Beruflich Dokumente
Kultur Dokumente
:
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 1 of 17
Date Issued :
1/15/2007
I.
PURPOSE
Establish procedure as basic guidance team to do PSSR in the Tuban Petrochemical
complex.
II.
OBJECTIVE :
To ensure that facilities are safe for starting up after completion of new project
construction, modifications to existing facilities or after completion of plant turnaround
activities.
To ensure new plant or modifications to existing facilities are reliable and comply with
applicable Policies, Guidelines, Standards and Statutory Requirements.
III. SCOPE
The pre-startup safety review shall be conducted after the following activities:
o
o
o
o
o
IV. DEFINITION
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 2 of 17
Date Issued :
1/15/2007
Pre-start up safety review is a safety review takes place before any highly hazardous
chemical is introduced into a process. Process Safety Management, therefore, requires the
employer to perform a pre-startup safety review for new facilities and for modified facilities
when the modification is significant enough to require a change in the process safety
information.
V.
PROCEDURE
5.1 Start-up Planning and Preparation
The startup team shall focus, among other requirements, on the following:
Preparation of operating manuals/procedures or revisions to existing
operating
Manuals / procedures, if there are modifications to the plant facilities.
Preparation on new equipment for startup.
Checkout of new facilities prior to startup
Training of the operators/engineers for normal and emergency operations.
5.2 Pre-startup safety Review
Prior to startup of the plant, the Operations Day-work Supervisor or PSSR Leader shall
coordinate with the Pre-Startup Safety Review Team, comprising of representatives
from the relevant functions to conduct a pre-startup safety review. Relevant function
shall mean:
(i) For new construction/facility modification, those functions involved in the design,
construction, operation, maintenance, and safety of the new or modified facility.
(ii) For re-startup of an existing plant, those functions involved in the
maintenance, operation, inspection and safety of the plant.
The pre-startup checklist provided in Appendix-2 is used to facilitate the review process.
The team may include other relevant checks / comments in the comment section of the
checklist. Members have to assure themselves that:
Construction is in accordance to specifications and all legal or permit
requirements are complied with.
All engineering design drawings and process information are updated and
available for operating the plant.
Adequate Safety & MSDS, Environmental, Emergency shutdown, Operations and
Maintenance procedures are in place.
Safety critical devices (Safety Interlocks/PSVs) are tested to be functioning or legal
PSV certificate available.
Fire protection systems are adequate and operationally ready.
All recommendations from risk assessment (or design HAZOP) and field quality
inspections which are critical to safe operations of the plant have been addressed
and required actions taken.
Process Control and monitoring systems required for operations are ready.
Any additional training of operations and maintenance personnel on the new
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 3 of 17
Date Issued :
1/15/2007
VII. DOCUMENTATION
The completed document shall be maintained by Operations Supervisors for a period of 3
months.
VIII.APPENDIX
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 4 of 17
Date Issued :
1/15/2007
8.1 Appendix-1
PRE-START UP SAFETY REVIEW SIGN-OFF FORM
PSSR Title/Operating Unit:
__________________________________________
REVIEW TEAM MEMBERS CHECK OUT
We have made the pre-start up safety review and with the best of our knowledge, the
plant is safe for start up.
YES / NO / NA
Name
Signature
Date
OPERATION
_____________
________
______
ENGINEERING
_____________
________
______
MECH./STA/PIPING
_____________
________
______
ELECTRICAL
_____________
________
______
INSTRUMENT
_____________
________
______
Q/C
_____________
________
______
CIVIL
_____________
________
______
SHE
_____________
________
______
_____________
________
______
_____________
________
______
OTHERS (specify)
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 5 of 17
Date Issued :
1/15/2007
8.2 Appendix-2
YES / NO / NA
Name/Sign
1.
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 6 of 17
Date Issued :
1/15/2007
Date
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 7 of 17
Date Issued :
1/15/2007
YES / NO / NA
Name/Sign
1.
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
Comments:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 8 of 17
Date Issued :
1/15/2007
_____________________________________________________________________
Date
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 9 of 17
Date Issued :
1/15/2007
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Name/Sign
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 10 of 17
Date Issued :
1/15/2007
Date
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 11 of 17
Date Issued :
1/15/2007
YES / NO / NA
Name/Sign
___________
___________
___________
___________
___________
___________
___________
___________
___________
Comments:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
Electrical Coordinator: ________________________________________
Signature: ______________________
Date
: _______________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 12 of 17
Date Issued :
1/15/2007
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
YES / NO / NA
Name/Sign
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
Comments:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 13 of 17
Date Issued :
1/15/2007
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
Instrument Coordinator: ________________________________________
Signature: ______________________
Date
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
2.
3.
Rev. No.
: 0
Page
: 14 of 17
Date Issued :
1/15/2007
YES / NO / NA
Name/Sign
___________
___________
___________
___________
___________
___________
___________
___________
Comments:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
QC Coordinator: ________________________________________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Signature: ______________________
Date
Rev. No.
: 0
Page
: 15 of 17
Date Issued :
1/15/2007
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
Name/Sign
1.
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
Comments:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
Rev. No.
: 0
Page
: 16 of 17
Date Issued :
1/15/2007
_____________________________________________________________________
CIVIL/STRUCTURE Coordinator: ________________________________________
Signature: ______________________
Date
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
2.
3.
4.
5.
6.
7.
8.
9.
YES / NO / NA
Name/Sign
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
___________
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc
Doc. No. :
SAFETY HEALTH AND ENVIRONMENT
PROCEDURE
PRE-START UP SAFETY REVIEW
PROCEDURE
10. Are drainage systems adequate to handle
worst case flows and flooding test has
been done?
11. Are storm water-potentially contaminated
water, OWS
well segregated?
Rev. No.
: 0
Page
: 17 of 17
Date Issued :
1/15/2007
___________
___________
Date
: _______________
(Note: Applicable items not completed prior to start-up must be followed up and completed
within a set time frame)
C:\Data\My Data\FSE File\SHE PROCEDURE AND INSTRUCTION\PT TPPI FIRE AND SAFETY PROCEDURE\PT TPPI SAFETY PROCEDURES\( IV ) LOSS PREVENTION PROCEDURE\(III) PSSR
PROCEDURE (rev00).doc