Project
LINDE ENGINEERING
Contractor Project No :
Project Rev.: A
2MH127
Tag/Item Number(s):
Unit(s):
PCWBS:
Page 2 of 65
5887
24.11.08
RT
UO/MK
AG
CCI
12.11.08
OK
UO/MK
AG
CCI
30.07.08
OK
UO
AG
CCI
10.04.08
RT
EE
ZG
ICC
17.03.08
RT
EE
ZG
IFR
21.02.08
RT
EE
ZG
IIR
Date
Description
GAMA
Rev.
No.
Project
Rev
No.
Status
Document Title:
LINDE ENGINEERING AG
Contractor
LOC470
Gama Qatar Co. W. L. L.
GAM
MTS
MEC
GTL
009
Org.
Code
Doc.
Type
Disc.
Code
Geogr.
Area
Seq.
No
Rev.
No
Vendor Code
Rev No: A
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
TableofContent
1
PURPOSE _____________________________________________________________________5
SCOPE________________________________________________________________________5
HSSE _________________________________________________________________________5
DEFINITIONS __________________________________________________________________6
REFERENCES _________________________________________________________________7
RESOURCES _________________________________________________________________20
6.1
Responsibilities ___________________________________________________________________ 20
Site Manager __________________________________________________________________________ 20
Mechanical Erection Manager ___________________________________________________________ 20
Site Engineer__________________________________________________________________________ 20
Site Supervisor (SS) ___________________________________________________________________ 20
Piping Supervisor (PS) _________________________________________________________________ 20
Artisans ______________________________________________________________________________ 20
QA/QC Officer / Inspector _______________________________________________________________ 21
6.1.1
6.1.2
6.1.3
6.1.4
6.1.5
6.1.6
6.1.7
6.2
6.2.1
6.2.2
General _________________________________________________________________________ 23
7.2
7.2.1
7.2.2
7.2.3
7.2.4
7.2.5
7.2.6
QUALITY ASSURANCE________________________________________________________42
ATTACHEMENTS _____________________________________________________________43
9.1
9.2
9.3
9.4
T-4.250.904 Rev. A
Page 4 of 65
Q A T A R
1
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
PURPOSE
This document describes the methods proposed to be used for the Erection Operations that
will be carried out as part of ASU Construction Works of Qatar Shell GTL Plant (Pearl) in Ras
Laffan Industrial City (RLIC) of Qatar including similar works in TSF Area.
SCOPE
This method statement identifies the general steps, arrangements and precautions for the
assembly and erection works of one ACC at the following site; FD at C2 area. Since the sites
are identical to FD; this method statement shall also apply to other sites as FA, FB, FC and
GA, GB, GC, GD at C2 area.
This method statement also defines piping erection of all SPX equipment at the site which is
developed for installation of steam condensed piping, extraction, cleaning systems and
instrumentation.
ACC consists of four streets with four modules per street with fan units and associated
equipment which will be erected on top of the steel structures.
The scope of the ACC starts from the turbine exhaust steam turbine outlet with the main
steam duct, which feeds to the Air Cooled Condenser (ACC). The latter is equipped with
drain pot that collects the condensate to the condensate tank which is located at module N of
street # 4.
The steel structure will be erected at site according to the ACC Construction Manual T4.121.350, by means of crane and/or certified lifting equipment utilizing equipment specified
in section 6.2, with competent personnel.
The works will also include the erection, installation and alignment of equipment above the
steel structure as follows: fan screen and stack, motor bridge with drive and blades/impellers,
condensate and steam manifolds, bundles (heat exchangers), associated steel structures,
pipe works for steam recovery, and other amenities for access and walkways necessary for
maintenance.
The sequence of construction by street will be 3,4,2 then 1 taking into consideration to
specific requirement on the erection of condensate tank, steam ejectors and associated
equipment which will be located with separate steel structure beneath the module N of street
4 (please refer to drawing T-4.149.204).
The sequence of activities will be applicable to other sites.
Scaffolding will be required during the duration of the works. Scaffolding shall be inspected
by HSE before work starts. Periodic scaffolding inspection will be required.
HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan
Industrial City and International standards/codes, and Company and Contractor requirements
and instructions.
All personnel will go through Gama, Linde and Company Safety Induction courses as well as
other trainings as identified by their supervisor. Please refer Document T-4.219.615 for
details.
A Job Safety Analysis (JSA) specific for this work including a Risk Assessment is prepared as
per Gama procedure T-4.219.606 and is attached herein. Such JSA addresses the hazards
T-4.250.904 Rev. A
Page 5 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
associated with each task within the scope of this Method Statement and introduces the
controls that will be implemented to reduce the associated risks to acceptable levels. The
JSA will be used by the Site Supervisor as the basis of his TSTI / TSTO and Toolbox Talks.
All personnel will have PPE required for their specific tasks in addition to the minimum PPE
(coveralls, safety goggles, safety shoes, high-visibility vests, gloves, double lanyard full body
harness) at site at all times as required.
In the event of a release, fire or explosion, employees will secure their area and evacuate to
the nearest muster point. Once all employees are evacuated the supervisor will conduct a
headcount to verify all employees are out of danger. The supervision will report this to
Contractor Emergency Contact numbers for Company, Contractor and Gama will be posted
onsite.
All vehicles and equipment used for the subject work will be inspected and certified as
required.
