Sie sind auf Seite 1von 21

Pearl GTL

Project
Shell Project No: HP-3000-QAT
Project Document Number: T- 4.250.930

Purchase Order Number:

2MH127

Tag/Item Number(s):

N/A

Unit(s):

ASU

PCWBS:

LINDE ENGINEERING

Contractor Project No:


Project Rev.: O

Page 2 of 19

5887

QATAR SHELL GTL PROJECT (PEARL)


C2 AIR SEPARATION UNITS CONSTRUCTION

10.12.2007

Issued for Company comments

BR

AU/MC

ZG

ICC

22.11.2007

Issued for Review

BR

AU/MC

ZG

IFR

20.11.2007

Issued for Internal Review

BR

AU/MC

ZG

IIR

Date

Description

GAMA
Rev.
No.

Project
Rev
No.

Prepared Checked Approved


By
By
By
ORIGINATOR

Status

Document Title:

PROCEDURE FOR CLEANLINESS


LINDE ENGINEERING AG
Document No.

Contractor

Gama Qatar Co. W. L. L.

LOC470
GAM

PRO

QAC

GTL

037

Org.
Code

Doc.
Type

Disc.
Code

Geogr.
Area

Seq.
No

Rev.
No

Project Document Number: T-4.250.930

Vendor Code

Rev No: O

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

TABLE OF CONTENTS
1.

PURPOSE _____________________________________________________________________6

2.

SCOPE________________________________________________________________________6

3.

HSSE _________________________________________________________________________6

4.

REFERENCES _________________________________________________________________6

5.

DEFINITIONS __________________________________________________________________6

6.

RESPONSIBILITY ______________________________________________________________7
6.1.

SITE MANAGER __________________________________________________________________7

6.2.

CONSTRUCTION MANAGER ______________________________________________________7

6.3.

EQUIPMENT MANAGER __________________________________________________________7

6.4.

SITE ENGINEER__________________________________________________________________7

6.5.

SITE SUPERVISOR/FOREMAN_____________________________________________________7

6.6.

QC ENGINEER ___________________________________________________________________8

6.7.

QC INSPECTOR __________________________________________________________________8

6.8.

HSSE MANAGER _________________________________________________________________8

6.9.

HSSE OFFICER ___________________________________________________________________8

Cleanliness of Non-Oxygen Service Piping Systems _____________________________8

7.

General _________________________________________________________________________________8
7.1.

Steam blowing _____________________________________________________________________8

7.2.

Air blowing _______________________________________________________________________9

7.3.

Flushing __________________________________________________________________________9

7.4.

Medium/Quality __________________________________________________________________10

8.

Cleaning of Gaseous Oxygen System __________________________________________10

9.

Cleanliness rEQUIREMENTS __________________________________________________11


9.1.

Pre-Cleaning _____________________________________________________________________12

9.2.

Post Erection (In-Situ) Cleaning _____________________________________________________13

10.

Inspection Methods _________________________________________________________13

10.1.

Direct inspection________________________________________________________________13

10.2.

Indirect inspection (for Cleanliness Class S2) ________________________________________13

10.3.

Target blowing _________________________________________________________________14

11.

Cleanliness Classes ________________________________________________________14

12.

Additional requirements ____________________________________________________17

12.1.

General _______________________________________________________________________17

12.2.

Preservation of Cleanliness _______________________________________________________17

T-4.250.930 REV-O

Page 4 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

12.3.

Pressure and Leak Testing _______________________________________________________17

12.4.

Marking_______________________________________________________________________17

13.

Documentation, Verification _________________________________________________17

14.

QUALITY ASSURANCE______________________________________________________18

15.

ATTACHMENTS ____________________________________________________________18

T-4.250.930 REV-O

Page 5 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

1. PURPOSE
The purpose of this Procedure defines internal cleanliness requirements, cleaning
methods, inspection for piping systems at C2 ASU Pearl GTL Project by Gama Qatar
located inside the Ras Laffan Industrial City in Qatar.

