Sie sind auf Seite 1von 6

1.

GENERAL DESCRIPTION
The method basically consists of insulating the required surface of Dished Ends
and converting the same into its own self-contained furnace. high velocity oil
burners with angled
K type Chromel / Alumel thermocouples are attached on the Clean outdoor to record
the temperature continuously. Control and temperature monitoring is achieved using
these thermocouples connected to recording instruments.
The temperature distribution obtained by this method of heat treatment is within
standard codes, E.g. ASME VIII, DIV 1.
The client is presented with a certified temperature chart of the heat treatment,
together with a sketch showing the location of thermocouples.

2. SCOPE OF WORK
Type of Job

Dished Ends

Size

Various size

Material of Construction

SA 516 Gr.-70

Quantity
Site Location

3. HEAT TREATMENT SPECIFICATION


Unrestricted Heating Rate Up to 400 C.
Heating rate of maximum above 400 C: - 170C/Hr .
Holding temperature 610C + 15C.
Soaking Time : 60 Minutes/inch (50min. minimum)
Cooling rate of maximum upto 400 C:- 217C/Hr .
Unrestricted cooling rate from 400 C (in Still Air)

4. HEATING SYSTEM
The heat treatment operation will be affected by the introduction of 02 no. high
velocity Oil burner units from both sides. The burner will be designed to release
maximum thermal release as follows.

Each burner rating.


Thermal release 1.5 x 10 6 kcal / hr b) Combustion air flow 3559 corm /
hour
The burner are designed to give a maximum flame length of approximately
300 mm and consequently only hot combusted gases will effect heat transfer to
the component .The turn down ratio will be extremely high in order to 30 : 1
and this feature gives complete and accurate control. No hot spots and
produced maximum uniformity are achieved. The hot gases which are emitted
from the burner at high velocity (150 m / sec) will produce effective heat
transfer to the component and promote a high degree of temperature
uniformity. The combustion products are accurately controlled at all times and
minimum oxidation of the surface occurs. Complete combustion of the fuel
shall be ensured.
a)

Coupled to each burner via flexible hose is a combustion air fan which can be
accurately controlled to deliver exact quantities of air to the burner.
The burner shall be fitted with angled / straight cones to give a uniform firing.
Hot gases will be exhausted through other suitable opening
The fuel supply from tank shall be routed to the combustion equipment and
sufficient supply shall be available for the whole temperature cycle.
On completion of insulation of the vessel, installation of combustion equipment, the
Senior Technicians would carry out the firing of the vessel and produce a temperature
record at the end of the stress as per specification. Two Senior Technicians would be
in constant observation during the heat treatment on a continuous basis until the job
has cooled down to below 300 oC.

5. THERMAL INSULATION
We propose to carry out the heat treatment by our Trolley type Bogie
furnace at our Chikhali Works. All different size jobs will be placed inside
the Trolley type Bogie furnace as per requirement.
The size of Trolley type Bogie furnace will be 7.5 Mtr. (Wide) X 4.25 Mtr.
(High) X 12.5 Mtr. (Long) to accommodate the largest job. The Trolley
type Bogie furnace will be designed to be top loading type and door will be
lifted up to facilitate loading and unloading of the jobs in the Trolley type
Bogie furnace.
The jobs will heat treated by utilising 02 Nos burners which will be
inserted form suitable opening in the Trolley type Bogie furnace side
panels. The burners will be located such a manner that the clear distance
between job and the flame shall be access of 1 Mtr to avoid heat spots and
localising heating of jobs.
The Trolley type Bogie furnace shall be insulated with high quality
Ceramic Fiber insulation material. Accordingly, please find enclosed our
most competitive detailed techno-commercial proposal for your
consideration. We request you to go through the above and in case of any
further clarification / information, please feel free to contact us.
6. SHOP ELECTRICAL SUPPLY
The various site electrical requirements are required are
a) 3 Phase 380 / 415 Volts 50 Hz, 60 Amps supply to be provided to
combustion air fans and oil pumping units, adjacent to the burners to be
individually switched at source.
1. Combustion air fans : 02 Nos.
2. Oil pumping unit : 02 Nos.
3. Compressor
: 02 Nos.
b) Stabilized single phase 220 V 50 Hz ,5 Amp supply to be provided to each
temperature recorder

7. SITE FUEL SUPPLY.


The combustion equipment is capable of running from oil (HSD). The oil will be
supplied from tank to the combustion equipments, with flexible safety hoses.

