Beruflich Dokumente
Kultur Dokumente
NRIC : S7485630F
Email : t.sanjvi@yahoo.com
05-8-2013
WSH Act
WSH (Construction) Regulation
Factories (Scaffold) Regulations
Approved Code of Practices (ACOP)
2. Identify and apply the relevant and appropriate clauses stated in the legal and other requirements to formulate control
measures of WSH risk on site (with reference to item 1) for any 4 of the following activities but not limited to:
Working in confined space.
Laying of sewer pipe in trench.
Demolition of reinforced concrete residential building .
Casting of floor beams and slabs on the timber formwork with concrete bucket and a mobile crane.
Erection or dismantling of scaffold.
Bracing, work platforms, boards, planks stairs, standards, ledgers transoms.
Construction of timber scaffold.
Vehicular
1
WSH
28.(1) Where in a worksite, any work is performed over, on or in close proximity to a street, public
(Construction)
road or any other place where public vehicular traffic may cause danger to any person who carries out
Regulations 2007 the work, it shall be the duty of
(a)the employer of any person who carries out the work in the worksite; or
(b)the principal under whose direction any person carries out the work in the worksite,
to ensure that
(i)the worksite is barricaded;
(ii)suitable warning signs and warning lights are set up to direct traffic away from the worksite; and
(iii) Where necessary, the traffic is specially controlled by designated persons.
(2) It shall be the duty of the owner of any vehicle used in a worksite to ensure that the vehicle is of
good construction and roadworthy.
(3) No person shall drive a vehicle of any class or description in a worksite unless he has obtained the
authorization of the occupier of the worksite to do so.
(4) It shall be the duty of the occupier of a worksite to ensure that no person shall drive a vehicle of any
class or description in the worksite, except a person who has obtained the authorization to do so refer to
in paragraph (3).
WSH
(Operation of
Cranes)
Regulations 2011
Lifting
Lifting plan
4. (1) Where any lifting operation involving the use of any crane is carried out in a workplace by a
crane operator, it shall be the duty of the responsible person to establish and implement a lifting plan
which shall be in accordance with the generally accepted principles of safe and sound practice.
(2) It shall be the duty of the responsible person to ensure that the lifting plan referred to in
paragraph (1) is made available for inspection upon request by an inspector.
9. The Commissioner shall keep an up-to-date register of all persons registered as crane operators.
17.(1) It shall be the duty of the responsible person to appoint a lifting supervisor before any lifting
operation involving the use of any crane is carried out in a workplace.
(2) It shall be the duty of the responsible person not to appoint any person as a lifting supervisor for
any lifting operation involving the use of a crane in a workplace unless the person is one who
(a)has successfully completed a training course acceptable to the Commissioner to equip him to become
a lifting supervisor; and
(b) Has, in the opinion of the responsible person, such relevant experience in lifting operations for a
period of not less than one year before the appointment as a lifting supervisor.
Appointment and duties of rigger
18.(1) It shall be the duty of the responsible person to appoint a rigger before any lifting operation
involving the use of any mobile crane or tower crane is carried out in the workplace by a crane operator.
Appointment and duties of signalman
19.(1) It shall be the duty of the responsible person to appoint a signalman before any lifting
operation involving the use of any mobile crane or tower crane is carried out in a workplace by a crane
operator.
WSH
Implementation of permit-to-work system
(Construction)
Regulations 2007 11.(1) It shall be the duty of the occupier of a worksite at which any high-risk construction work is or
is to be carried out to
Part III
(Permit-To-
Work System)
(a)any high-risk construction work at the worksite must be carried out with due regard to the safety and
WSH
health of persons carrying out the high-risk construction work in the worksite;
(Construction)
Regulations 2007 (b)such persons are informed of the hazards associated with the high-risk construction work and the
precautions they have to take; and
Part III
(Permit-ToWork System)
(c) the necessary safety precautions are taken and enforced when the high-risk construction work is
being carried out in the worksite.
WSH
Piling
(Construction)
Regulations 2007 Stability of adjacent structures
Part- XIV
PILING
129.(1) It shall be the duty of the occupier of a worksite to ensure that before carrying out any piling
work which may affect the stability of any structure within the worksite
(a)the structure is adequately supported by underpinning, sheet piling, bracing or other means of
shoring in accordance with the design of a professional engineer; and
(b)a certificate under paragraph (3)(ii) has been issued in respect of the underpinning, sheet piling,
bracing or other means of shoring.
Inspection
130.(1) It shall be the duty of
(a)the employer of any person who carries out any work involving the use of any piling equipment in a
worksite; or
(b)the principal under whose direction any person carries out any work involving the use of any piling
equipment in a worksite, to ensure that the piling equipment is inspected daily by a designated person
before the start of any piling work for the day and that every defect is corrected before the piling
equipment is used.
WSH
(Construction)
Pile driver not in use
Regulations 2007
131. It shall be the duty of
Part- XIV
(a)the employer of any person who carries out any work involving the operation of a pile driver in a
PILING
worksite; or
(b)the principal under whose direction any person carries out any work involving the operation of a pile
driver in a worksite,
to ensure that when the pile driver is not in use, the hammer is choked or blocked in the leads or
lowered to the ground.
Footing
133.(1) It shall be the duty of
(a)the employer of any person who carries out any work involving the placing or advancing of a piling
frame in a worksite; or
(b)the principal under whose direction any person carries out any work involving the placing or
advancing of a piling frame in a worksite,
to comply with paragraphs (2) and (3).
(2) Before placing or advancing a piling frame in a worksite, the ground of the worksite shall be
(a)inspected by a designated person; and
(b) made firm and level by suitable means where necessary.
(3) After placing or advancing a piling frame in a worksite, an inspection and correction of the footing
shall be carried out to ensure stability.
WSH
Falling hazards
(Construction)
22. (1) It shall be the duty of the occupier of a worksite to take, so far as is reasonably practicable,
Regulations 2007
such measures as are necessary to comply with paragraphs (2), (3) and (5) at the worksite where a
Part IV General person is liable to fall a distance of more than 2 meters.
Provisions
(2) Subject to paragraph (4), in a worksite, every open side or opening into or through which a
person is liable to fall more than 2 meters shall be covered or guarded by effective guard-rails, barriers
or other equally effective means to prevent fall.
WSH
Electrical Hazards
(Construction)
Regulations 2007 Electrical power circuits
Part V Electrical
Safety
WSH (General
Provisions)
Regulations
14.(1) It shall be the duty of the occupier of a workplace to ensure that every electrical installation and
electrical equipment in the workplace
(a)is of good construction, sound material and free from defects; and
WSH
Slipping hazards
(Construction)
Regulations 2007 26. It shall be the duty of
Part IV
GENERAL
PROVISIONS
(a)the employer of any person who carries out any work in any passageway, or on any scaffold, platform
or other elevated working surface in a worksite; or
(b)the principal under whose direction any person carries out any work in any passageway, or on any
scaffold, platform or other elevated working surface in a worksite, to ensure that the passageway,
scaffold, platform or other elevated working surface to be used by the person is kept free from slipping
hazards.