2. SCOPE
This procedure ensured that all cleaning activities on C2 ASU Pearl GTL project
will be carried out with adequate cleaning and testing methods to the degree required in
this Procedure

3. HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras
Laffan Industrial City and International standards, codes, LINDE ENGINEERING AG and
QSGTL and/or its PMC requirements and instructions.
In addition all employees and GAMA subcontractor employees on site will have through
LINDE ENGINEERING AG Site Safety Induction and GAMA Qatar Safety induction for site
safety, health, environmental and security prior to work activities. Other training courses will
be attended as required by LINDE ENGINEERING AG or QSGTL and/or its PMC as
required.

4. REFERENCES

T-4.234.542

GAM-PRO-QAC-GTL-012: HSSE Plan

T-13.377.360

: Flawless start-up Initiative (FSI)

T-4.096.688

: Cleanliness Procedure Piping systems

T-13.371.359

Specification for Gaseous oxygen service

70.10.80.11

Cleaning of Equipment

: Project Quality Plan

5. DEFINITIONS
Company

: QSGTL/or its PMC

Contractor

: LINDE ENGINEERING AG

Sub Contractor

: GAMA QATAR

T-4.250.930 REV-O

Page 6 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

Contract

: QSGTL Pearl Plant - C2 ASU Project

CS

: Construction Supervisor

ITP

: Inspection and Test Plan

QCR

: Quality Control Record

QCP

: Quality Control Procedure

QCE

: Quality Control Engineer

QCI

: Quality Control Inspector

QA/QC

: Quality Assurance / Quality Control

TPI

: Third Party Inspection

6. RESPONSIBILITY
6.1.

SITE MANAGER

The site manager will provide inputs to the project execution plan to ensure that lifting
strategies & philosophy are addressed.

6.2.

CONSTRUCTION MANAGER

The construction manager is responsible for the overall management of the project
construction team to ensure that safe and effective operations are conducted and
properly documented.

6.3.

EQUIPMENT MANAGER

The equipment manager will be responsible for the transporting equipments availability
and good order.

6.4.

SITE ENGINEER

Shall report to Construction Manager


Shall be responsible for planning, execution and implementation of all site activities
related to this procedure

6.5.

SITE SUPERVISOR/FOREMAN
Shall report to Site Engineer

T-4.250.930 REV-O

Page 7 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

Shall be responsible for execution of construction activity


Shall also prepare daily site construction records

6.6.

QC ENGINEER

Shall report to Manager (QA/QC) and shall be responsible for overall implementation,
monitoring and control of QC activities.

6.7.

QC INSPECTOR
Shall report to QC Engineer
Shall be responsible for attending all Inspection Stages as required by ITP
Shall be responsible of performing all checks and shall prepare necessary
Inspection Reports

6.8.

HSSE MANAGER
Shall report to Project Manager and shall be responsible for over all control and
Inspection of HSSE issues.

6.9.

HSSE OFFICER
Shall report to HSSE Manager
Shall be responsible for all safety aspects for this procedure

7. CLEANLINESS OF NON-OXYGEN SERVICE PIPING SYSTEMS


GENERAL
This Procedure applies to piping systems where the oxygen content of the medium
is less than 25% Volume. For cleanliness of oxygen systems (oxygen content
larger than 25% Volume) refer section 8.0 as per cleaning procedure T-4.096.688

7.1.

STEAM BLOWING
The purpose of steam blowing is to remove debris, loose scale and rust from
recently welded steam lines applicable only for steam turbine operation. The
effectiveness depends on the steam velocity, the change of temperature in time
and the number of blows.
Line cleaning should not commence until all related piping and process equipment
are fully installed, the system has been checked for conformance with the piping
and instrumentation diagrams, and the piping systems have been hydro tested.
Temporary piping and silencers for depressurizing to atmosphere shall be properly
anchored. All restrictions in the piping such as orifice plates, flow measurement
tubes and thermo wells shall be removed prior to steam blowing, openings to be
blinded.
Control valves shall be replaced with spool pieces. Steam should be blown from a
clean system to unclean systems. In order to thermally shock the piping to remove

