Beruflich Dokumente
Kultur Dokumente
Project Specification
SECTION 22 14 00
FACILITY STORM DRAINAGE
PART 1:
1.01
A.
GENERAL
SECTION INCLUDES
Storm water drainage systems including, but not limited to the following:
1. Piped storm water drainage network.
2. Catch basins.
3. Manholes.
4. Concrete channels.
1.02
RELATED SECTIONS
A.
Section 03 30 00
B.
Section 22 05 00
C.
Section 22 05 13
D.
Section 31 23 16
Excavation.
E.
Section 31 23 16.13
Trenching.
F.
Section 33 05 13
G.
Section 33 32 16
H.
Section 33 46 00
Subdrainage.
1.03
REFERENCES
A.
ANSI A 40
B.
ASTM C 14
C.
ASTM C 76 M
D.
ASTM C 443
Joints for Circular Sewer and Culvert Pipe Using Rubber Gaskets.
E.
ASTM C 478
F.
ASTM C 497
G.
ASTM C 518
H.
ASTM C 913
SECTION 22 14 00 - 1
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
I.
ASTM C 923
J.
ASTM D 698
K.
ASTM D 1557
L.
ASTM D 1785
M.
ASTM D 2321
N.
ASTM D 2729
O.
ASTM D 2751
P.
ASTM D 3033
Q.
ASTM D 3034
R.
ASTM D 3017
Test Methods for Moisture Content of Soil and Soil and Soil
Aggregate Mixtures.
S.
SASO 14
T.
SASO 15
U.
1.04
A.
1.05
A.
1.06
SUBMITTALS
Comply with Section 01 33 00.
OPERATION AND MAINTENANCE DATA
Comply with the requirements of Sections 01 78 23 and 22 05 00.
DELIVERY, STORAGE AND HANDLING
A.
B.
Inspect all products at time of delivery for damage and for compliance with specifications.
C.
Repair or remove immediately from the site and replace any products that are found to be
damaged or not in accordance with the Specification. For repair, obtain the Engineers
approval before the proposed action.
D.
Handle and store all products as recommended by the manufacturer to prevent damage and
deterioration.
SECTION 22 14 00 - 2
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
E.
Supply handling equipment such as lifting beams, reinforced canvas slings, protective padding,
struts, cradles, etc., required to handle products without damaging hardware or linings and
coatings.
F.
Store each pipe unit, stack and handle into the final location in such manner, and by such
means, that afford its total protection from damage. The manufacturer's recommendations shall
be taken as the minimum requirement.
G.
Protect the products against damage and ambient conditions both during transport, site storage
and immediately up to the time the products are installed. Protect products from mechanical
damage and the effects of sunlight and heat, until backfilling operations have been completed.
H.
Consider all safety aspects when locating, planning and constructing pipe stacking areas, and
whilst stacking pipes.
PART 2:
2.01
PRODUCTS
ACCEPTABLE MANUFACTURERS
Not Used.
2.02
MANHOLES
A.
B.
Unless otherwise agreed by the Engineer, construct manholes after laying pipes, except that
manhole bases may be constructed earlier to avoid deterioration of the formation.
C.
Sizes of manholes shall be related to the depth of the inlet below ground level and the number
of branch connections. Refer to schedule of external Storm Water manholes. The minimum
size of manholes governed by the number of branch connections shall be 300 mm per branch of
100 mm diameter and 400 mm per branch of 150 mm diameter, with adequate allowances for
the angle of entry.
D.
Protect exterior surfaces of all manholes in accordance with the provisions of Section 03 30 00.
E.
Construct in-situ concrete manholes in accordance with Section 03 30 00. Finish of interior
faces shall be fair-faced and exterior faces cast against formwork:
1. Cast concrete bases on a firm formation. A preliminary blinding layer of concrete 70 mm
thick shall be placed, prior to the construction of bases.
2. Construct manholes with Class C 35 S reinforced concrete as detailed on the Drawings.
F.
2.03
A.
Construct pre-cast concrete manholes of pre-cast concrete rings conforming to ASTM C 478.
Pipe entries into pre-cast concrete rings shall be pre-formed or core drilled to suit.
