Beruflich Dokumente
Kultur Dokumente
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
GS-4113
PAGE
REV.
2 OF 42
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
GS-4113
PAGE
REV.
3 OF 42
A
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
GS-4113
4 OF 42
NOTE:
CAUTION
An operating procedure, practice, etc. which, if not strictly observed, could result in
damage to, or destruction of, equipment.
WARNING
An operating procedure, practice, etc. which, if not correctly followed, could result in
personal injury or loss of life.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
5 OF 42
GS-4113
TABLE OF CONTENTS
EXTENDED STORAGE REQUIREMENTS FOR HORIZONTAL PUMPS
General
Inspection Upon Arrival
Storage Area
Storage Preferred (Dry)
Rotor Storage
Inspection and Maintenance
Storage Non-Preferred (WET)
Painting and Preservation
Start-Up
Drivers
INTRODUCTION
Description
Detail Description
Casing
Impeller
Casing Rings / Impeller Rings
Shaft
Ball Bearings
Impeller Nuts
Mechanical Seal Units
Coupling
INSTALLATION
Check Upon Arrival
Care During Storage
Rust Preventive
Cleaning the Pump
LOCATION
FOUNDATION
Lifting
INSTALLATION SEQUENCE
LEVEL THE BASEPLATE
GROUTING
SHAFT / COUPLING ALIGNMENT
Types of Misalignment
Alignment
Horizontal Move
Vertical Move
Check Coupling Alignment
Assemble and Lubricate Coupling
Dowel Pump and Driver
Hot Alignment Check
Alignment Data Sheet (Sheet 1 of 2)
Alignment Data Sheet (Sheet 2 of 2)
Example
7
7
7
7
7
8
8
9
9
9
9
10
10
10
10
10
10
10
10
10
10
10
11
11
12
12
12
12
12
13
14
14
15
16
16
17
19
19
20
20
20
21
22
22
23
SPECIFICATION
RUHRPUMPEN INC.
PIPING
Main Piping
Minimum Flow By-Pass
Seal Piping
SUCTION STRAINER
LUBRICATION
Make Periodic Inspections
Oil Specifications
ASTM Standards
Constant Level Oiler
Pure Oil Mist Lubrication
OPERATION
Initial Start-Up
Normal Start-Up
Operating Checks
Securing the Pump
TROUBLESHOOTING
DISMANTLING PROCEDURE
Coupling Removal
Radial Bearing Removal
Thrust Bearing Removal
ROTOR REMOVAL
Dismantling of Rotor
Impeller for Removal
INSPECTION OF PARTS
Casing Rings / Impeller Rings
BEARING HANDLING INFORMATION
Handling
Installation
Removal
Cleaning
REASSEMBLE
Reassemble the Rotor
Check Rotor for Run Out
Installing Rotor Assembly in Casing
Horizontal and Vertical Alignment
Set Thrust Bearing End Play
Initial Thrust Bearing Assembly
Final Thrust Bearing Assembly
Final Radial Bearing Assembly
Final Assembly
ORDERING INSTRUCTIONS
RECOMMENDED SPARE PARTS
SPECIFICATION
NUMBER
PAGE
REV.
6 OF 42
GS-4113
24
24
24
24
24
26
26
27
27
27
27
29
29
31
31
31
32
33
33
33
34
34
35
35
36
36
37
37
37
38
38
38
38
38
39
39
40
40
40
41
41
42
42
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
7 OF 42
GS-4113
CAUTION
IF PUMP IS EQUIPPED WITH A MECHANICAL SEAL AND IS STORED OR HAS NOT BEEN RAN FOR ONE (1)
YEAR OR MORE, THE MECHANICAL SEAL MUST BE REMOVED BEFORE START-UP AND FACES RE-LAPPED
TO GUARD AGAINST THE POSSIBILITY OF SEAL LEAKAGE. WHEN REINSTALLING THE SEAL, NEW O
RINGS AND GASKETS MUST BE USED.
The following information regarding receiving is only offered as a general guide to the customer.
Ruhrpumpen, Inc. requires that all receiving be conducted in accordance with the specifications set
forth in Chapter 3 Jobsite Receiving and Protection from API Recommended Practices 686/PIP REIE
686, First Edition.
When the pump is received, it should be inspected for damage or other signs of rough handling. Any damage found
should be reported to the carrier immediately.
Inspect the preservative coating on the various parts. If necessary, renew the preservative in areas where it has been
rubbed off or scraped.
Inspect all painted surfaces. If necessary, touch up the areas where paint has been chipped or scraped.
Inspect all covers over pump openings and piping connections. If covers or seals for the covers are damaged or loose,
they are to be removed and a visual inspection made of the accessible interior areas for accumulation of foreign
materials or water. If necessary, clean and re-coat the interior parts with preservative to restore the parts to the as
shipped condition. Install or replace covers and fasten securely.
STORAGE AREA
When selecting a storage area, the following should be taken into consideration:
1.
2.
The deterioration of the equipment will be proportionate to the class/type of storage provided.
The expenses involved in restoring the equipment at time of operation will be proportionate to the class/type of
storage provided.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
8 OF 42
GS-4113
ROTOR STORAGE
It is recommended that pump rotor be stored in the pump. Multistage diffuser-type pump rotors that cannot be stored
in the pump must be supported at the channel rings so that rotor weight is evenly distributed. Single-stage and volutetype pump rotors not stored in pump must be supported close to impeller(s) to eliminate sag that may cause rotor to
take a permanent set.
CAUTION
IF PUMP IS EQUIPPED WITH SLEEVE BEARINGS, THE OIL RING INSPECTION PLUG ON TOP OF THE
BEARING HOUSING IS TO BE REMOVED AND A SMALL AMOUNT OF OIL POURED OVER THE
JOURNALS BEFORE TURNING.
e)
f)
g)
h)
i)
2.
Single-stage and volute-type pump rotors stored separately should be rotated 1-1/4 revolutions weekly.
Pump covers are periodically removed from openings and interior accessible areas inspection. If surface rusting has
occurred, clean and repaint or re-coat with preservative.
If rusting occurs on exterior surfaces, clean, and repaint or re-coat with preservative.
Loosen casing drain plugs to allow seepage of any accumulated moisture.
Periodically remove bearing covers and inspect for accumulation of moisture, rust and foreign material. As required,
clean bearings and bearing housing and represerve. Install bearing cover and secure to assure maximum protection.
Bearings removed for storage should be coated with preservative, wrapped in oil/wax paper, and stored in a warm dry
area.
Check individually wrapped parts for signs of deterioration. If necessary, renew preservative and wrapping.
An inspection of all periodic inspection records as kept on file by the customer and all inspection reports that have been
compiled during the storage period.
An inspection of the storage area to determine the as stored condition of the equipment prior to any protection covers
being removed.
An inspection of the equipment with protection covers and flange covers removed.
Depending upon the length of time the equipment was stored, the class/type of storage provided, (i.e. indoor, heated,
unheated, ground floor, concrete floor, out-of-doors, under roof, no roof, waterproof covering, on concrete, on ground)
and as a result of the inspection of a, b, and c above, the Ruhrpumpen Representative may require a partial or
complete dismantling of the equipment.
SPECIFICATION
RUHRPUMPEN INC.
e)
PAGE
SPECIFICATION
NUMBER
REV.
9 OF 42
GS-4113
Dismantling may necessitate restoration of painted or preserved surfaces and/or replacement of gaskets, o-rings,
packing, and/or machanical seal and bearings.
