Discrepancies noticed at SKND Panel Interlocking

(A) MAJOR DISCREPANCIES:


1. UP Distant & Flyover line DN Distant are not in working order.
2. Bunching of 16 strand cables has not been done inside the Relay room.
3. Approved Circuit diagram is not available.
4. SIP, Relay disposition, Location particulars, Contact analysis chart, IPS Power
distribution diagram, Track bonding plan, FPD, Cable corage plan, Cable route plan,
RCC etc not available at SKND.
5. E-type locks are not provided in any Battery location box.
6. No Crank Handle telephone provided in any of 08 CH Locations.
7. Line No. 6 berthing Track Axle counter not working.
8. GI wire double bonding with Transverse bond has not been done.
9. No Register has been provided for Track circuit record, Point measurement record,
Axle counter maintenance records, Counter registers, TLBI (Diado) records, Earth
testing record etc.
10. IPS earth value measured more than 10 Ohm and new earthing required.
11. North & South LED Boards are not fixed on DN Home signals & UP Advance starter
signals of SKND Yard.
12. Plastic table & Chairs have been provided at Relay room for circuit reading.
13. No Exhaust fan has been provided in the battery room.
14. For UP direction, when S-1 set to Line-1 with dead end then for DN direction the
S-2 set to Line-4 with dead end as overlap is not being possible.
15. SH-5 for UP direction when taken off for any route (A to F) then the UP Advance
starter to Flyover line (S-43) rises back if taken off.
16. Power cable not laid for SSDAC from Relay room to both side Goomty.
17. The load distribution of New & Old IPS has not been done proportional to Battery
capacity such that the new Statcon IPS takes around 40Amp on 110V DC with 300AH
battery Bank & Old HBL IPS takes around 10Amp on 110V DC with 200AH Battery
bank.
18. Spare Signalling cables used in place of power cable therefore no spare signaling cable
core available from Relay room to both sides Goomty.
19. Earthing of IPS is more than 10 Ohm so that should be shifted to a suitable location
(Preferably near OFC hut) for proper surge protection.
20. For New laid 6- quad cable between SKND-JKPR cable layout diagram not provided.
The list of Joints & location particulars and Emergency sockets position are also not
provided.
21. The Quarter JBs used for 6-quad cable termination are not earthed with cable armour in
the section, which will give rise noisy communication in RE area.
22. Power cable not laid from Relay room to UP Goomty for 110V DC & 24V DC
23. Datalogger has not been provided.
24. Sand filling and plastering is not done inside the relay room.
25. Lighting arrangement not proper inside the Relay room.
26. Cable armour earthing not done.
27. Exhaust fan not provided.
28. Lettering for condenser and resistance not done.
29. Modified Interface circuit at JKPR, has not been provided in connection with
Twin line work.

(B) Location wise Discrepancies:


Loc Box no 31
1.
2.
3.
4.
5.
6.

Loc Box Fixing nut-bolt is not fixed properly.


Anti Vibration arrangement not done for choke.
Sand filling and plastering not done.
Fuse not provided.
Earth enclosure for the loc earth not provided.
Loc Box painting not done.

Loc Box no 32
1.
2.
3.
4.
5.

Fuse not provided.


Choke, Charger & Resistance are not fixed.
Sand filling and plastering not done.
Earth continuity not done.
Loc Box painting not done.

Battery Box
1.
2.
3.
4.

E-Type lock not provided.


Loc box fixing, sand filling & plastering not done.
Wooden plank not provided.
Loc Box painting not done.

Loc Box no 30
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Earth continuity not done.
Loc Box painting not done.
Description inside the location not done.

Loc Box no 29
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done


Earth continuity not done.
Choke, Charger & Resistance are not fixed.
Earth enclosure for the loc earth not provided.

Battery Box
1. Loc box fixing, sand filling & plastering not done.
2. E-Type lock not provided.
3. Wooden plank not provided.

Loc Box no 28 (LVCD-SKND/JKPR old line)


1.
2.
3.
4.

Equipment fixing not done.


Fuse not provided.
Earth enclosure not provided.
T-Joint of track device not fixed.

Loc Box no 27
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Earth enclosure for the loc earth not provided.

