Beruflich Dokumente
Kultur Dokumente
In this practical, you will use Microsoft Project to complete a Gantt chart by:
1.
2.
3.
4.
Remember to save the project file as you will continue with it in the next practical.
Before we look at the project scenario, lets do a small exercise to warm up first. We will use
Microsoft Project to do a simple WBS for the Requirement Gathering Activity that you have
discussed during the practical last week. A sample WBS may be:
1. Requirement Gathering Activity
o Understand requirement overview
o Draft questions to ask during interview
o Arrange a meeting with users
o Conduct interview with users
o Document detailed requirements
o Review requirements with users
o Correct and finalize requirements
Estimated duration
1d
1d
0.5d
1d
2d
0.5d
1d
IT2116/SWENG
Now you may proceed to the next exercise for more complicated scenario.
Project Scenario: There are 3 phases involved in this project and they are defined as follow:
Phase 1 Design
Task 1 Gather information
Task 2 Analysis
Task 3 Prepare/Present options
Task 4 Design/document
Milestone Design complete
5d
10d
6d
15d
0d
Phase 2 Develop
Task 1 Develop prototype
Task 2 Testing/QA
Task 3 Develop final product
Task 4 Final testing/QA
Milestone Development complete
20d
5d
15d
10d
0d
Phase 3 Implement
Task 1 Install
5d
Task 2 Test
5d
Task 3 Train user
10d
Task 4 Onsite support
20d
Milestone Implementation complete 0d
Instruction 1: Create a new project in Microsoft Project and enter these tasks accordingly.
Next, we look at the dependency scenario among the tasks. There are 3 basic scenarios:
Sequential
Concurrent and
Overlapping
The following Network diagram and Gantt chart shows the representation of the above 3
dependency scenario.
a. Sequential tasks
b. Concurrent tasks
IT2116/SWENG
c. Overlapping tasks
To specify FS-50%,
Select Task 2
Select Information
Select Predecssors
Select Finish-to-Start at
the Type column
Specify -50% at the Lag
column
Click Ok
IT2116/SWENG
Instruction 2: Now you may construct the Gantt chart by identifying the dependencies
(sequential, concurrent or overlapping) of the tasks given above.
If you have interpreted the dependencies correctly, your final Gantt chart should look like this
(except that the dates should be current dates):
Instruction 3: View the critical path. (Select Gantt Chart -> Tracking Gantt. It should look
something like this).
Instruction 4: Identify the slack time in the schedule and give the details below.
Task Description
IT2116/SWENG
Remember to save your project file and we will continue in the next practical.
Review Questions:
1. A project is carried out and slack time is consumed on individual tasks, the slack left
over for the remaining tasks is:
a. Insignificant
b. Reduced
c. Unchanged
d. Increased
2. The critical path in a schedule is the path that:
a. Takes the longest time to complete
b. Must be done before any other tasks
c. Allows some flexibility in delaying a task
d. Is not affected by schedule slippage
3. Which of the following involves subdividing the major project milestones into smaller
and more manageable components?
a. Define scope
b. Create WBS
c. Allocate enough resources
d. Accurate estimate
4. Identify the critical path of the following Gantt chart.
IT2116/SWENG