Upon completion of the inspection, the Ruhrpumpen Representative shall submit a report to the customer and to
the Manager of Customer Service stating, in detail, the results of the inspection.
3.
2.
b)
Corrosive Pumpage fill pump with a 1% solution of Immunol 1809 and water (or owner approved preservative).
Immunol is a water-phase corrosion inhibitor for ferrous and mixed-metal couples and is composed of 5% sodium nitrite
with polyglycois, copper corrosion inhibitor, and other organic materials. The pump should be filled to highest level
possible, affording the greatest protection possible to all internal parts of the pump. This solution, when drained, will
result in a thin residual oil film (less than .0005) on all internals after the water has evaporated. This residue provides
added corrosion protection until pump is again filled with liquid or put into service.
Non-Corrosive Pumpage fill pump with pumpage to the highest level possible. Periodically open drain connection to
drain off any moisture that may have accumulated. Refill to highest level possible. Drain and inspect pump prior to
start-up.
3.
Rotate pump rotor 1-1/4 revolutions at least once a week. Make sure bearings have adequate lubrication before
turning rotor.
4.
Periodically remove bearing covers and inspect for accumulation of moisture, rust and foreign material. As
required, clean bearings and bearing housing and represerve. Install bearing cover and secure to assure
maximum protection.
START-UP
Prior to and during start-up, any requirement for the service of a Ruhrpumpen Representative will revert to the original
contract agreement for the equipment that was purchased.
DRIVERS
Generally storage must be indoors and dry. See the specific manufacturers storage requirements.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
10 OF 42
GS-4113
INTRODUCTION
This instruction book was written for your guidance. It is our hope you will become acquainted with its
contents as an aid to better pump performance. The Sectional Assembly and General Arrangement
drawings furnished should be consulted for accurate details.
DESCRIPTION (Refer to Sectional Assembly Drawing)
The pump is a single stage, double suction, dual volute pump with top suction and top discharge nozzles. Shaft sealing
is accomplished via a mechanical seal unit (120 and 120-1) located in each pump stuffing box. The shaft is supported
on pure oil mist lubricated radial ball bearing and ball thrust bearings. Axial thrust of the pump is absorbed by a double
row thrust ball bearing (654).
IMPELLER (176)
SHAFT (167)
COUPLING
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
11 OF 42
GS-4113
INSTALLATION
NOTE: The installation/commissioning of this equipment must be conducted in accordance with API
Recommended Practices 686/PIP REIE 686 First Edition. Refer to API 610 Eighth Edition
Appendix L for baseplate grouting requirements.
Copies of API Recommended Practices 686/PIP REIE 686 First Edition may be obtained from
America Petroleum Institute, 1220 L Street, N.W., Washington, D.C. 20005. Telephone: (202) 682-8000.
The following ASTM Specifications are furnished as references for test methods used in conjunction
with installation of grouting materials and should be used to obtain proper results.
ASTM C78-84
ASTM C109-90
ASTM C469-87a
ASTM C496-90
ASTM C531-85
ASTM C666-90
ASTM C939-87
ASTM C942-86
ASTM C1090-88
ASTM C1107-91
ACI 351 (CRD-C-621-92)
24-Hour Test
Fire Resistant
Minimum Compressive Strength 12000 PSI
Height Change @ 90F (38C) Positive Effective Bearing Area 95%
-3
Maximum Creep in one (1) year 1.6 x 10 in/in at 140F, 400 PSI
Minimum Tensile Strength 1800 PSI (12.4 Mpa)
Minimum Flexural Strength 3800 PSI (26.2 Mpa)
6
4
Minimum Flexural Secant Modulus 1.8 X 10 PSI (1.2 x 10 Mpa)
ASTM C531
-6
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
12 OF 42
SPECIFICATION
NUMBER
GS-4113
LOCATION
Install the unit close to the source of the liquid to be pumped. When selecting the location, be sure to allow
adequate space for operation as well as for maintenance operations involving dismantling and inspection of
parts. Headroom is an important consideration as an overhead lift of some type is required.
FOUNDATION
NOTE: The following information regarding foundation is only offered as a general guideline to the customer.
Ruhrpumpen Inc. requires that all foundation be designed/installed in accordance with specifications
set forth in Chapter 4 Foundations from API Recommended Practices 686/PIP REIE 686, First Edition.
The design of foundations is not the responsibility of Ruhrpumpen Inc. It is, therefore, recommended
that the customer consult a competent specialist skilled in the field of foundations, to insure proper
design/installation of the foundation.
The foundation should be sufficiently rigid and substantial to prevent any pump vibration and to
permanently support the baseplate at all points.
The most satisfactory foundations are made of reinforced concrete.
advance of the installation to allow proper time for drying and curing.
The General Arrangement drawing will furnish anchor bolt locations, size of bolts, etc.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
13 OF 42
GS-4113
The sketch below illustrates a recommended foundation bolt arrangement. Notice the large washer with
lugs at the bottom. It should be welded to the bolt and pipe sleeve to prevent turning.
Allow a little more than the specified threaded bolt length above the rail of the baseplate. The excess can
always be cut off if not needed.
A rough finish top surface is best when applying grout.
The following information regarding lifting is only offered as a general guideline to the customer.
Ruhrpumpen, Inc. requires that all lifting and rigging be performed in accordance with specifications
set forth in Chapter 2 Lifting and Rigging from API Recommended Practices 686/PIP EEIE 686, First
Edition.
WARNING
ENSURE THAT LIFTING RIGS, CRANES, CHAINS, AND/OR STRAPS ARE CAPABLE OF LIFTING AND
SUPPORTING THE ENCOUNTERED WEIGHTS. REFER TO THE APPROPRIATE WEIGHTS SECTION
OF THIS MANUAL TO DETERMINE SUITABILITY OF LIFTING EQUIPMENT.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
14 OF 42
GS-4113
INSTALLATION SEQUENCE
1.
2.
3.
4.
5.
6.
Level Baseplate
Preliminary Alignment
Grout Baseplate
Align Shaft/Coupling
Piping
Check Coupling Alignment
The following information regarding leveling of equipment is only offered as a general guideline to
the customer. Ruhrpumpen Inc. requires that all leveling of equipment be performed in accordance
with specifications set forth in Chapter 5 Mounting Plate Grouting from API Recommended
Practices 686/PIP ERIE 686, First Edition.
Before putting the unit on the foundation, thoroughly clean the top of the foundation. Break off any loose
pieces of cement and roughen the top with a chisel to afford a good hold for grout.
NOTE: Coupling bolting and spacer piece (when used) must be removed from between pump/driver half
couplings before lifting baseplate with pumping element.
NOTE: When lifting pump and baseplate together, sling baseplate from four of the eight lifting eyes
provided. Select the four lifting eyes that will maintain levelness and stability during lifting
operation. Failure to do this may result in permanent deformation of the baseplate.
Prepare enough iron wedges or shims to be placed on each side of each foundation bolt. These wedges
should be about 4 to 6 inches long, 2 to 3 inches wide, and thick enough to allow for 1-1/4 inches of grout
under the edge of the baseplate. Place wedges as shown in sketch.
Level the baseplate by using a machinists level on the machined surfaces of the pump and driver pads.
When the baseplate is leveled, pull down the foundation bolts so they are snug. The baseplate may have
been disturbed by tightening down the foundation bolts, therefore, recheck with level and make necessary
adjustments by wedges or shimming.
