Beruflich Dokumente
Kultur Dokumente
HOMER N. MEAD'
MEMBER AIME
T. P. 4200
ABSTRACT
This report develops equations for decline curve
analysis based upon the premise that the rate of change
of the reciprocal of decline for succeeding time intervals is constant when the reservoir is vroduced under a
fixed set of conditions. A method is shown for predicting maximum production rate against cumulative production for any reservoir. A method is also presented
for predicting future production rate by an analysis of
past production performance after decline has heen established.
INTRODUCTION
No significant contribution to the analysis of decline
curves by the loss-ratio method has been made since
J. J. Arps' paper'. The concept of loss-ratio that was
developed by Arps and his contemporaries has been redefined in another way and the concept of instantaneous
loss-ratio at time zero has been added. In the mathematical development by Arps, production rate was related as a continuous function with time and his equations were developed on that basis. In this paper, production is considered to be a series of segments for
equal time intervals and equations have been developed
based upon these finite differences.
It is realized that decline curve analysis is not the
answer to all predictions of reservoir behavior. However, as production must decline from an initial maximum rate to zero in any reservoir, if such decline can
be expressed as an infinite series, this series should accurately predict production. Decline curve analysis
should be considered a valuable tool that may be used
in conjunction with predictions of future recoveries by
other methods. Various uses of the decline curve method will be discussed in this paper. Equations predicting
Original manuscript received in Petroleum Branch office on Jan.
15, 1955. Revised manuscript received on Dec 13 1955
':'Homer N. Mead is now enrolled in the School 'of Bu"siness Administration at the University of California.
'References given at end of paper.
SPE 464-G
DECLINE
P, (1 - r)
,,-1
(1)
P, - P, (1 r
Since P, (1 - r)n
C
r) U
---~---
Pn + 1
P, - P n +1
(2)
LOSS-RATIO
In this paper the calculation for loss-ratio has been
changed from the method presented by Johnson and
Bollens'. The first loss-ratio to be calculated is a, it is
the initial production per unit of time after declin'e has
set in divided by the difference between the initial and
the second production rate. This loss-ratio is for the
first time interval. After b (which is the constant change
11
\ K' ~
o ASSUMED lNlTIl
o RATE OF
o 65!/..!!.N~~Er\ 1---
1"'-
.:::,. -f"-..,
f"..
0
0
'"
r-.....
r----
"
B~
.-
4000
l"'-
EFFECT OF
t- ;::::: ~b.
1"-16000
7000
RECOVERY.
.-
.-IJP
1/
IV
,
/,
YI
1M
VI,
rl
V
V
1---:"-
-f-- f--
v
I
I}
If/
-1-1--
f-- I-r-
-I- I--i0 01
--
i.- f--
,> P
I--
I
,
50
UNITS OF TIME
FIG. 2 -
EFFECT OF
ON TIME-RATE OF RECOVERY
tion for that period of time. Fig. 3 shows this graphically. There are three methods for making a rate-cumulative plot. In the first method the production per unit
of time is related to the cumulative production at the
end of the period, as is shown in Fig. 3 in the upper
dotted curve marked (1). The advantage of using this
plot is that it is easier to take data directly from actual
production history. Because of the ease of plotting, this
method is the one used on the accompanying rate-cumulative graphs, in which actual production data have been
plotted. Another method for plotting a rate-cumulative
curve is to relate the production per unit of time to the
cumulative production existing at the beginning of the
period. This is shown in the dotted line on Fig. 3
marked (2). Third, if it is desired to plot a curve showing the best approximation of instantaneous rate versus
cumulative production at any time, it will be necessary
to connect the midpoints of the segments. This is shown
in the dotted line on Fig. 3 marked (3). Since the
equations developed in this paper are based upon finite
differences in production rather than making rate a continuous function with time, the third method described
will not be considered. The lines obtained by all three
methods converge at ultimate recovery. It is emphasized that production for equal units of time must be
used in decline curve analysis.
HYPERBOLIC DECLINE
EQUATIONS
In hyperbolic decline the reciprocal of the rate of
decline for each succeeding quantity of production per
unit time increases by a constant factor called h. As
is shown in Table 1, a o cannot be calculated from actual production history but is equal to a 1 - b. The following definitions are used to develop an equation for
cumulative production using a summation of production quantities for equal time intervals.
P,
p,
P,
P,
+ ... +
Pn
(3 )
(4)
12
:..-f--
I"'-
CUMULATIVE PRODUCTION
FIG. 1 -
3/
I--
I---
C = P,
'" I.........
',,-
I'- ."
6075
B~O
~--~~~-----~~------------
TABLE 1
Time
Interval
0
1
2
3
4
5
Production
Per Unit
Time
- ---
10,000
6,000
4,000
2,857
2,142
(1
r)
0.6000
0.6667
0.7143
0.7500
Rote of
Decline
(r)
--
0.4000
0.3333
0.2857
0.2500
Reciprocal
of r
(0)
-2.0
2.5
3.0
3.5
4.0
0.5
0.5
0.5
I I I I I
I I
I I I
"1 7
":
I I
I I I
, "~',',,":: ,y--+t--t1+'1trf
""'1Io'..
