCM/TP 05

Name of Work :
Agreement No.:
Sl.
No.
1.

Test/Parameter

2.

Physical Properties

Water absorption

Estimated Cost :
Sanction No. and date:
Acceptance / Performance
Standard
IS 1124
MOSRTH 1004
IS 1124
MOSRTH 1004

Sampling

Test for Assurance

One Sample

Weekly

One Sample

Weekly

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-6

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.6.

Test Plan for Cement


RCM/TP 06

Name of Work :
Agreement No.:
Sl.
No.
1.

Test/Parameter

Estimated Cost :
Sanction No. and date:
Sampling Criteria

Acceptance Criteria

Physical and Chemical Test

Acceptance / Performance
Standard
IS 4031

Every consignment.

Conformance to specification

2.

Ordinary Portland cement. 33 Grade

IS 269

Every consignment.

Conformance to specification

3.

Portland Slag Cement.

IS 445

Every consignment.

Conformance to specification

4.

Portland Pozzolana cement.

IS 1489

Every consignment.

Conformance to specification

5.

Rapid hardening Portland cement.

IS 8041

Every consignment.

Conformance to specification

6.

Ordinary Portland cement 43 grade.

IS 8112

Every consignment.

Conformance to specification

7.

Ordinary Portland cement 53 grade.

IS 12269

Every consignment.

Conformance to specification

8.

Sulphate resistant Portland cement.

IS 12330

Every consignment.

Conformance to specification

Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-7

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.7.

Test Plan for Admixture


RCM/TP 07

Name of Work :
Agreement No.:
Sl.
No.
1.

Test/Parameter

2.

Test.

Pre-qualification and
recommendation.

i. Chemical Analysis
ii. Physical Analysis.
iii. Performance

Estimated Cost :
Sanction No. and date:
Acceptance / Performance
Standard
IS 9103/ASTMC 494

Sampling Criteria

Acceptance Criteria

Before commencement of
work and change of
source

Before start of work and when


source is changed.

IS SP 23
IS 9103
IS SP 23
IS 9103
ASTMC-494

New Source / minimum


once in a year
New Source / minimum
once in a year
New Source / minimum
once in a year

New Source / minimum once


in a year
New Source / minimum once
in a year
New Source / minimum once
in a year

Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-8

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.8.

Test Plan for Reinforcement Steel


RCM/TP 08

Name of Work:
Agreement No.:
Sl.
No.
1.

2.

Test/Parameter
Physical test / Chemical composition
Mild Steel
Grade Designation S240

H.Y.S.D. Steel Grade designation S


415

Estimated Cost:
Sanction No. and date:
Acceptance / Performance
Standard
IS 432 Part 1

Sampling Criteria

Acceptance Criteria

Physical Test.
For each consignment
Chemical test.
Once at the beginning /
every source change.

Conformance to specification

IS 1786

Physical Test.
For each consignment
Chemical test.
Once at the beginning /
every source change.

Conformance to specification

Note: Additional tests may be carried out, whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-9

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.9.

Test Plan for Bitumen


RCM/TP 09

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl.
No.
1.

Test/Parameter
Pre-qualification of source

Acceptance / Performance
Standard
Project Specification IS 73

2.

Test.
a) Physical
b) Chemical

Project Specification IS 73
Project Specification IS 73

Sampling Criteria

Acceptance Criteria

New source / as per


requirement

New source / as per


requirement

Each lot
New source / as per
requirement

Once in week
New source / as per
requirement

Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-10

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.10. Test Plan for CC/RCC Pipes and Collars


RCM/TP 10
Name of Work:
Agreement No.:
Sl.
No.
1.

Test/Parameter

Estimated Cost:
Sanction No. and date:
Sampling Criteria

Acceptance Criteria

Classification

Acceptance / Performance
Standard
MOSRTH 10/ IS 458

Each Lot

Conformance

2.

Dimensional Check

IS 458

Each Lot

Conformance

3.

Visual Inspection

IS 458

Each Lot

Conformance

4.

Strength

IS 458

Each Lot

Conformance

Note : Additional tests may be carried out whenever there is any change of source or in case of any disputes

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-11

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.11. Test Plan for A.C. Pipes


RCM/TP 11
Name of Work:
Agreement No.:
Sl.
No.
1.

Test/Parameter

2.

Estimated Cost:
Sanction No. and date:
Sampling Criteria

Acceptance Criteria

Visual Inspection

Acceptance / Performance
Standard
MOSRTH 2706

Each lot

Conformance

Hydraulic Check

MOSRTH 2706

Each lot

Conformance

Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-12

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.12. Test Plan for CC/RCC Pipes and Collars


RCM/TP 12
Name of Work:
Agreement No.:
Sl.
No.
1.

Test/Parameter

Estimated Cost:
Sanction No. and date:
Sampling Criteria

Ordinary Paint

Acceptance / Performance
Standard
IS 164

Acceptance Criteria

(a)

Normal physical tests.

IS 164 MOSRTH 803.3

One/ batch/lot

Conformance to spec.

2.

Hot applied thermoplastic paint.

IS 164

One/ batch/lot

Conformance to spec.

(a)

Normal physical test.

One/ batch/lot

Conformance to spec.

3.

Reflectors paint

ASTM-D-36/BS 3262 Part-1


MOSRTH 803.4
MOSRTH

One/ batch/lot

Conformance to spec.

4.

Gradation.

MOSRTH 803.4.3

One/ batch/lot

Conformance to spec.

5.

Roundness

MOSRTH 803.4.3

One/ batch/lot

Conformance to spec.

6.

Refractive index

MOSRTH 803.4.3

One/ batch/lot

Conformance to spec.

7.

Free flowing properties

MOSRTH 803.4.3

One/ batch/lot

Conformance to spec.

One/ batch/lot

Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-13

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.13. Test Plan for CC/RCC Pipes and Collars


RCM/TP 13
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Test/Parameter
No.
1.
Concrete

Acceptance Standard

Sampling Criteria

Acceptance Criteria

IS 456

As per IS

Conformance to IS

2.

Reinforcing steel

IS 1786

As per IS

Conformance to IS

3.

Bolts, nuts, washers

IS 1367

As per IS

Conformance to IS

(a)

High strength bolts

IS 1367

As per IS

Conformance to IS

(b)

Precision bolts nuts

IS 1364

As per IS

Conformance to IS

4.

Plates and supports

IS 2062

As per IS

Conformance to IS

(a)

Plates

IS 2062

As per IS

Conformance to IS

(b)

Supports

IS 2062

As per IS

Conformance to IS

5.

Aluminum sheets

As per IS

Conformance to IS

6.

Retro reflective sheets.

Designation 24345 or 1900 of


IS 736
MOSRTH 801.3

As per IS

Conformance to IS

7.

Massage borders

Layout check MOSRTH


801.3.4

As per IS

Conformance to IS

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-14

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.14. Test Plan for Road Furniture


RCM/TP 14
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl.
No.
1.

Test/Parameter

Acceptance Standard

Sampling Criteria

Acceptance Criteria

200 Metre Stones.

IRCM-26 MOSRTH-804

As per Standard

Conformance

2.

Kilometre Stones.

IRCM-8 MOSRTH-804

As per Standard

Conformance

3.

Road Delineators.

IRCM-79 MOSRTH-805

As per Standard

Conformance

4.

Boundary Stones.

IRCM-25 MOSRTH-800

As per Standard

Conformance

5.

Fencing.

As per Standard

Conformance

6.

Tubular Steel railing.

IS226 and Drawing


MOSRTH-807
IS1239 MOSRTH-804

As per Standard

Conformance

7.

Metal beam crash barriers.

MOSRTH 810

As per Standard

Conformance

8.

Road traffic signals.

IRCM-93 IS7537
MOSRTH 11-811

As per Standard

Conformance

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-15

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.15. Test Plan for Geo Synthetics

Synthetic Material: Geo Textile, Geo Grid, Geo net, Geo membrane, Geo Composite.
RCM/TP 15
Name of Work:
Agreement No.:
Sl.
No.
1.
2.

Estimated Cost:
Sanction No. and date:

Test/Parameter

Acceptance Standard

Sampling Criteria

Acceptance Criteria

Pre-qualification

MORT and H 700

As per Standard

Conformance

As per Standard

Conformance

3.

Physical / Mechanical properties,


colour, form, and other properties.
Geo systems.

MORT and H 701.2.1

As per Standard

Conformance

4.

Geo grid.

MORT and H 701.2.2

As per Standard

Conformance

5.

Geo net.

MORT and H 701.2.3

As per Standard

Conformance

6.

Geo membrane.

MORT and H 701.2.4

As per Standard

Conformance

7.

Geo composite.

