ANALIZA CENA
ZIDARSKI RADOVI:
1. MALTERISANJE ZIDOVA CETVRTOG SPRATA -PRENOS KRANOM
ifra normativa: 126004 - Graevinske norme
-Materijal: KRECNI MALTER 1:3 u II sloja : 0.028m31:3/m2zida
=M=850.305din/m31:3
-Radnici: RII (spravljanje maltera): 2.310 N/ m 31:3 * 110 din/ N = 254.1 din/ m31:3
kr
Voda
2014-2015
2014-2015
REKAPITULACIJA:
R V (N) .. 0.633
N/ m2zida
R II (N) .. 0.301
N/ m2zida
radnik
Norma
Casa(m2)
Radnika
dana
brigada
dana
4=1*3
5=4/n
611.77
RV
0.633
387.25
48.41
R II
0.301
184.14
23.02
BETONSKI RADOVI
2014-2015
=M=6457.6 din/m3b
-Radnici: RII (spravljanje betona): 1.860 N/ m3b * 110 din/ N = 204.6 din/ m3b
RII (doziranje): 0.220 N/ m 3b * 110 din/ N = 24.2 din/ m3b
RII (prenos cementa): 0.396 N/ m 3b * 110din/ N = 43.56 din/ m3b
2014-2015
REKAPITULACIJA:
R V (N) ..
0.396 N/ m2P
R III (N) ..
0.396 N/ m2P
R II (N) ...
0.761 N/ m2P
radnik
Norma
Casa(m2)
Radnika
dana
brigada
dana
4=1*3
5=4/n
186.36
R II
0.761
141.8
17.62
RV
0.396
73.8
9.23
R III
0.396
73.8
9.23
2014-2015
ARMIRAKI RADOVI:
3. MAINSKO SEENJE, ISPRAVLJANJE, SAVIJANJE, RUNO
POSTAVLJANJE I VEZIVANJE ARMATURE 14 (GN-400-108)
Koliina iz predmera 19.07 m3betona i pretpostavljamo da ima 100
kgarmature/m3betona
-Materijal:
Armatura : 1 kgarmature * 1,06 kgelika/ kgarmature * 85 din/ kgelika = 90.10 din/ kgarmature
Paljena ica : 0.0035 kgice/kgarmature x 140 din/ kgice = 0.490 din/ kgarmature
din/kgarmature
AIII : 0.0022 N/ kgarmature * 130 din/ N = 0.286
din/kgarmature
Savijanje:
din/kgarmature
AIII : 0.0022 N/ kgarmature * 130 din/ N = 0.286
din/kgarmature
Prenos:
din/kgarmature
=R = 4.153 din/
kgarmature
2014-2015
REKAPITULACIJA:
R IV (N)
.0.0134 Nc/
m3betona
R III (N)
..0.0164
Nc/ m3betona
R II (N) ...
0.0001 Nc/ m3betona
Radnik
Norma
Casa[m3]
Radnika
dana
brigada
dana
4=1*3
5=4/n
R III
0.0164
31.27
3.91
1907
2014-2015
R IV
0.0134
25.55
3.19
R II
0.0001
0.191
0.024
armature
TESARSKI RADOVI:
4.OPLATA MEUSPRATNE KONSTRUKCIJE
-ukupna koliina oplate : 303,14 m2
Materijal : GN 601-203A
Za izradu :
2014-2015
2014-2015
Koliina
rada
[
m2
Radnik
]
303,14
303,14
Nc
m2
Radnih
dana
Brigada
Dana
7
4=1x3
5=4/n
TV
0,43
130,35
16,29
T III
0,43
130,35
16,29
R II
0,072
21,83
2,73
T III
0,15
45,47
5,68
R II
0,152
46,08
5,76
2014-2015