,1.14;J::+'I_+-IH-+-HIH-+-+-++-H-+--l
'l!;kl
I
,", '" I rf,' ,
I
40
3-
':'
(13 )
. (14)
i
:;0
60
CUMULATIVE
FIG,
'
P,
---~--F\ - Pn+l
PRODUCTION
CUMULATIVE PRODUCTION.
b
(5)
Substituting Eq. 4 and 5 into Eq. 3, we obtain,
C = (a 1 PI - a 1 P,) + (a, P, - a, P,,) + (a" p, - a3 Pol)
a" + 1 = a"
= (a o
(a,
P, +
3)
+ 1
a"P,,+,
Therefore,
(6)
1 - b
(2)
when P"+l =
0,
C = Q so,
t-p~
Letting PI -C P"+l
(7)
x and 1
C
=y
b= ~alx .
(8)
y-x
If it is assumed that when ultimate recovery is
obtained, P n+1 equals zero and if Q equals the recovery left from and including P" and P1 and P, are the
production for two equal, successive time intervals when
the reservoir is producing at maximum rates, then:
P1
(Q ~ p)p,
P1
(9)
P,
Df?LETION
a"
b -
(-Q-----)
O-C
\
\
J.
,I
'\
'"1'\
\
\
P",
+
;~~1~-=~rp"+1
PRESSURE MAlrn:::NANCE
\ /1
--
r-=
_P' -
I
NATURAL
Q ) (
P,
)
(10)
( Q-P
~p,
1
b
PI (P, +
b P,)
Q - ---- -------(11 )
P 1 - P,
When a series of equal time intervals are taken with
P, the initial rate and P" the last rate with C as the
cumulative production from P , to P" inclusive, then:
\
\
I""
5
(12)
""
"-
FIG.
4-
HYPOTHETICAL
EXAMPLE
COMPARISON
OF
RANGES FOR b
0.50 to 0.85
0.20 to 0.85
o to 0.40
0.20 to 0.50
o to 0.20
HYPOTHETICAL EXAMPLE
In order to demonstrate the use of decline curve analysis for predicting reservoir behavior on a reservoir that
has not been produced long enough to establish a decline rate, the following example is presented. In this
hypothetical case it is assumed that a reservoir had been
produced which by volumetric and materials balance
calculations had 50 mililon bbl of stock-tank oil originally in place. It was established that there was no water
drive and no original gas cap. All of the wells producing from this reservoir were examined and it was estimated a maximum of 400,000 bbl per month could be
produced initially. It was determined that 20 per cent of
the total oil in place could be produced ultimately by
natural depletion and 40 per cent of the original oil in
place could ultimately be produced if the reservoir pressure were maintained by gas injection. The problems
are: (1) what are the time-rates of recovery by natural
depletion and pressure maintenance and how do they
compare, (2) how long will it be possible to produce at
a sustained rate of 5,000 BID before decline sets in.
It was assumed that b equals 0.5 for natural depletion
since this reservoir would be produced in an efficient
manner. A similar value of b equals 0.5 was used for
pressure maintenance so that the comparison with natural depletion would be on a conservative basis.
Ultimate recovery in this paper is defined as the total
amount of oil recovered when the reservoir rate has
decreased to zero. Obviously cost factors of production
would make this impossible to achieve. The economic
ultimate recovery of any reservoir after capital equipment has been installed is when the direct or variable
cost of producing one barrel of oil is equal to the price
received by selling that barrel. This minimum production rate will consequently vary for each reservoir depending upon the factors of cost. It is possible for two
identical reservoirs produced at different times, places
and depths to have different economic ultimate recoveries yet both have the same total ultimate recovery if
costs were not taken into account. It is for this reason
that ultimate recovery has been defined as total producible oil. It is the obligation of the engineer to decide
from cost data to what minimum rate the reservoir can
be produced.
Under natural depletion (see Tables 2 and 3) in 15
years the yearly production rate will have dropped to
74,000 bbl and 8,832,000 bbl of oil will have been produced. Under pressure maintenance (see Tables 4 and
5) in 15 years the production rate will have dropped to
230,000 bbl per year and 15,508,000 bbl will have been
produced.
