Whatisthetakingoffprocess?
Thequantitysurveyingprofessionhasbeenongoingformanyyears:Theearliestquantitysurveying
practiceonrecordisaReadingfirm,(HenryCooperandSons),whichwasoperatingin1785(Seeley&
Winfield,1999).Predominantly,quantitysurveyorsdealwiththecostsandcontractsofaconstruction
project.
Therearearound75,000professionalquantitysurveyorsworkingintheUKalone(RICS,2010).The
RoyalInstitutionofCharteredSurveyors(RICS)wassetupin1881,andisanindependentprofessional
bodywhichregulatespropertyprofessionalsandsurveyorsintheUKandworldwide.TheRICSprovide
educationandtrainingstandardstoallmembersandprotectsconsumerswithstrictcodesofpractice.The
mottooftheRICSisEstmodusinrebus(whichtranslatesintoEnglishas:Thereismeasureinall
things).TheRICSisrepresentedinover146countriesandhasmorethan159,000members.
BillofQuantities
TheBillofQuantitiesisadocumentwhichisusedforthetenderingprocessinaconstructionproject,in
whichmaterials,parts,andlabourareitemized.Italsodetailsthetermsandconditionsofthe
http://www.constructionchat.co.uk/articles/takingoffprocess/
1/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
constructioncontractanditemisesalltheworkforasubcontractortoprice.
TheBillofQuantitiesispreparedbyaquantitysurveyor.Thepreparationdividesitselfintotwodistinct
stages,thefirstbeingthe
TheessaywilllookintotheTakingOffprocessrepresentedinaBillofQuantitiesandalsolookinto
wheretheTakingOffprocesscanbeused.IwillstartbylookingintowhatTakingOffactually
is.measurementofdimensions,andthecompilationofdescriptionsfromthedrawingandspecification.
ThisisknownasTakingOffwhichisthetopicthatIwilldiscussinthissectionoftheessay.
ThesecondstageisthepreparationoftheBillthisinvolvescalculationsofvolumesandareas(squaring
thedimensions),followedbyenteringthedescriptionsandthedimensiononanabstract(abstracting)and
finallycollecttheitemstogetherandpresenttheminabillorder(billing)(Lee&Trench&Willis,2005).
TheTakingOffProcess
TheTakingOfflistisaprocessofanalysingtechnicaldrawingsandspecificationstoidentifyelements.
Listsshouldincludeeverybuildingelementfromthesmallesttothelargestcomponent.Thedevelopment
ofcomputerisedmeasurementandbillingsystemshavemadethetraditionalmethodlesscommon
nowadayshowever,itisstillusedinpractice(Lee&Trench&Willis,2005).
TheTakingOfflistissymbioticwithRICSNewRulesofMeasurement.TheRICSNewRulesof
MeasurementThisdocumentprovidesfundamentalguidanceonthequantificationofbuildingworksfor
thepurposeofpreparingcostestimatesandcostplans(www.rics.org/uk).TheRICSNewRulesof
Measurementisacodebookwhichdetailsthespecificationandalsomethodofhoweachiteminthe
constructionindustryistobemeasured.Itcoversabsolutelyallphasesofaproposedbuildingproject.
Thepresentationoftheinformationisdoneinclassificationtableswhichprovideinformationonthe
givenitemtobetakenoff.TheuseoftheRICSNewRulesofMeasurementmeansthatallconstruction
projectsaretakenoffinthesamestandardorderandensuresconsistencyacrosstheindustry.Quantity
surveyinghasbecomeincreasinglyinvolvedwithprojectFINANCING ,thustakingoffisavaluable
processtounderstandwhenestablishingprojectfeasibility.FromagoodTakingOfflistaquantity
surveyorcanquantifydimensionsandlatercreateabillofquantities.(Seeley,1999)
Ifthedrawingsareunclear,thenaquantitysurveyorwillenteranyqueriesonaquerysheetforthe
architect.Atypicalquerysheethasthequantitysurveyorsquestionsononesideandthearchitects
answersontheother.
http://www.constructionchat.co.uk/articles/takingoffprocess/
2/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
WillissElementsofQuantitySurveying.ByS.Lee,W.Trench&A.Willis.