Drivers and operators will be competent and will have attended all required trainings set forth
in the project procedures and specifications.
DEFINITIONS
Company
Contractor
Subcontractor
Contract
QCP
ITP
QA/QC
HSSE
JSA
Street
SDM
CCM
SS
ACC
PTW
LP
RA
FSI
NDT
TSTI
TSTO
PPE
RLIC
SPX
T-4.250.904 Rev. A
Page 6 of 65
Q A T A R
5
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
REFERENCES
ASME B 31.3
ASME Sec II;
ASME SEC. IX
ASME SEC.V
DEP 34.28.00.31
DEP 70.10.70.11
DEP.30.8.60.18
DEP.31.38.01.11
DEP.31.38.01.31
T-13.377.360
Process Piping
Specification for Welding Rods, Electrodes & Filler Metals
Welding And Brazing Qualification
Non Destructive Examination
Technical Specification Steel Structures
Preservation Of Old And New Equipment And Piping Standing Idle
Welding Of Metal (Amendments/Supplements To Api Rp 582
Piping General Requirements
Shop & Field Fabrication Of Steel Piping Amendment T.13.376.796e
Flawless Start-Up Initiative (FSI)
T-13.377.438
T-13.377.441
T-4.095.303
T-4.095.723
T-4.116.905
T-4.116.909
T-4.116.910
T-4.116.970
T-4.121.193
T-4.121.194
T-4.121.212
T-4.121.213
T-4.121.214
T-4.121.215
T-4.121.226
T-4.121.227
T-4.121.228
T-4.121.230
T-4.121.231
T-4.121.232
T-4.121.233
T-4.121.234
T-4.121.235
T-4.121.236
T-4.121.237
T-4.121.238
T-4.121.239
T-4.121.240
T-4.121.241
T-4.121.244
T-4.121.245
T-4.121.246
T-4.250.904 Rev. A
Page 7 of 65
Q A T A R
T-4.121.257
T-4.121.261
T-4.121.262
T-4.121.264
T-4.121.265
T-4.121.266
T-4.121.270
T-4.121.271
T-4.121.272
T-4.121.273
T-4.121.274
T-4.121.275
T-4.121.276
T-4.121.277
T-4.121.278
T-4.121.281
T-4.121.282
T-4.121.284
T-4.121.287
T-4.121.298A
T-4.121.304
T-4.121.305
T-4.121.323
T-4.121.350
T-4.121.350
T-4.121.350
T-4.121.350
T-4.121.357
T-4.129.656
T-4.129.850
T-4.129.852
T-4.129.853
T-4.129.854
T-4.129.855
T-4.129.856
T-4.129.857
T-4.129.859
T-4.129.860
T-4.129.861
T-4.129.864
T-4.129.865
T-4.129.866
T-4.129.867
T-4.129.868
T-4.129.871
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 8 of 65
Q A T A R
T-4.129.872
T-4.131.762
T-4.131.763
T-4.133.661
T-4.133.662
T-4.133.665
T-4.133.666
T-4.133.667
T-4.133.970
T-4.149.204
T-4.149.213
T-4.149.274
T-4.149.277
T-4.149.295
T-4.184.595
T-4.184.826
T-4.186.019
T-4.193.137
T-4.193.139
T-4.193.298
T-4.193.303
T-4.193.304
T-4.193.320
T-4.193.323
T-4.193.324
T-4.193.325
T-4.193.326
T-4.198.504
T-4.198.505
T-4.198.506
T-4.198.509
T-4.198.510
T-4.200.135
T-4.200.144
T-4.200.145
T-4.200.146
T-4.200.152
T-4.200.159
T-4.200.160
T-4.200.163
T-4.200.164
T-4.200.165
T-4.200.166
T-4.200.167
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 9 of 65
Q A T A R
T-4.200.168
T-4.200.169
T-4.200.170
T-4.200.171
T-4.200.172
T-4.200.179
T-4.200.180
T-4.200.182
T-4.200.183
T-4.200.184
T-4.200.189
T-4.200.190
T-4.200.191
T-4.200.192
T-4.200.193
T-4.200.194
T-4.200.195
T-4.200.196
T-4.200.197
T-4.200.198
T-4.200.199
T-4.200.200
T-4.200.201
T-4.200.202
T-4.200.203
T-4.200.204
T-4.200.205
T-4.200.206
T-4.200.207
T-4.200.208
T-4.200.209
T-4.200.210
T-4.200.211
T-4.200.212
T-4.200.213
T-4.200.214
T-4.200.215
T-4.200.216
T-4.200.217
T-4.200.218
T-4.200.219
T-4.200.220
T-4.200.221
T-4.200.222
T-4.200.223
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 10 of 65
Q A T A R
T-4.200.224
T-4.200.225
T-4.200.226
T-4.207.344
T-4.207.345
T-4.207.346
T-4.207.347
T-4.207.348
T-4.207.349
T-4.207.350
T-4.207.351
T-4.207.352
T-4.207.353
T-4.207.354
T-4.207.355
T-4.207.356
T-4.207.357
T-4.207.358
T-4.207.359
T-4.207.360
T-4.207.361
T-4.207.362
T-4.207.363
T-4.207.364
T-4.207.365
T-4.207.366
T-4.207.367
T-4.207.368
T-4.207.369
T-4.207.370
T-4.207.371
T-4.207.372
T-4.207.373
T-4.207.374
T-4.207.375
T-4.207.376
T-4.207.377