Hazards arising from protruding objects
27. It shall be the duty of the occupier of a worksite to ensure that at the worksite
(a)all passageways, stairs, platforms and other means of access or places of work in the worksite are
kept free from debris or protruding objects or any other obstruction that could cause tripping; and
(b)any sharp projection which is present in any passageway, stair, platform and other means of access
or place of work in the worksite and which may injure any person is removed or otherwise made safe.
Reason to use clause:
Protruding and lose materials are possible to laying on the work area. May cause trip and slip
WSH (Noise)
Reg 2011
NOISE CONTROL High noise to worker when pile head knocking to remove the soil.
Measures to reduce or control noise
4.(1) It shall be the duty of the occupier of a workplace to take, so far as is reasonably
practicable, such measures to reduce or control the noise from any machinery or
equipment used, so that no person
NOISE MONITORING, HEARING PROTECTORS AND TRAINING
Hearing protectors
8.(1) It shall be the duty of the responsible person to provide suitable hearing
protectors to every relevant person
Name of Activity :- External Plastering:
S/No
WSH (Operation
of cranes)
Reg 2011
(d)not to carry out any lifting operation unless he has been briefed by the lifting
supervisor on the lifting plan referred to in regulation 4;
WSH
(Construction) Reg
Vehicular hazards
2007
location
Slipping hazards
26. It shall be the duty of
WSH
(a) the employer of any person who carries out any work in any passageway, or
(Construction) Reg on any scaffold, platform or other elevated working surface in a worksite; or
2007
(b) the principal under whose direction any person carries out any work in any
passageway, or on any scaffold, platform or other elevated working surface in a
worksite,
to ensure that the passageway, scaffold, platform or other elevated working
surface to be used by the person is kept free from slipping hazards.
2007
Lighting
32. It shall be the duty of the occupier of a worksite to
(a) provide and maintain in the worksite
(i) sufficient and suitable lighting, whether natural or artificial, in every part of
the worksite in which persons are at work or passing; and
(ii) emergency lighting for use in the event of a power failure affecting the
general lighting; and
(b) ensure that the level of illumination provided by the emergency lighting
shall be sufficient in intensity and distribution to allow for the safe evacuation
or rescue of persons in the worksite.
PERMIT-TO-WORK SYSTEM
WSH
(Construction) Reg Permit for working lifting of cement and sand bags
10. This Part shall apply only to the following types of work that form part of
2007
any building operation or works of engineering construction (referred to in
these Regulations as high-risk construction work):
(a) demolition work;
(b) excavation and trenching work in a tunnel or hole in the ground exceeding
1.5 metres depth;
(c) lifting operations involving tower, mobile or crawler crane;
Implementation of permit-to-work
11.(1) It shall be the duty of the occupier of a worksite at which any high-risk
construction work is or is to be carried out to
(a) appoint a project manager for the worksite;
(b) appoint a safety assessor (who shall be either a workplace health and safety
officer for the worksite or a competent person);
2007
WSH (General
Provision) Reg
2006
Ventilation
5.(1) Subject to paragraph (3), it shall be the duty of the occupier of a factory
to ensure that every workroom of the factory is provided with adequate
ventilation.
Lighting
Sanitary conveniences
8. It shall be the duty of the occupier of a factory
(a) to provide, maintain and keep clean, sufficient and suitable sanitary
conveniences for the persons at work in the factory; and
(b) to provide and maintain sufficient and suitable lighting for these sanitary
conveniences.
Hazardous substances handling the cement for plastering
WSH (General
Provision) Reg
2006
41. (1) All hazardous substances in a workplace shall be placed under the
control of a competent
Person who has adequate knowledge of the properties of the hazardous
substances and their dangers.
(2) Adequate warning notices in languages understood by all persons at work in
a workplace
WSH (General
Provision) Reg
2006
Lifting gears
gear)
(to unload the tile and cement & sand palate using lifting
24. (1) All goods, articles and substances which are stored, stacked or placed
in a workplace shall be
stored, stacked or placed
(a) in such manner as not to interfere with
(i) the adequate distribution of natural or artificial light;
construction worksites
Second Column Construction Safety Orientation Course
Citation 2. First Column (8) Forklift Operators: any person who drives or
operates a forklift truck in a
Factory Second Column Forklift Drivers Training Course
WSH(Scaffolds)
Regulations 2011
Only approved scaffold contractor to construct, erect, install, reposition, alter, maintain, repair
or dismantle certain scaffolds
4.(1) No person shall construct, erect, install, re-position, alter, maintain,
repair or dismantle any scaffold, not being an excluded scaffold, in any
workplace unless he is an approved scaffold contractor.
(2) For the purposes of paragraph (1), excluded scaffold means (a) a tower
scaffold; (b) a trestle scaffold; or (c) a scaffold (other than a suspended scaffold,
hanging scaffold or a scaffold erected on cantilever or jib supports) which, when
completed and excluding the handrails and their supports at the uppermost lift
of the scaffold, is less than 4 metres in height.
(Approved scaffold contractors)
Work platforms 18.(1) It shall be the duty of the responsible person to ensure
that the requirements of paragraphs (2) to (6) are complied with.
(2) Work platforms in a workplace shall be provided
(a) at any place of work which does not afford a proper and secure foothold;
and
(b) in the case of a building under construction, around the edge of the building
at every uppermost permanent floor which is under construction.
(3) Notwithstanding paragraph (2)
(a) work platforms shall be provided at intervals of not less than every alternate
lift of any scaffold,
except a tower scaffold or a trestle scaffold, used in
any premises where building operations
are being carried on; and
(b) unless approval is given in writing by the Commissioner, the vertical
distance between any 2
work platforms shall not exceed 4 metres.
(4) Every work platform provided under paragraph (3) shall cover the lift of a
scaffold throughout its entire
length.
(5) Every work platform provided under this regulation shall
(a) be closely boarded, planked or decked;
(5) The height of toe-boards provided under paragraph (2) shall not be less
than 90 millimetres.
(6) The vertical distance
(a) between any 2 adjacent guard-rails provided under paragraph (2); and
(b) between any work platform or workplace and the guard-rail immediately
above it shall not exceed 600 millimetres.
Inspection of scaffolds 26.(1)
Subject to paragraph (4), it shall be the duty of the occupier of a workplace in
which a scaffold is constructed, erected or installed to ensure that no scaffold is
used unless it has been inspected by a scaffold supervisor
(a) upon completion of its construction, erection or installation, as the case
may be;
(b) thereafter, at intervals of not more than 7 days immediately following the
date of the last inspection by the scaffold supervisor; and
(c) after exposure to weather conditions likely to have affected its strength or
stability or to have displaced any part.
(2) It shall be the duty of the scaffold supervisor to
(a) enter the results of every inspection referred to in paragraph (1) into a
register containing such details as may be required by the Commissioner; and
(b) provide the register to the occupier of the workplace.
(3) Subject to paragraph (4), it shall be the duty of the occupier of the
workplace in which a scaffold is constructed, erected or installed to
(a) keep the register referred to in paragraph (2) at the workplace; and
(b) produce the register for inspection upon request by an inspector.