T-4.250.930 REV-O

Page 8 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

mill scale, the steam valve controlling the blow down should be of the quarter turn
type (quick opening).
The valve should be located well upstream of the piping to be cleaned. At the inlet
flange of the silencer, a target strip of polished copper or aluminum shall be
clamped to judge the finished cleanliness.
Blows should first be made at low pressures to remove large objects in the piping,
gradually raising the pressure during later blows to the maximum operating
pressure. Between the blows there should be a cool down period of at least 60
minutes for UN insulated pipes and 240 minutes for insulated pipes.
A system is considered to be acceptably clean when the target plate has less than
a predetermined number of impact pock marks. The following requirements apply
for blowing steam lines:
Steam flow during blowing shall be at least three times the maximum flow rate
during operation;
There shall be not more than one total particle count (pock mark) per square
centimeter of target plate surface if not otherwise specified by manufacturer
There shall be no evidence of embedded material (e.g. weld splatter, sand, etc.).
Target plates shall not show individual rough impressions
The blow shall be of not less than 10 minutes duration, At least 15 blows shall be
made if the piping is not to be put immediately into service; the system shall be
purged with nitrogen to remove any air and should be placed under an inert nitrogen
blanket.

7.2.

AIR BLOWING
The purpose of Air blowing is to remove debris and loose scale. Air is usually
supplied from temporary high-pressure large-capacity air compressors or air filled
vessels.
These rental air compressors have to be supplied with filters to remove oil and
moisture from the compressed air system.
An air reservoir may be available during the blow down process. The piping is then
cleaned by pressurizing the piping system to be agreed with Company and then
opening a temporary quick acting valve to allow depressurization to atmosphere.

7.3.

FLUSHING
The purpose of the activity, flushing, is to remove loose rust, mill scale and
construction debris from piping systems before Erection.
Flushing can be defined as the act of running water, in sufficient quantity and
velocity, through a given section of pipe or piping, completely filling that section of

T-4.250.930 REV-O

Page 9 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

pipe or piping, such that the flow of water through the system will forcibly remove any
loose rust, mill scale or construction debris from the system.
There are some basic guidelines which should always be followed when flushing
lines with water:
Flushing shall be carried-out under the supervision of the Gama Piping
Superintend.
Gama/Linde Piping Inspector inspect the cleaned system and sign the Report.
Flushing shall be performed through fully open flanges and/or open pipe ends.
Flushing through smaller openings, such as drains or vents, is not acceptable
Flush from the highest elevation to the lowest, where possible following the
Normal flow Direction of the system.
When flushing is completed, de-water the system and dry as soon as possible.

7.4.

MEDIUM/QUALITY
Stainless steel lines:
Potable/demineralized water, with chloride content < 20 ppm.
Carbon steel and alloy lines:
Potable water/plant water or any other prior approved flushing medium.
The flushing duration for an "open ended" system is such that for a period of > 5
minutes "clear water" (no debris or other foreign materials) must be discharged.
Closed circuit loop flushing until the circulating pump strainer is free of foreign
materials (debris) and the circulating water is clear. The following systems
and/or lines shall not be flushed.
Process lines in which the presence of water would cause operational difficulties.
Instrument air lines: these lines will be service tested and blown with air. The air
used must be free from oil, use existing instrument air supplies where possible or
mobile compressors fitted with oil filtering devices.
Nitrogen systems: these will be service tested after blowing with instrument air.
Steam supply systems: after hydro test the water shall be drained and the system
Blown with steam, when available.

8. CLEANING OF GASEOUS OXYGEN SYSTEM


Oxygen in the context of this section is a gas mixture with an oxygen content of
more than 25 percent by volume.
The importance of meticulous degreasing and careful cleaning cannot be overT-4.250.930 REV-O

Page 10 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

emphasized, as remnants of organic matter and minute solid particles in the


presence of high pressure and/or high velocity oxygen may ignite, with the possibility
of violent reaction.
Careful attention shall, therefore, be paid to the cleanliness of oxygen systems.
Removal of contaminants such as greases, oil, thread lubricants, dirt, water, filings,
weld splatter, paints, and other foreign matter is essential.
An acceptable level of cleanliness can be accomplished by pre-cleaning all parts and
maintaining this condition during construction; by completely cleaning the system
after construction; or, as is normally the case for a large plant facility, by a
combination of the two. Any cleaning procedure shall be such that the final surface
cleanliness, prior to system commissioning, will meet the inspection criteria given in
section 9 of this procedure