T-4.207.378
T-4.207.379
T-4.207.380
T-4.207.381
T-4.207.382
T-4.207.383
T-4.207.384
T-4.207.385
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 11 of 65
Q A T A R
T-4.207.386
T-4.207.387
T-4.207.388
T-4.207.389
T-4.207.390
T-4.207.391
T-4.207.392
T-4.207.393
T-4.207.394
T-4.207.395
T-4.207.396
T-4.207.397
T-4.207.398
T-4.207.399
T-4.207.400
T-4.207.401
T-4.207.402
T-4.207.403
T-4.207.404
T-4.207.405
T-4.207.405
T-4.207.406
T-4.207.407
T-4.207.408
T-4.207.409
T-4.207.410
T-4.207.411
T-4.207.416
T-4.207.423
T-4.207.432
T-4.207.446
T-4.207.447
T-4.207.448
T-4.207.466
T-4.207.483
T-4.207.484
T-4.207.485
T-4.207.485
T-4.207.486
T-4.207.487
T-4.207.488
T-4.207.500
T-4.207.888
T-4.207.890
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 12 of 65
Q A T A R
T-4.207.891
T-4.207.892
T-4.209.301
T-4.209.302
T-4.209.303
T-4.209.304
T-4.209.305
T-4.209.306
T-4.209.307
T-4.209.308
T-4.209.309
T-4.209.310
T-4.209.311
T-4.209.312
T-4.209.313
T-4.209.314
T-4.209.315
T-4.209.316
T-4.209.317
T-4.209.318
T-4.209.319
T-4.209.320
T-4.209.321
T-4.209.322
T-4.209.323
T-4.209.324
T-4.209.325
T-4.209.326
T-4.209.327
T-4.209.328
T-4.209.329
T-4.209.330
T-4.209.331
T-4.209.332
T-4.209.333
T-4.209.334
T-4.209.335
T-4.209.336
T-4.209.337
T-4.209.338
T-4.209.339
T-4.209.340
T-4.209.341
T-4.209.342
T-4.209.343
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 13 of 65
Q A T A R
T-4.209.344
T-4.209.345
T-4.209.346
T-4.209.347
T-4.209.348
T-4.209.349
T-4.209.350
T-4.209.351
T-4.209.352
T-4.209.353
T-4.209.354
T-4.209.355
T-4.209.356
T-4.209.357
T-4.209.358
T-4.209.359
T-4.209.360
T-4.209.361
T-4.209.362
T-4.209.363
T-4.209.364
T-4.209.365
T-4.209.366
T-4.219.314
T-4.219.455
T-4.219.606
T-4.219.615
T-4.219.660
T-4.219.688
T-4.219.691
T-4.219.793
T-4.219.946
T-4.219.947
T-4.219.948
T-4.219.949
T-4.219.950
T-4.226.179
T-4.233.692
T-4.233.731
T-4.234.058
T-4.234.059
T-4.234.060
T-4.234.061
T-4.234.062
T-4.234.063
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 14 of 65
Q A T A R
T-4.234.067
T-4.234.080
T-4.234.084
T-4.234.104
T-4.234.105
T-4.234.106
T-4.234.107
T-4.234.108
T-4.234.109
T-4.234.110
T-4.234.111
T-4.234.112
T-4.234.113
T-4.234.114
T-4.234.115
T-4.234.116
T-4.234.117
T-4.234.118
T-4.234.119
T-4.234.120
T-4.234.121
T-4.234.122
T-4.234.123
T-4.234.124
T-4.234.125
T-4.234.126
T-4.234.127
T-4.234.128
T-4.234.129
T-4.234.130
T-4.234.131
T-4.234.132
T-4.234.133
T-4.234.542
T-4.245.162
T-4.245.163
T-4.247.910
T-4.247.911
T-4.247.912
T-4.247.913
T-4.247.914
T-4.247.915
T-4.247.916
T-4.247.917
T-4.247.918
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 15 of 65
Q A T A R
T-4.247.919
T-4.247.920
T-4.247.921
T-4.247.922
T-4.247.923
T-4.247.924
T-4.247.926
T-4.247.927
T-4.247.929
T-4.248.106
T-4.249.856
T-4.249.889
T-4.249.890
T-4.249.891
T-4.249.892
T-4.249.893
T-4.249.894
T-4.249.895
T-4.249.896
T-4.249.897
T-4.249.898
T-4.249.899
T-4.249.900
T-4.249.901
T-4.249.902
T-4.249.903
T-4.249.904
T-4.250.896
T-4.250.902
T-4.250.907
T-4.250.916
T-4.250.917
T-4.250.921
T-4.250.930
T-4.250.931
T-4.250.932
T-4.250.938
T-4.250.940
T-4.250.944
T-4.250.954
T-4.250.957
T-4.250.958
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 16 of 65
Q A T A R
T-4.250.980
T-4.251.018
T-4.256.989
T-4.256.990
T-4.256.991
T-4.256.992
T-4.256.993
T-4.256.994
T-4.256.995
T-4.256.996
T-4.256.997
T-4.256.998
T-4.256.999
T-4.257.000
T-4.257.005
T-4.257.014
T-4.257.015
T-4.271.404
T-4.271.405
T-4.271.406
T-4.271.407
T-4.271.408
T-4.271.409
T-4.271.410
T-4.271.411
T-4.271.412
T-4.271.413
T-4.271.414
T-4.271.415
T-4.271.416
T-4.271.428
T-4.271.429
T-4.271.430
T-4.271.431
T-4.271.432
T-4.271.433
T-4.271.434
T-4.271.435
T-4.271.436