MORT and H 701.2.5

As per Standard

Conformance

Note: Additional tests may be carried out whenever there is any change of source or in case of any disputes.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-16

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.16. Checklist for General Inspection of Site


RCM/CL 01
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item
2.
Pre execution checks have been completed
date and reference.
3.
The site office, laboratory, godown and
labour camp are maintained in good
conditions.
4.
The first aid box is having with all the
necessary medicines.
5.
The furniture and equipments in site office
and laboratory are maintained in good
condition.
6.
The machinerys provided in laboratory are
maintained properly in good conditions.
7.
Insurance of technical staff, supervisory staff
and labour is updated.
8.
Approved copy of tender, plans and work
order book is available and maintained in
good condition.
9.
Various Performa required for testing of
materials are available on site and are being
filled up regularly.
10. There is no stagnation of wastewater.
11. Adequate traffic safety arrangement up to
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-17

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
date.
12. Labour registers are maintained up to date.
13. CAR insurance policy is updated.
14. Additional observation if any:
15. Conclusion by inspecting officer:The execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. ..
If not satisfactory the contractors to report
the corrective action taken and inform for the
re-inspection.
16. Contractor / Authorized representative
name:
Designation and Signature.
17. Inspecting Officer Name
Designation and Signature

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-18

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.17. Checklist for Calibration of Inspection, Measuring and Test Equipment


RCM/CL 02
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
All Surveying and Measuring Instruments
are uniquely identified.
3.
All Sand M Instruments are calibrated.
4.
All S and M instrument calibrations have
tractability to national standard.
5.
Range,
accuracy,
correction,
factor,
acceptance criteria, user details of all S and
M instruments have been recorded.
6.
Due dates of next calibration have been
identified and recorded on labels.
7.
Additional observations if any.
8.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reinspection.
9.
Contractor / authorized representative name,
designation, signature.
10. Inspecting officer, name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-19

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.18. Checklist for Surveying and Setting Out


RCM/CL 03
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
The leveling instrument like dumpy levels /
theodolites etc, are calibrated (refer
calibration status of the instrument).
3.
The instruments and tripod are in good
working condition (visual inspection).
4.
Required numbers of ranging roads and
wooden
pegs
are
available
(refer
requirement submitted by JE).
5.
Required quantity of cord, lime, paint etc,, is
available for marking lettering etc,.. (refer
requirement submitted by JE).
6.
Steel tapes of length 30 m and 15m are
available in good condition, (visual
inspection).
7.
Required quantity of red flags, traffic, cones
etc,. are prepared for traffic safety (refer
requirement submitted by JE/AE).
8.
Adequate trained labours are available.
9.
Level books, field books are available on
site (refer requirement submitted by JE/AE).
10. Minimum two aluminum leveling staffs are
available.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-20

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
11. Benchmark is established at required
intervals with respect to GTS benchmark.
12. The benchmarks are established on
permanent structures or built up in masonry
etc,. so that the same are available in good
condition till finalization of work.
13. Additional observation if any.
14. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reinspection.
15. Contractor / authorized representative name,
designation, signature.
16. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-21

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.19. Checklist for Surveying and Setting Out


RCM/CL 04
Name of Work:
Agreement No.:
Sl.
No.

Location and Ref, of GTs


Bench of work

Estimated Cost:
Sanction No. and date:
Value of GTS Bench Mark

Location and Ref, of


permanent bench mark
on site with sketch

Signature of Junior Engineer

Value of permanent
bench mark on site

Remarks

Signature of Deputy Engineer

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-22

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.20. Checklist for Publicity Utility Services


RCM/CL 05
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
The execution check share completed date
and reference.
3.
Representative
of
concerned
utilities
services is present during extension of work.
4.
Proper case is taken during excavation.
5.
If there is any damage for utility service, the
same is informed to the concerned authority.
6.
Additional observation if any.
7.
Conclusion by inspecting officer
The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
8.
Contractor / authorized representative name,
designation, signature.
9.
Inspecting officer, name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-23

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.21. Checklist for Curst Design Of Flexible Pavement


RCM/CL 06
Name of Work:
Agreement No.:
Sl. Location of
No. Sample collected
with date
1

Estimated Cost:
Sanction No. and date:
Ref. and Date of
sending sample for
testing

Name of
laboratory

Results of CBR value


Soaked

Unsoaked

Ref and Date of


receipt of results
7

Remarks

Signature of the JE/SO

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-24

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.22. Checklist for Excavation For Road Work (Utility related)


RCM/CL 07
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Name of utility Name of concerned Location


and Whether shifting / If yes, date Date of shifting / Remarks
No. services
department
references
removal required and ref made removal
yes / no
to concerned
department
1

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-25

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.23. Checklist for Excavation for Road Work (Tree related)


RCM/CL 08
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Location
of No. of affected trees
No. trees Chainage
to Chainage

Date and Ref Date of joint Date of receipt Completion date Remarks
intimation
to inspection with of approval of of
removal
/
tree authority
tree authority
tree authority
shifting of trees

Signature of Junior Engineer

Signature of Asst. Engineer

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-26

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.24. Checklist for Excavation for Road Work


RCM/CL 09
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
The execution inspection checks have been
completed - date and reference.
3.
The
traffic
diversion
and
safety
arrangements have been made as per the
approved plan.
(Refer traffic diversion plan).
4.
Equipment as verified in The execution
check are available in good working
condition.
5.
Required depth of excavation is achieved as
per cross-sections.
(Refer cross section).
6.
Camber, profile and gradient is maintained
as per approved drawing
7.
Usable material is stacked at specified
dumping location.
8.
Usable material is tested and approved as
per test plan no
If yes, date and reference.
9.
Care is taken to see that no portion of
existing pavement designated for retention is
loosened or disturbed.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-27

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. All utilities / trees / poles / drains / sewers
etc,. found during excavation are protected.
11. The finalized sub grade is protected from
movement of vehicular traffic and conforms
to approved c-section and l-sections.
12. The final levels of excavation are taken with
reference to GTS.
Field Book No. Page No:
13. The supervision of contractors is adequate
(refer QA Plan).
14. Additional observation if any:
15. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
16. Contractor / authorized representative name,
designation, signature.
17. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-28

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.25. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 10
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / Chainage / Description of item.
2.
Site is clean (visual inspection).
3.
Line out is approved
If yes, date of approval ..
4.
Initial ground levels are taken with reference
to GTS and recorded in field book.
If yes, Filed Book No:
Page No:
5.
Ground is leveled and compacted to
facilitate the first layer of earthwork (visual
inspection).
6.
7.
8.

9.

/ / 200

/ / 200

Limits of embankment / sub grade are


marked by fixing battered pegs at regular
interval (visual inspection).
Foundation embankment is in an area with
stagnant water.
If yes, water is removed (visual inspection).
Material to be used for the earth work is
tested and approved as per test plan
no
If, yes, date and reference.
Height of embankment (value)

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-29

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. If height less than 3.0m minimum dry unit
weight is 15.2 kN/Cum when tested as per
IS 2720 (Part-8)
11. Earthwork is required for sub grade / earth
side shoulders / verges / back fill if yes, then
dry unit weight.
(should be minimum 17.5 kN/Cum. When
tested as per IS2720 (Part-8)]
12. Borrowed material tested and proved if yes,
date and reference.
(test report shall be received 7 days before
the date of commencement).
13.
14.
15.
16.
17.

/ / 200

/ / 200

Required quantum of material is available at


source. (Quarry inspection) site.
Required numbers of labourers and workers
are available on site.
Adequate equipment are available and are
in good working condition.
(visual inspection)
Contractors supervisory staff and labours
are adequate
(refer QA Plan)
Traffic diversion plan have been prepared
and got approved from traffic authority. If
yes, date and reference

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-30

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
18. Adequate traffic safety devices are procured
as per traffic safety plan approved by
engineer-in-charge
(refer approved traffic safety plan)
19. Trees / utility services etc, are removed /
shifted.
20.
21.

22.
23.

/ / 200

/ / 200

Additional observation if any.


Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
Contractor / authorized representative name,
designation, signature.
Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-31

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.26. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 11
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks have been
completed date and reference.
3.
Graph of density against moisture content
submitted by contractor (refer graph).
4.
Relationship between density moisture
content and C.B.R. for light / heavy
compactive efforts submitted by contractors.
5.
Laying of embankment material is in uniform
thickness of 300 mm over entire width of
embankment.
6.
7.
8.
9.

/ / 200

/ / 200

Earthwork laid is as per specified grade and


camber.
Refer field book no.. Page no.
The moisture content is as per IS2720
(Part-2) at the site of placement prior to
compaction
The static weight of vibratory roller used for
compaction is within 80 to 100 KN (refer
weigh bridge challan).
The each layer thoroughly compacted to
achieve least 95% of PD (refer EWF-2).

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-32

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. The field density least are carried out as per
IS2720 (Part 28) (should be at least 95%
PD).
11. The cross fall of surface of the embankment
/ sub-grade is maintained as specified (Refer
approved C/S and L/S).
12. Traffic safety arrangements have been
made and maintained in good conditions.
(Refer approved traffic diversion plan).
13. Contractors supervision is adequate. (Refer
QA Plan).
14. Contractors supervision is adequate.
15. Additional observation if any.
16. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
17. Contractor / authorized representative name,
designation, signature.
18. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-33

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.27. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 12
Name of Work:
Agreement No.:
Sl.
No.
1

Particulars of
Item
2

Estimated Cost:
Sanction No. and date:
Location

Layer

Compacted thickness at every 30 m


Edge
Center
Edge
5
6
7

Signature of -Contractor

Type of roller
and weight
8

No. of
passes
9

Remarks
10

Signature of Engineer

No of passes required shall be decided by the Engineer-in-charge after ascertaining the required field density.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-34

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.28. Checklist for 95% PD Earth Work (To be Completed for each Layer)
RCM/CL 13
Name of Work:
Agreement No.:
Sl.
No.

