Doc No: HT/COPI/0002

JOB SAFETY ANALYSIS

DATE ISSUED:
LAST REVIEWED DATE:

Job Description: Cable Disconnect & Termination

REVIEWED BY:

Area/Unit: Main Deck Area, Control Room and Switchgear room

SIGNATURE OF SUPERVISOR.

Tag No/Equipment Description: SCU , SPCU , UPS , PHPU and TUTU etc

Page: 1 OF3.

References:
PPE Required doing this Job: STANDARD PPE AND SAFETY HARNESSES AS REQUIRED.

IF YOU DONT MEET THE REQUIREMENTS AS STATED IN THIS PROCEDURE DO NOT PROCEED WITH PERFORMING THE JOB

Machine/Equipment/Tool
involved in each step

JOB STEP

Planning & permit

Personnel

Potential Hazard/Loss

Risk
Level
before
Mitigate
(H,M,L)

Control Statement

Untrained personnel
New personnel
Asset Damage
Non Certification of people
Permits not in place
Incorrect information
Weather conditions

Preparation material and


tools.

Materials
[Cable]

Safety harness in poor or


damaged condition

Safety harness

Tools damaged or broken

Hand tools

Work vest

Risk
Level
after
Mitigate

Ensure personnel undergo


appropriate HSE Training and PTW
training prior to mobilization.
Qualified & certified personnel for
all tasks.
Supervisor to attend daily PTW / tool
box meetings.
Obtain FM/OIM Approval for
critical procedures
Raise PTW, JSAs, & any related
documents-:check lists
Ensure all tools and material safe for
use.

Correct PPE to be used

Wrong tool for job

Ensure that scaffolding safe

Manual handling

Unsafe scaffold materials

Use safety harness with double


lanyard. Retractor reels can be used if
required.

Check all your equipment for


damage

Ensure all tools and material safe for


use

Work vest in poor or damaged


condition

M
M

Cable Pulling
Cable dressing
Working over the side.
Working at height
Replaced MCT

Cable glanding
Cable termination
Cable insulation resistance
check
Cable continuity test
Working at height

Manual labor
Hand tools
Safety harness

Manual labor
Hand tools
Megger
Continuity tester
Safety harness

Falling from height

Unauthorized Access to Site

Barricade area as required put up


signage

Sprains & strains, pinch points

Beware of loose objects or tools


falling use restraints if at all possible

Damage to plant

Poor access/ egress

Working in live plant

Be aware of working around live


equipment watch small Stainless
Steel tubing

Falling objects

Have good access/ egress

No scaffold tag

Use scaffold tags

Man overboard.

All personnel over the side to wear


Work Vest.

Ships master informed and location


workboats informed in case rescue
required.

M
M

Standby person on watch at all times.

Electrical shock

Falling from height

Barricade area as required put up


signage

Unauthorized Access to Site

Beware of loose objects or tools


falling use restraints if at all possible

Sprains & strains, pinch points

Have good access/ egress

Damage to plant

Use scaffold tags

Poor access/ egress

Working in live plant

All personnel over the side to wear


Work Vest.

Falling objects

Standby person on watch at all times.

No scaffold tag

L
L

L
L

House keeping area

Manual labour
Chain block
Scaffold trolley

Tripping hazards

Waste materials laying around

Transfer material using correct lifting


techniques

Clips left at height on ledges

help one another

Tools left at height on ledges

Clean & tidy area

Good housekeeping and clear path to


& from work site.

Check around site for tools &


equipment left sitting on ledges

Follow waste management procedures

L
L

WORK LEADER AND WORK TEAM TO CONFIRM PJSM, JSA REVIEW HAS BEEN HELD, DISCUSSED AND UNDERSTOOD

Work Team Member

Form No. COPI-HS-FR-00016


Rev. 2
Issue Sept. 200

Signature (1)

Start Date

Work Permit Duration max 8 periods