(4) This regulation shall not apply to
(a) a trestle scaffold; or
(b) a scaffold, from no part of which a person is liable to fall more than 2
metres.
(5) Any person who contravenes paragraph (3) shall be guilty of an offence and
shall be liable on conviction to a fine not exceeding $2,000.
Labelling of scaffolds after inspection 27.(1) It shall be the duty of the
scaffold supervisor who carries out the inspection of a scaffold under regulation
26 to, immediately after such inspection, display a notice or label indicating
whether the scaffold is safe for use or otherwise.
(2) The notice or label referred to in paragraph (1) shall
WSH (Construction)
Regulations 2007
any person who carries out the work, it shall be the duty of
(a)the employer of any person who carries out the work in the worksite; or
(b)the principal under whose direction any person carries out the work in the worksite,
to ensure that
(i)the worksite is barricaded;
(ii)suitable warning signs and warning lights are set up to direct traffic away from the
worksite; and
(iii) Where necessary, the traffic is specially controlled by designated persons.
(2) It shall be the duty of the owner of any vehicle used in a worksite to ensure that the
vehicle is of good construction and roadworthy.
(3) No person shall drive a vehicle of any class or description in a worksite unless he
has obtained the authorization of the occupier of the worksite to do so.
(4) It shall be the duty of the occupier of a worksite to ensure that no person shall drive
a vehicle of any class or description in the worksite, except a person who has obtained
the authorization to do so referred to in paragraph (3).
(5) It shall be the duty of
(a)the employer of any person who drives any vehicle in a worksite; or
(b)the principal under whose direction any person drives any vehicle in a worksite,
WSH (Construction)
Regulations 2007
to ensure that the person does not drive the vehicle unless the person
(i)has been fully instructed as to the dangers likely to arise in connection therewith and
the precautions to be observed; and
(ii) has received sufficient training to operate or drive the vehicle.
(6) Nothing in this regulation shall derogate from the effect of the Road Traffic Act
(Cap. 276).
(7) Any person who contravenes paragraph (3) shall be guilty of an offence and shall be
liable on conviction to a fine not exceeding $1,000 and, in the case of a second or
subsequent conviction, to a fine not exceeding $2,000.
WSH
(Operation of
Cranes)
Regulations 2011
Lifting
Lifting plan
4.
(1) Where any lifting operation involving the use of any crane is carried out in a
workplace by a crane operator, it shall be the duty of the responsible person to establish
and implement a lifting plan which shall be in accordance with the generally accepted
principles of safe and sound practice.
(2) It shall be the duty of the responsible person to ensure that the lifting plan
referred to in paragraph (1) is made available for inspection upon request by an
inspector.
supervisor.
(a)tested and examined the hoist or lift after its installation; and
(b) Issued and signed a certificate of test and examination, specifying the safe working
load of
the hoist or lift.
Lifting gears
WSH
(Operation of
Cranes)
Regulations 2011
WSH (Construction)
Regulations 2007
Storage of goods
Storage and placement of materials and equipment
24. It shall be the duty of
Part IV GENERAL
PROVISIONS
(a)the employer of any person who carries out the work of storing, stacking or placing
materials or equipment in a worksite; or
(b)the principal under whose direction any person carries out the work of storing,
stacking or placing materials or equipment in a worksite,
to ensure that the material or equipment is not stored, stacked or placed so close to any
opening or edge of a floor, scaffold, platform or structure as to endanger persons below
the opening or edge.
24.(1) All goods, articles and substances which are stored, stacked or placed in a
workplace shall be stored, stacked or placed
(a)in such manner as not to interfere with
WSH (General
Provisions)
Regulations
WSH (Construction)
Regulations 2007
Part V ELECTRICAL
SAFETY
(b)the principal under whose direction any person carries out any work in the course of
which the person may come into contact with any part of an electrical power circuit in a
worksite,
Part V ELECTRICAL
SAFETY
(b)the principal under whose direction any person carries out any work in the course of
which the person may come into contact with any electric wiring or cable in a worksite,
WSH(Scaffolds)
Regulations 2011
Only approved scaffold contractor to construct, erect, install, reposition, alter, maintain, repair
or dismantle certain scaffolds
(a) upon completion of its construction, erection or installation, as the case may
be;
(b) thereafter, at intervals of not more than 7 days immediately following the
date of the last inspection by the scaffold supervisor; and
(c) after exposure to weather conditions likely to have affected its strength or
stability or to have displaced any part.
(2) It shall be the duty of the scaffold supervisor to
(a) enter the results of every inspection referred to in paragraph (1) into a
register containing such details as may be required by the Commissioner; and
(b) provide the register to the occupier of the workplace.
(3) Subject to paragraph (4), it shall be the duty of the occupier of the workplace
in which a scaffold is constructed, erected or installed to
(a) keep the register referred to in paragraph (2) at the workplace; and
(b) produce the register for inspection upon request by an inspector.
(4) This regulation shall not apply to
(a) a trestle scaffold; or
(b) a scaffold, from no part of which a person is liable to fall more than 2 metres.
(5) Any person who contravenes paragraph (3) shall be guilty of an offence and
shall be liable on conviction to a fine not exceeding $2,000.
Labelling of scaffolds after inspection 27.(1) It shall be the duty of the
scaffold supervisor who carries out the inspection of a scaffold under regulation
26 to, immediately after such inspection, display a notice or label indicating
whether the scaffold is safe for use or otherwise.
(2) The notice or label referred to in paragraph (1) shall
(a) be in a form readily understood by the persons employed in the workplace;
and
(b) be displayed at every designated access point.
(3) Subject to paragraph (4), it shall be the duty of
(a) the employer of any person who uses or is to use any scaffold in a workplace
to which regulation 26 applies; or
(b) the principal under whose direction any person uses or is to use any scaffold
in a workplace to
which regulation 26 applies,
to ensure that the person does not use the scaffold unless a notice or label is
displayed at the designated access point indicating that the scaffold is safe for
use.
(4) Paragraph (3) shall not apply in relation to a person who is
WSH (General
Provisions)
Regulations
Ventilation
5.(1) Subject to paragraph (3), it shall be the duty of the occupier of a workplace to
ensure that every workroom of the workplace is provided with adequate ventilation.
[S 517/2011 wef 10/09/2011]
(2) Where gases, vapours or other impurities are generated in the course of any process
or work carried out in a workplace which may be injurious to health, it shall be the duty
of the occupier of the workplace to provide effective and suitable ventilation
(a)for securing and maintaining the circulation of fresh air in the workplace; and
(b) to render harmless, so far as is reasonably practicable, all such gases, vapours or
other impurities.
[S 517/2011 wef 10/09/2011]
Lighting
6. It shall be the duty of the occupier of a workplace to provide and maintain sufficient
and suitable lighting, whether natural or artificial, in every part of the workplace in
which persons are at work or passing.