Particulars
of Item

Estimated Cost:
Sanction No. and date:
Location
/ layer of
test

Moisture content
test (2720 Part 2)

Field content test


(IS2720 Part 28)

CBR Test (IS2720 (Part 6)

Quantum
Executed

Quantum
Executed

Quantum
Executed

Value

Value

Value
Soaked

Un-marked

10

Signature of Contractor

Results
acceptable
/ not
acceptable

Remarks

11

12

Signature of Engineer

*One test per 250 Cum. of work ** One test per 1000 Sq.m. of work ***One test per 3000 Cum. of work.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-35

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.29. Checklist for 100% PD Earth Work


RCM/CL 14
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks have been
completed date and reference.
3.
Graph of density against moisture content
submitted by contractor (refer graph).
4.
Relationship between density moisture
content and C.B.R. for light / heavy
compactive efforts submitted by contractors.
5.
Laying of embankment material is in uniform
thickness of 300 mm over entire width of
embankment.
6.
Earthwork laid is as per specified grade and
camber.
Refer field book no.. page no.
7.
The moisture content is as per IS2720
(Part-2) at the site of placement prior to
compaction
8.
The static weight of vibratory roller used for
compaction is within 80 to 100 KN (refer
weigh bridge challan).
9.
The each layer thoroughly compacted to
achieve least 95% of PD
10. The field density least are carried out as per
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-36

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
IS2720 (Part 28) (should be at least 95%
PD).
11. The cross fall of surface of the embankment
/ sub-grade is maintained as specified (refer
approved C/S and L/S).
12. Traffic safety arrangements have been
made and maintained in good conditions.
(refer approved traffic diversion plan)
13. Contractors supervision is adequate. (Refer
QA Plan).
14. Additional observation if any.
15. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for rre-inspection.
16. Contractor / authorized representative name,
designation, signature.
17. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-37

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.30. Checklist for Hard Murrum for Side Shoulder


RCM/CL 15
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre execution inspection checks are
completed date and reference.
3.
Adequate safety devices are provided.
4.
Spreading of hard murum is done as per
clause 305.3.5.1. of MOSRTH5.
Compaction is carried out as per the clause
305.3.6. of MOSRTH.
6.
Necessary surface drawing arrangement is
provided The execution.
7.
The finishing operations are carried out as
per the clause of 305.3.9 of MOSRTH.
8.
Additional observations if any.
9.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
10. Contractor / authorized representative name,
designation, signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-38

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.31. Checklist for Granular Sub Base


RCM/CL 16
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre execution inspection checks have been
completed date and reference.
3.
Mixing any ingredients of GSB is done as
per MOSRTH clause 401.2.1.
4.
Is there any deficiency of moisture in mix?
(refer from GSBF)
If Yes, additional water sprinkled.
5.
The static weight of vibratory roller used for
compaction is within 80 to 100 KN when
thickness exceeds 100 mm (refer weigh
bridges challan).
6.
Rolling being done from lower edges
forwards upper edges.
(Visual inspection).
7.
The field density tested as per IS 2720
(should be 98% of dry density) refer form
GSBF).
8.
Traffic safety arrangements have been
made and maintained in good condition
(refer approved traffic diversion plan).
9.
Contractors supervision adequate (refer QA
Plan).
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-39

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. Final grade and camber of the GSB layer is
as per approved C/S and L/S (refer field
book no page no.).
11. Additional observations if any.
12. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
13. Contractor / authorized representative name,
designation, signature.
14. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-40

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.32. Checklist for Water Bound Macadam (Gr.1) In Layers


RCM/CL 17
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference..
3.
The grade-1 metal is uniformly spread on
prepared sub-grade / sub-base to proper
profiles by using template placed across the
road at 6m apart
4.
The grade-1 metal laid is of required
thickness to get compacted layer of 0.115m
after compaction.
5.
The segregation of metal is controlled while
spreading to avoid any pocket of the
material.
6.
The rolling is done with vibratory roller of 80
to 100 kN static weight.
(Refer weigh bridge challan and form)
7.
Rolling is done from lower edges towards
Centro and from inner edge to the outer
edges for super elevation portion.
8.
Polled surface is checked transversely and
longitudinally with templates.
9.
The shoulders are built up simultaneously
along with WBM
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-41

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. The surface is applied over rolled surface in
dry condition.
11. Dry rolling is done after application of
screenings.
12. Brooming and spreading is done during dry
rolling till all the voids are filled.
13. The water is sprinkled, swept and rolled after
dry rolling.
14. The sprinkling, sweeping and rolling
operation is continued till the coarse
aggregate are thoroughly keyed, well
bonded and firmly set in its full depth.
15. After final compaction the surface is allowed
to dry over night.
16. The hungry spots are filled with screening
after next day.
17. Adequate machinery and equipment are
available on site.
(refer QA Plan)
18. Adequate traffic safety arrangements are
provided.
(refer approved traffic safety
diversion plan).
19. Required field tests namely, aggregate
impact value, grading, flakiness index and
elongation index, Atterberg limit of binding
materials have been taken and record
maintained in the form WBMF-2.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-42

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reinspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-43

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.33. Checklist for Water Bound Macadam (Gr.II) In Layers


RCM/CL 18
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference..
3.
The grade-II metal is uniformly spread on
prepared sub-grade / sub-base to proper
profiles by using template placed across the
road at 6m apart.
4.
The grade-II metal laid is of required
thickness to get compacted layer of 0.115m
after compaction.
5.
The segregation of metal is controlled while
spreading to avoid any pocket of the
material.
6.
The rolling is done with vibratory roller of 80
to 100 kN static weight.
(refer weigh bridge challan and form )
7.
Rolling is done from lower edges towards
Centro and from inner edge to the outer
edges for super elevation portion.
8.
Polled surface is checked transversely and
longitudinally with templates.
9.
The shoulders are built up simultaneously
along with WBM
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-44

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. The surface is applied over rolled surface in
dry condition.
11. Dry rolling is done after application of
screenings.
12. Brooming and spreading is done during dry
rolling till all the voids are filled.
13. The water is sprinkled, swept and rolled after
dry rolling.
14. The sprinkling, sweeping and rolling
operation is continued till the coarse
aggregate are thoroughly keyed, well
bonded and firmly set in its full depth.
15. After final compaction the surface is allowed
to dry over night.
16. The hungry spots are filled with screening
after next day.
17. Adequate machinery and equipment are
available on site.
(refer QA Plan)
18. Adequate traffic safety arrangements are
provided. (Refer approved traffic safety
diversion plan).
19. Required field tests for, aggregate impact
value, grading, flakiness index and
elongation index, Atterberg limit of binding
materials have been taken and record
maintained.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-45

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-46

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.34. Checklist for Water Bound Macadam (Gr.III) In Layers


RCM/CL 19
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference..
3.
The grade-III metal is uniformly spread on
prepared sub-grade / sub-base to proper
profiles by using template placed across the
road @ 6M apart (refer WBMF-1)
4.
The grade-III metal laid is of required
thickness to get compacted layer of 0.115m
after compaction.
5.
The segregation of metal is controlled while
spreading to avoid any pocket of the
material.
6.
The rolling is done with vibratory roller of 80
to 100 KN static weight.
(refer weigh bridge challan and form WBMF1)
7.
Rolling is done from lower edges towards
Centro and from inner edge to the outer
edges for super elevation portion.
8.

/ / 200

/ / 200

Polled surface is checked transversely and


longitudinally with templates.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-47

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
9.
The shoulders are built up simultaneously
along with WBM
10. The surface is applied over rolled surface in
dry condition.
11. Dry rolling is done after application of
screenings.
12. Brooming and spreading is done during dry
rolling till all the voids are filled.
13. The water is sprinkled, swept and rolled after
dry rolling.
14. The sprinkling, sweeping and rolling
operation is continued till the coarse
aggregate are thoroughly keyed, well
bonded and firmly set in its full depth.
15. After final compaction the surface is allowed
to dry over night.
16. The spots are filled with screening after next
day.
17. Adequate machinery and equipment are
available on site.
(refer QA Plan)
18. Adequate traffic safety arrangements are
provided.
(refer approved traffic safety
diversion plan).
19. Required field tests for aggregate impact
value, grading, flakiness index and
elongation index, atterberg limit of binding
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-48

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
materials have been taken and record
maintained.
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-49

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.35. Checklist for Road Side Gutter in Cement Concrete


RCM/CL 20
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre execution activities are complete date
and reference.
3.
Adequate safety arrangements is provided
on site.
4.
Excavation is done as per the approved
drawing.
5.
Excavated material is stacked properly or
disposed of as directed by Engineer incharge
6.
Bed level are taken after excavation and
approved by engineer-in-charge.
If yes, date and reference.
7.
Sand and boulder filling is done in
foundation as per approval drawing.
8.
Sand and boulder filling is well compacted
normally or by any other approved method.
9.
Top level of Sand and boulder filling is taken
for verification .If yes, date and reference.
10. Mixing of bed concrete is done for grade of
concrete specified in agreement.
11. The bed concrete is well completed by plate
vibrator / manually.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-50