As a final baseplate alignment check on spacer type couplings, install a mounting bracket for dial indicator
on driver hub. Fasten or clamp indicator on mounting bracket so that dial indicator button is contacting face
on pump half coupling and zero the dial indicator. (Non-spacer type coupling should be checked with
tapered wedge or feeler gages.) Make sure shaft end distance is per General Arrangement drawing.
Rotate the driver half coupling (in direction of pump rotation) 90.
procedure until readings have been taken at four (4) 90 positions.
Using this procedure shim and/or wedge baseplate until pump and driver are within .003 inch.
Repeat this
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
15 OF 42
SPECIFICATION
NUMBER
GS-4113
GROUTING
NOTE: The following information regarding grouting of equipment is only offered as a general guideline to the
customer. Ruhrpumpen Inc. requires that all grouting be installed in accordance with specifications
set forth in Chapter 5 Mounting Plate Grouting from API Recommended Practices 686/PIP ERIE 686,
First Edition.
It is recommended that the customer consult a competent specialist skilled in the field of grouting to
insure the proper installation of all grouting.
Build a dam around the foundation. It is a matter of personal preference whether the leveling wedges
under the baseplate should be removed after grouting. If you want to remove the wedges, carefully mark
their locations before pouring grout.
When the grout is thoroughly hardened, remove the dam and wedges, if desired, filling in the holes they
leave with grout.
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
16 OF 42
SPECIFICATION
NUMBER
GS-4113
SHAFT/COUPLING ALIGNMENT
NOTE: The following information regarding shaft alignment is only offered as a general guideline to the
customer. Ruhrpumpen Inc. requires that all shaft alignment be performed in accordance with
specifications set forth in Chapter 7 Shaft Alignment from API Recommended Practices 686/PIP
REIE 686, First Edition.
CAUTION
SHAFT ALIGNMENT MUST BE CORRECT FOR SUCCESSFUL OPERATION. RAPID WEAR,
NOISE, VIBRATION, AND ACTUAL DAMAGE TO THE EQUIPMENT MAY BE CAUSED BY
SHAFT MISALIGNMENT. THE SHAFTS MUST BE ALIGNED WITHIN THE LIMITS GIVEN.
NOTE: Adjustment to correct the alignment in one direction may alter the alignment in another direction.
Always check in all directions after making any adjustment.
Coupling equipment must be aligned to minimuze unnecessary stresses in shafts, bearings, and coupling.
Flexible couplings will not compensate for appreciable misalignment. Foundation settling, thermal
expansion, nozzle loads resulting in baseplate/foundation deflection and vibration during operation may
require the full coupling misalignment capability.
TYPES OF MISALIGNMENT
There are two types of shaft misalignment: angular and offset. Therefore, two sets of measurements and corrections
are required. Both types of misalignment can occur in horizontal and vertical planes and are present in most
applications.
A.
Angular Misalignment
In angular misalignment, the centerline of the shafts intersect, but are not on the same axis.
ANGULAR MISALIGNMENT
B.
Offset Misalignment
In offset misalignment, the shaft centerlines are parallel but do not intersect.
OFFSET MISALIGNMENT
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
17 OF 42
GS-4113
ALIGNMENT
A.
Measure Gap
The first step in shaft/coupling alignment is to bring the pump and driver shafts into their proper axial position.
The shaft gap or distance between coupling hubs must be in accordance with the certified General Arrangement
drawing and must be measured with pump and driver shafts in the center of their axial end float. Motor with
sleeve bearings are to be aligned with rotor at magnetic center.
Move driver to insure proper gap distance.
NOTE:
B.
It is recommended that the pump hold down bolting be torqued and pump be doweled before taking any
alignment measurements. This makes the pump the fixed machine and the driver the moveable machine. In
certain cases, however, it may be impractical to move the driver, therefore, the pump may have to be moved.
When this case exists, the pump should not be doweled until after final alignment.
2. Starting with the 12 oclock markings of both hubs in the top center position, measure the gap at top, bottom,
right, and left side. Record these dimensions on ALIGNMENT DATA SHEET, Sheet 1, Part 1 in the
0column.
NOTE:
Right side and left side are determined when viewing the driver coupling from the pump.
3. Rotate both shafts 90 in the direction of pump rotation. Measure gap dimensions at the four (4) locations as
in Step 2. Record on ALIGNMENT DATA SHEET, Sheet 1, Part 1 in the 90 column.
4. Repeat Step 3 until measurements have been taken at the four (4) 90 positions (0, 90, 180, 270).
5. Rotate both shafts to the starting position (12 oclock markings at top center) and recheck dimension
recorded in Step 2.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
18 OF 42
GS-4113
6. For 0, 90, 180, and 270 columns, subtract the bottom from the top and left from right. Record in their
respective blocks on Data Sheet. Watch sign notations.
7. Total the different numbers (reading across), divide by four (4) and record the average ______. Record in
Open At ______ the shaft relative angular position.
NOTE:
C.
The inside faces of the driver and pump half hubs must be parallel within .001.
D.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
19 OF 42
GS-4113
3. Record vertical offset from Sheet 1, Part 2 and vertical move obtained from calculations in the INBOARD
and OUTBOARD DRIVER PEDESTAL SHIFT columns. Also record the required direction of shift (raise or
lower).
4. Record horizontal offset from Sheet 1, Part 2 and horizontal move obtained from calculations in the
INBOARD and OUTBOARD DRIVER PEDESTAL SHIFT columns. Also record the required direction of
shift (right or left).
5. Total the move requirements (watch move direction). This will yield the required hozizontal move (right or
left) and the vertical move (raise or lower) required at each mounting foot..
HORIZONTAL MOVE
The dial indicators, as shown in figure, are required to accurately measure the move in the horizontal direction. Move
the driver by bumping with soft hammer/mallet or using the jackscrews (if provided). The amount of horizontal
relocation required is the total of the horizontal move calculation (bottom of Sheet 2).
VERTICAL MOVE
Before moving the equipment vertically, it is important that the vertical thermal expansion be taken into consideration.
The proceeding vertical move calculations are based on pump and driver shafts being set on the same plane. Refer to
general arrangement notes and/or driver instructions for recommended cold vertical setting (if thermal expansion is a
foactor).
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
20 OF 42
GS-4113
The shims between the equipment feet and mounting surface should be clean and dry. This is especially critical for
pumps in service for some time and need to be realigned. Water, dirt, and rust may change the height of the shim
pack over a period of time. Shims should be made large enough to support the weight of the equipment on its
mounting foot. Do not use many thin shims as this may result in a spongy mounting.
Move the equipment vertically by adding or removing the calculated thickness of shims. Torque equipment hold down
bolting to required values.
NOTE: It is recommended, the completed ALIGNMENT DATA SHEET be retained as part of your permanent
maintenance file.
CHECK COUPLING ALIGNMENT
The angular and offset coupling alignment must be rechecked.
1. Coupling faces are to be parallel within a .001 TIR.
2. Coupling outside diameters are to be aligned within .003 TIR.
3. Bump the motor and check motor rotation.
ASSEMBLE AND LUBRICATE COUPLING
1. Assemble and lubricate coupling per the manufacturers instructions.
2. Install coupling guard.
DOWEL PUMP AND DRIVER
A. Cold Pumps
Pump hold down bolts are to be torqued to the proper valve and dowel pins are put in two (2) feet (diagonally
opposite).
B. Pump Driver
Refer to driver outline drawing and/or driver instructions for doweling information.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
21 OF 42
GS-4113
WARNING
DO NOT ATTEMPT ANY MAINTENANCE, INSPECTION, REPAIR, OR CLEANING IN THE VICINITY OF
ROTATING EQUIPMENT. SUCH ACTION COULD RESULT IN INJURY TO OPERATING PERSONNEL.