MANHOLE COVERS AND FRAMES
Covers and frames shall be the type, size and weight as shown on the Drawings, and as
specified in Section 33 05 13. Frames set in 1:3 cement mortar and to the levels shown on the
Drawings but with minor adjustment to suit actual finished levels. Level differences shall be
SECTION 22 14 00 - 3
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
made up by pre-cast concrete raising pieces between the frame and the top of the manhole or
shaft.
B.
The words "STORMWATER" in Arabic and English shall be cast on the covers.
C.
For each type of cover installed, supply five sets of lifting keys.
2.04
A.
2.05
A.
2.06
A.
2.07
A.
2.08
A.
PART 3:
3.01
EXECUTION
GENERAL
A.
Install products comprising the Storm Water system in accordance with the approved method
statement, manufacturer's instructions and recommendations, appropriate standards or as
directed by the Engineer.
B.
Excavation for trenches, bedding for pipework, and compaction of backfill shall be in
accordance with Section 31 23 16.13.
C.
Where a pipelines passes into or out of a structure and where settlement is likely to occur, two
flexible joints shall be formed. The first joint shall be as close as practicable to the structure
and the second at the further end of the first pipe. This first pipe length shall not be more than
600 mm for pipes up to and including 150 mm diameter and not more than 900 mm for larger
SECTION 22 14 00 - 4
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
Project Specification
diameters up to 500 mm. Provisions for pipes larger than 500 mm diameter shall be as shown
on the Drawings.
D.
Where significant settlement is likely to occur, the Engineer may require more than two
flexible joints at each location.
E.
When a pipeline passes through a wall or other structure less than one pipe length wide, the
above requirement shall not apply and a sleeve shall be formed through the structure so that
there is a clear space of at least 75 mm wide all round the pipe. Adequate means shall be
provided to prevent soil from entering this gap.
3.02
INSPECTION
A.
B.
Immediately prior to installation, inspect products for damage. Products that are found to be
damaged or not in accordance with their respective standards and specifications shall not be
incorporated in the permanent works, and shall be removed from site. Any remedial measures
shall have the prior approval of the Engineer before being carried out.
3.03
A.
3.04
A.
Excavation and backfilling shall be carried out in accordance with Section 31 23 16.
B.
C.
Channels through manholes shall be properly benched at the bottom of manholes and chambers
as shown on the Drawings.
D.
The pre-cast manufacturer shall cast all step irons for pre-cast concrete manholes integrally into
the pre-cast manhole sections.
E.
Where main the drain size increases at a manhole, the main channel shall be constructed to the
larger pipe size. Pipe size change shall be effected using an eccentric reducer upstream of the
manhole with pipe soffits level.
F.
Unless stated otherwise on the Drawings or in the manhole schedule, all branch connections
shall discharge over the main channel at half channel height and shall be swept in the direction
of flow.
G.
Branch connections direct to main drain lines which are not through a manhole or inspection
chamber shall be soffit to soffit connections.
3.05
A.
B.
PIPEWORK
Excavation and backfilling be carried out in accordance with Section 31 23 16.13.
Install pipework in accordance with Section 33 05 00. Anchor and thrust blocks shall be
provided as specified therein.
SECTION 22 14 00 - 5
MINISTRY OF HOUSING
Western Sector Projects
Sitework & Infrastructure
OMRANIA and ASSOCIATES
C.
3.06
A.
3.07
A.
3.08
Project Specification
Marker tape shall be installed in trenches at a minimum height of 300 mm above all buried
drains, pipelines and building connections during backfilling.
PUMP STATIONS
Install pump stations in accordance with Section 33 32 16.
CONNECTION TO SEWERS
Make all necessary arrangements to connect new pipework to existing sewers to the
satisfaction of the authority having jurisdiction, including the payment of all connection and
supervision charges.
TESTING
A.
B.
3.09
A.
B.
Before handing over any pipeline, pass through a rubber disc plunger or swab and in the case of
jointed pipelines, simultaneously flush the line with clean water. Both ends shall then be closed
by temporary plugs or bulkheads to prevent entry of dirt or foreign matter.
END OF SECTION
SECTION 22 14 00 - 6