T-4.271.444
T-4.271.463
T-4.271.464
T-4.280.107
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Lifting Study for ACC Structures above 10 Tonnes for Dwg. # SPXCTOEO2-N-ZV-1001.001, 1001.002, 1001.003 & 1001.004 (Optional 120T
100T)
Procedure for Structural Steel Repair Works at Site
Trapezoid Sheet (Z0050318)
Trapezoid Sheet (Z0050320)
Trapezoid Sheet (Z0050321)
Trapezoid Sheet (Z0050322)
Trapezoid Sheet (Z0050323)
Trapezoid Sheet (Z0050325)
Trapezoid Sheet (Z0050326)
Trapezoid Sheet (Z0050327)
Trapezoid Sheet (Z0050348)
Trapezoid Sheet (Z0050349)
Part List Windwall Claddings
Part List Partition Wall Claddings
Packing and Preservation Loose Ball Valves
Metso Automated Control Valves Preservation Instructions
Neway Check and Gate Valves Packing and Preservation Procedure
(ASM) Bracing (Z0050821)
(ASM) A-frame Beam (Z0055838)
(ASM) A-frame Beam (Z0055834)
(ASM) A-frame Beam (Z0055846)
(ASM) A-frame Beam (Z0055848)
(ASM) A-frame Beam (Z0055868)
(ASM) A-frame Beam (Z0055875)
(ASM) A-frame Beam (Z0050456)
(ASM) Hanger (Z0056446)
(ASM) A-frame Head (Z0050445)
(ASM) Sealing Beam (Z0055343)
(ASM) Sealing Beam (Z0055342)
(ASM) Sealing Beam (Z0055341)
(ASM) Partition Wall and Monorails (Z0050344)
(ASM) Partition Beam (Z0050286)
(ASM) Partition Beam (Z0050298)
(ASM) Partition Beam (Z0050300)
(ASM) Door Frame (Z0050334)
(ASM) Door Side Beam (Z0050345)
(ASM) Door Side Beam (Z0050347)
(ASM) Partition Wall II (Z0050356)
Part List Partition Wall (Steel Work) (D0050792)
Part List (ASM) Fan Units (D0042211)
Instrument mountion Support (Z0072213)
(ASM) Distance Angle (Z0065166)
(ASM) Sealing Beam (Z0055340)
Page 17 of 65
Q A T A R
T-4.280.108
T-4.280.109
T-4.280.110
T-4.280.111
T-4.280.112
T-4.280.113
T-4.280.114
T-4.280.115
T-4.280.116
T-4.280.117
T-4.280.118
T-4.280.119
T-4.280.120
T-4.280.121
T-4.280.122
T-4.280.123
T-4.280.124
T-4.280.125
T-4.280.126
T-4.280.127
T-4.280.128
T-4.280.129
T-4.280.130
T-4.280.131
T-4.280.132
T-4.280.133
T-4.280.134
T-4.280.135
T-4.280.136
T-4.280.137
T-4.280.138
T-4.280.140
T-4.280.141
T-4.280.142
T-4.280.143
T-4.280.144
T-4.280.145
T-4.280.146
T-4.280.147
T-4.280.148
T-4.280.149
T-4.280.150
T-4.280.151
T-4.280.152
T-4.280.156
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 18 of 65
Q A T A R
T-4.282.688
T-4.282.689
T-4.282.690
T-4.282.691
T-4.282.692
T-4.282.693
T-4.282.694
T-4.282.695
T-4.282.696
T-4.282.697
T-4.282.698
T-4.282.699
T-4.282.737
T-4.282.738
T-4.282.739
T-4.282.740
T-4.282.741
T-4.282.742
T-4.282.743
T-4.282.744
T-4.282.745
T-4.282.746
T-4.282.747
T-4.282.748
T-4.282.749
T-4.282.750
T-4.282.751
T-4.282.752
T-4.282.793
T-4.282.845
T-4.282.920
T-4.305.053
T-4.305.085
T-4.305.144
T-4.305.149
T- 4.318.527
T-4.318.571
T-4.318.572
T-4.318.585
T-4.368.020
T-4.250.904 Rev. A
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Page 19 of 65
Q A T A R
6
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
RESOURCES
6.1
Responsibilities
Conduct TSTI with the concerned work force prior to start of work.
Ensure that relevant work permits for the job are obtained prior to start of work.
Conduct daily toolbox talks for the entire work force prior to start day work.
Assigning a competent work crew for specific activities, details of activities and task
information will be given to the work crew.
Organizing tools and equipment needed to the work site.
Inspection and supervision of work.
Ensure that all Contractor and Company safety regulations are followed as applicable.
6.1.6 Artisans
Group of skilled and semi skilled workers who will be responsible for the execution of
works and other jobs related to the completion of construction of ACC at C2 area.