WARNING
BEFORE ATTEMPTING ANY INSPECTION OR REPAIR ON THE PUMP, THE DRIVER CONTROLS
MUST BE IN THE OFF POSITION, LOCKED AND TAGGED TO PREVENT INJURY TO PERSONNEL
PERFORMING SERVICE ON THE PUMP.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
GS-4113
PAGE
REV.
22 OF 42
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
GS-4113
PAGE
REV.
23 OF 42
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
24 OF 42
GS-4113
PIPING
NOTE:
The following information regarding piping is only offered as a general guideline to the customer.
Ruhrpumpen Inc. requires that all piping and related systems be designed/ installed in accordance
with specifications set forth in Chapter 6 Piping from API Recommended Practices 686/PIP REIE
686, First Edition.
The design of piping and related systems is not the responsibility of Ruhrpumpen Inc. It is,
therefore, recommended that the customer consult a competent specialist skilled in the field of
piping to insure proper design/installation of all piping.
MAIN PIPING
Suction and discharge piping should be of ample size, be installed in direct runs, and have a minimum of bends. Refer
to the General Arrangement drawing for pertinent piping data.
NOTE:
Do not connect any piping until the foundation bolts have been finally pulled down.
The piping should be independently supported and must not be drawn into position with the flange bolts.
Provision must be made to support the piping external to the pump in order to prevent excessive nozzle loads and
maintain pump-driver alignment.
MINIMUM FLOW BY-PASS
WARNING
CUSTOMER TO PROVIDE A SUITABLE MINIMUM FLOW BY-PASS SYSTEM CONNECTED TO PUMP
DISCHARGE PRIOR TO FIRST VALVE. THE BY-PASS FLOW SHOULD BE DIRECTED TO THE
SOURCE OF PUMP SUCTION AND DESIGNED TO HANDLE A MINIMUM FLOW OF 291 M3/HR (1282
GPM) WITH A PRESSURE BREAKDOWN OF 4,175 m(13,697 FT) AT DESIGNED SPEED. A BACK
PRESSURE DEVICE LOCATED DOWNSTREAM OF THE MINIMUM FLOW VALVE MAY BE REQUIRED
TO SUPPRESS VALVE CAVITATION OR DOWNSTREAM LINE FLASHING.
PUMP SHOULD BE STARTED WITH CLOSED DISCHARGE VALVE AND OPEN MINIMUM FLOW BYPASS LINE.
SEAL PIPING
Refer to seal piping drawing for information pertaining to your system.
SUCTION STRAINER
In a new installation, great care should be taken to prevent dirt, scale, and welding beads from entering the
pump. Even when piping has been previously flushed, it is difficult to break loose the oxides and mill scale
which will become free when the pipe heats and cools several times. Numerous close running clearances
are vulnerable to abrasive matter present in new piping. Foreign material may be large enough, or of
sufficient volume, to jam a pump, with probable damage to both pump and drive equipment. Smaller
material passing through the pump can cause rapid pump wear and premature pump failure.
This pump is provided with the exception that it will be pumping clean liquids (unless otherwise stated in the
order and addressed in the proposal). Ruhrpumpen pumps are provided with running clearances ranging
typically from 0.12 mm(0.005 inch) to 0.80 mm(0.030 inch), depending on the service. It is impractical to
install a suction strainer to remove particulate of this size. Such particles will normally pass through the
pump without causing damage, providing the concentrations are minor.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
25 OF 42
GS-4113
The possibility exists that, on shutdown of the pump, such particles can become trapped in the close
running clearances during coastdown, causing binding. Ruhrpumpen cannot recommend a procedure that
will totally prevent such binding; however, we strongly suggest that systems be cleaned and thoroughly
flushed prior to connecting the pump to the piping to minimize particles entering the pump. Starting and
stopping of the pump should be MINIMIZED as pumps are most susceptible to dirt during starts and stops.
In the event that binding on coastdown occurs, it is unlikely that the binding can be remedied by hand
rolling the rotor, and partial disassembly may be required to clean the affected parts. It should be noted
that increased particle concentrations increase the probability of coastdown binding and seizures, as well
as erosion damage.
CAUTION
EXCESSIVE FORCE USED TO TRY TO FREE A BOUND ROTOR MAY CAUSE DAMAGE BEYOND
MINOR CLEAN-UP AND REPAIR OF ROTOR PARTS.
Generally, a pump should not be installed without strainer protection. The suction system should be
thoroughly flushed before installing the suction strainer and making up the suction piping to the pump. The
strainer should be installed in the inlet piping near the pump, making certain that it is located where it may
be readily serviced (cleaned). Be sure, however, that the installed strainer will not distort the flow to the
pump suction.
Do not install the strainer directly on the pump suction nozzle. For a cone-type strainer, the downstream
end of the cone should be no closer than four (4) pipe diameters from the pump suction connection.
Basket-type strainers typically introduce greater flow disturbances and should be installed at least six (6)
pipe diameters from the pump suction nozzles.
The Ruhrpumpen standard for suction strainers consists of conical-shaped steel plate with 3.175 mm(1/8
inch) perforations. The open area of the strainer should be a minimum of three times the area of the pump
suction.
At all times when using suction strainers, it is critical that the pressure drop across the strainer be
constantly monitored to ensure that the pump suction pressure does not fall below that required to prevent
pump cavitation. Pressure (or vacuum) gauges should be installed on both sides of the strainer so that the
pressure drop across the strainer can be monitored. During startup of the system, the gauges should be
monitored continuously. Consult the plant engineer or system designer for the allowable pressure
differential across the strainer prior to operating the pump. Pressure differential across the strainer and/or
screen is typically no more than 13.8 20.7 Kpa(2-3 psig). An increase in the differential pressure between
the two gauges indicates that the strainer or screen is becoming clogged with dirt and scale. Before the
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
26 OF 42
GS-4113
pressure drop becomes so severe that cavitation occurs, the pump should be shut down and the strainer
cleaned. Alarm settings to protect the pump from damaging cavitation and loss of suction need to be
supplied by the plant engineer or system designer prior to operating the pump. Typically alarm settings to
protect the pump from damaging cavitation and loss of suction would be 5 psig differential pressure across
the strainer (screen). The suction piping should be arranged such that the ultimate strainer configuration
(location) allows ready access for cleaning.
The strainer may be fitted with a finer screen to filter the inlet flow. When this is done, 40 mesh screen is
typically used for start-up operation, at reduced flow rates. For final operation in a closed system, the
suction strainers are normally removed after the system is cleaned. For critical pump applications where
continuous screening of suction flow is desirable, and in open systems, 20 mesh screening is typically used
for permanent strainers. At all times, when using screens and suction strainers, it is critical that pressure
drop across the screen and/or strainer be constantly monitored to ensure that the pump suction pressure
does not fall below that required to pevent cavitation.
When dirt and scale have been removed from the system, as indicated by no further change in pressure
drop across the strainer with time, the startup strainer may be removed or the screen may be replaced with
one having larger openings. If a permanent strainer will be used during normal operations, the pressure
differential needs to be monitored on a continuous basis.
If a permanent strainer is not used, the startup strainer needs to be temporarily reinstalled whenever the
system is opened up for repair or routine maintenance. As long as a suction strainer or screen remains in
place, the differential pressure should be monitored on a regular basis.