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
12. Top levels bed concrete is taken if yes, date
and reference.
13. Proper curing of bed concrete is done for
required period.
14. Concrete for foundation is checked
15. Centring for walls and gutter is approved by
engineer-in-charge.
If yes, date and reference.
16. Top level of wall is marked on centering if
yes, date and reference.
17. Mixing of concrete for walls of gutter is of
grade specified in concrete.
18. Concrete for walls of gutter is checked as
per test plan no:
If yes, Date and reference.
19. Ghani register is maintained for concrete
work, if yes, date and reference.
20. Cement consumption register is maintained
for concrete work. If yes date and reference.
21. Mixer operating register for duration of
mixing of maintained.
22. Concrete laying is not done for more than
60 Cubic Meter at a time.
23. Proper bonding is provided between
subsequent lift of walls.
24. AC Pressure relief pipe use at interval
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-51

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
specified in agreement / drawing or as
directed by engineer-in-charge.
25. Additional observations, if any.
26. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
27. Contractor / authorized representative name,
designation, signature.
28. Inspecting Officer, name,
Designation and Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-52

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.36. Checklist for Tack Coat


RCM/CL 21
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre-extension checks have been completed
date and reference.
3.
The spraying temperature of bituminous
emulsion is in the range of 20 Degree to 60
Degree.
4.
Binder is applied with self propelled or towed
bitumen pressure sprayer with self-heating
arrangements.
5.
The rate of application of binder is
maintained as per Table 500.2:MOSRTH/or as specified on the item of
tender.
6.
The application of binder quantity is as
specified. In tender (to be ascertained by
weighing it).
7.
Contractors supervision is adequate.
8.
Adequate safety measures have bee taken.
9.
Additional observations if any.
10. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-53

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
11. Contractor / authorized representative name,
designation, signature.
12. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-54

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.37. Checklist for Bitumen Bound Macadam


RCM/CL 22
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Receiving
surface
is
clean
(visual
inspection).
3.
The 40mm size metal is uniformly spread.
4.
Tack coat at 50Kg / 100 sq.m applied the
surface.
5.
The metal laid is of required thickness to get
compacted layer of 0.075 m after
compacted.
6.
The 20mm key aggregates shall evenly
spread at the rate of 1.50 m3 / 100m2.
7.
The segregation of avoid any pocket of fine
material.
8.
The rolling is done with vibratory roller of so
to 100KN state weight.
9.
Rolling is done from lower edges to censer
and from inner edges to the outer edges for
super-elevation portion.
10. Bitumen of IS Grade S-35 having 30/40 or
S-65 having 60/70 penetration heated to
through a pressure sprayed (browzer)
uniformly at the rate of 250 Kg / 100m2.
11. 12mm chips are uniformly spread over the
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-55

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
surface as blindage at the rate of 1.80 m 3 /
100m2 and are broomed immediately to
ensure uniform thicken.
12. The surface is again rolled to obtain full
compaction and the farce the blindage chips
in to the interstices of course aggregate.
13. The
contractor
provides
adequate
supervisory staff.
14. Adequate safety measures are taken The
execution of work.
15. Additional observation if any.
16. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
17. Contractor / authorized representative name,
designation, signature.
18. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-56

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.38. Checklist for Surface Dressing


RCM/CL 23
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Per execution check carried out date and
reference.
3.
Stone chipping is spread uniformly as per
MOSRTH table 500.13. requirement.
4.
Bitumen is sprayed uniformly as per
MOSRTH table 500.13 requirement.
5.
Rolling is done as per MOSRTH 1995
clause No. 508.1.3.5.
6.
Adequate supervisory and technical staff are
employed by the contractor.
7.
Additional observations, if any.
8.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
9.
Contractor / authorized representative name,
designation, signature.
10. Inspecting officer, name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-57

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.39. Checklist for Surface Dressing


RCM/CL 24
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
The temperature of bitumen is 150 degree to
163 degree.
4.
Adequate traffic safety devices are provided.
5.
The bitumen is spread as per the clause
508.1.3.3. of MOSRTH-1995.
6.
The stone chipping / aggregate is spread as
per the clause 512.2.2. of MOSRTH-1995.
7.
Rolling is carried out by 80-100 KN smooth
wheeled wheel roller or 80-100 KN static
weight vibratory roller.
8.
Rolling is commenced at edge and progress
towards the top.
9.
Supervision of contractor is adequate.
10. All test on materials required to be carried
out as per test plans If yes, date and
reference.
11. Additional observation, if any.
12. Conclusion by inspecting officer The
execution activities are satisfactory / not
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-58

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
13. Contractor / authorized representative name,
designation, signature.
14. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-59

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.40. Checklist for Bitumen Macadam


RCM/CL 25
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Tack coat is properly sprayed as required to
the surface where B.M. is to be laid. If yes
date and reference of checklist for tack coat.
3.
Equipments as verified in The execution
check are available in good working
condition.
4.
The mix is prepared in drum mix plant or any
other specified item.
5.

6.

/ / 200

/ / 200

The temperature of binder and aggregate is


maintained in the range between 150 to 163
degree and 155 to 163 degree respectively
at the time of mixing
The discharge temperature of mix is in
between 130 to 160 degree.

7.

The tipper / dumper is properly covered with


tarpaulin to avoid fall in temperature during
transport.

8.

The temperature of mix at the time of laying


is in between 120 to 160 degree

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-60

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
9.
The mix is tested for
Bitumen content.
Gradatiion..
10. Proper offsets have been provided in
longitudinal joints of each layer)
11.
12.
13.

14.
15.
16.
17.
18.

/ / 200

/ / 200

The initial or intermediate rolling is followed


by vibratory roller of 80 to 100 KN capacity.
.
The final rolling is done by 60 to 80 KN
tandem roller or by switching off vibratory
system.
The rolling is continued till the entire surface
has been rolled by 95% of average
laboratory density.
The surface finish of the construction
conforms to requirements of clause 02 of
MOSRTH 1995 (refer QA Plan).
The rolling is done as per clause 507.4.6. of
MOSRTH 1995 - (refer QA Plan).
The final levels are taken with reference to
GTS.
Adequate traffic safety arrangements are
provided (refer QA Plan).
The supervision of contractor is adequate
(refer QA Plan).

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-61

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
19. Additional observation if any.
20. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
21. Contractor / authorized representative name,
designation, signature.
22. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-62

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.41. Checklist for Bitumen Macadam


RCM/CL 26
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl.
No.

Date
and
Time

Vehicle
No.

Type of
Mix

Agg.
Impact
value

Flakiness
index
value

Elongation
index value

Signature of the Contractor

Grading of aggregate
(Two tests per day per plant)
Metal-1 Metal-2 Combined

10

Bitumen
content

Grade of
bitumen

Remarks

11

12

13

Signature of Junior Engineer

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-63

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.42. Checklist for Bitumen Macadam


RCM/CL 27
Name of Work:
Agreement No.:
Sl.
No.

Date

Estimated Cost:
Sanction No. and date:

Location Ch.
.to Ch /
Site / Layer
No.

Lane no /
width

Time

Vehicle

Weight
Gross Tear

Net

Temp. at
time of
laying

10

Signature of the Contractor

Passes of
Initial
or Final rolling
intermediate
by 60-80KN
rolling
by Static roller
100KN
vibratory roller

11

12

Remarks

13

Signature of Junior Engineer/AE

Note: Achievement of required density. shall be ascertained by Engineer-in-charge

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-64

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.43. Checklist for Bitumen Macadam


RCM/CL 28
Name of Work:
Agreement No.:
Sl.
No.

Date

Location
Ch to
Ch./
Side
3

Estimated Cost:
Sanction No. and date:
Line No/
width

Time

Vech.
No

Temp. at
time of
laying

Signature of the Contractor

Bitumen
content (one
test per day on
site)
8

Rate of spread
weight of BM
Area
9

Field density
(one test per
500 Sqmt.
Area)
10

ThickNess
of spread =
Density rate
of spread
11

Remarks

12

Signature of Junior Engineer

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-65

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.44. Checklist for Mix Seal Surface


RCM/CL 29
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution check carried out date and
reference.
3.
Tack coat is anticorrosive applied uniformly
anticorrosive the rate specified in the
agreement.
4.
Mix is spread uniformly with paver.
5.
The thickness is as per requirements.
6.
The rolling is done with static roller followed
by vibratory roller.
7.
The rolling is done from lower edge to higher
edge and from miner edge to outer edge for
super elevation portion.
8.
Adequate supervisory / technical staff is
provided by the contractor.
9.
Additional observation if any.
10. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for reProcedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-66

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
inspection.
11. Contractor / authorized representative name,
designation, signature.
12. Inspecting officer,
Name.
Designation and Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-67

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.45. Checklist for Pre-Mix Carpet


RCM/CL 30
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed, date and reference.
3.
The temperature of bitumen is 130 degree to
160 degree.
4.
Tack coat is applied uniformly at the rate
specified in tender.
5.
Tack coat is applied of binder used for tack
coat is as per clause 503.3.2.
6.
The mix is tested as per the table no. 500.16
of MOSRTH .
7.
Adequate safety measures are provided The
execution.
8.
The mix is spread in uniform thickness
specified in tender.
9.
Rolling is done by 80-100 KN roller smooth
wheel tandem type.
10. Rolling is begun from lower edge to upper
edge.
11. Surface finish of the construction conforms
to requirement of clause 902 of MOSRTH.
12. The seal coat is applied as per clause 513 of
MOSRTH.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-68

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
13. Additional observation if any.
14. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
15. Contractor / authorized representative name,
designation, signature.
16. Inspecting officer, Name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-69

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.46. Checklist for Dense Bituminous Macadam


RCM/CL 31
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Tack coat is properly sprayed as required to
the surface where BM is to be laid. If yes
date and reference of checklist for tack coat.
4.
Equipment are available in good working
condition.
5.
The mix is prepared in drum mix plant or any
other specified item.
6.