Battery Box
1. Loc box fixing, sand filling & plastering not done.
2. E-Type lock not provided.
3. Wooden plank not provided.
Loc Box no 26 (LVCD-SKND/JKPR new line)
1.
2.
3.
4.
5.

Loc box fixing, sand filling & plastering not done.


Equipment fixing not done.
Fuse not provided.
Track device armor screen earthing not done.
T-Joint of track device not fixed.

Loc Box no 25
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Earth enclosure for the loc earth not provided.

Battery Box
1. Loc box fixing, sand filling & plastering not done.
2. Anti-theft arrangement not provided.
3. In place of connector battery are connected with wire.
Loc Box no 24
1. Loc box fixing, sand filling & plastering not done.
2. Choke, Charger & Resistance are not fixed.
3. Fuse not provided.
4. Earth enclosure for the loc earth not provided.
Battery Box
1. Plastering not done.
2. Hylum not fixing.

3. Battery float not provided.


4. Earth enclosure not provided.
Loc Box no 23
1.
2.
3.
4.
5.
6.
7.

Telephone not provided.


Wooden plank not provided.
E-type lock not provide.
Plastering not done.
Antitheft arrangement not provide.
Earth enclosure for the loc earth not provided.
Earth continuity not provided.

Loc Box no 22
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Relay not fixing.

Battery Box
1. Plastering not done.
2. E-type lock not provided.
3. Battery float not provided.
Loc Box no 21A
1. Loc box fixing, sand filling & plastering not done.
Loc Box CH-5
1. Telephone not provided.
2. Painting not done.
3. E-type lock not provided.
Loc Box no 21
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Fuse not provided.
Earth not provided.
EJB fixing not done.

Loc Box no 20
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Fencing required for protect location box.

Loc Box no 19
1. Loc box fixing, sand filling & plastering not done.
2. Choke, Charger & Resistance are not fixed.
3. Fuse not provided.
Battery Box
1. Plastering not done.
2. Battery float not provided.
Loc Box no 18B
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


E-type lock not provided.
Wooden plank not provided.
Earth not provided.

Loc Box no 18A


1. Loc box plastering not done.
2. Earth not provided.
Loc Box no 18
1. Loc box plastering not done.
2. Relay not fixing.
Loc Box no 17
1. Loc box plastering not done.
2. Fuse not provided.
3. EJB not fixing.
Loc Box no 16
1. Loc box plastering not done.
2. Fuse not provided.
3. EJB not fixing.
Loc Box no 15
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Relay not fixing.

Battery Box
1. Plastering not done.
2. E-type lock not fixing.

3. Battery float not provided.


Loc Box no 14
1. Loc box plastering not done.
2. Fuse not provided.
3. E-type lock not provided.
4. Wooden plank not provided.
Loc Box no 13
1. Loc box plastering not done.
2. Choke are not fixed.
3. Fuse not provided.
Loc Box no 12
1. Loc box plastering not done.
2. Earth enclosure not provided.
3. Earth continuity not done.
Loc Box no 11
1.
2.
3.
4.

Loc box fixing, sand filling & plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Earth enclosure not provided.

Battery Box
1. Plastering not done.
Loc Box no 10
1.
2.
3.
4.
5.

Loc box plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Earth enclosure not provided.
Relay base nos. broken.

Battery Box
1. Plastering not done.
Loc Box no CH-3
1.
6.
7.
8.

Loc box plastering not done.


Painting not done.
Telephone not provided.
E-type lock not provided.

Loc Box no 8A
1.
2.
3.
4.
5.

Loc box fixing, sand filling & plastering not done.


Fuse not provided.
E-type lock not provided.
Earth not provided.
Painting not done.

Battery Box
1. E-type lock not provided.
2. Painting not done.
Loc Box no 8
1.
2.
3.
4.
5.

Loc box plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Relay not fixing.
Earth enclosure not provided.

Battery Box
1. Plastering not done.
2. Earth continuity not done.
Loc Box no 7
1.
2.
3.
4.
5.

Telephone not provided.


Wooden plank not provided.
Earth continuity not done.
Loc box plastering not done.
Fuse not provided.

Loc Box no 6
1.
2.
3.
4.
5.

Loc box plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Relay base not writing.
Earth enclosure and earth continuity not provided.