CAUTION
THE PRESSURE DROP ACROSS THE STRAINER IS A DIRECT REDUCTION IN THE NPSH AVAILABLE TO THE
PUMP.
NPSH AVAILABLE MUST ALWAYS EXCEED THE NPSH REQUIRED BY THE PUMP.
THIS
REQUIREMENT MAY LIMIT THE PUMP FLOW RATE, PARTICULARLY DURING STARTUP OPERATION.
ALARMS OR AUTOMATIC PUMP SHUT-DOWN DEVICES SHOULD BE INSTALLED TO MINIMIZE THE
POSSIBILITY OF PUMP DAMAGE. IT IS THE RESPONSIBILITY OF THE PUMP OPERATOR TO OBTAIN THE
ALLOWABLE PRESSURE DROP ACROSS THE STRAINER FOR SAFE PUMP OPERATION FROM THE PLANT
ENGINEER OR SYSTEM DESIGNER PRIOR TO OPERATION OF THE PUMP.
LUBRICATION
WARNING
OPERATION OF THE UNIT WITHOUT PROPER LUBRICATION CAN RESULT IN OVERHEATING OF
THE BEARINGS, BEARING FAILURES, PUMP SEIZURES, AND ACTUAL BREAKUP OF THE
EQUIPMENT, EXPOSING OPERATING PERSONNEL TO INJURY.
The plain end and thrust end housings (278) are equipped with a Trico Oiler.
SETTING page.)
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
27 OF 42
GS-4113
OIL SPECIFICATIONS
The ideal bearing lubricant is a straight, well refined, neutral mineral oil, preferably of the turbine type. It should not
contain free acid, sulfur, chlorine, or more than a trace of free alkali. It is suggested that the oil conform to the following
physical characteristics based on tests by ASTM Standard Methods.
ASTM STANDARDS (For Mineral Oils)
Sdff
101-180F (38-82C)
158 Seconds
335 Seconds
20F (-7C)
20F (-7C)
400F (204C)
400F (204C)
32
68
In a majority of instances, ISO 68 (nominally equivalent to SAE 20 turbine oil) will meet the above specifications.
The minimum bearing oil temperature is 60F. If necessary, the oil in the bearing housing(s) should be drained
and replaced with warm oil.
When ambient temperature falls below 50F, it is recommended that the bearing housings be heated by use of
heating tapes.
When pure oil mist lubrication is supplied, the oil mist is the only lubricant provided. The oil mist generator
must be running before starting the unit.
When pure oil mist lubrication is supplied, a constant level oiler or oil rings are not supplied.
Basic oil mist system should include the following:
1.
2.
3.
4.
5.
An air-line filter-water separator to assure a clean air supply to oil mist generator.
An air pressure regulator to control the oil mist generator atomizing air pressure.
An oil mist generator which includes a venturi nozzle, oil lift tube, reservoir and oil flow adjustment screw.
Mist distribution manifold to convey the oil mist application fittings.
Spray application fitting to meter and convert the oil mist at each lubrication point.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
28 OF 42
GS-4113
Provide oil mist spray directly to bearing balls by adjusting reclassifier length. Oil mist should be vented out
oil mist outlet. (When pump is idle and mist generator is on, a mist should be visible exiting the vents.
When pump is running, the windage associated with the shaft, bearing, and coupling makes it difficult to
see the mist.)
Periodically inspect the plastic sediment bottle underneath the bearing housings. Drain as required. If
bearing housing is dismantled, flush bearing housing with a clean light oil. Be certain bearings have a light
coating of oil before start-up.
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
29 OF 42
SPECIFICATION
NUMBER
GS-4113
OPERATION
WARNING
THE UNIT MUST NOT BE OPERATED UNLESS COUPLING GUARD IS IN PLACE. FAILURE TO
OBSERVE THIS WARNING COULD RESULT IN INJURY TO OPERATING PERSONNEL.
CAUTION
PRIOR TO STARTUP, OIL MUST BE POURED OVER THE JOURNAL AREAS AT OIL RINGS. A
SUFFICIENT AMOUNT OF OIL IS REQUIRED TO INSURE PROPER LUBRICATION OF BEARINGS AT
STARTUP.
CAUTION
CHECK TRICO OILERS TO ENSURE THAT THE PUMP BEARINGS HAVE BEEN FILED TO THE
PROPER LEVEL WITH LUBRICATING OIL. (REFER TO TRICO OILER PAGE.)
INITIAL START-UP
1.
Check all main and auxilliary piping making certain it is connected properly.
independently supported and must not be drawn into position with flange bolting.)
NOTE:
(Piping must be
a. If the piping was connected after the unit was aligned, recheck alignment.
b. Provision must be made to support piping external to the pump to prevent excessive nozzle
loads and maintain pump-driver alignment.
2.
3.
4.
5.
Check the trico oilers to be sure that the pump bearing housings have been filled to the proper level with
lubricating oil. (See LUBRICATION section instructions.)
WARNING
OPERATION OF THE UNIT WITHOUT PROPER LUBRICATION CAN RESULT IN OVERHEATING OF
THE BEARINGS, BEARINGS FAILURES, PUMP SEIZURES AND ACTUAL BREAKUP OF THE
EQUIPMENT EXPOSING OPERATING PERSONNEL TO INJURY.
CAUTION
WHEN THE AMBIENT TEMPERATURE FALLS BELOW 50F., IT IS RECOMMENDED THAT THE OIL IN
THE PLAIN/THRUST BEARING HOUSINGS BE PREHEATED.
6.
Warm up pump prior to starting. Casing temperature must be within 100F of available suction liquid
temperature prior to pump operation. The warming rate of the casing should not exceed 2F per minute.
Customers to supply 50 gpm of warming liquid to the pump discharge. Customer to provide a warming liquid
inlet line between pump discharge nozzle and first valve. Run outlet flow through pump suction back to source of
suction.
Close valves in discharge and minimum flow lines to isolate pump during warm-up and hot standby.
The warming liquid inlet line must be closed immediately prior to pump operation. Suction and minimum flow
lines must be opened immediately to pump operation.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
30 OF 42
GS-4113
CAUTION
PRIOR TO PUMP OPERATION, CASING TEMPERATURE MUST BE WITHIN 100F OF AVAILABLE
SUCTION LIQUID TEMPERATURE. PUMP SHOULD BE STARTED WITH CLOSED DISCHARGE
VALVE AND OPEN MINIMUM FLOW BY-PASS LINE.
WARNING
TO AVOID OVER PRESSURIZING PUMP SEALS AND SUCTION LINE, THE WARMING LIQUID
OUTLET LINE MUST ALWAYS BE OPEN WHEN THE WARMING LIQUID INLET LINE IS OPEN. OPEN
THE WARMING LIQUID OUTLET LINE BEFORE OPENING THE INLET LINE. CLOSE THE WARMING
LIQUID INLET LINE BEFORE CLOSING THE OUTLET LINE.
7.
8.
9.
10.
11.
12.
Check that pump is vented by observing leakage from vent line. Close vent when liquid is emitted.
Check pump rotation by starting pump momentarily. Note the pump coasts to a gradual stop.
WARNING
THE DRIVER ROTATION MUST BE CHECKED BEFORE MAKING UP COUPLING. ACTUAL DAMAGE
TO THE EQUIPMENT AND PERSONAL INJURY COULD RESULT FROM OPERATING THE UNIT
WITH WRONG ROTATION.
CAUTION
IF PUMP STOPS ABRUPTLY ON SHUTDOWN OF DRIVER, INVESTIGATE FOR PUMP BINDING.
