Beruflich Dokumente
Kultur Dokumente
SUBMITTED TO
BY
July 2009
AGAINST
CLIMATE
CHANGE
2.0 ABSTRACT
This is a fourth progress report on implementation of the Fight against Climate Change-Choma/
Chigwere Biogas Project. It is also the first report for the 2009/ 2010 financial year and covers
activities, which have been undertaken in implementing the project from April to June 2009.
The main activity carried out during this period was the construction four-biogas plants. The
construction work is expected to finish in the next quarter. It was expected that the donor was to
release more money (approximately MK6, 000,000.00): this being the funding of the project for the
current financial year 2009/ 2010. However, up to now funds have not yet been released. This has
therefore adversely affected the work, as some of the planned activities have not been carried out
due to lack of funds.
Most of the technical work is being undertaken and supervised by Mzuzu University staff.
3.3 Training
Mr Fredrick Munthali was scheduled to attend a Biogas Technology Course organised by ESAMI
and was to take place in Arusha, Tanzania. The course was however, cancelled therefore an
appropriate course will be identified during the year.
Mr Collen Zalengera will attend a four week Environmental Management Course in July 2009. The
course is organised by ESAMI and will take place in Lilongwe, Malawi. This course was identified
in the place of the one that was cancelled in the first quarter. (Mr Zalengera has since started
attending the course). The University has provided the additional funds for the training; which will
be reimbursed once the project funds have been received.
Members of the technical team (TCRET staff) were supposed to undertake a GIS training course
however, the organiser cancelled the course therefore an alternate provider will be identified in the
next quarter.
One of the builders leaving employment with the university towards the end of the month of
May 2009. This has adversely affected the rate of construction work.
Community participation in some sites is poor. This has been mainly due to their commitment
to other activities such as farming.
Delays in the disbursement of funds for the year 2009/ 2010. This has resulted into a number
of activities (such as awareness campaigns, procurement of materials etc) not being
implemented. In addition, this will also affect future activities.
Identification of four sites for the construction of the next plants (Plants 6 9).
8.0 CONCLUSION
Progress of work in this quarter would have been much slower if it was not for the decision to
construct four plants concurrently.
Construction work of the next four plants will continue. Identification of sites for the construction of
an additional four plants will be carried out. This will be done in consultation with the Biogas
Committee and members of communities.
9.0 APPENDICES
Appendices 1, 2, 3 and 4 attached.