Tweet
PreparationoftheBill
ThissectionwilldescribethesecondsectionoftheBillofQuantitieswhichisthepreparationofthebill.
Thisisalsosometimesknownasworkingup.Thisissplitintothreesections.
Share
0
1.Calculationofvolumes,areasetc.(Squaringanddimensions)Squaringthedimensionsand
http://www.constructionchat.co.uk/articles/takingoffprocess/
3/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
enteringtheresultinglengths,areas,andvolumesinthethird(orsquaring)columnofthedimension
41
paper.
Like
2.Enteringthedescriptionsandsquareddimensionsonanabstract(Abstracting)Transferringthe
squareddimensionstotheabstract,wheretheyarewritteninarecognisedorder,readyforbilling
underthecorrectworkheading.
3.Collectingitemstogetherandpresentinginarecognisedbillorder(Billing)Theitemsofwork
whichmakeupthetotalbuildingarelistedintheappropriateworksectionheadingwhichgivesthe
descriptionoftheitemandtherecognisedunitsofmeasurement,asperthelayoutinRICSNew
RulesofMeasurement.Thebillalsocontainsanemptyrateandpricecolumn.Theclientgivesthe
BillofQuantitiestothecontractor,andthecontractorthencanaddshisrateandpricewhen
tenderingfortheproject.(Lee&Trench&Willis,2005)
Themostrecognisedpurposeofthebillisthatitcanbesenttocontractorswhomaywanttotenderfor
theconstructioncontract,andenablesthemtobasetheirpriceonthesameinformation.Takingoffis
veryimportantbecauseitprovidesanaccuratemeasurementoftheconstructionworkneededtobe
carriedout.
Constructioncosts
TheTakingOffprocesscanbeveryusefulinestimatingtheconstructioncostsofaprojectbecauseas
mentionedpreviouslythecontractorbasesthepricingoftheworkontheBillofQuantities.Thebillis
createdbytheclientsquantitysurveyor,whoistraditionallyreferredtoasaProfessionalQuantity
SurveyororPrivatePracticeQuantitysurveyor,andcompletedbythecontractorsquantitysurveyor.Part
ofthebillisthetakingoffprocesswhichneedstobeaccurate,sothecorrectpricingcantakeplace.The
BillofQuantitiesisusedtoassistthecontractorwhenpreparinganestimateforthetender.Thepriced
billthenbecomespartofthecontractdocuments,providingthebasisforthevaluationofthework.
TheTakingOfflistisaveryimportantpartoftheBillofQuantitiesbecauseitallowsthequantity
surveyortousethebillforthevaluationoftheworkcompleted,whichallowshimtoworkoutthestage
paymentsneededinagivencontract.Thecontractorsquantitysurveyorcanalsoworkoutthepricefor
eachstagepaymentofaprojectforeachindividualsubcontractor.
Clientsperspective
Theclientsmainconcernistoseetheprojectcompletedontime,onbudget,andtotherequiredquality.
However,theclientalsowantsbetterinformationontheprojectandthiscanbeprovidedbythetaking
offprocess.ThefinancialinformationintheBillsofQuantitycanbetranslatedintootherinformation
suchascashflows,periodicprojectaccounts,andcostvariations.Theinformationcanthenbeeasily
communicatedtotheclienttokeephiminformedoftheprogressandfinancialstatusoftheproject
(Rashid&Mustapa&Wahid,2006).
Consultantsperspective
Theconsultantrepresentstheclienthehastoensuretheclientgetsvalueformoney.Theconsultant
concentratesonmakingsuretheclientreceiveahighqualityproduct,abuildingwhichiscompletedon
time,andmoreimportantly,withintheestimatedbudget.Thepricedbillbythecontractorprovides
usefulinformationtoaconsultantbecauseitidentifiesthetotalcostoftheprojectandalsothemarket
conditions.Qualitativeandquantitative(includingfinancial)informationpresentedinthetakingoff
http://www.constructionchat.co.uk/articles/takingoffprocess/
4/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
processandthustheBillofQuantitiesprovidestheconsultancywithusefultenderevaluationand
selectionofcontractorforagivenproject.Thepricedbillcanbetranslatedintoaworkprogramme,cost
planandprojectcashflowandbudget.Thiscanhelptomakemoreeffectiveprojectsupervisionandcost
controlling.Thebillalsoprovideseffectivelyashoppinglistofitemsrequired(Rashid&Mustapa&
Wahid,2006).