9. CLEANLINESS REQUIREMENTS
This section defines methods which are suited to obtain the cleanliness condition
prescribed for the single pipes or assembled piping system. Usually cleaning methods
are mechanical processes and chemical processes. it is a condition that the items to be
cleaned are either already machined or have, in the state as delivered, a smooth, noncorroded and un scaled surface without painting. Corroded or scaled surfaces shall be
prepared by pickling or grit blasting. This section defines methods which are suited to
obtain the cleanliness condition prescribed for the single pipes or assembled piping
system.
Table 1 Mechanical cleaning
Identification
Code

Method

M1

Sweeping or wiping with lint free cloth

M2

Air Blowing or flushing

M3

Vacuum cleaning

M4

Air burst cleaning

M5

Grit Blasting

T-4.250.930 REV-O

Page 11 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

Table 2 chemical cleaning


Identification
Code

9.1.

Method

C1

Submerging and moving of the component in a vessel


with cleaning agent

C2

Spraying of the component with cleaning agent and


running off of the agent

C3

Filling of the component with cleaning agent, moving of


component or liquid

C4

Flushing of the component under permanent circulation


of the cleaning agent

C5

Degreasing with condensing cleaning agent (in a


degreasing facility)

C6

High pressure steam degreasing (steam-cleaning with


addition of a cleaning agent)

PRE-CLEANING

All piping materials including, fittings, strainers etc, shall be pre-cleaned prior to final
assembly/site erection. In the majority of cases, this cleaning requirement is part of a
purchase order or shop fabrication.
For Vendor package systems the internal cleanliness of the system components shall
be preserved at least until they are installed in the plant on-site, by means of:
1) Hermetically sealed wrapping, containing desiccant bag, for small items
2) Firmly secured end-caps, plugs or gasketed blind flanges, as appropriate, to
seal all openings on non-hermetically packaged items
3) Desiccant (bags), but not vapor phase inhibitors, attached to the inside of
(temporary) end-caps and blank flanges
All pre-cleaned parts or final assemblies shall be lapelled / marked

T-4.250.930 REV-O

Page 12 of 19

Q A T A R
9.2.

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

POST ERECTION (IN-SITU) CLEANING

If the pre-cleaned condition has been maintained during construction and erection,
and there has been minimal site welding, in-situ cleaning can be limited to blowing the
pipe work out with high (near sonic) velocity, oil-free air, supplemented where
applicable with brush pigs. If the pre-cleaned condition has not been maintained
during construction and erection, pipe work shall be cleaned as specified in the
relevant cleanliness class s, see par.8.3. Any in-situ cleaning required shall be carried
out after any hydrostatic testing and by specialist contractors. A system that is
complete and has received final cleaning, but is not to be put into immediate service,
shall be preserved by pressurizing with clean, dry, oil-free nitrogen.

10. INSPECTION METHODS


10.1.

DIRECT INSPECTION

All surfaces shall be subjected to direct visual inspection where possible, by both
bright white light and ultra-violet light methods.
The inspected surface shall be dry and free from
cleaning agents
Adhered scale, weld spatter, loose particles or fibers
organic substances such as grease, oil, paint, sealants If direct inspection by ultraviolet light is not possible, surfaces shall be wiped with a clean, white, lint-free cloth
that may be dipped in solvent. The cloth shall then be inspected to ensure the
absence of any oil, residue, discoloration, fibers, etc.

10.2.