Storage of goods 24. (1) All goods, articles and substances which are stored,
stacked or placed in a factory shall be stored, stacked or placed
(a) in such manner as not to interfere with
(i) the adequate distribution of natural or artificial light;
(ii) the proper operation of any machinery or other equipment;
(iii) the unobstructed use of passageways or traffic lanes; and
(iv) the efficient functioning of sprinkler systems or the use of other fire-fighting
equipment;
(b) on a firm foundation not liable to settle;
(c) in such manner as not to overload the foundation or floors; and
(d) in such manner, and using such supporting structures as may be necessary, as to
ensure the stability, and to prevent the collapse, of the goods, articles or substances.
Hazardous substances 41. (1) All hazardous substances in a factory shall be placed
under the control of a competent person who has adequate knowledge of the properties
of the hazardous substances and their dangers.
(2) Adequate warning notices in languages understood by all persons at work in a
factory specifying the nature of the danger of the hazardous substances shall be placed
(4) All hazardous substances in a factory shall be kept, stored, used, handled or
disposed of in such a manner as not to pose a risk to the health and safety of any person
at work in the factory.
(5) It shall be the duty of the occupier of a factory to comply with paragraphs (1) to (4).
(6) Any person at work in a factory who wilfully or recklessly does any act that may
result in any other person being exposed to hazardous substances shall be guilty of an
offence and shall be liable on conviction to a fine not exceeding $20,000 or to
imprisonment for a term not exceeding 2 years or to both.
Warning labels 42. It shall be the duty of the occupier of a factory in which there is
any container of hazardous substances to ensure that, so far as reasonably practicable,
every such container is affixed with one or more labels that
(a) are easily understood by all persons at work in the factory;
(b) warn of the hazards involved with the hazardous substance in the container; and
(c) specify the precautionary measures to be taken when dealing with the hazardous
substance in the container.
Safety data sheet 43. (1) Where any hazardous substance is used, handled or stored
in a factory, it shall be the duty of the occupier of the factory to
(a) obtain a safety data sheet of the substance;
(b) assess the information in the safety data sheet and take precautionary measures to
ensure the safe use of the substance; and
(c) make available the safety data sheet to all persons at work in the factory who are
liable to be exposed to the substance.
(2) Where any hazardous substance is sold to any person for use in a factory, the seller
or any agent of the seller who caused or procured the sale shall provide the buyer with a
safety data sheet for the substance, giving accurate and adequate information on the
substance, including as far as is reasonably practicable
(a) information on the identity of the substance;
WSH
(Construction)
Regulation
3.
CONTROL OF
VECTORS AND
PESTICIDES
ACT
(CHAPTER 59)
4.
PART IV
CONTROL OF
VECTORS AND
PESTICIDES
ACT
(CHAPTER 59)
(b) advertise or otherwise hold himself out as a vector control operator, unless he is
registered as a vector control operator under this Act.
PART V
CONTROL OF
VECTORS AND
PESTICIDES
ACT
(a)in the course of any trade or business, undertake or engage in vector control work; or
(CHAPTER
59)PART V
CONTROL OF
VECTORS AND
PESTICIDES
ACT
(CHAPTER 59)
PART V
granted under section 29(3)(a) shall each be valid for a period of 3 years from the date
of the grant and subject to the provisions of this Act, may each be renewed upon its
expiry.
3. Generate an inspection plan and conduct inspection for at least any 4 of the workplace activities identified in item 1 to
check for compliance against the legal and other requirements.
Assessment criteria
Yes
No
Description of non-compliance
(including exact location)
Recommended
corrective measure and
timeline
displayed?
2
Any
designated/trained
valid license?
Lifting operation
Lifting Machine Crawler / out
1
rig rested on steel plate
Lifting machine and lifting
2
gears have valid certificate
No proper access to
concrete mixer lorry at
Blk 10A
Provide
steel Mr Tan, General
plate with hard foreman
core base.
Lifting
supervisor
should ensure all
the
lifting
activity should
be cordon off
and
Lifting
Crews
must
present at the
lifting area.
Not checked for past Lifting
2days
supervisor must
ensure
that
crane daily check
list
maintain
properly.
MrKannan,
Lifting
supervisor
MrKannan,
Lifting
supervisor
Machine Hazards
1
2
3
4
Electrical Hazards
1
2
Mr.Karim Bin
kadier ,
Electrical
foreman
Falling Hazards
Mr Kannan,
Lifting
supervisor
the lifeline?
All bore holes is covered?
work practice.
Raise up casing
height at least 1
meter from
ground level
immediately
Mr Tan, foreman
Tripping Hazards
Site supervisor
No training provided
to the rebar bending
Machine operator
Mr Hossian ,
foreman
Arrange inhouse
training for
operators
immediately
plug , )
4
Not available
(stakeholders)
Arrange for
noise labelling
process not
paste the lable
immediately
Mr Hossain,
foreman
Item
Yes
Recommended
corrective measure and
timeline
Assessment criteria
No
Description of non-compliance
(including exact location)
Plastering Works
Permit to work system
1
PTW Displayed in
area?
work
No .
Observed
didnt
Separate PTW
for work at
height need to
applied
Trade
supervisor
Brief
workers
on selection &
usage
of
appropriate
PPE.
In
addition,
Supervisor
PPE
workers
wear an appropriate
respirator
while
performing painting
work
provide training
on safe method
of wearing PPE.
Advice to worn
safety
glasses
while doing the
Foreman
painting work.
Scaffolds
1
2
3
4
No scaffold
inspection
experied
Scaffold
flat
from
stored with excessive
construction material?
Chemical Hazard
1
2
3
4
Warning signage
displayed relating to
chemical hazard?
Harness to be
100%,tie-off
while working
at height
HSE Supervisor
Worker
worn
appropriate PPE
to
avoid
expose
to
chemical?
SDS
briefed
to
workers?
SDS Displayed in the
work area?
No , involved workers
not wearing any
respirator during
plastering.
Conduct toolbox Mr
Hossain,
meeting educate foreman
pupose
of
respirator
during
plastering.
Not displayed
Display SDS
immediately
Mr karthik,
plastering
supervisor
(stakeholders)
Item
Assessment criteria
Yes
No
Description of non-compliance
(including exact location)
Recommended
corrective measure
and timeline
Action By Person/
Party)
Vehicular Hazard
Any designated/trained
person controlled Traffic?
Lifting Operation
Immediately to
Traffic controller
display suitable Safety
warning signage supervisor
for vehicles and
as a traffic
controller
ensures to check.
Storage of Goods
Sufficient lighting is
provided?
Unobstructed use of
passageways is Provided?
Electrical Hazards
Mani ,Site
supervisor/
Mani ,Site
supervisor/
Supervisor
ensures to check
all the electrical
equipment and
tools should be
guarded.
Vimal .Safety
supervisor
Vimal .Safety
supervisor
Electrical appliance or
current carrying
equipment is effectively
earthed?
Work platform
Ventilation
As supervisor
should ensure to
check the
working area
and should be
provided
suitable &
effective
Site supervisor
Safety
supervisor
ventilation for
the working
place.
2
Manual Handling
2
3
No
Educate worker
to wear
appropriate PPE
for respective
work
Padding or warping
provided when stack the
material?