7.

/ / 200

/ / 200

The temperature of binder and aggregate is


maintained in the range between 150 to 163
degree and 155 to 163 degree respectively
at the time of mixing
The discharge temperature of mix is in
between 130 to 160 degree.

8.

The tipper / dumper is properly covered with


tarpaulin to avoid fall in temperature during
transport.

9.

The temperature of mix at the time of laying

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-70

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
No.
Date
is in between 120 to 160 degree
10. The mix is tested for Bitumen content.
Gradation.

Remarks (Y / N / NA / Observation if any)


/ / 200

11.

Proper offsets have been provided in


longitudinal joints of each layer).

12.

The initial or intermediate rolling is followed


by vibratory roller of 80 to 100 kN capacity.

13.

The final rolling is done by 60 to 80 kN


tandem roller or by switching off vibratory
system.
The rolling is continued till the entire surface
has been rolled by 95% of average
laboratory density.

14.

15.
16.
17.
18.

/ / 200

/ / 200

/ / 200

/ / 200

/ / 200

The surface finish of the construction


conforms to requirements of clause 02 of
MOSRTH - (refer QA Plan).
The rolling is done as per clause 507.4.6. of
MOSRTH - (refer QA Plan).
The final levels are taken with reference to
GTS.
Adequate traffic safety arrangements are
provided (refer QA Plan).

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-71

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
19. The supervision of contractor is adequate
(refer QA Plan).
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-72

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.47. Checklist for Dense Bituminous Macadam


RCM/CL 32
Name of Work:
Estimated Cost:
Agreement No.:
Sanction No. and date:
Sl.No. Particulars
Remarks (Y / N / NA / Observation if any)
Date
/ / 200
/ / 200 / / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
One set of three Marshall specimen samples
of DBM collected at random for verifying
stability of mix.
If Yes,
Dumper No.
Date: Time:
3.
The samples are sealed, labeled and signed in
presence of contractor
If yes, details
4.
The samples are sent to the laboratory
If Yes,
Name of Laboratory.
Date and Ref..
5.
Additional observations, if any.
6.
Conclusion by inspecting officer The execution
activities are satisfactory / not satisfactory. If
satisfactory, further road construction activity
to commence by.. .
If not satisfactory, the contractors to report the
corrective action taken and inform for the reinspection.
7.
Contractor / authorized representative name,
designation, signature.
8.
Inspecting officer, name, Designation and
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

Issue 01, Rev 00


Page No.: RC/7-73

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:
Sl.No. Particulars
Date
Signature.

Estimated Cost:
Sanction No. and date:
Remarks (Y / N / NA / Observation if any)
/ / 200
/ / 200 / / 200
/ / 200
/ / 200

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

Issue 01, Rev 00


Page No.: RC/7-74

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.48. Checklist for Asphaltic Concrete


RCM/CL 33
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Tack coat is properly sprayed as required to
the surface where B.M. is to be laid. If yes
date and reference of checklist for tack coat.
4.
Equipment as verified during execution
check are available in good working
condition.
5.
The mix is prepared in drum mix plant or any
other specified item.
6.

7.
8.

9.

/ / 200

/ / 200

The temperature of binder and aggregate is


maintained in the range between 150 to 163
degree and 155 to 163 degree respectively
at the time of mixing
The discharge temperature of mix is
between 130 to 160 degree.
The tipper / dumper is properly covered with
tarpaulin to avoid fall in temperature during
transport.
(
The temperature of mix at the time of laying

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-75

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
is in between 120 to 160 degree
10. The mix is tested for
Bitumen content.
Gradation..
11. Proper offsets have been provided in
longitudinal joints of each layer)
12. The initial or intermediate rolling is followed
by vibratory roller of 80 to 100 KN capacity.
13.
14.

15.
16.
17.
18.
19.

/ / 200

/ / 200

The final rolling is done by 60 to 80 KN


tandem roller or by switching off vibratory
system.
The rolling is continued till the entire surface
has been rolled by 95% of average
laboratory density.
The surface finish of the construction
conforms to requirements of clause 02 of
MOSRTH (refer QA Plan)
The rolling is done as per clause 507.4.6. of
MOSRTH - (refer QA Plan)
The final levels are taken with reference to
GTS. .
Adequate traffic safety arrangements are
provided (refer QA Plan).
The supervision of contractor is adequate
(refer QA Plan).

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-76

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
20. Additional observation if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-77

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.49. Checklist for Asphaltic Concrete


RCM/CL 34
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Random one set of three Marshall specimen
sample of DBM is collected for verifying
stability of mix.
If Yes,
Dumper No.
Date: Time:
3.
The samples are sealed, labeled and signed
in presence of contractor
If yes, details
4.

5.
6.

/ / 200

/ / 200

The samples are send to the laboratory


If Yes,
Name of Laboratory.
Date and Ref..
Additional observations if any.
Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-78

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
re-inspection.
7.
Contractor / authorized representative name,
designation, signature.
8.
Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-79

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.50. Checklist for Mastic Concrete


RCM/CL 35
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Tack coat is properly sprayed as required to
the surface where BM is to be laid. If yes,
date and reference of checklist for tack coat.
4.
Equipment as verified in The execution
check are available in good working
condition.
5.
The mix is prepared in drum mix plant or any
other specified item..
6.
The temperature of binder and aggregate is
maintained in the range between 150 to 163
degree and 155 to 163 degree respectively
at the time of mixing
7.
The discharge temperature of mix is in
between 130 to 160 degree.
8.

The tipper / dumper is properly covered with


tarpaulin to avoid fall in temperature during
transport.

9.

The temperature of mix at the time of laying

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-80

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
No.
Date
is in between 120 to 160 degree
10. The mix is tested for
Bitumen content.
Gradation

Remarks (Y / N / NA / Observation if any)


/ / 200

11.

Proper offsets have been provided in


longitudinal joints of each layer)

12.

The initial or intermediate rolling is followed


by vibratory roller of 80 to 100 KN capacity.

13.

The final rolling is done by 60 to 80 KN


tandem roller or by switching off vibratory
system.
The rolling is continued till the entire surface
has been rolled by 95% of average
laboratory density.

14.

15.
16.
17.

/ / 200

/ / 200

/ / 200

/ / 200

/ / 200

The surface finish of the construction


conforms to requirements of clause 02 of
MOSRTH - (refer QA Plan)
The rolling is done as per clause 507.4.6. of
MOSRTH - (refer QA Plan)
The final levels are taken with reference to
GTS.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-81

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
18. Adequate traffic safety arrangements are
provided (refer QA Plan)
19. The supervision of contractor is adequate
(refer QA Plan)
20. Additional observations ,if any.
21. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
22. Contractor / authorized representative name,
designation, signature.
23. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-82

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.51. Checklist for Mastic Concrete


RCM/CL 36
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
One sample of each for bitumen coarse
aggregate fine aggregate, filler is collected
at random for verifying its properties.
If Yes, Location No.
Date: Time:
3.
Random sample for mastic asphalt is
collected for verifying hardness number.
If yes, No: .
Date Time..
4.
The samples are sealed, labeled and signed
in presence of contractor
If yes, No. Date:
5.
The samples are sent to the laboratory
If Yes,
Name of Laboratory.
Date and Ref..
6.
Additional observations if any.
7.
Signature.
Designation.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-83

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.52. Checklist for Concrete Pavement


RCM/CL 37
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
complete if yes, date and reference.
3.
The formwork is as per approved drawings
and designs (refer approved form work
drawing).
4.
The dowel bars are adequate and are as per
required length and diameter.
5.
Openings are made for dowel bars in the
shuttering.
6.
Adequate arrangements for compaction are
made to the shuttering.
7.
Equipments on like skid vibrator, needle
vibrator, plate vibrators are available and are
in good working conditions.
8.
Separation membrane is laid on the sub
base as per clause 602.5. of MOSRTH.
9.
Dowel Bars are as per clause 602.3.5. of
MOSRTH.
10. Tie bars are as per clause 602.6.6. of
MOSRTH.
11. Batching, mixing, transportation, placing of
concrete, surface texture, curing are as per
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-84

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
clause 602.9. of MOSRTH
12. Joints are as per clause 602.10.5.2. of
MOSRTH.
13. Preparation and sealing of joint grooves.
14. Tolerance for surface regularity, level,
thickness and strength are according to
clause 903.5. of MOSRTH.
15. Concrete cubes and beams in required
numbers are taken as per clause 602.3.3.2.
of MOSRTH.
16. Slump tests are taken.
17. Field tests required are taken as per the
frequency mentioned in clause no. 903.5. of
MOSRTH
18. Exposed surface of concrete pavement is
kept continuously in a damp or wet condition
by pounding jute gunny bags kept constantly
wet for a period of not less than 14 days
from the date of placing of concrete.
19. When steam curing is adopted, it is ensured
that it is done in a suitable enclosure to
minimize moisture and heat losses.
20. Permission for using curing compound is
accorded by engineer.
21.