INDIRECT INSPECTION (FOR CLEANLINESS CLASS S2)

Parts which are inaccessible to visual examination, either directly or with a


boroscope or similar instrument, shall be inspected as per table 3- P3. Alternatively
the system may be inspected by having a solvent circulated through them. A
representative sample of the effluent solvent shall be taken and inspected as follows
The sample shall be inspected under bright white light and compared with a sample
of new, unused solvent. No difference shall be detectable and there shall be no
residue
The sample shall also be inspected under ultra-violet light (wavelength between
0.32 m and 0.38 m) and again compared with unused solvent. Contamination of
0.1 g oil/litre or more will cause fluorescence of the solvent
In doubtful cases, an analysis of the solvent used may be required. After
evaporation at 100 C, the sample shall not contain more than 20 mg/kg solvent
residue.
T-4.250.930 REV-O

Page 13 of 19

Q A T A R

10.3.

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

TARGET BLOWING

Position a white sheet covered with petroleum jelly, e.g., Vaseline, at the end of the
line, and blow line with oil-free nitrogen. Dirt picked up by the nitrogen stream will be
visible on the sheet.
Table 3 Inspection Methods
Identification
Method
code
P1
Visual examination at clear daylight, or under bright white light.
P2

Visual examination under ultraviolet light

P3

Wiping test by using a white, lint-free cloth or filter paper, aided by


ultraviolet light

P4
P5
P6

Solvent flushing test / weight determination of residue after


evaporation
Particle measurement / volume determination after vacuum cleaning
Particle measurement / visual inspection of an adhesive tape test of
the surface compared with an adhesive tape test of a reference
specimen

11. CLEANLINESS CLASSES


The cleanliness classes define the requirements for the surfaces of piping being in
contact with fluids. The cleanliness class shall be correlated to plant sections or to
plant equipment according to oxygen content and allowable working pressure and
function. The Cleanliness Classes are selected acc. Linde internal procedure and
are shown in the PEFS's-(Piping Engineering Flow Diagrams). The cleanliness
requirements are covered by four cleanliness classes S4 to S1 as defined hereafter:
S4, being the class with the lowest requirements and S1 the class with the highest
requirements. However, cleanliness class S1 is only applicable to equipment such
as columns, plate fin heat exchangers in services with oxygen content above 98%.
Each cleanliness class is correlated to its own requirements.

T-4.250.930 REV-O

Page 14 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

Cleanliness class S2
Fabrication
Sequence

Piping
parts
(pipes,
fittings,
flanges
etc.)
Prefabricat
ed piping
spools
Piping
spools prior
to
installation
Piping after
installation
(precommissio
ning)

DN
Limi
ts

Ferriti
c
Steels

Cleaning
Austenitic
Steels,
Aluminium

Ferritic
Steels

Inspection
Austenitic Steels,
Aluminium

>50

M5

C6 8)

P2

P2 and P3

`>25
and
50

N/A

M6 11)

N/A

P3 4)

Acceptance Criteria

oil/ grease <=


200mg/m 10)
Corrosion protection
/ Painting: not
allowed not visible
Liquids: solvent /
water drops not
visible

ALL
M2 9)

P2

M4

P1 4)

ALL

Cleanliness class S3
Fabrication
Sequence

Piping parts
(pipes, fittings,
flanges etc.)
Prefabricated
piping spools

DN
Limi
ts

>50

Piping after
installation
(precommissioning)
T-4.250.930 REV-O

Cleaning
Austenitic
Steels,
Aluminium

Ferritic
Steels

M5 or
M2 5)

Inspection
Austenitic Steels,
Aluminium

Acceptance
Criteria

P1

`
>25
and
50

Piping spools
prior to
installation

Ferrit
ic
Steel
s

M2
and
C6 6)

M2 and C6 6)
P1

P1

Free of mill
scale, paint,
dirt and
other debris

ALL
M1 3)

P1

M4 7) or M2

P1 4)

ALL

Page 15 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

Cleanliness class S4
Fabrication
Sequence

Piping parts
(pipes, fittings,
flanges etc.)
Prefabricated
piping spools

DN
Lim
its
>5
0

Piping after
installation
(precommissioning)

Cleaning
Austenitic
Steels,
Aluminium

Ferritic
Steels

M1 or
M2 5)
or M5
1) 2)

Inspection
Austenitic Steels,
Aluminium

Acceptance
Criteria

P1

`
>2
5
an
d
5
0

Piping spools
prior to
installation

Ferritic
Steels

AL
L
AL
L

M2
M1 or
M2 5)