Site supervisor
9.Noise Hazard
1
Educate worker
to wear proper
hearing
protector
Site Superviser
(stakeholders)
Item
Assessment
criteria
Yes
No
Has the
appointed pest
control operator
submitted the
vector control
programmed to
the Vector
Control
Department,
NEA?
a
b
1. 2. Environment
Access free from
obstruction
Fogging area
provided with
Description of non-compliance
Recommended
corrective measure
and timeline
adequate
lighting.
3.PPE
a
Vector Control
provided with
appropriate
PPE?
Is the PPE in
good working
condition?
Inspected by :sanjeevi ,
WSHC
(stakeholders)
4. Plan for and administer mandatory training in WSH for the relevant personnel at the workplace which include : x 1 (Only
include training courses Madatory/ non-madatory related to the work activity)
S/No
Title of mandatory
Training course
Conducted by (Name of
Approved Training Provider
Lifting
supervisor
course
BCA
1/07/2013
Scaffold
supervisor
course
Mega Engineering
Rana-site supervisor
11/07/2013
Scissor lift
(MEWP)
Gammon
Suresh- Supervisor
15/07/2013
Training Course
Chemical Safety
Awareness
Course
Moorthy Supervisor
15/07/2013
05
Work at height
course for
supervisor
Jackson
29/7/2013
Name of
workers/supervisor
Course attended
Ah Seng (Site
supervisor)
S/No
1
2
Results
12/07/2013, BCA
Passed
Suresh- Supervisor
Passed
20/07/2013 , Gammon
Moorthy
Supervisor
Chemical Safety
Awareness Course
Passed
(Scaffold Supervisor)
05
Jackson
Pass
5. Indicate ways to monitor and manage WSH legal compliance issues which may include: (Provide evidence) x 1
a.
b.
c.
d.
e.
S/No
Inspections
Compliance audit
Tracking of new and amendment to legal requirements
Advising on actions to stay in compliance
Method to Monitor
WSH Legal
Compliance
Legal requirements
Non-compliance
found or
New legal
Requirements
Inspection
Subscribe to OSH
alert
Excavation more
than 1.5m. but there
is no provide
shoring
New legal
requirements
New legal
requirements
Compliance Audit
New Regulation
Eg. Consultant
Regulations
Requirement
Register
Collapse of falsework
Cutting
Collapse of formwork
Noise
Inhalation of dust and
solvent
Step on object
Struck by falling object
Collapse of scaffold
Collapse of sides
Struck by moving
vehicle
vibration
Step on object
Structural instability during
demolition process
vibration
vibration
2. Recommend at least one control measure for each of the hazard identified (in item 1) in relevant context with :- x 4 (one for each activity)
Process External Plastering
Risk :- Falling from Height (Working on A-Frame Ladder)
Hierarchy of Control
Elimination
NA
Substitution
NA
Engineering Control
Administrative Control
Elimination
NA
Substitution
N/A
Engineering Control
Administrative Control
NA
SAFETY TALK
NA
Elimination
NA
Substitution
N/A
Engineering Control
Administrative Control
Elimination
Substitution
Engineering Control
N/A
Administrative Control
3. Recommend control measures for different stages of construction projects to relevant stakeholders for formulation of
implementation plan in accordance with the hazards identified- x 4
4. RA for Bore Piling Works
Risk Assessment Report-1
Company
Conducted by
SANJEEVI
Process
12/06/2013
Location
11/06/2016
Hazards
identified
Possible Accident
/ill-health & Persons
at risk
Risk Index
1.
Access preparation
for boring rig
Overloading of
crane
Fatality/Bodily injury
due to crane
collapse.
Engineering:
1. Park the machine on
level ground.
2. All rigs to be sited on
steel plate during
operation.
3. Level the ground if
Additional Control
Measures
Re Ma Me 1. Daily toolbox
meeting.
Action Officer
(Designation
and follow-up
date)
Robert (Site
supervisor)
2. Refresh
training SWP.
Kumar (Lifting
supervisor)
3. Inspection of
ground
condition by
John (Site
safety
supervisor)/ On
necessary, do not
overload crane.
4. Hard-core to be laid if
soft ground conditions.
2
Pre-Boring
Open side of
bore hole
Bodily Injury/Fatality
due to person falling
with holes.
Engineering:
1. Auger/boring bucket
should not be removed from
bored hole until casing is
ready to be installed.
2. Steel mesh is to be
placed on bored holes.
lifting
supervisor
before start
work for the
day.
Re Ma Me 1. Daily toolbox
meeting.
2.Refresher
training SWP and
fall protection plan
going
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
Administrative:
1. Only trained or authorized
operators can operate
equipment or machinery.
2. Only authorized workers
are allowed to work near the
bored hole are.
3. SWP and fall protection
plan.
3
Lifting point
welding give
away
Bodily
Injuries/Fatality due
to casing failure.
Engineering:
1. The lifting Point to be PE
design.
2. Check all lifting gears,
wire ropes with shackles to
be suitable for the lifting.
3.SWP
4.Proper use of safety
helmets
5. Proper use of safety
boots and cotton gloves.
6.PTW,FPP, LP
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP.
Robert (Site
supervisor)
Kumar (Lifting
supervisor)
John (Site
safety
supervisor/ Ongoing.
Lifting Gears
Corroded
Administrative:
1. Competent signalman
person to be present at all
times.
2. Proper communication
between signalman and
operator.
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP.
Kumar (Lifting
supervisor)/Ongoing
3. Supervision by lifting
supervisor.
4. Use of tagline to control
suspended load.
5. Lifting team should keep
a look out and warn people
to stay away from operation
area.
6. Do not hoist suspended
load over workers
8. Qualified crane operator
to operate crane.
9. Use only certified lifting
machine and lifting gear.
10.Apply PTW
11.SWP,FPP,LP,ERP
PPE:
1.Use safety Helmet
2. Safety shoe/boots.
Placing of
casing into the
hole .
Fatality/Bodily injury
Engineering:
1. The casing has to be at
least 3m or 15% of casing
length embedded into
ground.
2. Boreholes to be done to
depth of only 70% of casing
length.
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP.
Robert (Site
supervisor)
John(Site
safety
supervisor)/
On-going
Administrative:
1. Only trained or authorized
operators can operate
equipment or machinery.
2. Only authorized workers
are allowed to work near the
bored hole are.
3. Competent signalman to
be present at all times.
4. Proper communication
between signalman and
operator.
5. Supervision by lifting
supervisor.
6. SWP.
6
Remove loose
materials using
cleaning bucket
Uncovered bore
hole
Fatality/Bodily injury
Engineering:
1. To ensure that the height
of casing is about 1 metre
from ground.
2. Covered bored hole with
steel mesh.
Fatality/Bodily injury
Engineering:
1. To ensure that the height
of casing is about 1 metre
from ground.
2. Covered bored hole with
steel mesh.
Not hooked
designed
Rigging point
Fatality/Bodily injury
due to cages
collapse
Administrative:
1. Competent signalman to
be present at all times.
2. Proper communication
between signalman and
operator.
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP &
FPP
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP &
FPP
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP &
FPP
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
3. Supervision by lifting
supervisor.
4. Use of tagline to control
suspended load.