Battery Box
1. Plastering not done.
2. E-type lock not provided.
Loc Box no 5
1. Loc box plastering not done.

2.
3.
4.
5.

Choke, Charger & Resistance are not fixed.


Fuse not provided.
Cable bunching not done.
Earth enclosure and earth continuity not provided.

Battery Box
1. Plastering and sand filling not done.
2. Wooden plank not provided.
Loc Box no 4
1.
2.
3.
4.

Loc box plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Earth enclosure and earth continuity not provided.

Battery Box
1. Plastering not done.
Loc Box no 3
2.
3.
4.
5.
6.

Loc box plastering not done.


Choke, Charger & Resistance are not fixed.
Fuse not provided.
Earth enclosure not provided.
Cable bunching not done.

Battery Box
1. Plastering not done.
Loc Box no 2
1.
2.
3.
4.
5.
6.

Loc box plastering not done.


Choke are not fixed.
Fuse not provided.
Relay not fixing.
Earth enclosure not provided.
Lettering of cable termination is confusing.

Loc Box no 2A
1.
2.
3.
4.
5.

Loc box sand filling and plastering not done.


Fuse not provided.
Earth enclosure not provided.
Writing at fuse terminal is confusing.
Cable dressing not done.

Battery Box

1. Plastering and sand filling not done.


Loc Box no 2B
1.
2.
3.
4.

Loc box sand filling and plastering not done.


Earth not provided.
Cable dressing and bunching not done.
Cable writing not done.

Loc Box no 2C
1.
2.
3.
4.
5.
6.
7.
8.

Loc box plastering not done.


SSDAC unit fixing.
Fuse not provided.
Painting not done.
E-type lock not provided.
Soil filling around location box.
T joint of track device is not fixing.
6Quad cable and signalling cable armour not soldering.

Loc Box no 1
1.
2.
3.
4.
5.
6.

Loc box sand filling and plastering not done.


Fuse not provided.
Relay not fixing.
Earth not provided.
Cable termination not done.
Cable bunching not done.

(C) SIGNALS:
S-2
1. Unit lock not provided.
2. Earth enclosure not provided.
3. Signal post plumbing not done.
S-6
1.
2.
3.
4.
5.

Unit lock not provided.


Earth enclosure not provided.
Cable directed provided without any pipe for calling on signal unit.
Number plate not provided.
Signal post plumbing not done.

S-45
1. Unit lock not provided.

2.
3.
4.
5.
6.
7.
SH-4
1.
2.
3.
4.
5.

Earth enclosure not provided.


Number plate not provided.
Foundation plaster not done.
Ladder base not concreted.
Unit painting not done.
Signal post plumbing not done.
Unit lock not provided.
Earth not provided.
Lamp guard not provided.
Glass not provided.
Signal post plumbing not done.

S-43
1.
2.
3.
4.
5.

Unit lock not provided.


Earth enclosure not provided.
Number plate not provided.
Ladder base not concreted.
Signal post plumbing not done.

SH-8
1.
2.
3.
4.

Unit lock not provided.


Earth enclosure not provided.
Number plate not provided.
Signal post plumbing not done.

S-27
1.
2.
3.
4.
5.
6.

Unit lock not provided.


Earth enclosure not provided.
Number plate not provided.
Ladder base not concreted.
Shunt 27 dummy aspect not covered.
Signal post plumbing not done.

S-25
1.
2.
3.
4.
5.
6.
7.
8.
S-23

Unit lock not provided.


Earth enclosure not provided.
Number plate not provided.
Ladder base not concreted.
Unit hood not fixing.
Signal unit and route unit painting not done.
SH-25 dummy aspect not covered.
Signal post plumbing not done.

1. Unit lock not provided.


2. Earth enclosure not provided.
3. Number plate not provided.
4. Ladder base not concreted.
5. Route indicator one hood not provided.
6. LED not fixing.
7. Signal unit not painting.
8. SH-23 dummy aspect not covered.
9. Calling on hood not fixing.
10. Foundation plastering not done.
11. Ladder painting not done.
12. Signal post plumbing not done.
S-41
1. Unit lock not provided.
2. Earth enclosure not provided.
3. Number plate not provided.
4. Ladder base not concreted.
5. Route indicator one hood not provided.
6. Signal unit not painting.
7. Foundation plastering not done.
8. Ladder painting not done.
9. Signal post plumbing not done.
10. One number hole covered on the route unit.
S-19
1. Unit lock not provided.
2. Earth enclosure not provided.
3. Number plate not provided.
4. Ladder base not concreted.
5. Route indicator one hood not provided.
6. Signal unit not painting.
7. SH-19 dummy aspect not covered.
8. Foundation plastering not done.
9. Ladder painting not done.
10. Signal post plumbing not done.
S-21
1.
2.
3.
4.
5.
6.
7.
8.