P1

M1 3)

M2

P1

Free of mill
scale, paint,
dirt and
other debris

P1

P1 4)

Remarks to Cleanliness Classes S2 to S4


1) Only if necessary for removal of internal coating. Not applicable to water lines.
2) Steam lines shall be internal grit blasted and cleaned as specified in Para. 7.2
3) Ensure the lines are drained / empty before installation and free of dirt and debris.
4) Determination of cleanliness (acceptance criteria) by visual assessment of the
quality of blowing or flushing medium
5) Blowing of pipes with dry air during prefabrication only if applicable, to remove dust
or debris.
6) Only if presence of oil or grease is detected, i.e.: receiving inspection or during
fabrication
7) Apply only to process piping. Not applicable for water lines and utilities
8) Apply final blowing, preferably with hot nitrogen, to ensure dew point of -20 C.
9) Blowing of pipes with oil and moisture free air.
10) Oil content <200mg/m2 will be achieved, when UV-light inspection does not reveal
indications.
11) The "pig" shall consist of a white lint-free cloth wetted with a suitable agent (i.e.
acetone). The evaluation of cleaning result (colour of pulled "pig") shall be supported by
UV-Light in a darkened surrounding

T-4.250.930 REV-O

Page 16 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

12. ADDITIONAL REQUIREMENTS


12.1. GENERAL
Process air piping, from the Mol sieve Absorber vessels to the cold box, shall be
inspected by means of UV-light
Valves and other piping components such as strainers, have the same cleanliness
class than the connected piping.
Gama/Linde witnessed and recorded cleanliness inspections during the installation
of underground cooling water pipe.

12.2. PRESERVATION OF CLEANLINESS


The cleanliness of each delivered, mechanically finished and already cleaned item
shall be preserved during any storage, intermediate transport, pre-fabrication and final
installation until commissioning. New contamination of the inner surfaces shall be
avoided by suitable preservation measures, i.e. covering of pipe ends with plastic foil
properly fastened or closing the pipe ends with plastic caps.

12.3. PRESSURE AND LEAK TESTING


Pneumatic tests and leak tests shall be performed with dry, oil free air or dry, oil free
nitrogen. Clear potable uncontaminated water shall be used for hydrostatic tests or at
least for flushing after hydrostatic tests. Water residues shall be removed by
discharging, blowing out with air and, in case of corrosive metals, by drying.

12.4. MARKING
The packing of a cleaned component or plant equipment shall be marked punching or
by means of an undetectable, durable and well legible label or tag:
Furthermore, a note shall be attached for the receivers informing on vacuum packing
or inert gas filling or on susceptive bags to be removed (position and number of bags
to be stated!).

13. DOCUMENTATION, VERIFICATION


Cleaning and Inspection shall be recorded and signed by LINDE /PMC for all spool,
as per respective Isometric drawing.
The degrees of cleanness depend on service and piping class. The FSI (Flawless
startup initiative) should be followed in all categories.
T-4.250.930 REV-O

Page 17 of 19

Q A T A R

Doc. Title

GAM-PRO-QAC-GTL-037
PROCEDURE FOR CLEANLINESS

Date

10.12.07 Rev. C

14. QUALITY ASSURANCE


A Quality Assurance System shall be operated conforming to related standards.
Controls and checks shall be established and documented.

15. ATTACHMENTS

GAM-QCR-QAC-GTL-070

T-4.250.930 REV-O

Page 18 of 19

C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY

CLEANLINESS ACCEPTENCE REPORT

Q A T A R

Item Location
Area:

Isometric No:

Item Description:

sub system:

Form No:

sheet

Sub Contract Ref:

Cleanliness
class

Spool

Cleaning
Method

GAM-QCR-QAC-GTL-070

Inspection
method

Inspection Result

Pre Fabrication

Erection

Report No:
Inspection Date
GAMA QATAR
Signature

Date

LINDE
Signature

QSGTL or its PMC


Date

Signature

Date

Das könnte Ihnen auch gefallen