5. Lifting team should keep
a look out and warn people
to stay away from operation
area.
6.Do not hoist suspended
load over workers/buildings
7. Do not stand under
suspended load.
8. Qualified crane operator
to operate load.
9.Use only certified lifting
machine and lifting gear.
10.PTW,SWP,
11. Suitable PPE
9
Concrete work
Vehicle Enter/
Exit in site
without
banksman
Guidance.
Fatality/Bodily injury
due to vehicle hit
working personnel.
Administrative:
1. Designate traffic
controller.
Re Ma Me 1. Daily toolbox
meeting.
2. Refresher
training SWP
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
4.SWP
10
Excessive heat
Excessive dust
Faint, dehydration or
heat stroke to
person
Inhalation of dust by
person
Administrative:
Re Mo Lo
Administrative:
1. If possible, minimize the
Re Mo Lo
1. Supervisor is to
ensure workers
drink plenty of
water.
Robert (Site
supervisor)
2. Daily toolbox
meeting.
John (Site
safety
supervisor)/
On-going
Daily toolbox
meeting
Robert(Site
supervisor)
John (Site
safety
supervisor)/
On-going
Working under
noisy area.
Excessive noise
Noise induce
deafness to person
Engineering:
Re Mo Lo
1.Supervisor on
duty is to remind
workers to use ear
plugs
2. Daily toolbox
meeting.
PPE:
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
Manual handling
Repetitive
movement
Bodily injury
Engineering:
1. When possible use
mechanical means such as
cranes, wheel barrow etc.
Administrative:
1.Reduce the weight of the
load
2. Assign additional worker
to help.
3. Implement job rotation.
PPE:
Proper use of hand gloves.
2. Proper use of safety
shoes/boots.
Re Mi
Lo
1. Daily toolbox
meeting
2. Need
demonstration of
safe procedures of
Manual Handling
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
12
Emergency
situation
Due to
rushing/run the
person
Administrative:
Re Mo Lo
Likelihood (L)
Abbreviation
Severity (S)
Abbreviation
Abbreviation
Remote
Re
Minor
Mi
Low
Lo
Occasional
Oc
Moderate
Mo
Medium
Me
Frequent
Fr
Major
Ma
High
Hi
Conducted by
SANJEEVI
Process
12/06/2013
Location
11/06/2016
Emergency drill to
be conducted
every six month by
main contractor.
Robert (Site
supervisor)
John (Site
safety
supervisor)/
On-going
Delivery of Materials
Pre-Packed Spatter
Dash
Cement
Sand
Additive
Pre-packed plaster
Corner Beads
Wire Mesh, etc
Unloading of
Materials
Worker could
suffer injury &
long-term pain if
regularly lifting /
carrying heavy or
awkward objects
Security check,
properly
constructed access,
traffic controller,
traffic warning
signs
Poor visibility
Injury / Death to
person(s) and / or
damage to property/
site facility due to
collision between
vehicle man /
machine / material /
property
Security check,
properly
constructed access,
traffic controller,
traffic warning
signs
Parking at Uneven
ground, over load
Security check,
properly
constructed access,
traffic controller,
traffic warning
signs
Parking at Uneven
ground, over load
Outrigger fully
extended, qualified
lifting personnel of
lifting supervisor,
rigger and signalman
Ma
Re
Med
Ma
Re
Med
Ma
Re
Med
Ma
Re
Med
Regular
maintenance of
site access &
traffic signs that
are subjected to
wear & tear
Security
Guard &
Appointed
Person in
charge of
site exit /
entry point
Regular
maintenance of
site access &
traffic signs that
are subjected to
wear & tear.
unload in day
time only
Security
Guard &
Appointed
Person in
charge of
site exit /
entry point
Regular
maintenance of
site access &
traffic signs that
are subjected to
wear & tear
Security
Guard &
Appointed
Person in
charge of
site exit /
entry point
Standing
supervision by
Lifting Supervisor
Lifting
Supervisor,
Rigger &
Signalman
Unloading of
Materials
Toppling of material
leads to Injury /
death to person(s) &
damages to
materials
Unloading zone
cordoned off,
qualified lifting
personnel, truck /
lorry crane
stationed on even
ground
Using of corroded
lifting gear
Failure of lifting
gear leads to Injury /
death to personnel
and property
damage
Untrained rigger
Material topple,
failure of rigging
gear due to wrong
selection of rigging
gear
Qualified rigger
Blind spot
Signalman to
communicate with
Back injury
Display of correct
manual lifting
technique at site
notice board
Store on even
ground / pallets with
proper stacking
within safe height
(contd)
Storage of Materials
Mo
Re
Low
Ma
Re
Med
NA
Lifting
Supervisor,
Rigger &
Signalman
Lifting
Supervisor
Implement
periodic check list
for LG
Ma
Re
Med
Ma
Re
Med
Ma
Re
Med
Mi
Re
Low
WSHO /
WSHS
Advance
scheduling or
urgent recall of
qualified rigger
for unloading
Site
Manager
Daily toolbox
meeting on safe
lifting
Lifting
Supervisor
&
Signalman
WSHO /
WSHS
Foreman-incharge
NA
Storeman
& Foremanin-charge
or death
limit of 2.3 m, no
storage at edge of
excavation / drop &
use of PPE (helmet &
safety boots) at
storage zones
Falling material
leads to Injury /
Death
Mi
Re
Low
NA
Storeman &
Foreman-incharge
Back injury
Display of correct
manual lifting
technique at site
notice board
Mod
Re
Low
Storeman &
Foreman-incharge
Respiratory tract
irritation
Mod
Re
Low
NA
Foreman-incharge &
Use of rubber
gloves by plasterer.
Random inspection
by foreman / safety
personnel
Mod
Use of goggles by
plasterer. Random
inspection by
foreman / safety
Mod
protective goggle
not worn
Skin irritation
Eye injury
WSHO /
WSHS
Re
Low
NA
Foreman-incharge &
WSHO /
WSHS
Re
Low
NA
Foreman-incharge &
WSHO /
WSHS
personnel
Mixing of plaster
cement mortar mix
or pre-packed
plaster
Bad posture
Back injury
Briefing on safe
manual lifting
Mod
Re
Low
NA
Foreman-incharge
Inadequate
respirator
Respiratory tract
irritation
Wearing of
respirator (dust
mask). Random
inspection by
foreman / safety
personnel
Mod
Re
Low
NA
Foreman-incharge
Damaged Electrical
cable exposed
Electrocution leads
to Injury / Death
Suspension of
electric cables on
non-conductive
supports. Provision &
maintenance of safe
Socket-OutletAssembly and
Distribution Board
Ma
Re
Med
Monthly LEW
checks with
prompt follow up
on rectification by
safety personnel
& project team
Foreman-incharge
WSHO /
WSHS &
LEW
Mixing of plaster
cement mortar mix
or pre-packed
plaster (contd)
Putting / filling
cement packet in to
the cement mixer
machine
Safety briefing on
precautionary
measures & effective
guarding of moving
parts of mixer
Mi
Re
Low
NA
WSHO /
WSHS
Foreman-incharge
Transferring of
plaster cement
mortar mix or prepacked plaster mix
to the various
locations of
plastering
Slippery surface
Maintenance of
unobstructed access
and good
housekeeping
condition
Mi
Re
Low
NA
Forman-incharge,
Open edge of a
scaffold
Ma
Re
Med
Weekly Scaffold
Inspection, Weekly
Tool Box Meeting
Forman-incharge,
Scaffold
Safety
Supervisor
(emphasizing on no
prematured removal
Plastering
Ma
Re
Med
Weekly Scaffold
Inspection, Weekly
Tool Box Meeting
and Implement
Permit-To-Work at
Height above 2 m
&
WSHO /
WSHS
Forman-incharge,
Scaffold
Safety
Supervisor
&
WSHO /
WSHS
Skin Irritation
Mi
Re
Low
NA
Foreman-incharge
Accidental contact of
plaster with eye (eg.
