Schedule
Deliverables
Work in Progress: SPS 2.0 (OGC09-000)
Work in Progress: sweCommon (OGC 08-094)
Work in Progress: SPS for EO Application profile (OGC 07-018)
Work in Progress: SFRE Requirements Baseline Document
AOB
RESTRICTED
DMS-DQS-QREPM04-MOM-20-E
Minutes of Meeting
Code:
HMA-FO-DMS-PMD-MOM01-E-R
Issue:
1.0
Date:
05/11/2009
Page:
2/3
Actions
Issues
Due
No.
Actionee
Minutes to be written by Reuben and added to HMA wiki, along with slides
RW
06/11/09
Action tracking for Task 2 will use the same format of spreadsheet as Yves
Coene used from KO. Yves has sent this across and RW is to add these actions.
RW
06/11/09
JE
06/11/09
PGM
06/11/09
RW
13/11/09
JE
13/11/09
Johannes described the most recent work on SPS 2.0 specification. Noted
dependency on on Common Service Model (OGC 09-001) and described use of
SWE service model (which is shared with SOS).
There will only be minor changes after 19 Nov, so we can have vote in
December to go to RFC (request for comment). We are using what we can of
new OGC specification model (OGC 08-131r3).
Migration to OWS Common 1.2 is being discussed. It is currently in eVote.
Johannes to give info to ESA on our requirements/comments. We will publish on
HMA Wiki
RESTRICTED
DMS-DQS-QREPM04-MOM-20-E
Minutes of Meeting
Code:
HMA-FO-DMS-PMD-MOM01-E-R
Issue:
1.0
Date:
05/11/2009
Page:
3/3
Actions
Issues
Due
No.
Actionee
Yves to make other partners aware of this process and encourage other
contributions before sending to OGC and resolve issues internally if there are
any. Suggest review until end of 17 Nov 17, and email discussion ASAP and
possible teleconfon 18 or 18 Nov. ESA can then vote based on this harmonised
view. Voting on OWS Common 1.2 closes on 20 Nov.
There is potential for voting being conditional on the comments acceptance. To
clarify what was said during the telcon: a YES vote with comments means afaik - that the comments are only minor and the SWG is free to take them
into account. A NO vote has to be justified and if there are two of those
votes I think the vote failed or at least is paused, so the SWG needs to
work out what is deemed to justify the NO vote. As I said during the telcon
it would be polite to use the first option (YES with comments), separately
telling the SWG chair that these comments should be worked out if at all
possible.
YC
19/11/09
Philippe described the ongoing work on both SweCommon and SPS Application
profile for Earth Observation.
Again, attempts are being made to harmonise with new OGC specification model
(OGC 08-131r3) however complete harmonisation is unlikely in this time frame.
Estimate sensor workload operation is being worked on at present.
The specifications should be into "pending docs" area at OGC by 19 November.
PM
19/11/09
RW
06/11/09
RESTRICTED