The calculations for Tables 2, 3, 4 and 5 were made
as follows: It was assumed that the production rate
would be zero when 10 million and 20 million bbl were
produced by natural depletion and pressure maintenance
respectively. Since P n +, will be zero,
P, ao
C = --- + 0
1 - b
Because it was assumed that b equals 0.5 III both
cases,
0.5 C
P,
14
FIELD EXAMPLE -
RESERVOIR A
all :...::
10,000,000 X (1 -
b)
----400~_'
.5)
. = 12.5
Monthly
Rate
Month
0
1
2
3
4
5
6
7
8
9
10
11
12
.1M bbl,)
.,
12.5
13.0
13.5
14.0
14.5
15.0
15.5
16.0
16.5
17.0
17.5
18.0
18.5
400
369
342
318
296
276
258
242
227
214
202
191
.0769
.0741
.0714
.0690
.0667
.0645
.0625
.0606
.0588
.0571
.0556
.0541
.9231
.9259
.9286
.9310
.9333
.9355
.9375
.9394
.9412
.9429
.9444
.9459
3,335
Years
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Ultimate Recovery X (1 -
b)
---------~--'
~1i.~L
3,335
1,668
1,001
667
476
357
278
222
182
152
129
111
96
84
74
~bbl'}
3,335
5,003
6,004
6,671
7,147
7,504
7,782
8,004
8,186
8,338
8,467
8,578
8,674
8,758
8,832
10,000,000 X (1 - .5)
--3-,335,000-' = 1.5
a
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
8.5
9.0
-r-
.5000
.4000
.3333
.2857
.2500
.2222
.2000
.1818
.1667
.1538
.1429
.1333
.1250
.1176
.1111
.5000
.6000
.6667
.7143
.7500
.7778
.8000
.8182
.8333
.8462
.8571
.8667
.8750
.8824
.8889
00
Month
Monthly Role
_ (M bblsL.
0
1
2
3
4
5
6
7
8
9
10
11
12
400
384
369
355
342
330
318
307
296
286
276
267
a
25.0
25.5
26.0
26.5
27.0
27.5
28.0
28.5
29.0
29.5
30.0
30.5
31.0
1 -
.0392
.0385
.0377
.0370
.0364
.0357
.0351
.0344
.0339
.0333
.0328
.0323
.9608
.9615
.9623
.9630
.9636
.9643
.9649
.9656
.9661
.9667
.9672
.9677
or
(160,000 + X) = 900,000 - 6x
7x = 900,000 - 858,700 = 41,300
x = 5,900
p, = (160,000 + 5,900) or 165.9 M bbl
195.1
01 = ~165.9 = 6.68
698,700
P, = 195.1 M bbl/month
3,930
n
~---~~-~------------
-------01
Yearly Prod.
(M bbls)
Cum. Prod.
(M bbls)
3,930
2,620
1,871
1,403
1,091
873
714
595
503
431
374
327
289
257
230
1 2.50
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
8.5
9.0
9.5
10.0
3,930
6,550
8,421
9,824
10,915
11,788
12,502
13,097
13,600
14,031
14,405
14,732
15,021
15,278
15,508
.3333
.2857
.2500
.2222
.2000
.1818
.1667
.1538
.1429
.1333
.1250
.1176
.1111
.1053
.1000
RESERVOIR B
I,
I-- ~ST
(6)
- IT~ST
\
Lx
losslLE
INITIAL RATE
1\
P,
1'\.0
I~P2
1-". . 1"-.
!
,
1 f'..
I
I
i
I
f-'I
I
i I
A.
FIGURE
1\
1::-'
OCi
l94
~
j-1.-'O"
Gl'3 INJECTION
STARTED NOV 194
J/
I"
00 0
r-...:: "'0
0
FOR DETERMINING
~RODUCTION
I 1
CIRCLES ARE
I i i
I I I i
05
RESERVOIR
~~~~~;ISCU~\
I
i~
, I
, I
I I
P,
I
I
.4631
I
i
n Pn+1
1,225.2 M bbl
(300,000 B/M)
r,
.1104
CONCLUSION
I
1 I
1',
FIG. 5 -
Pn+l
= 6.68
i',
------
tracting 965.7 M bbl from 11 million bbl for the ultimate recovery that was left to be produced including P"
Eq. 6 was used and b calculated to be 0,74, ao was calculated from Eq. 7 and equals 9.92. With these data the
decline curve was plotted as shown in Fig. 7. It will be
observed that this curve follows quite closely the actual
production data .
MAX POSSIBLE
INITIAL RATE
(300,000 81M)
Pl
.6667
.7143
.7500
.7778
.8000
.8182
.8333
.8462
.8571
.8667
. 8750
.8824
.8889
.8947
.9000
_
y ~ 1 -
= 11
C =
--"'------
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
x=
---~-----.
Yeors
GAS INJECTION
c
~~(4Nr3
f-- f--
~
3
FIG. 6 -
RESERVOIR
1-1-t-,\\+-i0ECLlNE CURVE
ANIILYS'S'+--t-H--+-+-++-t-H-t--t---t-t-1
~
~
'"
~200~-+-+\~+--t-~-+-+-++-t-H-t--t---t-t-H-t-t-~
I~ ,ool-++-+-+-+---+-,K~o;t---i-+-+++-l-+-+++--+-t-+-++-t--i
Number of equal time intervals from the beginning of initial production to the end of
that time for Pn'
C = Cumulative production in barrels from the
beginning of initial production to the end
of the P n interval.
ro = Instantaneous decline rate at time o.
r, = Decline rate for time interval 1.
rn = Decline rate for time interval n.
a,,, a" an = Reciprocal of rate of decline or loss-ratio.
b = Constant difference between successive lossratio.
PI -
---c --
_ 1
FIG. 7 SHOWING
How
16
y-
Pn+l
n' P O + 1
--C-
***