Unit lock not provided.


Ladder base not concreted.
Signal unit not painting.
SH-21 dummy aspect not covered.
Foundation plastering not done.
Ladder painting not done.
Signal post plumbing not done.
Cable directed provided without any pipe for calling on signal unit.

S-1
1. Unit lock not provided.
2. Ladder base not concreted.
3. Signal unit not painting.
4. Foundation plastering not done.
5. Ladder painting not done.
6. Signal post plumbing not done.
7. Soil filling required around the signal foundation.
8. Earth enclosure and earth continuity not provided.
9. Cable directed provided without any pipe for calling on signal unit.
10. Offset hole not covered.
S-44
1.
2.
3.
4.
5.

Unit lock not provided.


Ladder base not concreted.
Ladder painting not done.
Signal post plumbing not done.
Earth enclosure and earth continuity not provided.

S-24
1.
2.
3.
4.
5.
6.

Unit lock not provided.


Ladder base not concreted.
Ladder painting not done.
Signal post plumbing not done.
Earth not provided.
Cable directed provided without any pipe for calling on signal unit.

S-26
1.
2.
3.
4.
5.
6.

Unit lock not provided.


Ladder base not concreted.
Signal unit not painting.
Ladder painting not done.
Signal post plumbing not done.
SH-26 dummy aspect not covered.

S-2 (MESCO siding)


1.
2.
3.
4.
5.
6.

Unit lock not provided.


Ladder base not concreted.
Signal unit not painting.
Signal post plumbing not done.
Earth enclosure and earth continuity not provided.
Number plate not provided.

S-36(MESCO)

1.
2.
3.
4.
5.

Unit lock not provided.


Ladder base not concreted.
Signal post plumbing not done.
Earth enclosure and earth continuity not provided.
Cable directed provided without any pipe for calling on signal unit.

S-42
1.
2.
3.
4.

Unit lock not provided.


Ladder base not concreted.
Signal post plumbing not done.
Screening required for signal unit.

S-28
1.
2.
3.
4.
5.

Unit lock not provided.


Ladder base not concreted.
Signal post plumbing not done.
Earth continuity not provided.
SH-28 hood not fixing.

S-30
1.
2.
3.
4.
5.

Unit lock not provided.


Ladder base not concreted.
Signal post plumbing not done.
Earth continuity not provided.
Fencing required around the post.

S-32
1.
2.
3.
4.
5.
6.

Unit lock not provided.


Ladder base not concreted.
Signal post plumbing not done.
Earth not provided.
SH-32 dummy aspect not covered.
Cable directed provided without any pipe for calling on signal unit.

(D)Track Circuits:
1.
2.
3.
4.
5.
6.
7.

Nut & bolt not provided at all track TLJB.


Z-bond parallel GI bond not provided at all track circuit.
72 BT track circuit Jumper TLJB not provided.
77 BT track circuit Feed end TLJB not fixing.
79 BT track circuit Jumper TLJB not fixing.
55 BT track circuit Jumper cable not provided.
21 Nos. track circuits new batteries provided out of 50 Nos. track circuits.

(E) POINT MACHINE:


1. Pad lock not provided for any point machine.

(F) DN GOOMTY:
1.
2.
3.
4.
5.

All Relay rack and CT rack bunching required.


Fuse not provided.
Confusing writing at CT rack.
Sand filling and plastering is not done.
Lighting arrangement not proper in side the goomty.

(G) UP GOOMTY:
1.
2.
3.
4.
5.
6.

All Relay rack and CT rack bunching required.


Fuse not provided.
Confusing writing at CT rack.
Sand filling and plastering is not done.
Lighting arrangement not proper in side the Goomty.
Skylight broken at Goomty.