Beruflich Dokumente
Kultur Dokumente
RM Bridge V8i
September 2008
RM Bridge
Demo Example Box Girder Bridge with Skew Abutments
Contents
1
General ...................................................................................................................... 1
6.1
6.2
6.3
Traffic Loads........................................................................................................... 11
7.1
7.2
Results ..................................................................................................................... 14
Bentley Systems
Austria
RM Bridge
General
General
This example demonstrates the design of a 4 span pre-stressed concrete box girder
bridge.
Bentley Systems
Austria
RM Bridge
Demo Example Box Girder Bridge with Skew Abutments
General
2
Bentley Systems
Austria
RM Bridge
Bentley Systems
Austria
RM Bridge
Demo Example Box Girder Bridge with Skew Abutments
Bentley Systems
Austria
RM Bridge
Bentley Systems
Austria
RM Bridge
The box girder is modeled with beam elements, the bearings are modelled with spring
elements and the abutment is modeled with another spring element. (The whole abutment can be represented with a spring having stiffnesses in all six directions using an
auxiliary calculation separate from the program).
The end of the bridge deck girder is defined with two nodal points -One on the top of
the girder and the second one on the top of the abutment.
Eccentric connections are used to correctly model the connection between the deck, the
substructure elements (plus bearings) and these two nodes.
Eccentric connections are specified by their components in the global X-, Y-, Zcoordinate directions.
Bentley Systems
Austria
RM Bridge
Note:
The nodal points along the girder are not placed on the girder centroid, but on the top of
the girder.
The advantage is that the road (or rail) elevation of the project is usually known and is a
specific distance from the top of the girder and not from the centroid of the girder.
Eccentric connections are used to connect the girder centroid to the nodal points on the
top.
A special input code is used when assigning the cross sections to the beam elements so
that the program generates the correct eccentric connections for the corresponding cross
sectional values.
The cross section geometry, in this example, is specified using the interactive facility in
the program GP. The cross section geometry can be tied to the varying cross fall using
dynamic formulae that are station value related. The cross section geometry can also be
tied to the varying width of the deck (where applicable) in a similar way.
Bentley Systems
Austria
RM Bridge
Different pre-stressing cables can have different geometry in one section. Two geometrys are defined and assigned to the various cable groups:
The bridge deck is built in two stages and the cable groups are split into the same two
construction stages.
Stage I Elements 9 to 32 inclusive
Stage II Elements 1 to 8 plus Elements 33 to 40
The cable groups are activated in their appropriate construction stage.
Cable groups 2: + 5:
Bentley Systems
Cables for Construction Stage I. The cables go from the beginning of element 9 at the end of the first span through the second
and third spans to the end of element 32 at the beginning of the
fourth span
Austria
RM Bridge
Cables for Construction Stage II. The cables go from the beginning of element 1 to the end of element 8 in the first span.
Cables for Construction Stage II. The cables go from the
beginning of element 33 to the end of element 40 in the fourth
span.
Bentley Systems
Austria
RM Bridge
Construction Stages
10
Construction Stages
Bentley Systems
Austria
RM Bridge
Traffic Loads
11
Traffic Loads
The traffic loading calculation is carried out in accordance with the German design code
(DIN) in this example. The basic procedure for using the LIVE loading facility is therefore demonstrated. The LIVE loading facility can be similarly used for calculating traffic loading in accordance with any other design code.
The whole roadway must be divided into lanes. The most critical lane must be defined
as the main lane. The load train must be defined for each lane. The max/min envelopes
are calculated for each lane using influence lines. The influence lines and their summation are stored for future use (saves a lot of time during future computations).
The definition of the lane loading and the superposition of the individual envelopes are
shown diagrammatically below.
The German code requires that the main lane load (in this example 2.75 kN/m) should
be placed in the same lane as the lane carrying the 60 ton truck load.
The section is shown in a sketch below.
The traffic loads with eccentricity on the extreme right side of the bridge are indicated.
The same loads must also be applied to the left side of the bridge and a symmetrical
arrangement should also be considered.
SLW-Loading calculation
SLW60 - m 1,15
Calculation of the dynamic factor ( m 1,15 )
1,4 0,008 * l y
kN
kN
kN
* 1,15 3 2 2,75 2
2
m
m
m
SLW30 - 1,0
PSLW 30 300kN *1,0 300kN 3 *100kN
Bentley Systems
Austria
RM Bridge
Traffic Loads
12
Traffic loads applied on the extreme right side of the bridge carriageway (left side load
is symmetrical but mirrored)
Figure 10: Traffic lanes on the right hand side of the deck girder.
Bentley Systems
- Lane 1
lane1.sup
- Lane 5
lane5.sup
- Lane 2
lane2.sup
- Lane 6
lane6.sup
- Lane 3
lane3.sup
- Lane 7
lane7.sup
- Lane 4
lane4.sup
- Lane 8
lane8.sup
Left:
Austria
RM Bridge
Traffic Loads
13
SupAnd
lane2.sup
SupAnd
lane3.sup
SupAnd
lane4.sup
SupAnd
totalri.sup
SupAdd
lane5.sup
SupAnd
lane6.sup
SupAnd
lane7.sup
SupAnd
lane8.sup
SupAnd
Bentley Systems
SupOr
total.sup
totalle.sup
Austria
RM Bridge
Results
14
Results
Bentley Systems
Austria
RM Bridge
15
Figure 13: Fiber stress at the top and bottom of the deck after 9125 days.
Bentley Systems
Austria