dropped into eye)
Mo
Re
Low
NA
Foreman-incharge
Skin Irritation
Mo
Re
Low
NA
Foreman-incharge
Construction material
placed in scaffold
blank
Maintenance of
unobstructed access
and good
housekeeping
condition
Mo
Re
Low
NA
Forman-incharge,
Ma
Re
Med
Weekly Scaffold
Inspection, Weekly
Tool Box Meeting
(emphasizing no
Forman-incharge,
Scaffold
Safety
platform with
guardrails at all open
areas.
Gap
scaffold
platform
Ma
Likelihood (L)
Abbreviation
Severity (S)
Abbreviation
Abbreviation
Remote
Re
Minor
Mi
Low
Lo
Occasional
Oc
Moderate
Mo
Medium
Me
Frequent
Fr
Major
Ma
High
Hi
Re
Med
prematured
removal of cross
bracings at
extensive areas for
plastering works )
and Implement
Permit-To-Work at
Height above 2 m
Supervisor
&
Weekly Scaffold
Inspection, Weekly
Tool Box Meeting
and Implement
Permit-To-Work at
Height above 2 m
Forman-incharge,
Scaffold
Safety
Supervisor
&
WSHO /
WSHS
WSHO /
WSHS
Conducted by
SANJEEVI
Process
12/06/2013
Location
11/06/2016
S/No Description of
Work Activity
(Step-by-step)
Hazards
identified
Possible
Accident /illhealth &
Persons at risk
Existing Control
measures
1.1
Transport of
material and
equipment to
SGH
Pathology site
Vehicle
Reversing
without
Guidance
Hit against
equipment
causing
damage or
crushing
workers
standing
behind/
Vehicles to be
roadworthy and
have valid certificate
and insurance.
Risk Index
Re
Ma
Me
Additional Control
Measures
Action Officer
(Designation
and follow-up
date)
Mr. Ramu
(Safety
Supervisor
(upon
Transportation)
Drivers and
operators must have
valid licences.
Ensure Reversing
warning signal
device in working
condition.
1.2
Transport of
material and
Unsecured
materials
Crush by fall of
Ensure Material/
Equipment secure
Re
Ma
Me
No overloading
Mr. Ramu
(Safety
equipment to
NUH site
loaded on
lorry
load
Safely
Supervisor /
Driver
(upon
Transportation)
2.1
Loading
/unloading of
material and
equipment
using
tower/mobile/lo
rry crane
Lifting
operation by
un authorized
personnel.
Crush by fall of
load
Re
Ma
Me
Lifting Supervisor to
brief the workers
and to coordinate
the operation.
Lifting
Supervisor,
Mr. Ramu
Safety
Supervisor,
Rigger,
Signalman,
crane operator
(upon Material
Handling)
Ensure crane
operator has valid
MOM certification.
For lorry crane,
approved Lorry
Loader Safety
course certificate.
Lifting Supervisor to
ensure the lifting
Permit /lifting plan
are applied and
approved before
work commenced.
2.2
Overloading
of crane
Crush by fall of
load and crane
Re
Ma
Me
Lifting supervisor to
ensure maximum load
capacity of the lifting gears
Lifting
Supervisor
boom.
operator to produce
MOM crane license,
Crane operator to
fully extend all
outriggers on steel
plates and on firm
levelled ground with
all wheels above the
ground.
Miscommuni
cation
between
signalman &
Crane
operator
Crush by fall of
load and crane
boom
Crane Operator
(upon loading
/Unloading of
material)
Site Supervisor
Daily inspection of
crane using checklist
before start work to
ensure all limit
switches are
functional. Lifting
supervisor to ensure
the lifting permit/
lifting plan are
applied and applied
and approved before
work commenced.
2.3
Re
Ma
Me
Lifting
Supervisor
Signalman
Crane Operator
(upon loading
/Unloading of
material))
3.1
Use of
Cantilever
Material
platform to
hoist up air
con ducting
and material.
Work in close
of the
cantilevered
platform
opening
without
proper
anchorage.
Fall of workers
Death/serious
injury to
workers/rigger/
signalman
Ensure independent
life line is there to
anchor accordance
with PE design.
Re
Ma
Me
Lifting
supervisor
Site supervisor
Rigger
Ensure Material
platform has been
inspected by
competent person at
every 7 days
interval.
3.2
overloading
of cantilever
material
platform
Crushing of
workers
/property
damage by
falling material
platform and
worker
Ensure Material
platform has been
inspected by
competent person at
every 7 days
interval.
Ensure not to alter
or modify cantilever
material platform
and follow
manufacturers
recommendations
Ensure materials or
equipment is Within
the SWL of
cantilever material
platform
Mr. Ramu
Safety
supervisor
signalman
Re
Ma
Me
Mr. Ramu
Safety
supervisor
Lifting
supervisor
Site supervisor
Rigger
Signalman
4.1
Handling of
materials &
equipment
Work in close
proximity of
sharp edges
of metal
sheet
Cuts &
lacerations on
Hand injury to
workers
Use padding to
enclose sharp edges
5.1
Drilling holes
and install duct
supports using
Scissors lift
Death/ serious
injury
5.4
Lo
Mr. Ramu
Safety
supervisor / Site
supervisor
Inspection of colour
tagging of electric
drill, tools
&extension cables
by LEW.
Re
Ma
Me
Site Supervisor
Mr. Ramu
Safety
supervisor
Only industrial,
weather proof plugs
& sockets to be
used.
5.2
5.3
Mo
Using of
temporary
electrical
supply with
damaged
cable
Re
Work with
damaged
electrical
tool.
Drilling of
holes in
concrete with
flying chips
and dust
Eye, facial
injuries
Hang up cables
above ground using
insulated cable
stands & S hooks.
Re
Ma
Me
No hanging of cables on
scaffold tubes ,Scissors lift
rails
Site supervisor
Re
Mo
Lo
Site Supervisor
Workers to wear
double eye
protection safety
glasses & face
shield during drilling
Re
Site supervisor
Mo
Lo
Mr. Ramu
(Safety
supervisor
.