T-4.250.904 Rev. A
Page 20 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
6.2
6.2.1 Equipment
Crane (1) each for 250 T, 120, 100 T, 80 T, 70 T and 50 T lifting capacities
hydraulic or crawler type will be utilized
Forklift 15 and 5 T capacity
Boom Truck 5 T capacity
Aerial Work Platform (man lift equipment) capable to 45 meters reach, (2) numbers
either telescopic and /or folding hydraulic type
Man basket for 3 persons
Trailer for transport of materials from lay down area to assembly site
Rigging and lifting equipment approved, certified and color -coded
Scaffolding as per requirement
Gas cutting torch with arrestors and welding machines
Grinding machine with correct grinding wheels and tool speed
Survey and level instruments
Portable diesel generator and portable lights to service night works
Hilti DX 76 Fastening tool
Air compressor
Hand and electric tools Note: No prefabricated tools will be allowed and shall be in
good working order
Paints and accessories Only for repair and touchup
6.2.2 Manpower
Management
Site Engineer
Foreman
HSSE personnel
Certified Crane operator
Certified Forklift operator
T-4.250.904 Rev. A
Page 21 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
If the above-listed equipment or manpower proves not sufficient for the timely completion of the
facilities and project; additional will be provided to complete the works on time and in line with
rules, regulations and specifications of Contractor, Company and RLIC.
T-4.250.904 Rev. A
Page 22 of 65
Q A T A R
7
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
METHOD OF EXECUTION
7.1
General
This chapter explains the methods to be used for the erection of all structural steel works,
piping and duct works, installation of air cooled condensers with associated equipment, and
steam recovery at the following site; FD at C2 area.
This method shall also apply to the other sites FA, FB, FC, and GA, GB, GC, GD at C2 area.
7.2
Pre-Commencement Works
Prior to works commencement, all seating foundations are checked for load bearing
of all steel erection as per approved drawings issued by the vendor or the company.
Any deviations as per plan will be recorded and served as guideline during the
execution of works and shall be within the tolerances recommended by the
manufacturer
Survey report on the main level references from Civil will be generated and submitted
before start up of construction to anticipate problems which can be encountered
during construction and alignment stages. Any deviations from the general
arrangements, drawings shall be identified
Materials and equipment required during the duration of works shall be available
nearby and checked
Lay down area for materials and equipment shall be located in such a place that
double handling can be minimized or can be totally eliminated. Due to space
limitations at the assembly area, a minimum supply of materials or structures for at
least three days will be maintained to assure continuous works without interruption.
This will also reduce risk for possible damage and distortion of materials from
handling and during assembly
Lifting procedures will be followed as per documents T-4.234.084 for Lifting General
Scaffolding will be followed as per separate method of statement and PTW (permit
to work) will be initiated before any works can commence; please refer to document
T-4.234.080. The use of scaffoldings will only be at selected area where height and
space have some limitations example as: pipe installation and welding works inside
the A-frame with bundles structures, piping below the fan deck; installation and
connection of condensate duct from turbine to the SDM
All works areas are to be secured, barricaded, and posted with signboards indicating
that works are in progress, and lifting operations are being conducted
Only authorized personnel's will be allowed to work within the perimeter
All barriers will be kept in place during the progress of works, and/or until the works
are completed
T-4.250.904 Rev. A
Page 23 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Part no.
Description
Wt.
No.
Total Wt.
A0080123 Column 1
1864.4
2
3728.8
A0087913 Column 1
1920.8
2
3841.6
A0088074 Column 1
1164.4
2
2328.8
A0087511 Hor. Bracing
727.836
1
727.836
A0087512 Hor. Bracing
554.345
1
554.345
A0087506 Hor. Bracing
924.12
2
1848.24
Wt of two adjoining columns & braces 13029.621 Kg
13.03 T
T-4.250.904 Rev. A
Page 24 of 65
Q A T A R
2
3
4
5
6
7
8
9
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Part no.
A0087709
A0087701
A0088079
A0088025
A0088074
A0087511
A0087512
A0087506
A0080136
A0087493
A0087495
Description
Wt.
No.
Column
1745.3
1
Column
1745.3
1
Column
1838.4
1
Column
1838.4
1
Column
1164.4
2
Hor. Bracing
727.836
1
Hor. Bracing
554.345
1
Hor. Bracing
924.12
2
Hor. Bracing
312.166
2
Hor. Bracing
312.166
2
Hor. Bracing
330.493
2
Wt. of two adjoining columns & braces
Total Wt.
1745.3
1745.3
1838.4
1838.4
2329.8
727.836
554.345
1848.24
624.332
624.332
660.332
14536.617 Kg
14.54 T
T-4.250.904 Rev. A
Doc. Title
Part no.
Description
Wt.
No.
Total Wt.
A0087898 E. Motor
1700
1
1700
A0086149 Gearbox
1400
1
1400
A0091415 Motor Bridge Complete 5102.812
1
5102.812
Motor Bridge consists of the following: A0091417 Railings
A0091360 Gear Support
A0091352 Transversal Beam
A0091358 Transversal Beam
A0091357 Transversal Beam
A0091398 Press Lock Grating
A0091396 Press Lock Grating
A0091395 Press Lock Grating
A0091393 Press Lock Grating
A0091394 Press Lock Grating
A0091397 Press Lock Grating
A0091399 Press Lock Grating
A0075068 Fan Impeller
126.88
7
888.16
Wt. of Motor Bridge & Structure 9090.972 Kg
9.10 T
Page 25 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Part no.