TAKE NECESSARY REMEDIAL ACTION BEFORE RESUMING OPERATING.
13.
14.
15.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
31 OF 42
GS-4113
NORMAL START-UP
The starting procedure to be followed for normal start-up is the same as that for initial starting with the exception that
Steps 1 through 4, and Step 11 do not have to be repeated.
OPERATING CHECKS
WARNING
DO NOT ATTEMPT ANY MAINTENANCE, INSPECTION, REPAIR, OR CLEANING IN THE VICINITY OF
ROTATING EQUIPMENT. SUCH ACTION COULD RESULT IN INJURY TO OPERATING PERSONNEL.
Systematic checks following start-up operations are a factor in avoiding costly shutdowns. Immediately
after startup, and frequently during running, check the following:
1.
Check suction and discharge pressure gauges to see that they indicate the proper operating conditions.
If at any time the suction/discharge gauges should drop to zero, shut down the pump immediately.
The discharge gauge should show an increase in the pressure as the pump picks up speed. If it does not, shut
down the pump and locate the cause of the trouble.
2.
Mechanical Seal check for leakage; there should be not visible leakage.
3.
4.
5.
Any time unit is running, frequently check the oil mist lubrication system and the bearing lubrication.
6.
Check pessure differential between the gauges located on each side of the suction strainer (when used).
7.
Recheck alignment recheck pump alignment after the pump has been in operation for a few hous.
8.
The pump should be shut down rapidly to protect wearing parts which are lubricated by the liquid being pumped.
Lubrication is reduced when the unit is stopped slowly and seizure could result.
2.
If pump stops abruptly when motor is shut down, investigate for pump binding. Take necessary remedial
action before restarting pump.
Lubrication is reduced when a pump is stopped slowly and seizure could result.
3.
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
32 OF 42
SPECIFICATION
NUMBER
GS-4113
TROUBLESHOOTING
The following chart presents the probable troubles that can occur to the pump along with the probable
causes and remedies for the troubles.
TROUBLE SHOOTING CHART
TROUBLE
CAUSE
REMEDY
Open suction valve wide.
Check power supply for correct voltage to motor.
Mechanical defects
Wearring rings worn.
Impeller damaged
Sheared impeller key
Pump vibrates
Clogged impeller
Tighten bolts.
Misalignment
Mechanical Defects:
Shaft bent
Bearings worn
Tighten
Improper lubrication
Pump is noisy
Cavitation
Loose parts
Noise in driver
Remove and
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
33 OF 42
GS-4113
DISMANTLING PROCEDURE
WARNING
BEFORE ATTEMPTING ANY INSPECTION OR REPAIR ON THE PUMP, THE DRIVER CONTROLS
MUST BE IN THE OFF POSITION, LOCKED, AND TAGGED TO PREVENT INJURY TO PERSONNEL
PERFORMING SERVICE ON THE PUMP.
WARNING
DO NOT ATTEMPT ANY MAINTENANCE, INSPECTION, REPAIR, OR CLEANING IN THE VICINITY OF
ROTATING EQUIPMENT. SUCH ACTION COULD RESULT IN PERSONAL INJURY TO OPERATING
PERSONNEL.
WARNING
BEFORE ATTEMPTING TO DISASSEMBLE PUMP, PUMP MUST BE ISOLATED FROM SYSTEM BY
CLOSING SUCTION AND DISCHARGE SYSTEM VALVES, DRAINED OF LIQUID AND COOLED IF
PUMP IS HANDLING HOT LIQUID.
WARNING
WHEN PUMP IS HANDLING HOT LIQUID, EXTREME CARE MUST BE TAKEN TO ENSURE SAFETY
OF PERSONNEL WHEN ATTEMPTING TO DRAIN PUMP. HOT PUMPS MUST BE ALLOWED TO
COOL BEFORE DRAINING. PROTECTIVE GLOVES OR OTHER SUITABLE PROTECTION MUST BE
WORN.
Open and tag motor circuit breaker.
Disconnect the coupling and remove the spacer piece.
Remove all auxiliary piping.
Remove the drain plug(s) and drain the casing (1).
WARNING
USE EXTREME CAUTION WHEN DRAINING THE CASING OF HOT AND/OR CORROSIVE LIQUID.
COUPLING REMOVAL
Refer to manufacturer instructions and observe supplemental notes offered by the Manufacturer.
Remove coupling guard.
Release the two set screws and remove the pump half coupling nut (251) and coupling key (676-1). Apply heat and
use an approved type pulled to facilitate removal.
NOTE:
Remove pump half coupling hub by heating to approximately 300F in successive stages from periphery of
coupling towards center. NEVER APPLY AN OPEN FLAME TO COUPLING HUB TEETH.
Drain any oil accumulated at the bottom of the bearing housing by opening up the valve at the bottle (665).
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
34 OF 42
GS-4113
WARNING
USE EXTREME CAUTION TO PREVENT INJURY WHEN DRAINING BEARING HOUSING (278) OF HOT OIL.
Step 2)
Remove outboard end cover to radial bearing housing bolting. Slide outboard end cover (281) with bearing
guard (117-1) from shaft.
Step 3)
Remove inboard end cover to radial bearing housing bolting. Slide inboard end cover (280) with bearing
guard (117) back on shaft towards center of pump.
Remove bolting which secures bearing housing (278) to pump cover (051).
Step 4)
Step 5)
Step 6)
Step 7)
Step 8)
Carefully slice bearing housing (278) from the ball bearing (655).
Release locking tab of lockwasher (673). Loosen and remove locknut (878) and lockwahser from shaft.
Remove spacer sleeve (225) from shaft. Remove ball bearing (655) using a puller that will bring pressure
against the inner bearing race only.
Remove pump-side end cover (280) with bearing guard (117) from shaft.
Drain any oil accumulated at the bottom of the bearing housing by opening up the valve at the bottle (665).
WARNING
USE EXTREME CAUTION TO PREVENT INJURY WHEN DRAINING BEARING HOUSING (278) OF HOT OIL.
Step 2)
Step 3)
Remove inboard end cover to thrust bearing housing bolting. Slide inboard end cover (280-1) back on shaft.
Step 4)
Remove bolting which secures the bearing housing (277) to the case (001).
Step 5)
Step 6)
Release the locking tab of lockwasher (673-1). Loosen and remove locknut (878-1) and lockwasher (673-1).
Step 7)
Remove ball bearings (654) using a puller that will bring pressure against the inner bearing race only.
Remove shims.
Step 8)
Remove bearing shims. Measure and record thickness of shims; the together for reassembly. Remove
inboard end cover (280-1) with o-ring (747) and shims (262/262-1) from shaft.
Remove mechanical seals per MECHANICAL SEAL instructions found in the manual.
Step 2)
Remove bolting holding pump cover (051) to casing (001). Jack screws are provided to separate joint
between pump cover and case.
Step 3)
Using eyebolt, rig to overhead hoist and remove pump cover (051). Remove gaskets (744 & 744-1).
NOTE:
Step 4)
The outboard end of pump shaft must be supported during and after removal of pump
cover (051).
Rig pump shaft with slings, using a protective devise to protect shaft from damage by slings. Slide shaft
complete with impeller (176) from pump case and place on horses. Block the shaft to prevent rolling. It will
be necessary to re-rig the inboard end of shaft so that shaft is removed properly.