The

honeycombing,

broken

edges

/ / 200

/ / 200

or

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-85

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
corners and other defects if observed, are
thoroughly cleaned, saturated with water
and carefully pointed with mortar of cement
and fine aggregate mixed in the same
proportions used in the grade of concrete.
22. All construction and expansion joints in the
completed work are left carefully tooled and
free from any mortar concrete.
23. Expansion joint filler is left exposed for its full
length with clean and true edges.
24. Immediately on removal of forms, the
engineer examines the concrete work before
any defects are made good.
25. Additional observations, if any.
26. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
27. Contractor / authorized representative name,
designation, signature.
28. Inspecting officer, name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-86

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.53. Checklist for Road Marking Paint - Thermoplastic Plant


RCM/CL 38
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks are completed date
and reference.
3.
Adequate traffic safety measures are
provided.
4.
Line out is marked and approved.
5.
Painting is being done by machine /
approved manual method.
6.
The temperature of the receiving surface is
more then 10% and the paint is as specified
by the manufacturer.
7.
The thickness of paint is 2.5 mm.
8.
The glass beads are applied at the rate of
250gm / sq.mt area on hot paint surface in
quick succession of paint by spraying
operator.
9.
Traffic shall be open after setting of
thermoplastic paint surface.
10. Additional observations if any.
11. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-87

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
12. Contractor / authorized representative name,
designation, signature.
13. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-88

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.54. Checklist for Kerb Stone for Central Verge


RCM/CL 39
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
Adequate safety arrangement is provided.
4.
Soling is done in foundation is well
compacted with plate vibrator / power roller /
manually.
5.
The thickness of soling is as per approved
drawing.
6.
Proper mixing for grade of cement concrete
is done as specified in agreement for
foundation.
7.
Thickness of foundation oriented over the
foundation concrete is as per approved
drawing.
8.
The pre-cast kerb stones oriented over the
foundation concrete is as per approved
drawing.
9.
The vertical and horizontal tolerance is equal
to 6mm with respect to line and level shown
in approved drawing.
10. The gap between road and kerbstone is
tilled with cement concrete of grade
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-89

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
specified in agreement.
11. Kerb on drainage ends in super elevated
portions shall be cast as per approval
drawing.
12. Portion on back side of kerb is tilled with the
approved material specified in agreement /
drawing.
13. The filled material is compacted with plate
vibrator / material specified in agreement.
14. Adequate supervisory staff is provided by
the contractor.
15. Pointing is done in cement mortar of
proportion specified in agreement.
16. Additional observations, if any.
17. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
18. Contractor / authorized representative name,
designation, signature.
19. Inspecting officer name, Designation and
Signature.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-90

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.55. Checklist for Kilometre Stone and 200 metre Stones


RCM/CL 40
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed ; date and reference.
3.
Proper safety arrangements are provided.
4.
Pits excavated are as per size specified in
drawing.
5.
Soling is done as per drawing.
6.
Proper mixing of bed concrete is done as
specified in agreement.
7.
Thickness of bed concrete is as shown in
drawing.
8.
The kilometer / 200 meter stones is provided
over bed concrete and oriented as shown in
drawing.
9.
The gaps around kilometer / 200 meter
stones are filled by cement concrete and
compacted.
10. The colours, arrangement of letters and
script of kilometer / 200 meter stones is as
per approved drawing and agreement.
11. Adequate supervisory staff is provided by
the contractor.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-91

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
12. Additional observations, if any.
13. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
14. Contractor / authorized representative name,
designation, signature.
15. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-92

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.56. Checklist for Cast Iron Pipe Railing and Parapets


RCM/CL 41
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been completed
date and reference.
3.
Proper safety arrangement is provided.
4.
Excavated material for back filling is
classified and stacked properly as approved
by engineer-in-charge.
5.
The unusable material is disposed of from
site.
6.
The bed of foundation is properly leveled
and rammed.
7.
Bed concrete is provided as per the mix and
dimension shown on approved drawing.
8.
Curing is done at least for Seven days.
9.
Hole and drilled in the posts at the distance
specified in the approved drawing.
10. Posts are erected vertically to its line, level
and alignment as required as per the
approval drawing.
11. Horizontal pipes are properly places and
jointed.
12. Painting for structural work is done in three
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-93

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
coats on primer coat or as specified in the
contract.
13. The post to be embedded in bed concrete is
coated with coal tar.
14. Additional observations, if any.
15. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
16. Contractor / authorized representative name,
designation, signature.
17. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-94

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.57. Checklist for Guard Stones


RCM/CL 42
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
Adequate safety arrangements are provided.
4.
Pits excavated are as per size specified in
drawing.
5.
Soling is done as per drawing.
6.
Proper mixing of bed concrete is as shown
in drawing.
7.
Thickness of bed concrete is as shown in
drawing.
8.
The guard stones is provided over bed
concrete and oriented as shown in drawing.
9.
The gaps around guard stones are filled by
cement concrete and compacted.
10. White washing is done in required number of
coats specified in agreement.
11. Adequate supervisory staff is provided by
the contractor.
12. Additional observations if any.
13. Conclusion by inspecting officer The
execution activities are satisfactory / not
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-95

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
14. Contractor / authorized representative name,
designation, signature.
15. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-96

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.58. Checklist for Boundary Stones


RCM/CL 43
Name of Work:
Agreement No.:
Sl.
No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.

Estimated Cost:
Sanction No. and date:

Particulars

Remarks (Y / N / NA / Observation if any)

Date
Location / chainage / description of item.

/ / 200

/ / 200

/ / 200

/ / 200

/ / 200

/ / 200

The execution inspection checks are


completed date and reference.
Adequate
safety
arrangements
are
provided.
Pits excavated are as per size specified in
drawing.
Soling / sand and boulder filling is done as
per drawing.
Proper mixing of bed concrete is as shown
in drawing.
Thickness of bed concrete is as shown in
drawing.
Boundary stones are provided over bed
concrete and oriented as shown in drawing.
The gaps around boundary stones are filled
by cement concrete and compacted.
White washing is done in required number
of coats specified in agreement.
Adequate supervisory staff is provided by
the contractor.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-97

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:
Sl.
No.
12.
13.

14.

Estimated Cost:
Sanction No. and date:

Particulars

Remarks (Y / N / NA / Observation if any)

Date
Additional observations, if any.

/ / 200

/ / 200

/ / 200

/ / 200

/ / 200

/ / 200

Conclusion by inspecting officer The


execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
the re-inspection.
Contractor / authorized representative
name, designation, signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

Issue 01, Rev 00


Page No.: RC/7-98

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.59. Checklist for Cross Drainage Works (Hume Pipe Drain)


RCM/CL 44
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution inspection checks are
completed date and reference.
3.
Adequate traffic safety arrangements are
provided.
4.
Excavation for pipe laying is done to the
lines and grade as shown on the approved
drawing or as directed by the engineer-incharge.
5.
Strata classification is done and approved by
the engineer-in-charge.
6.
Excavated material required for back fill
stacked properly.
7.
Unusable material is disposed of as directed
by engineer-in-charge.
8.
It is ensured that the ground where pipe is to
be placed is reasonably firm.
9.
Soling / approved granular material layer is
suitable laid as shown in approval drawing
and well compacted.
10. Concrete bedding is suitably provided as per
the dimensions shown in the approved
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-99

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
drawing.
11. The mix for the concrete is not leaner than
M-15 and cured for at least 7 days and the
constituents are tested as per the .
Test plan no for cement.
If yes, date and reference.
Test plan no for fine aggregate
If yes, date and reference.
Test plan no for coarse aggregate.
If yes, date and reference.
12. Pipes have been laid before the setting of
the concrete.
13. It is ensured that pipes are in good
conditions before and after laying.
14. The minimum distance between outer
surface of two pipes is half the diameter of
pipe or minimum 450 mm.
15. The arrangement for lifting, loading,
unloading, and laying of pipe in the bed is
approved by the engineer-in-charge.
16. Pipe laying started from proceeding from
outlet to inlet.
17. Invert level of the pipes are as per the
required grade.
18. There is no defective pipe.
19. If yes, it is removed by the contractor at his
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-100

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
own cost.
20. The caulking space of the joints is between
13mm to 20 mm or as shown in the drawing.
21. Caulking material is wet mix CM in
proportion of 1:2 mixed with caulking irons.
22. There is even annular space at the joints.
23. Joint space is filled properly with 1:2 cement
mortar.
24. Joints are properly finished.
25. Curing is done at least for four days.
26. Back filling is done after the joining material
is hardened.
27. Back fill soil is clean, free from boulders,
large roots and excessive amounts of sods
or other vegetable materials and logs.
28. The back fill material is approved by
engineer-in-charge.
29. The back filling is compacted in the layers
not exceeding 150MM with the help of
approved equipment.
30. Back filling is done simultaneously on both
sides of the pipe.
31. Head walls, wing walls, apron and other
ancillary
works
are
carried
out
simultaneously in accordance with the
approved drawing.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-101

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
32. Contractor supervisor is trained to supervise
the work.
33. The masonry work for the wall is carried out
confirming to section 1400 MOSRTH - and
aprons conforming to section 2500 of
MOSRTH .
34. It is ensured that height of filling about the
pipe is more than 600 mm.
35. Additional observations if any.
36. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
37. Contractor / authorized representative name,
designation, signature.
38. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-102