A0080285
A0080291
A0080280
A0080330
A0084581
A0088149
A0080320
A0080316
A0080302
10
11
12
13
14
15
16
17
A0080309
A0089231
A0089232
A0080338
A0091097
A0091096
A0091101
A0091100
Description
A Frame
A Frame
A Frame
Bracing
Top Girder
Top Girder
Hanger
Monorail
Top Steam Header
Support Beam
Outrigger
Outrigger
Outrigger
Bracing
Sealing Beam
Sealing Beam
Sealing Beam
Sealing Beam
Wt.
1568
820
2322.5
260.215
938.37
689.2
55.267
195.4
237.63
No.
2
2
2
8
1
1
2
2
1
Total Wt.
3136
1640
4645
2081.72
938.37
689.2
110.534
390.8
237.63
69.138
61.81
63.423
2
138.396
2
123.62
2
126.846
2
33.801
95.801
1
95.801
95.801
1
95.801
95.801
1
95.801
95.801
1
95.801
Wt. of A Frame 14675.121 Kg
14.67 T
T-4.250.904 Rev. A
Part no.
A0080519
A0080520
A0080521
A0086422
A0080522
Description
Spool
Spool
Spool
Spool
Spool
Wt.
No.
5420
1
4700
1
3700
1
3650
1
3323
1
Wt. of steam Manifold
Total Wt.
5420
4700
3700
3650
3323
20793 Kg
20.8 T
Page 26 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
11
12
T-4.250.904 Rev. A
Part no.
A0079847
A0079904
A0079900
A0079896
A0079898
A0079904
A0079902
A0092946
A0089654
A0084106
A0082543
A0082456
A0084105
A0081962
A0089614
A0089588
A0089516
A0086912
A0079878
A0098394
A0086912
A0086911
A0086973
Description
Wt.
No.
Total Wt.
Longitudinal Beam
328.664
2
657.328
Longitudinal Beam
328.664
2
657.328
Fan Deck Cross Beam 102.318
4
409.272
Diagonal Beam
180.388
2
360.776
Diagonal Beam
270.831
2
541.662
Parallel Beam
225.28
2
450.56
Parallel Beam
187.849
2
375.698
Spring Support Beam
68.225
1
68.225
Spring Support Beam
68.225
1
68.225
Beam
21.705
1
21.705
Beam
21.313
4
85.252
Beam
21.313
4
85.252
Beam
21.704
1
21.704
Beam
472.99
1
472.99
Column Head
520.149
2
1040.298
Support Beam
85.534
1
85.534
Support Beam
128.704
1
128.704
Support Beam
171.993
1
171.993
Platform End Profile
751.931
1
751.931
Support Beam
274.061
1
274.061
Support Beam
171.993
1
171.993
Support Beam
128.704
1
128.704
Platform End Profile
151.769
1
151.769
Wt. of Fan Deck Structure 7180.964 Kg
7.2 T
Page 27 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Avoid related equipment operate over or near pre-installed and covered lines.
Ensure such equipment access lifting area through identified access ways. (FSI
Ref.: Q1-1.3.1.)
Avoid related equipment cause over settling of concrete pits resulting shears at the
grip pipe connections. Following the lifting operations, ensure proper condition of
any nearby underground piping (with video cameras if necessary). (FSI Ref.: Q11.3.4.)
T-4.250.904 Rev. A
Page 28 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Proceed to erect the sub structures at the upper deck (see proceeding item, 7.2.5.2).
The first street will be levelled and aligned before connecting any steel structures of
another street.
Final bolt torque should be completed after thorough inspection has been performed
and found acceptable, and they are to be colourcoded indicating that bolts are
properly checked and correct torque is applied.
All erection works will be done by competent and certified erectors, and banks man for
all lifting operations.
Grouting will be done on steel structure foundation with approved materials as per site
specifications after complete alignment and acceptance of fan deck assembly of each
street.
See illustration for similar installation for a similar project by other agencies: -
STEP 1
STEP 2
STEP 3
T-4.250.904 Rev. A
Page 29 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Aerial work platform (AWP) will be used by the erectors in connecting the structure to
the built columns. Proceed until the whole street is completed forming a complete
working table. Wherever necessary, man lifts will be also be used.
Inspection for the elevation and verticality will be done after it is determined and
conditions are acceptable within the given tolerances. It will serve as a guide or
reference in foregoing installation of equipment and structure to the adjacent streets
After completing the erection of the fan deck structures at street 3, erect the columns
and steel structures at N module of street 4 (south corner). Stairs and walkways will be
assembled and will serve as access going to the fan deck or upper structure. This will
provide us some leeway of maximizing the utilization of man lifts to other area and
eliminate expensive scaffoldings
One bracing is required to be temporarily removed to allow installation of condensate
tank and steam evacuation unit. Further study on the removal of the bracing will be
provided in ref. T-4.305.085
Note: It is not permitted to proceed with erection of other equipments as motor bridge,
A-frame, CCM and SDM until completion of condensate tank and steam evacuation unit
and installation of temporarily removed bracing is complete
Deck plates and gratings are to be secured by Hilti fastening tool; catch nets to be
provided and laid out on the fan deck screens to prevent materials, etc from falling and
other safety reasons.