CAUTION
CARE MUST BE TAKEN NOT TO DAMAGE ROTOR WHILE PASSING THROUGH THE CASING.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
35 OF 42
GS-4113
DISMANTLING OF ROTOR
Step 1)
Release the set screws in each impeller nut (246 and 246-1), then remove impeller nuts from shaft (167).
Step 2)
Measure and record the distance from the coupling end of the shaft (167) to the face of the impeller hub as
shown in figure below. Record this dimension to ensure impeller (176) is properly positioned when
reassembling pump.
IMPORTANT
MARK THE IMPELLER (176) IN SOME MANNER SO THAT IT CAN BE INSTALLED FOR CORRECT
ROTATION AT THE TIME OF ASSEMBLY.
Step 3)
Tap impeller hub lightly with rubber hammer and remove the impeller (176). Remove impeller key (676).
If the impeller does not move freely off the shaft (this is rare case), heat may be necessary. Heat impeller
using following procedure:
IMPELLER REMOVAL (IF HEATING IS REQUIRED)
A.
Apply heat (torch with rosebud tip) to periphery of impeller until temperature reaches 375 minimum to 400F
maximum. Use tempilstick to determine temperature.
B.
Maintaining temperature between 375-400F at the periphery, apply heat to the shrouds.
C.
With periphery and shroud at temperature, apply a quick heat to the hub of the impeller.
D.
E.
If the impeller does not move freely off the shaft, additional heat may be necessary. THIS HEATING SHOULD
BE STARTED AT THE PERIPHERY OF THE IMPELLER, NOT THE HUB. (Additional heating of the hub area at
this time will tighten the impeller on the shaft, not loosen it.) If the impeller still fails to come free, the impeller and
shaft should be allowed to cool completely, and the heating process repeated, starting at A.
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
36 OF 42
SPECIFICATION
NUMBER
GS-4113
INSPECTION OF PARTS
WARNING
DO NOT ATTEMPT ANY MAINTENANCE, INSPECTION, REPAIR, OR CLEANING IN THE VICINITY OF
ROTATING EQUIPMENT.
SUCH ACTION COULD RESULT IN PERSONAL INJURY TO OPERATING
PERSONNEL.
1.
Having completely dismantled the rotor, place shaft on V blocks or rollers (positioned) under the normal bearing
areas). Check shaft for run out using a dial indicator. Run out not to exceed .002 TIR.
2.
Wire brush the pump parts thoroughly. Clean off all scale, carbon, etc. Examine parts for wear, corrosion, and
erosion.
Check thrust bearing (654) for excessive wear, rust, and/or flat spots. Replace as necessary. (See page titled
BEARING HANDLING INFORMATION.)
Check impeller nuts (246 and 246-1) for wear. Replace as necessary.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
37 OF 42
GS-4113
3.
4.
5.
Clean the complete casing (001) and bearing housings (278) of all foreign matter.
6.
7.
Renew all gaskets (744 and 744-1) and o ring (747) during pump reassemble procedure.
There are two simple methods of providing a heat source for expanding the inner race of the bearings to facilitate
mounting. In the first method, bearings still wrapped in their original intimate wrape are placed on a shaft in a
temperature controlled oven, or in an enclosure lined with foil and heated with foil and heated with electric light
bulbs. A temperature of 150F for one half hour should be sufficient.
A second method consists of locating a light bulb (100 to 150 watt) in the bore of the bearing. The light bulb will
heat, prmarily, the inner ring and the bearing can usually be handled by the outer ring without special gloves.
Care must be taken to keep the bearing clean and uncontaminated.
LIGHT BULBS ARE LOCATED IN THE BORE OF THE BEARING AS A HEAT SOURCE FOR
EXPANDING THE INNER RACES OF BEARINGS FOR MOUNTING.
NOTE: The old and popular method of heating bearings in an oil bath is DEFINITELY DISCOURAGED. HEATING
INNER RING WITH A GAS TORCH IS PROHIBITED. In either case, it is difficult to control the heating rate
and final temperature and even more difficult to keep the oil and/or bearing clean.
SPECIFICATION
RUHRPUMPEN INC.
2.
SPECIFICATION
NUMBER
PAGE
REV.
38 OF 42
GS-4113
When bearings are installed on shaft, make sure bearing is installed squarely and is firmly seated. Hold bearing
in place until it has cooled sufficiently so that it will not move from position. Cover bearings to protect them from
dirt.
NOTE: When installing the bearings, the mounting pressure should never be applied in such a manner that it is
transmitted through the rollers. Apply the mounting force directly against, and only against, the inner ring.
3.
When installing bearing and shaft in bearing housing, or installing outboard bearing on shaft, bearing housing
bores and bearing outside diameter should be coated with grease or lubricating oil to be used to facilitate
assembly.
BEARING REMOVAL
If the bearings cannot be removed with the tools available, never use a torch under any circumstances. Split the outer
ring with a small hand grinder, was through the ball/roller retainer, and split the inner ring about three quarters through
with a grinder and break with a cold steel chisel.
BEARING CLEANING
NOTE: Do not attempt to inspect condition of bearings until they have been cleaned.
1.
Solvent for cleaning bearings should be in a clean container. Place bearings in solvent and let soak for a short
time. Slosh the bearing around near the top of the container, giving it a turn now and then until it is clean. Rinse
in a clean container of clean solvent.
NOTE: Do not spin dirty bearings. Rotate them slowly while washing.
2.
Dry the thoroughly cleaned bearings. If an air hose is used for drying, use clean, dry air.
NOTE: Do not allow the bearing to spin by force of air. Hold both the inner and outer rings to prevent bearing from
spinning.
3.
Inspect bearings immediately. If there is any question as to the condition of a bearing, it must not be reused.
There are many conditions that contribute to the deterioration of the bearings. A qualified bearing representative
should be consulted if there is any question of bearing condition.
4.
Inspected bearings which will be reused should be packed with new grease or dipped in clean lubricating oil,
covered with clean lint free rags or other suitable covering and placed in a clean box or carton until ready for
installation.
NOTE:
REASSEMBLE
REASSEMBLE THE ROTOR
Step 1)
Step 2)
Install impeller (167) as done for disassembly and install impeller over the outboard end of the shaft until the
impeller hub face is in contact with the face of the shoulder on the shaft.
CAUTION
Install space sleeve (225) and impeller nut (246) on shaft. Tighten the set screws in impeller nut.
Place rotating element on rolls or V blocks and check runout of shaft. Run out not to exceed .003 TIR.
Step 2)
With a dial indicator, check impeller rings (201) for runout or high spots. Run out not to exceed .003 TIR.
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
39 OF 42
GS-4113
ROTOR INSTALLATION
Step 1)
Install shaft complete with impeller in casing. Care must be taken when inboard section of shaft passes
through the casing. Avoid nicks and burrs to the shaft.
NOTE: Outboard end of pump shaft must be supported prior to installation of pump cover (051).
Step 2)
Using eyebolt provided and an overhead hoist, install pump cover (051) with new gaskets (744 and 744-1)
over shaft (167). DO NOT USE THE OLD GASKETS.
Step 3)
Use a good grade of thread lubricant on studs. Replace nuts on pump cover (051) and tighten until flange is
in metal-to-metal contact with casing. Do not exceed recommended torque value. (Refer to TORQUE
VALUES, on page )
a. Install inboard end cover (278) with bearing guard (117) on shaft. Slide towards center of pump.
b. Heat radial bearing (655) and install against shoulder of shaft.
c. Install space sleeve (225-1), bearing lockwahser (673), and locknut (878) on shaft. Tighten locknut but
do not secure tabs on lockwasher at this time.
d. Assemble radial bearing housing (278), with reclassifier (612), into position over bearing (655). Install
bearing housing to casing bolting and snug capscrews. Be sure both horizontal and vertical adjusting
setscrews are installed in bearing housing.