Contractorsperspective
WhentenderingforaconstructionprojectthecontractorisgiventheBillofQuantitiesbytheclient.Thisincludesthe
TakingOfflist,whichisassociatedwithestimatingasittakesplacepriortotheconstructionprocess.Theestimating
departmentofthecontractorthencalculatesasaccuratelyaspossiblethecostsofthegivenconstructionproject.The
estimatorusescurrentpricinginformationfordifferentaspectsoftheproposedconstruction(Ashworth,2002).
TheTakingOfflistisofmostimportancetothecontractorwhenestimatingcosts,becauseitcanbeused
tocalculatethecostsforpreparationofthetender.ThebillisbasedontheTakingOfflist.Eachcompany
usesitsowntablesofstandardworkoutputsfordifferenttypesofconstructionoperationwork,which
theyenterintotheunpricedbill.Whenthisiscompletedthebillcanbesaidtohavebeenpriced,andcan
besentbacktotheclient.TheTakingOfflistintheBillofQuantitiescanbeusedbythecontractorwhen
preparingpricingfornewprojectsasanestimateoftheconstructioncosts.Thisshouldbereviewedoften
whenconstructionstarts(Ashworth,2002).
TheTakingOfflistisessentialinworkingoutthetargetcosts.Theestimatedcostsareadoptedasa
basisoftheconstructionoperationscostsonsite.Thetargetorbudgetcoststrytorelatetotheactualtasks
happeningonsite.Inthebilltheestimatorusesanaverageoutputforthewholeofagivenitem.These
costsarethenanalysedseparately,dependingonthetypeorworkandthedifficultly.Thetargetcostsuse
theaverageestimatorsrateasbasisbutwillvarythisinrelationtotheactualachievementexpected.
Targetcostsareoftenslightlylowerthantheestimatedcostbecauseofacontractorsincentivescheme
andtheunforeseenriskwhichisinvolved(Ashworth,2002).
Thefinaltypeofcostistheactualcostpreviouslythebasisofworkingouttheestimatedcostsand
targetcostwastheTakingOfflistandthebillintheBillofQuantities.Theactualcostuserecordeddata
onsite.Actuallabouroutputsfromthesitearecomparedwiththebudgetoutputs.Whencomparingthe
estimatedcostsandactualcosts,thismayshowahugedifferencehowever,comparingtheactualand
targetcostsshouldshowonlyasmallamountofdifference(Ashworth,2002).
Subcontractors
ThemaincontractorcanusetheTakingOffprocesstoassistwiththeseparationoftheBillofQuantities
intotradesectionsfordifferentsubcontractors.Theseparatedestimatedpricedsectionswillbesentoff
toseveralsubcontractorsfortheirownpricing,andthensentbacktothemaincontractorforcomparison.
Notjustthelowestpricewinstheworkthemaincontractorwilltakeintoaccountitemssuchasprevious
experience,reputation,flexibility,time,qualityofworketc(Ashworth,2002).
Materials
Whenobtainingquotationsformaterialstobeusedonsite,theTakingOffprocesscanbeused.Thebills
aresenttosuppliersandtheysendbackapriceforthematerials.Commonmaterialsthatthecontractor
mayrequirecanbepurchasedthrougharegularlocalsupplier.Thepricingofthematerialcanbeaffected
byanumberoffactorssuchasordersize,deliverycostsandexchangerates.TheBillofQuantitiesis
splitintoorderedsectionsaccordingtoRICSNewRulesofMeasurement.Thisallowsthematerial
http://www.constructionchat.co.uk/articles/takingoffprocess/
5/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
orderingtobeeasilyidentifiedandcarriedout(Ashworth,2002).