Catch nets specification: PE or Polyester or PP perimeter debris netting for construction
industry (Mesh size 2.5 x 2.5 mm, width 2000mm) subject to approval by Linde
Engineering AG/PMC
Subject to prevailing conditions at site, an alternative scheme can be device to be able
to install the fan deck plates at the fan deck structure
After erecting the fan bell with screen into the structure, platform openings can only be
closed by fan deck plates during the course of construction, hence additional safety
measures for people working at height is mandatory. Additional lifelines aside from the
proposed will be provided i.e., lines installed midpoint from each cell. The latter will be
use for people to be positioned inside the fan bell assembly during the laying out &
fastening the fan deck sheets into the structure. They will be assisted by a third person
riding in the manlift
Lifting of the fan deck plates will be done according to attached procedure - Lifting ACC
fan deck plates & plate clamps lifter will not be allowed to be used
The Sequence will be repeated until the cell is covered by deck plates
It (deck plates) will be fixed permanently soon as activity 7.2.5.3 is completed
See illustration for similar installation by other agencies: -
T-4.250.904 Rev. A
Page 30 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
T-4.250.904 Rev. A
Page 31 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
7.2.5.4 Assembly of Motor Bridge with Drive unit and Fan Blades
Pre assembly of motor bridge with drive unit will be done by mechanical fitters at the
adjacent streets respectively to limit movement of lifting equipment. The latter structure
will be laid horizontally and levelled along with fabricated support beams at 1.2 meters
height. This will assure mobility of people working underneath for fan blade erection
Secure and align the gearbox with correct bolts and shims for correct levelling on the
motor bridge structure; then fasten the motors, taking note the orientation of the motor
control box. At this stage, gearbox will not be filled with oil; this will be done during the
commissioning stage. Refer to ACC construction manual T-4.121.350
Railings, grating materials and walkways will be installed before lifting the whole
structure with blades at the upper deck. The fan blades will be installed in vertical
position temporarily; to prevent damages during erection of other parts above the deck
Observe correct torque value for bolts on the gearbox shaft coupling to motor plus the
flanged connection to the fan hub plate, and then install and assemble the fan blades.
Ref.: 7.2.6.1 Bolting. Torque bolts on joints, blades for flange with 70% torque value
Prior to lifting, additional fasteners and/or soft ropes will be required to prevent
movement and rotation of the fan blades during the lifting operation to the upper sub
structure
Lift the structure assembly and secure into final position at the upper deck
Lifting of the motor bridge with drive unit and fan blades will be done by certified and
competent riggers and banks man.
See illustration for similar installation by other agencies: -
T-4.250.904 Rev. A
Page 32 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Following the erection, ensure proper preservation of rotating equipment (e.g. 4 weekly
vertical shaft rotation, oil top-up/greasing) and refer to equipment manuals as
necessary, for protection against heat, dust and humidity. (FSI Ref.: Q1-3.1.)
T-4.250.904 Rev. A
Page 33 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
7.2.5.7 Assembly of CCM, Bundles, SM, Piping Works and Wind wall
Erection of the remaining structures will be as follows: Condensate Collecting Manifold (CCM) first, secondary bundles and primary bundles,
and Steam Distribution Manifold (SDM) as third step
Assemble and weld two CCM spool on the ground, temporarily fixed with bolts after
lifting them at the upper deck. These bolts can be removed once the alignment and tack
welding of the CCM is done. Lift the next two joined spools, and join to the latter spools.
Final alignment of the joined spools and welding will be done at this stage, then
proceed to complete the street. Final welding on the manifold will be done as soon as
all the alignment of the manifold is achieved
Before erecting the bundles onto the A-frame, thorough inspection will be done for any
damages. The inspection shall be recorded and noted whether bundles are acceptable,
or require repairing
Lifting up of the bundles starts first with secondary, then the primary. Installation of
lifeline for people working in the bundle erection will be performed. Refer document
attached
Lifting up of the bundles will be alternate (to Left & to right side) to avoid unbalancing on
the structure. Bundles shall be lifted at the required A-frame slope, using offset sling
lengths.
Join two (2) opposite primary bundles with plate (A0080412) by welding after aligning
the bundles; taking into consideration on special procedures to avoid overheating of the
tube sheets. After welding completion and alignment, the steam distribution manifold
(SDM) will be installed.
The weight of the complete steam manifold exceeds 10 Tonnes, hence it is necessary
to have at least three (3) lifts; starting lift of spool 3 (A0080521) at the fixed point, which
is located on the top of the secondary bundle structure. Spool 4 (A0086422) & spool 5
(A0080522) will be assembled & welded on the ground prior to lifting; similarly with
spool 1 (A0080519) & spool 2 (A0080529). They will be joined with spool 3 after
erection at the structure. Lifting lugs will be provided for its joined spools, taking into
consideration of the centre of gravity. Seal plates at the end of manifold (spool 5) are to
be adjusted at the site after the bundles assembly & steam manifold installation is
completed and stitch welding of the manifold & bundle will commence.
Ensure all heat exchanger pipe protection covers removed before installation. (FSI Ref.:
Q2-2.1.)
Ensure pipes are internally clean before lifting into the structure (visual, air blow, liftingup at one end). (FSI Ref.: Q2-1.8.)
Ensure all open ends capped after work interruption or day end. (FSI Ref.: Q2-1.8.)