Step 2)
a. Install inboard end cover (280-1), with bearing guard (117), shims (262/262-1), and o-ring (747), on shaft.
Slide towards center of pump.
b. Assemble Dummy Bearing (not supplied) to shaft. (A Dummy Bearing can be mad by taking a used
set of ball bearings and opening up the bore so it has a .0005 to .0010 loose fit to the shaft). Compare
width of outside bearing races with new bearing races. Differences must be compensated when
adjusting for .005 to .010 end play.
c.
NOTE: Do not set locking tab of lockwasher (673-1) at this time: Dummy Bearing will have to be removed.
d. Carefully install bearing housing (277), with reclassifier (612-1), into position over bearings (654).
NOTE: Bearing bodies have been pre-set at factory. Rotor vertical and horizontal alignment should be
checked. Rotor should turn with no indication of binding. Should rotor require further adjustment,
proceed with Steps 3, 4, and 5.
e. Install capscrews that hold thrust bearing housing (277) to case (001); snug down capscrews. Install
both the vertical and horizontal adjusting screws in the bearing housing mounting flange.
Step 3)
Using a set of inside-spring calipers and the adjusting setscrews, adjust the horizontal and vertical position of
the shaft at the inboard end so that the distance between the shaft and the stuffingbox bore is the same all
the way around.
Step 4)
Repeat Step 3 on outboard end, then re-check radial end. Pump shaft should turn free with no indication of
binding or rubbing. This should be taken into consideration when making adjustments.
Step 5)
When vertical and horizontal alignment is obtained, tighten bearing housing bolting except the two top bolts
at the adjusting screws. Loosen adjusting setscrews and tighten the two top bearing housing bolts. (Refer to
TORQUE VALUE, Page )
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
40 OF 42
SPECIFICATION
NUMBER
GS-4113
Install inboard end cover (280-1) with bearing guard (117), shims (262/262-1) and o-ring (747). Tighten
capscrews.
Step 2)
Install a dial indicator on thrust bearing housing (280-1) so indicator contacts the end of the shaft. Push the
rotor inboard (towards coupling end) and set indicator at zero. Push rotor outboard. The dial indicator will
show amount of axial end play.
a. If distance indicated is between .005 - .010, no further shim adjustments is required.
b. If distance indicated is above .010, remove inboard end cover (280-1) and remove amount of shims
(262 and 262-1) which will reduce axial end play to .005 - .010.
c.
Step 3)
If distance indicated is below .010, remove inboard end cover (280-1) and add shims (262/262-1) to
increase axial end play to .005-.010 (shims may be cut for ease of assembly).
Install inboard end cover (280-1) with shims (262 and 262-1) and o-ring.
capscrews to proper torque value. (Refer to TORQUE VALUES, Page )
Tighten capscrews.
Torque
Using a strap wrench, rotate shaft to be sure rotor is properly aligned and dies not bind.
CAUTION
Step 2)
Step 3)
Remove bearing locknut (878-1), bearing lockwasher (673-1), and Dummy Bearing from shaft.
Step 4)
CAUTION
DO NOT TIGHTEN COLLAR SETSCREWS IN MECHANICAL SEAL AT THIS TIME.
FINAL THRUST BEARING ASSEMBLY
Step 1)
With inboard end cover (280-1), shims (262 and 262-1), bearing guard (117), and o-ring (747) in position on
shaft, install thrust bearings (654) on shaft. Heat bearings and install against shoulder of shaft in back-toback position (stamping witll be face-to-face) as shown on sketch. (Refer to BEARING HANDLING
INFORMATION)
SPECIFICATION
RUHRPUMPEN INC.
PAGE
REV.
41 OF 42
SPECIFICATION
NUMBER
GS-4113
Step 2)
Step 3)
Carefully assemble bearing housing (277), with reclassifier (612-1) into position over the thrust bearing (654).
Step 4)
Install capscrews that hold bearing housing (277) to case, tighten to the proper torque value. (Refer to
TORQUE VALUES, Page )
Step 5)
Assemble inboard end cover (280-1), with bearing guard (117), shims (262 and 262-1), and o-ring (747), to
bearing housing (277). Tighten capscrews to proper torque value. (Refer to TORQUE VALUES, Page )
Step 6)
Install end cover (279) with gasket and capscrews. (Refer to TORQUE VALUES, Page )
Attach previously installed inboard radial end cover (280) to radial bearing housing (278) by installing end
cover to bearing housing bolting and tightening. (Refer to TORQUE VALUES, Page )
Step 2)
Torque radial bearing housing to casing bolting. (Refer to TORQUE VALUES, Page )
Step 3)
Install end cover (281) with gasket, bearing guard (117-1), to bearing housing (278). Install end cover to
bearing housing bolting and tighten. (Refer to TORQUE VALUES, Page )
FINAL ASSEMBLY
Step 1)
Using a strap wrench, rotate shaft to be sure rotor is properly aligned and does not bind.
CAUTION
Step 2)
Tighten
Step 3)
Install coupling key (676-1) and coupling hub onto pump shaft. Install coupling nut (251), then tighten and
set the setscrews in coupling nut.
Step 4)
Check coupling / shaft alignment as described under SHAFT/COUPLING ALIGNMENT and assemble
coupling.
Step 5)
Step 6)
Step 7)
Fill pure oil mist lubrication system supply to the proper level with fresh lubrication oil.
Step 8)
SPECIFICATION
RUHRPUMPEN INC.
SPECIFICATION
NUMBER
PAGE
REV.
42 OF 42
GS-4113
ORDERING INSTRUCTIONS
Mail your order to Ruhrpumpen, Inc.
Refer to your Sectional Drawing which has every part numbered to correspond with the Engineering Parts
List furnished.
The following should be included when ordering any parts for your pump.
RURHPUMPEN PROJECT NUMBER
PUMP SIZE
SECTIONAL ASSEMBLY NUMBER
EXAMPLE:
NAME OF PART
SHAFT
167
PART NUMBER
2000598
QUANTITY
CLASS 2 (Average):
Cover recommended spare parts for a single unit where additional spare parts are
not readily available. Suggested for Domestic Service handling abrasive or
corrosive liquids where some interruptions in service are permissible.
CLASS 3 (Maximum):
Covers recommended spare parts for a single unit where maximum protection
from major shutdown must be afforded. Suggested for Domestic Export Service
or Domestic Service where minimum loss of service is essential.
The Ruhrpumpen Inc. Sales Representative in your area will gladly review the class of spares best suited to
your requirements.
WARNING
THE USE OF PARTS OTHER THAN RUHRPUMPEN APPROVED PARTS MAY CREATE
HAZARDOUS CONDITIONS OVER WHICH RUHRPUMPEN, INC. HAS NO CONTROL. SUCH
HAZARDOUS CONDITIONS CAN LEAD TO INJURY, OR RESULT IN DAMAGE TO THE
EQUIPMENT. RUHRPUMPEN INC. DOES NOT SUPPORT NOR WILL BE RESPONSIBLE FOR
THE USE OF NON RUHRPUMPEN INC. FURNISHED PARTS NOR THE USE OF MATERIALS
WHICH ARE NOT AS ORIGINALLY FURNISHED WITHOUT THE EXPRESSED WRITTEN
APPROVAL OF RUHRPUMPEN INC.