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.60. Checklist for Road Signs


RCM/CL 45
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
The execution checks have been competed
date and reference.
3.
Adequate safety arrangement is provided.
4.
Excavation is done as per approved
drawing.
5.
Excavation material is stacked / disposed
properly.
6.
Cement concrete of required grade as
specified in agreement /drawing is provided
in foundation.
7.
The board oriented over bed concrete is
checked by engineer-in-charge.
8.
The supports of the boards are fixed in
cement concrete of required grade as
specified in agreement.
9.
The frame embedded in soil is provided with
approved anti-corrosive treatment.
10. The frame and border is painted in approved
oil paint.
11. Additional observations, if any.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-103

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
12. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for
The re-inspection.
13. Contractor / authorized representative name,
designation, signature.
14. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-104

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

7.61. Checklist for Slab Drain


RCM/CL 46
Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
1.
Location / chainage / description of item.
2.
Pre-excavation
checks
have
been
completed date and reference.
3.
Excavation for foundation is done to the
lines and grade as shown on the approved
drawing or as directed by the engineer-incharge.
4.
Strata classification is done and approved by
the engineer-in-charge.
5.
Excavated material required for back fill
stacked properly.
6.
Unusable material is disposed as directed by
engineer-in-charge.
7.
It is ensured that the starta on which
foundation is to be places is reasonably firm
to take the load of slab drain and vehicular
traffic.
8.
Soling / approved granular material layer is
suitably laid as shown in approval drawing
and well compacted.
9.
Concrete bedding is suitably provided as per
the dimensions shown in the approved
drawing.
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-105

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
10. Curing of the concrete beading is carried out
for not less than Seven days.
11. De-watering is carried out and recorded in
maintained.
12. Centering for walls of slab drain is erected
and dimensions are verified as per the
approved drawing.
13. Concrete for walls is done in layer for height
not more than 90 cm.
14. Metal pins for proper bonding of subsequent
layers are provided as directed by the
engineer-in-charge.
15. Cement consumption register and gunny
register are maintained.
16. Minimum seven days curing is done for
walls.
17. Centering for slab is done and dimensions
are verified as per the approved plan.
18. Reinforcement are placed and verified as
per the approved drawing.
19. Cover for reinforcement at bottom, top and
sides are as per requirement.
20. Proper care is taken while placing the
concrete so that there is no suggestion.
21. Stem is as per requirement.
22. Required number of cubes are cast for
Procedure No.: QMS/WI/RC-07/Test Plans and Checklists
Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-106

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Name of Work:
Agreement No.:

Estimated Cost:
Sanction No. and date:

Sl. Particulars
Remarks (Y / N / NA / Observation if any)
No.
Date
/ / 200
/ / 200
/ / 200
/ / 200
testing.
23. Additional observations, if any.
24. Conclusion by inspecting officer The
execution activities are satisfactory / not
satisfactory. If satisfactory, further road
construction activity to commence by.. .
If not satisfactory, the contractors to report
the corrective action taken and inform for the
re-inspection.
25. Contractor / authorized representative name,
designation, signature.
26. Inspecting officer name, Designation and
Signature.

Procedure No.: QMS/WI/RC-07/Test Plans and Checklists


Controlled Document

/ / 200

/ / 200

Issue 01, Rev 00


Page No.: RC/7-107

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8. TESTS AND TEST PROFORMA


8.1.

Tests to be Conducted by Construction Division

8.1.1. Field Tests


Sl.
No.
1.
2.
3.
4.

5.
6.
7.
8.
9.

Item

Test to be conducted

Embankment

Density, Atterberg limits, Moisture Content


(Suitability before and The execution).
GSB
Gradation / Atterberg Limits / Moisture Content /
Density.
WBM
Impact Value, Gradation, Flakiness and Elongation.
Bituminous Works
Temperature (Binder / Mix) Rate of Spread of
Bitumen.
Gradation, Impact, Flakiness and Elongation for
Aggregates.
Binder Content.
Sand
Gradation
Silt / Clay / Deleterious Materials.
Bricks
Size and Shape
Coarse Aggregate
Gradation, Water Absorption, Impact, Flakiness
and Elongation.
Concrete
Slump
Any other test possible at field

Frequency for field test: 100 %.


Other tests are conducted by QC staff at laboratory.
Frequency for other tests to be decided after consultation with Quality
Division, Shimla.

8.2.

Tests to be Conducted by Quality Control Division

8.2.1. Laboratory Tests


Sl.
No.
1.

Item
Embankment

2.

GSB

3.

WBM

4.

Bituminous Works

5.

Sand

Test to be Conducted
Density, Atterberg limits, Moisture Content
(Suitability before and The execution).
Gradation / Atterberg Limits / Moisture Content /
Density, CBR*.
Impact Value, Gradation, Flakiness and Elongation,
Abrasion Test*.
Temperature (Binder / Mix) Rate of Spread of
Bitumen.
Gradation, Impact, Flakiness and Elongation for
Aggregates.
Binder Content, Stripping value, Marshall Stability
Analysis ( Mixture Design) Penetration value,
Softening Point, Viscosity, Density, Ductility*.
Gradation
Silt / Clay / Deleterious Materials.

Procedure No.: QMS/WI/RC-08/Tests and Test Proformae


Controlled Document

Page No.: RC/8-1

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

Sl.
No.
6.

Item
Bricks

7.

Coarse Aggregate

8.

Concrete

9.

Soil

10.

Cement

11.

Tiles

Test to be Conducted
Size and Shape, Compressive strength, water
Absorption*.
Gradation, Water Absorption, Impact, Flakiness
and Elongation, Abrasion Test*.
Slump, Compressive strength, Mix Design of
Concrete*.
SBC Test, Grain size analysis, Classification of
Soils, Density, Moisture Content, Atterberg
limits, Direct Shear Test, Triaxial shear test
CBR*.
Normal Consistency, Initial and Final setting
time, Fineness, Strength of Cement (3 days, 7
days, 28 days)*.
Water Absorption, Size and shape, Transverse
Flexural Strength*.

Test to be conducted at QC Lab only (100 % sampling frequency)


Other tests are conducted by both construction staff and QC staff
(10 % sampling frequency for QC Staff) For the other tests frequency to be
decided after consultation with Quality Control Division, Shimla.

Procedure No.: QMS/WI/RC-08/Tests and Test Proformae


Controlled Document

Page No.: RC/8-2

Issue 01, Rev 00

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.3.

Test report on aggregate characteristics of Grade 2 metal for WBM Work

Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification Section 400 clause 404 and test conducted as per IS 2386:1963

Test
No.

1.

1.
2.
3.

Details
of
Sample

Impact value 30% max

Los Angles Abrasion


Value 40% max

2.

3.

Water
absorption
value 2%
(max
4.

Flakiness
Index Max
20%

5.

Percentage passing by weight through IS Sieve


Designation (Table 400-7)
Remarks
90mm
100%
6.

63mm
90-100 %
7.

53mm
25-75%
8.

45mm
0-15%
9.

22.40mm
0-5%
10.

11.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-3

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.4.

Test Report on Cement Concrete Cubes

Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :

Letter No.

Dated :

Tested as per IS 516:1959

Test
No.

1.

1.
2.
3.

Details
of
Casting

2.

Date of
Testing

3.

Age of
Cube in
days

4.

Location of
Concreting

5.

Grade /
Proportion
of mix

6.

Wt. of
Specimen
in gms

7.

Compressive
strength of CC
cubes in kg/cm2

8.

9.

Requirement
as per IS
456:2000

Remarks

10. 11.

12.

13.
Compressive
strength of CC
cubes is computed
for 28 days curing
vide
MOSRTH
Table
900-5
Section 900

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-4

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.5.

Test Report of Sand Sample

Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Indian Standard Specification for coarse aggregate IS 383:1970 Table 1 and 4 and test carried out as per IS 2386:1963
Sample
No.

1.

1.
2.
3.

Description of
sand sample
tested
Grading limit
for
fine
aggregate as
per IS 383:
1970 Table 1
and
4
for
concrete work
2.

Deleterious material % by Wt
Passing
Coal
Clay
75
and
Others
lumps
Micron
Lignite
IS Sieve

Max
3.00%

3.

Max
Max
1.00% 1.00%

4.

5.

Max
1.00%

6.

% by weight passing the IS Sieve


Total

10
mm

100%
Max
100%
5.00%
100%
7.

8.

4.75
mm

90-100% 60-95%
90-100% 75-100%
90-100% 85-100%
9.

1.18
mm

0.600
mm

0.300
mm

0.075
mm

Grading
zone of
sand
sample

30-70%
55-90%
75-100%

15-34%
35-59%
60-79%

5-20%
8-30%
12-40%

0-10%
0-10%
0-10%

Gr - I
Gr - II
Gr - III

12.

13.

14.

2.36
mm

10.

11.

15.

Remarks

16.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-5

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.6.

Test Report of Brick Sample

Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :

Sl.
No.

Date of
Testing

Class
designation and
Identification
mark on the top
of the brick

1.

2.

3.

1.
2.
3.

Water
absorption
Value in
%

Crushing
strength of
brick
in
kg/cm2

4.