5.5
Working on
scissors lift
without
anchorage of
safety
harness.
operation
Death/ serious
injury
Workers to wear
safety harness with
double lanyard and
anchor to mid-rail or
secure anchorage
point provided to fall
restraint. Ensure
work at height permit
is approved and the
checklist is done
before work
commences
6.1
Lifting of Ducts
using manual
lifting or
manual chain
block
Carrying
heavy
materials
alone
repeated
times.
Strain or back
injury
(Workers
involves in
transferring)
Re
Ma
Me
Mr. Ramu
(Safety
supervisor
Site supervisor
Re
Mi
Lo
Site Supervisor
Re
Ma
Me
Lifting Supervisor to
ensure the use of
appropriate lifting gears
(i.e. length & ton of
webbing, shackle, etc.)
Materials are to be
secured belt sling (looping
method).
Lifting
supervisor
6.2
Working with
damaged
lifting gears.
Crush by
falling load
Death/ serious
injury
Rigger to check
lifting gears
(Webbing slings
shackle) daily before
use & report any
defects to lifting
supervisor.
Barricade areas that
are affected by the
lifting operations.
7
7.1
Installing of Air
con ducting
using Scissors
lift
Improper use
of tool
Re
using Scissors
lift
Work with
improper
maintenance
scissors lift.
Head ache
Monthly
Maintenance &
servicing by
competent person.
Re
Overloading
of scissors
lift.
Death/ serious
injury
Re
7.2
7.3
using Scissors
lift
Mo
Mo
Ma
Lo
Lo
Me
Site Supervisor
Daily inspection of
scissors lift using checklist
before use. Ensure
equipment has valid LE
certificate.
Mr. Ramu
(Safety
supervisor)
Mr. Ramu
(safety
supervisor)
Mr. Ramu
(Safety
supervisor)
Site supervisor
Site supervisor
7.4
7.5
7.6
Working with
Scissors lift
in poor
ground
conditions
soft or sandy
grounds,
Workers Crush
by falling
scissors lift.
Standing on
the scissors
lift handrails
to do work
Head /body
injury due to
falling.
Working on
scissors lift
with
overhead
structures.
Hit / crush or
cut by nearby
overhead
structures &
object
Re
Workers to wear
safety harness with
double lanyard and
anchor to mid-rail or
secure anchorage
point provided to fall
restraint. Ensure
W.A.H is approved
and the checklist is
done before work
commences
Re
Oc
Ma
Me
Mr. Ramu
(Safety
supervisor)
Site supervisor
Ma
Mo
Me
Me
Mr. Ramu
(Safety
supervisor)
Site supervisor
Mr. Ramu
(Safety
supervisor)
Site supervisor
each other on
intended
movements.
7.7
7.8
Working
without
secured tolls
Installing of Air
con ducting
using mobile
Scaffold.
Working on
mobile
scaffold
without
extended
outriggers.
Head injury/
shoulder
injury/
Causing
damage or
crush workers
working
nearby / on
scaffold.
Re
Ensure Outrigger
fully extended and
prop to ground level.
Oc
Mo
Lo
Mr. Ramu
(Safety
supervisor)
Site supervisor
Mo
Me
Ensure mobile
scaffold is inspected
and place safe to
Use green tag by
Scaffold Supervisor
Mr. Ramu
(Safety
supervisor)
Mr. Ramu
(Safety
supervisor)
Site supervisor
Ensure Working at
height permit
obtained and
approved by project
manager.
Ensure no
overloading as per
SWL
7.9
Working with
unsecured
working
Death/ serious
injury
Ensure working
platform at least 500
mm width and
Oc
Mo
Me
platform and
unsecured
guardrails on
scaffold.
any components of
scaffold.
Site supervisor
7.10
Working on
scaffold
without
secure tools
and brackets.
Serious injury
Ensure tools,
brackets and other
material is secured
on scaffolding
platform or body.
Oc
Mo
Me
Mr. Ramu
(Safety
supervisor)
Site supervisor
Likelihood (L)
Abbreviation
Severity (S)
Abbreviation
Abbreviation
Remote
Re
Minor
Mi
Low
Lo
Occasional
Oc
Moderate
Mo
Medium
Me
Frequent
Fr
Major
Ma
High
Hi
Conducted by
MR. NANA
Process
Risk Assessment
Date
25/06/2013
Location
24/06/2016
S/No
Description of Work
Activity
Storage of
Chemical
Hazards identified
Balance Chemical
Container left open in a
storage area
Using of unsuitable
PPE which is not
recommended by SDS
of that chemical.
Possible
Accident /illhealth &
Persons at risk
Existing
Control
measures
Spillage of
chemical cause
ground
contamination.
Do not store
chemical on
site use only
sufficient
chemical
Breathing in
fogged smoke
may cause
breathing
discomfort & ill
health
Expose to skin
may cause
dermatitis
Use
appropriate
attire and PPE
Provide
Risk Index
L
Re
Fr.
Mo
Me
Mo
Me
Additional
Control
Measures
Place store in a
cool area Avoid
Direct sunlight
DO not mix
with Water
Conduct
training on
using of
respirator.
Ensure the
fitness of
respirator is
being used.
Fr.
Mi
Lo
Monitor
workers
exposure to
Action Officer
(Designation and
follow-up date)
Mr. Kamal
WSHC
Mr .Kamal
WSHC
emergency
shower
Environmental
contamination
Provide
chemicals spill
kit while
mixing.
Environmental
contamination
Lower
Pressure
Mi
Lo
Re
Mo
Lo
Oc
Mo
Me
Keep nozzle
close to target
Do not spray in
windy condition
Sprayed chemical
inhaled by the user
Respiratory
Irritation / ill
health to user
Respirator ,
Mask
Monitor
workers
exposure to
insecticidesend them for
Medical
examination
periodically.
Mr .Kamal
Monitor
workers
exposure to
insecticidesend them for
Medical
examination
periodically
Mr Hossian foreman
WSHC
Likelihood (L)
Abbreviation
Severity (S)
Abbreviation
Abbreviation
Remote
Re
Minor
Mi
Low
Lo
Occasional
Oc
Moderate
Mo
Medium
Me
Frequent
Fr
Major
Ma
High
Hi
2. Illustrate the appropriate ways (using flowcharts/ template) to communicate the control measures and implementation
plan to the relevant stakeholders
3. Indicate the ways to monitor the implementation of control measures. (see above table)
4. Apply the control measures effectiveness criteria to evaluate the effectiveness of control measures (see above table)
S/No
.
Stakeholder
communicate
d to
Method of
Criteria set to
monitoring
determine
successful
effectiveness of
implementation of control measure
control measures
To install barricade/
toolbox meeting
Site foreman
and workers
Safety inspection
Zero observation
on missing
barricade
No accident and
incident report
arising from falling
implemented
successfully and
completed
Scaffold
erectors and
sub con
plastering
workers
Safety inspection
Scaffolding
Safety inspection
100% anchor
safety harness to
anchorage point
Status at
implementation
completed and
successful
erectors
Report to
management on
status of
implementation
of control
measures and
effectiveness
Truck
drivers/banks
man/Security
guards/
Safety inspection
WSH inspection/
Physical inspection.
At least 90%
compliance - on
tools using on site
were inspected by
LEW.
Implemented and
successfully
completed.