8. TEMPERATURE MEASUREMENT
TEMPERATURE RECORDING:

Temperature recorders shall be of the potentiometer self-compensating type,


calibrated in degrees cellists with respect to a nickel-chromium / nickelaluminum thermocouple, type K.
Temperature recorders shall be calibrated at intervals not exceeding 6 months.
If the calibration checks yield information that the temperature recorder is not
within the manufacturers specified tolerances (i.e.+0.25%.of scale deflection),
recalibration will be performed. The calibrations shall be recorded and
evidence to this affect kept with the instrument. The calibration certificate must
show both the conditions of the instrument. Instruments utilized for calibration
purposes shall certification traceable to a national standard and shall
themselves be calibrated at intervals not to exceed 12 months.
In the event that the calibration check reveals that the instrument has been used
with an error which would have led to the measured being outside the
permitted tolerances, as specified in the heat treatment procedure, then full
details of the welds involved shall be reported to the inspecting authority.
The chart speed shall be set at 25 - 30 mm / hr. and shall be checked during
calibration. On artificial restriction on pen travel shall be used.
A clear print out of data shall be demonstrated before commencement of a heat
treatment.

09. TEST PROCEDURE / HEAT TREATMENT FIRING


CONTROL
A.

fuel supply :
All fuel supply hoses are to be checked for leaks by pressurizing the hoses and
testing of joints at oil tank, pump, filter, regulator, valves & at injector.
Pressure regulators are to be checked for correct supply pressure settings.

B.

Combustion Air Fans :


After Checking that the voltage and frequency on the motor data plate comply
with the supply available, the fan is to be started and checked for correct
direction of rotation.

C.

Burners :
The burners should be test fired before commencing the heat treatment
wherever possible. This should be done by removing the burner from its firing
position and test firing it into the open air, provided it is safe to do so.
In the event of it being impossible to remove the burners for test firing, then
all fuel supply lines are to be purged before connection to the burner.
On no account are burners to be left in position and connected to the fuel
supply when not being fired.

D.

Temperature Measurement System :


All thermocouples / compensating cable circuits are to be checked for
continuity prior to the commencement of firing.
Immediately after the firing is started, all thermocouples are to be checked for
correct polarity.
As temperature control is complex, the burner and combustion fan are fired
and adjusted manually. Our Technicians will monitor the temperature
constantly. The actual firing process will be attended on a 24 - hour basis.

10. DOCUMENTATION
A Senior Supervisor will ensure the procedural requirements are fully complied with.
The supervisor will be responsible for completion of all documentation.
The documentation information will comprise of the following:
1.
Specification and chart receipt form.
2.
Heat treatment record sheet as applicable.
3.
Temperature chart with specification, thermocouple locations, etc.
4.
Recorder test Certificate
5.
Thermocouple wire conformance certificate
The heat treatment section of the Specification and Chart Receipt Form will be
completed by Superheat and endorsed accordingly by all parties. These would
confirm all parties agreement to the heat treatment specification.

12. SAFETY PROCEDURE


Superheat will ensure that:
1)
2)
3)
4)

All appropriate register and test certificates are up to date and valid as
required by statue
All plant provided for the contract is in good working order, properly
maintained, and suitable for the purpose of the intended works.
All personnel deployed on the contract are fully conversant with
Superheat safety rules and policies, and with any special notified
provisions for working at site.
All personnel are issued with appropriate safety wear and personnel
protection.

The Superheat Acting Safety Officer will be responsible for ensuring that:
The Superheat Acting Safety Officer shall be authorized to enact all necessary
disciplinary action in the event of any breach of Safety Rules by any Superheat
personnel at shop.

Das könnte Ihnen auch gefallen