Informationsenttothesupplierwillinclude:
1. Specificationofthematerial(whichisusuallyfoundinthepreambleoftheBillofQuantities).
2. Quantityofthematerialrequired(whichisusuallyfoundinthebillsectionoftheBillof
Quantities.)
3. Theaddressofthesite.
4. Thedeliverydatesrequiredbythecontractor.Thisisveryimportanttoallowstoragespaceonsite,
storagecosts,extraspacefordeliveriesandaforemantobepresentwhenunloadingthematerials,
ifrequired.
(Ashworth,2002)
Plant
TheTakingOffProcesscanbeveryusefulinaproposeddevelopmentprojectwhenobtainingquotations
forhire,lease,orpurchaseofplantandequipment.Thechoicebetweenrentingandpurchasingplantis
normallycalculatedfinanciallytoseeifitisviable.Thisisbasedupontheexpecteduseofthegiven
plant.TheTakingOffprocesshastobecorrect,andthecorrectinformationhastobesent.
Labour
TheTakingOffprocesscanalsohelpwithforecastingthelabourcosts.Thesecostsareusuallycalculated
usinganallinlabourrate,includesthebasicrateandguaranteedbonusplusitemssuchasweather,sick
pay,tradesupervisions,andextrapayments(forexampleskillorresponsibilityforrisk).
Themostcommonmethodofestimatingthecostsoftheconstructionworkisunitratesthiscanbeused
tomeasuretheBillofQuantitiesbythecontractor.Suchitemsaslabour,materials,subcontractors,and
plantcanallbemeasuredthisway.
BreakdownofMainParties
Belowisabreakdownofwhattheclient(representedbyaconsultancy)andacontractorofferinthe
tenderingprocess.
Providedbytheconsultants:
Theworktobeperformed
Thequalityandstandardsorworkrequired
Thecontractualconditionstobeapplied
Providedbythecontractor:
Thecostofthefinishedworks
Theconstructionprogramme
(Ashworth,2002)
OperationalWorkandProjectManagement
http://www.constructionchat.co.uk/articles/takingoffprocess/
6/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
NotonlyistheTakingOffprocessavaluablesourceofinformationinthetenderingprocessbutitcan
alsobeusedthroughouttheoperationalworkofaconstructionproject.Theaccuracyandthewaythe
TakingOfflistisdrawnupisveryimportantinthemanagementoftheproject.Ifthesiteteam
understandexactlywhattheTakingOffprocesssaysitcanleadtomoreeffectivemanagementofthe
projectandthegiventrades.Thelistofworkitemsandtheirquantitiesinthebill,givesthecontractora
detailedWorkBreakdownStructure(WBS)oftheproject.Thisisextremelyusefulinformationbecause
ithelpsinprojectplanningandpreparationoftheworkplanandprogramme.Itcanbeusedtoorganise
activitiesinalogicalsequencefordifferentsubcontractorsandcanbeusedtoestimatetheactivity
duration.Theestimatedcostsinthebillarealsousefultomonitorandcontroltheprojectfinances
(Rashid&Mustapa&Wahid,2006).
ProjectCostManagement,whichisabalancingofdemands,isanessentialpartofprojectmanagement.
Garrison(1998)believedthatinformationisvitaltothesuccessoffinancialmanagement.Inthe
absenceofadequate,accurate,andreliablecostinformation,aprojectcostmanagementexercisewould
beineffective.ThisshowsthattheTakingOffprocessisveryimportant.TheTakingOffprocesscan
alsohelpwiththeprojectdevelopmenthoweverthisalldependsonthetypesandemphasisofthe
project,egifthecostisthebiggestemphasisoftheprojectandthefundislimiteditisappropriatetouse
thebillbecauseitcontainshighlevelsofdetailofprojectcostitems.Thiscanthenbeusedfordetailed
projectaccountingandfinancialreporting(Rashid&Mustapa&Wahid,2006).
(Ashworth,2002)
TheabovediagramshowshowtheTakingOffprocesscanbeusedtohelpwithprojectrelatedcosts.An
estimatorestimatesthecostoftheworktobeperformedwhichisbasedonthebillintheBillof
Quantities.Ifthecontractorissuccessfulinwinningthetenderthentheworkcanbeputintopractice.