5.

Letter No.

Dated :

Average Value of bricks

Requirement as per IS 1077:1992

Water
absorption
in %
6.

Water
Crushing
absorption
strength of
Value in %
brick
in
20.00%
2
kg/cm
(Max)
7.
8.

Crushing strength
brick in kg/cm2 Remarks
35/50/75
kg/cm2
(min) based on
class of Bricks
9.
10.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-6

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.7.

Test Report of Coarse Aggregate (40mm and less / 20mm and less)

Name of work :
Reference : Executive Engineer
Letter No.
Dated :
Date of Testing :
Indian standard specification for coarse aggregate IS 383:1970 Tables -1 and 2 and test carried out as per IS 2386:1963
Size of coarse
Percentage by weight passing the IS Sieve
aggregate
Details of
Test
Aggregate
80mm
40mm
20mm
10mm
4.75mm
Sample
No.
Impact
40mm and less
100%
95-100%
30-70%
10-35%
0-5%
Collected
Remarks
Value Max
20mm and less
100%
95-100%
25-55%
0-10%
30%
1.
2.
3.
4.
5.
6.
7.
8.
9.

1.
2.
3.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-7

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.8.

Test Report of Cement Sample

Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :

Letter No.

Dated :

Tested as per IS 4031 :1988


Setting time in Minutes
Sl.
No.

Details of sample collected Brand Grade


Invoice Receipt No. and dt.

Standard
consistency of
cement in %

As per IS 8112:1976 (Reaffirmed 1989) for


OPC 43 grade
As per IS 12269:1987 (Reaffirmed 1999) for
OPC 53 grade
As per IS 1489(Pt 1): 1991 (Reaffirmed 1999)
for PPC (Fly Ash based)
As per IS 455:1989 (Reaffirmed 1995) for
PSC (Slag)

1.

1.
2.
3.

2.

3.

Min. Compressive strength of


cement at the age, MPa
Remarks

Initial setting
time, minimum

Final setting
time, max

3 days

7 days

28 days

30

600

23

33

43

30

600

27

37

53

30

600

16

22

33

30

600

16

22

33

4.

5.

6.

7.

8.

9.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900 and IS Specification.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-8

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.9.

Test Report on Aggregate Characteristics of Single Coat Surface Dressing

Name of work :
Reference : Executive Engineer PWD Division
Date of Testing :

No. of
Tests

1.

1.
2.
3.

Letter No.

Dated :

Requirement as per MOSRTH Specification Section 400 clause 404 and test conducted as per IS 2386:1963
Nominal
Grading Requirements for chips for surface dressing
size
Percentage by wt
Details
Impact
Water
Passing
of
value
Absorption 1%
19
13.2
9.5
6.3 2.36 0.075
13.2 mm Remarks
Sample
30%
(Max)
13 mm
mm
mm
mm mm mm
mm
retained on
Tested
(max)
9.5 mm
100 85-100 0-40 0-7
0-2
0-1.5
65% min
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-9

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.10. Test Report on Aggregate Characteristics of 20mm Thick Open Graded Premix Carpet / Seal Coat
Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Section 500 clause 511 and 513 and test conducted as per IS: 2386:1963
Grading for 20mm Open
Grading for Seal Coat
Graded Premix Carpet
Aggregate
(Table 500-23)
% Passing by weight
% passing by weight through
through IS Sieve
Required
Required
IS Sieve designation
Water
Details Impact
designation
Bitumen
Bitumen
value Absorption
of
Test
Type A
Type B
Content
in
Content
in
13.20 mm
11.20mm
value 1%
No. Sample 30%
(clause
(clause
%
for
seal
%
for
metal
metal
(max)
Tested (max)
513.2.2)
513.2.3)
coat mix
carpet mix
22.40 11.20 13.20 5.60
11.2 2.36 2.36 0.180
mm
mm
mm mm
mm mm mm
mm
100
0% 100% 0%
100%
0% 100% 0%
%
9
10
11
12
13
14
1.
2.
3.
4.
5.
6.
7.
8.

1.
2.
3.

Remarks

15

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-10

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.11. Test Report on Aggregate of Built-up Spray Grout


Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification (4th revision) Section 500 clause 506 and test conducted as per IS 2386:1963
Percentage passing by weight (Table 500-7)
Test No.

1.

1.
2.
3.

Details
of
Sample
Tested

Impact
value
30%
Max

2.

3.

Aggregate
Water
Absorption
value 2%
Coarse
Max

4.

IS Sieve Designation
53 mm

26.5mm

22.4mm

13.2mm

5.6mm

2.8mm

100

40-75

0-20

0-5

Key

100

100

100

40-75

0-20

0-5

5.

6.

7.

8.

9.

10.

Remarks

11.

12.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-11

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.12. Test Report on Coarse Aggregate for Bituminous Concrete


Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification (4th revision) Section 500 clause 509
Sl.
No.

1.
2.
3.
4.

Test
No.

Details
of
sample
collected

Impact
value
24%
(max)

Water
Absorption
value 2%
(max)

Grade
I
50-65
mm
II
30-45
mm

26.5
mm

Percentage by weight passing IS Sieve (Table 500-18)


19
13.2
9.5
4.75 2.36 1.18
0.6
0.3
mm
mm
mm
mm
mm
mm
mm
mm

0.15
mm

0.075
mm

100

79100

5979

5272

3555

2844

2234

1527

1020

5-13

2-8

--

100

79100

7088

5371

4258

3448

2638

1828

1220

4-10

Remarks

Apart from conformity with the grading and quality requirement for individual ingredients the mixure shall meet the requirements
set out in Table 500-19 (For Mixture Design)
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-12

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.13. Test Report on Aggregates Characteristic for SDBC


Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification (4th revision 2001) Section 500 clause 508 and test conducted as per IS 2386:1963

Sl.
No.

1.
2.
3.
4.

Test
No.

Details
of
sample
collected

Impact
value
27%
(max)

Water
Absorption
value 2%
(max)

Grade
I
13 mm
II
10 mm

Percentage by weight passing IS Sieve (Table 500-15)


13.20
9.5
4.75
2.36
1.18
0.3
19mm
mm
mm
mm
mm
mm
mm

0.075
mm

100

90-100

70-90

35-51

24-39

15-30

9-19

3-8

--

100

90-100

35-51

24-39

15-30

9-19

3-8

Remarks

Apart from conformity with the grading and quality requirement for individual ingredients the mixure shall meet the requirements
set out in Table 500-16 (For Mixture Design).
The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-13

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.14. Test Report on Aggregate Characteristics of Bituminous Macadam

Impact
value
Test
No.

1.

1.
2.
3.

Details
of
sample
Tested

2.

Water
Absorption
value

30%
Max

3.

2% Max

4.

Percentage passing by weight (Table 500-4)


IS Sieve Designation

Grade
I
(80-100
mm)
II
(50-75
mm)

5.

Bitumen
Content % by
weight of total
mix

45
mm

37.5
mm

26.5
mm

19
mm

13.2
mm

4.75
mm

2.36
mm

0.3
mm

0.075
mm

100
%

90100

75100

35-61

1322

4-19

2-10

0-8

3.1 - 3.4

100

90100

56-88

1636

4-19

2-10

0-8

3.3 - 3.5

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

Remarks

Name of work :
Reference : Executive Engineer PWD Division
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification (4th revision) Section 500 clause 504 and test conducted as per IS 2386:1963

16.

The test results relate to the sample tested and shall not be reproduced in part.
Materials need to be tested as per frequency of MOSRTH Section 900.
Test samples collected by the QC Division/supplied by the Concerned EE through field staff.

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-14

Quality Management System


Construction Manual (Work Instructions) for
Public Works Department of Himachal Pradesh (HPWD)

8.15. Test Report on Aggregates Characteristic for Dense Graded Bituminous Macadam

Test
No.

1.
2.
3.
4.

Details
of
Sample
Tested

Flakiness
Elongation
Index
(Combined)
Max 30%

AggreWater
gate
absorp
Impact
-tion
value
Max
Max
2%
27%

Nominal
aggregate
size

Grade

45
mm

40 mm

100

25 mm

II

37-5
mm
95100
100
%

Percentage by weight passing IS Sieve


26.5
19
13.2 4.75 2.36
0.3 0.075
mm mm mm
mm
mm
mm
mm
63 5538287-21- 2-8%
75
54
42
93
90- 715638287-21- 2-8%
100 95
80
54
42

Remarks

Name of work :
Reference :
Letter No.
Dated :
Date of Testing :
Requirement as per MOSRTH Specification Section-500 clause 507 Table 500-10 and test conducted as per IS 2386:1963

Apart from conformity with the grading and quality requirement for individual ingredients the mixure shall meet the requirements
set out in Table 500-16 (For Mixture Design).
Materials to be tested as per frequency of MOSRTH Section 900.
Test samples of aggregates were collected/supplied by the QC Division/supplied by the Concerned EE through field staff.
The Gradation of DBM in the proportion of the aggregate as mentioned above shall be adopted and gradation shall be got
confirmed in the filed by carrying filed gradation test

Asst./ Junior Engineer

Executive Engineer/In-charge
PWD (QC. Division)

Procedure No.: QMS/WI/RC-08/Tests and Test Performa


Controlled Document

Issue 01, Rev 00


Page No.: RC/8-15