Beruflich Dokumente
Kultur Dokumente
Abstract
The North East Bab (NEB) Project is currently under
construction by Abu Dhabi Company for Onshore Oil
Operations (ADCO). It is a grass root field development
project. New production facilities are installed to handle oil,
gas and water production from three separate oil fields; Al
Dabbiya, Rumaitha and Shanayel.
In accordance with the project HSE plan, a HAZID (Hazard
Identification) study was conducted during the conceptual
design phase. HAZOP studies were carried out during the
FEED and EPC phases of the project.
Al-Dabbaiya
-
Introduction
Rumaitha / Shanayel
Abu Dhabi Company for Onshore Oil Operations (ADCO) is
currently implementing Phase I of North East Bab (NEB)
Project, which is a grass root development. New processing
facilities will be required to handle oil, gas and water
production from three separate oil fields; Al-Dabbiya and
Rumaitha and Shanayel. Water and gas injection facilities
will also be required to provide pressure support and enhanced
oil recovery.
www.petroman.ir
SPE 93723
A block diagram of the Central Processing Plant (CPP) at AlDabbaiya is shown in figure 3
Unit.
For each vendor package, a vendor representative
participated in the HAZOP sessions.
Project Implementation
HAZOP Procedures
HAZOP Logistics
The Company has a number of qualified HAZOP leaders who
normally lead the HAZOP studies for the Company assets. It
is also a policy that for new projects, HAZOP studies are led
by a Team leader from the Company or an outside Team
Leader who is appointed by the Company rather than the
Engineering Contractor. It has been our experience that this
ensures that the study is more impartial and objective.
The HAZOP study for the EPC Contract was conducted in the
home office of the EPC Contractor, which was in Paris,
France. This meant mobilising the HAZOP team Leader and
the team members from Operations and Safety Departments to
Paris for the duration of the HAZOP. It is always more
efficient to carry out the HAZOP study at the location where
the centre of engineering activities are.
Major Findings
The total duration of the HAZOP studies was 7 weeks. They
were carried out in 4 different sessions as follows:
Central processing plant oil path: 2 weeks
Gas processing & compression facilities: 2 weeks
Clusters: 1 week
Vendor packages: 1 week
Flare & vapour recovery systems: 1 week
www.petroman.ir
SPE 93723
2.
3.
4.
5.
6.
7.
8.
9.
10. The design basis of the closed drain vessel was not well
defined. A recommendation was made to clarify and
document the basis of design of the system. The design
should be based on the draining of the largest vessel
inventory at a given time.
11. The design shows the closed drain vessel and the pumps
were in a concrete pit with the pumps at about 6 meters
below grade. Due to the presence of H2S in the fluids,
confined entry procedures have to be applied.
Furthermore, Al Dabbiya has higher water table (2 meters
below grade) and the pit can accumulate rain water and
sand. A recommendation is made to install the vessel
buried with two top mounted submersible pumps, one
duty and one stand-by.
12. The FEED HAZOP was based on two flares; HP and LP
flares. This was later replaced with a combined flare
system referred to as the HP flare. The HAZOP team
analyzed several scenarios to check the operability of the
current design. Some recommendations were made to
ensure that flare system pressure will not exceed the back
pressure necessary for the safe operation of other
equipment (e.g. the requirements form the compressor
vendor for the gas seals).
13. To carry out a pipeline repair job, it would require
depressurization of the entire gas injection network. For
example, in order to repair a leaking isolating spool in an
injection trunk line, oil export from both Rumaitha and
Dabbyia would have to be stopped. This is because
flaring is not allowed. A recommendation was made to
provide positive isolation (double block, bleed and
spectacle blind) on each of the four injection trunk lines.
Furthermore, each injection trunk line must have its
dedicated depressurization line to the plant flare.
14. There is no tank for the hot oil system. The current
design calls for manual filling of the system inventory
(some 150 m3) using 200-liter drums. Draining of the
inventory is done manually through the sump to the
trucks.
The oil medium has toxic fumes. A
recommendation was made to provide a storage tank sized
to handle the full system inventory.
15. A scenario has been identified whereby a reverse flow
from the water injection system would overpressure the
water disposal system. A recommendation was made to
protect the disposal water system by a relief valve.
16. Start-up issues were addressed during the HAZOP
session. The recommended approach to commissioning,
which is similar to what was used in other ADCO gas
projects, is to introduce sweet lean gas after nitrogen
purging. The system pressure is then increased gradually
for leak testing by running the compressor train on lean
gas.
www.petroman.ir
SPE 93723
where as during the EPC phase, any small change can have
cost, schedule and contractual implications.
Some of the recommendations made were not strictly HAZOP
issues, but more of design issues. The tight project schedule
meant that there was not enough time for complete design
review of the P & IDs before the HAZOP. The temptation to
combine design review with the HAZOP study should be
avoided. This can compromise the concept of HAZOP being
an independent process safety and operability review [4].
Conclusions
Based on the authors experiencing in leading the HAZOP
study for the NEB project and other projects, the following
conclusions are made. They are particularly relevant when
applying HAZOP studies in a project environment.
www.petroman.ir
SPE 93723
Acknowledgement
2.
3.
References
4.
1.
Parameter
Key word
Definition
Flow
More
Quantitative increase
Less
Quantitative decrease
(Includes no flow)
Pressure
Reverse
More
Opposite direction
More than normal operating
Temperature
Less
More
Level
Less
More
Others
Less
Different from
Table 1
www.petroman.ir
SPE 93723
Arabian Gulf
Qatar
NEB
Abu Dhabi
United Arab
Emirates
Saudi Arabia
www.petroman.ir
Oman
SPE 93723
Arabian Gulf
Cluster-A
D
Dabbiya
Dabbiya
CPP
Abu Dhabi
L
M
C
N
P
Rumaitha
R
Cluster-A
B
Rumaitha
CPP
D
C
Jebel Dhanna
M
G
H
www.petroman.ir
SPE 93723
LP
Rumaitha Gas
Gas Wells
Lean Gas
HP 1
MP
HP 2
WAG & GI
network
Dehydration Column
Local
Wells
Train 1
VR
1st Stage
Separator
Clusters
Train 2
2nd Stage
Separator
Export
1st Stage
Desalter
Manifold
Figure 3
2nd Stage
Desalter
Pump
Stabilization
Column
Tank
www.petroman.ir