Theprojectcostscanbemonitoredbythesitemanagementteamwhichcanthenbecomparedtothe
TakingOffprocess.Finallythecomparisonofthecostcanbesentbackasfeedback,whichcangive
informationontheworkandthetimeexpendedonalltheoperations.Thiscanberecordedandused
throughouttheproject(Rashid&Mustapa&Wahid,2006).
Law
TheTakingOffprocessispartofthecontractdocumentsinaconstructionproject.Thuswhensigning
thecontractdocumentyouarewillingtoacceptthatitiscorrectandyouwillbeheld(liable)to
everythinginit.TherearemanystandardformcontractswhichcanbefollowedsuchastheJCT(Joint
http://www.constructionchat.co.uk/articles/takingoffprocess/
7/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
ContractsTribunal)2005whichhasasectionfortheBillofQuantitiesandhasitslegalobligationsallset
out.(JCT,2010)
Conclusion
Asshown,theTakingOffprocesscanbeusedinmanyadministrationstagesofaproposeddevelopment/
constructionproject.BecausetheBillofQuantitiesisacontractdocumentitisalsoveryusefulforthe
legalsideofaproject.However,thebillisnotnecessarilyusefulineverytypeofprocurementmethod.I
havespokenabouttheTakingOffprocessinthetraditionalsensehowever,modernmethodsof
procurement,(forexamplefasttrackingprocurement,whichinvolvesdesign,documentationand
construction)tendtoruninparallel,thusrequiringnoBillofQuantities.Howeverthecontractorstill
mustprepareapropercostdocumentforthebidding.
Despitetheemergenceofnewgenreofprocurementsintheglobalconstructionindustry,theTaking
Offprocessisstillviabletobeusedasakeycostdocument.(Rashid&Mustapa&Wahid,2006)
References
Seeley,I&Winfield,R1999,BuildingQuantitiesExplained,Edition5,PalgraveMacmillan,UK
Lee,Sandra&TrenchWilliam&WillisAndrew2005,WillisselementsofQuantitySurveying,Edition
10,BlackwellPublishing,UK
Ashworth,A2002.Precontractstudies,developingeconomics,TenderingandEstimating,2ndEdition,
BlackwellPublishing,UK
Websites
RICS2013,RICSUK,availableat<http://www.rics.org/uk>
Journals
Rashid,R&Mustapa,MandWahid,S.(2006).BillsofQuantitiesAreTheyStillUsefulandRelevant
Today?InternationalConferenceonConstructionIndustry.1(1),19.
Leaveacomment
http://www.constructionchat.co.uk/articles/takingoffprocess/
8/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
12comments
Addacomment
AsjathKhan
SOTHANKS/.,/,/.
ReplyLikeFollowPost21Aprilat23:03
KristianHammondOwner/DirectoratPriestleyandTaffsLtd
Thisisveryinteresting,however,Imustadmit,inallmyexperienceinconstructionasa
QuantitySurveyor,CostManagerandnowOwnerIhaveneveractuallyhadtoprepare,nor
receivedfromasubcontractoratakeoffinthisformat.Thisisanextremelytimeconsuming
exercise,whichisdifficulttounderstandwithoutanytraining.Anaccuratetakeoffcanbe
preparedinamuchmoresimplisticwayasanexpansionofascopeofworks.Ihaveto
admit,Ifindthismethodveryoutdated.
ReplyLike
1 FollowPost6Februaryat17:54
View9more
Facebooksocialplugin
FindusonFacebook
ConstructionChat
Like
2,159peoplelikeConstructionChat.
Facebooksocialplugin
http://www.constructionchat.co.uk/articles/takingoffprocess/
9/10
5/3/2015
Whatisthetakingoffprocess?ConstructionChat
Tweets
Follow
China Xinhua
News
@XHNews
12h
Tweet to @ConstructChat
Testimonials
Articles
Contact
TermsandConditions
Privacy
Advertise
2013ConstructionChat.Allrightsreserved.CompanyNo.08605415
http://www.constructionchat.co.uk/articles/takingoffprocess/
10/10