Beruflich Dokumente
Kultur Dokumente
SAP AG
SAP AG
TAMM10 4.0B
34-1
SAP AG
SAP AG
TAMM10 4.0B
34-2
SAP AG
SAP AG
TAMM10 4.0B
34-3
Stock
Reorder point
Safety stock
Reorder point
Point of Delivery
Replenishment
lead time
Time
SAP AG
The basis of the reorder point planning is the comparison of the available warehouse stock and the fixed
receipts with the reorder point. If the available warehouse stock is less than the reorder point, then the
net requirements calculation is triggered.
The reorder point is composed of the expected average material requirements during the replenishment
lead time and the safety stock. Correspondingly, the following points must be considered when defining
the reorder point:
Safety stock,
Previous consumption or future requirements,
Replenishment lead time.
The safety stock must cover both the unplanned excess material consumption during the replenishment
lead time as well as the additional consumption caused by delayed deliveries.
If you want to take into account sales orders and manual reservations when planning, you can use
another reorder point procedure designed for external requirements.
SAP AG
TAMM10 4.0B
34-4
Reorder point
Purchase orders
Firmed planned orders
Firmed purchase
requisitions
Comparison
Stock
R
SAP AG
In reorder point planning, the available warehouse stock comes from the following calculation:
warehouse stock + open purchase order quantity (Purchase orders, firmed planned orders, firmed
purchase requisitions).
There will be a material shortage if the available warehouse stock is less than the reorder point.
The shortage quantity is the difference between the reorder point and the available warehouse stock. The
purchase order quantity is created from the lot-sizing procedure in the material master record.
The system sets the planning date as the basis for the requirements date.
SAP AG
TAMM10 4.0B
34-5
Processing time
for purchasing
Goods receipt
processing time
Delivery date
MRP date
SAP AG
The shortage quantity date for materials planned using reorder points is the date of the planning run. If
stock falls short of the reorder point, the procurement must be carried out immediately. The system
defines in scheduling, the date on which the material will be available, from the shortage quantity date.
This procedure is defined as forward scheduling.
In forward scheduling, first of all the purchasing department processing time in work days is added and
then the planned delivery time in calendar days and finally the goods receipt processing time in work
days to the present date. The result of the calculation is the MRP date.
The purchasing department processing time is the time available to the buyer to convert a purchase
requisition into a purchase order; it is defined specifically for a plant in Customizing.
The goods receipt processing time is the period of time between the receipt of a material and the addition
to stock. This time is, for example, required for checking the material and for the process of placement
into storage.
The planned delivery time and the goods receipt processing time are material-specific definitions.
SAP AG
TAMM10 4.0B
34-6
SAP AG
SAP AG
TAMM10 4.0B
34-7