Objectives:
To complete the testing and analysis of the effect of riser profile on the excitation mechanism
at atmospheric conditions, and determine the effect of an increase in pressure (up to 4 bar)
Activities:
A number of scale test experiments will be carried out (continuing experiments carried out in
the JIP Phase 1), and the following parameters will be tested:
Impact of cavity depth (3 depths)
Impact of edge radius up- and downstream (3 profiles)
Effect of change of flow direction (3 profiles)
Impact of pressure (1 bar and 4 bar) on the onset of resonance and pulsation amplitudes
(relation with shear layer thickness)
Deliverables:
A technical report describing the results, their interpretation and their implications for existing
and future riser carcass design.
Budget cost:
50,000
Time scale:
4 months
5
1
Objectives:
To complete the testing and analysis of the effect of riser profile on the excitation mechanism
at up to 40 bar, and to validate the scaling laws for acoustic damping at medium pressure
natural gas.
Activities:
Scale testing of two test profiles and 1 blank reference profile will be carried out (following on
from CTR 1), and the following parameters will be evaluated:
Impact of pressure (between 8 and 40 bar) on the onset of resonance and pulsation
amplitudes in natural gas
Impact of pressure (between 8 and 40 bar) on the damping of acoustic waves in a corrugated
pipe as a function of pressure, flow and frequency. An external pulsation source is used to
excite a corrugated pipe, which is not producing vortex shedding resonances (see also CTR 3)
Flow velocity range 0 to 20 m/s
Deliverables:
A technical report describing the measurement results, and their comparison with the low
pressure air test results for the same profiles, specifically the onset velocity and profile related
to the shear layer thickness
Budget cost:
50,000
Time scale:
3 months
5
1
Objectives:
To develop and validate the vortex blob method as a numerical prediction model for Strouhal
number and source strength
Activities:
Deliverables:
A technical report describing the numerical method used, simulation results and comparison
with field data and scale test results.
Budget cost:
30,000
Time scale:
10
5
1
Activity no.:4
Objectives:
To determine the effect of higher pressures on the onset of resonance and source strength,
on test specimens and actual riser sections, in air.
Activities:
Test 2 machined profiles and 2 actual riser sections in air for a range of static pressures up to
65 bar, over the velocity range 0 to 40 m/s.
Deliverables:
A technical report detailing the measurement results, and their comparison with the low
pressure test results for the same profiles.
Budget cost:
50,000
Time scale:
3 weeks.
11
5
1
Activity no.:5
Objectives:
Activities:
Test 2 machined profiles and 2 actual riser sections for other gases and compositions to give
representative Reynolds numbers and boundary layer thicknesses
Deliverables:
A technical reports detailing the measurement results, and comparing them with the low
pressure, and air at higher pressure results.
Budget cost:
50,000
Time scale:
3 weeks
12
5
1
Activity no.:6
Objectives:
To determine the impact of using a strong acoustic resonator, and the viability of discrete
isolators.
Activities:
Deliverables:
A technical report detailing the measurement results, and the effect of a strong acoustic
resonator and a discrete isolator.
Budget cost:
50,000
Time scale:
3 weeks
13
5
1
Activity no.: 7
Objectives:
Activities:
To carry out flow visualisation on at least 4 singing profiles under representative process
conditions.
Deliverables:
Budget cost:
30,000
Time scale:
2 months
14
5
1
Objectives:
Activities:
To either carry out an offshore measurement survey on a facility experiencing this problem, or
purchase already recorded data for analysis.
To analyse the data onshore for comparison with other assets, for example, the process
conditions for onset, the variation of pressure pulsation levels with gas flow velocity, pipework
vibration and stress levels etc.
Deliverables:
Budget cost:
20,000
Time scale:
2 months
15
5
1
Activity no.: 9
Objectives:
Activities:
Project launch to include announcements, liaison with current Operators, identify new
Operators and possible contractor involvement, help with contractual issues, organise launch
meeting etc
Secretariat progress reporting, organising and facilitating meetings, managing project
documentation, arranging JIP publicity, maintaining JIP website, acting as project focal point.
Budget cost:
51,500
Time scale:
16
5
1
Objectives:
Activities:
Summarize the empirical results of the other major CTRs into a single
document that can then be used by operators / designers to make
informed decisions on riser choice, process parameters, and topside
and subsea pipework design. In this way, the risk of flow induced
pulsation in a new design may be minimized.
Budget cost:
10,000
Time scale:
1 month