Condensate tank and structure will commence for erection after fan bell is erected at
module N of street # 4.
Condensate tanks, steam ejectors, the drain pump station and associated equipment
and instrumentation will be erected and piping will follow as soon as the upper
structures are done, then continue to work on the remaining streets.
T-4.250.904 Rev. A
Page 34 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
At this stage, the steam duct connecting the turbine exhaust and the ACC can
commence simultaneously with other works in the ACC; and it is necessary to start
works at each fixed points.
Installation of walkways and rails at street 4 going to the upper deck will be done to
minimize utilization of man-lift equipment during installation of structures on the
remaining streets.
Soon as the entire street installations are completed, panel sheeting of the interior will
be done.
The pre-assembly of the wind wall will be done on the ground level, lifting and
installation will be parallel and commence with A-frame erection at the upper structure.
The wind wall section will be connected and bolted to the main structure (fan deck) and
connected to the steam manifold bracings.
See illustration for similar installation by other agencies: -
T-4.250.904 Rev. A
Page 35 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
T-4.250.904 Rev. A
Page 36 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
The Steam ducting installation will start at the duct fix point. Sequence refer sketch as
given below in (illustration A & A1): -
Connection
Point SM
Connection
Point SM
Fixed Starting
Point
Illustration A
Illustration A1
The steam ducting has to be assembled and installed starting from the turbine outlet at
machine house to the air cooled condenser inlet joining streets 3/4 and streets 2/1
respectively. The expansion joints and ducting sections can be assembled and welded
together to a great extent at the ground level before lifting them into position.
Spool 1 a (Drg. No.:Z0060956; T-4.219.793) and expansion joint to be welded on site to
the turbine piece before turbine installation.
T-4.250.904 Rev. A
Page 37 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Install complete part to the turbine flange and lift together with turbine into the turbine
table.
After adjustment at spool 1, fabricated duct part-01 DN3820 (Drg. No.:Z0055358; T4.121.231) to be welded with the expansion joint. During installation of the expansion
joints and the vane elbows, special care and attention shall be taken to ensure that they
are installed correctly for the direction of steam-flow.
Additional stiffening brackets may have to be welded to the steam duct risers in the
area of expansion bellows for safeguarding and preventing damages on the rings
convolutions of the expansion rings.
All sections of the ducting must be connected together free of any "forces and
moments" by means of using the correct procedure and respectively, the planned
sequence of erection. It is not acceptable to assemble or install together by force as this
would lead to lateral deformation or misalignment of the supports. Even in such cases;
uncontrolled forces and moments can occur to the turbine connection.
After full completion of the ducting and piping systems; all temporary stiffening or
locking devices must be removed.
Separate Method statement for ducting will be prepared and got approved prior to
commencement of the erection of ducting.
T-4.250.904 Rev. A
Page 38 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Precautions:
All valves on steam, air extraction & condensate shall be open (except for vents and
drains)
Vent & drain on condensate tank can be partially open to improve air circulation in
the tank
Preservation with hot air cannot be considered for the ACC tube bindles since cooling
surface is high and air will cool down immediately, hence efficiency is limited. The
condenser, tanks, vessels and tubes to be drained. The condenser will be preferably
blown dry with air; if possible to be maintained under vacuum
3. Long term Shutdown
Long term shutdown is considered a period more than 6 weeks.
Condensate tank
Condensate pumps
After draining of all components, immediate drying of complete ACC will start
Dry air shall be blown into the steam duct and evacuated at hogging and holiday
ejector outlets.
Condensate Pump
Gearboxes
Greasing
T-4.250.904 Rev. A
Page 39 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
T-4.250.904 Rev. A
Torque value
(KN)
40
80
120
145
165
Page 40 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
6
M 27
7
M 30
8
M 36
Refer document T-4.193.320
bolts from the vendor.
200
900
220
245
1200
270
355
2100
390
for Grade 8.8, hot dip galvanized and lubricated nuts and
The following table will be implemented for Motor & Gear Box, coupling's, fan blades
and other machine components: #
dimensions
Strength class 8.8
Strength Class 10.9
1
M6
10 Nm
14 Nm
2
M8
25 Nm
35 Nm
3
M 10
49 Nm
69 Nm
4
M 12
86 Nm
120 Nm
5
M 16
210 Nm
295 Nm
6
M 20
410 Nm
580 Nm
7
M 24
710 Nm
1000 Nm
8
M 30
1450 Nm
2000 Nm
9
M 36
2530 Nm
3580 Nm
10
M 42
4070 Nm
5720 Nm
11
M 48
6140 Nm
8640 Nm
12
M 56
9840 Nm
13850 Nm
13
M 64
14300 Nm
21000 Nm
Refer Document T-4.200.145 as provided by SPX/vendor.
Additional Reference: DEP 34.28.00.31
Any other bolts of different grades, the torque values will be followed in line with the
vendor's recommendations.
T-4.250.904 Rev. A
Page 41 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
QUALITY ASSURANCE
A Quality Assurance System will be operated conforming to related standards and
vendor's recommendations.
T-4.250.904 Rev. A
Page 42 of 65
Q A T A R
Doc. Title
GAM-MTS-MEC-GTL-009
METHOD STATEMENT - MAIN ERECTION SEQUENCE for ACC
Date
Controls and checks will be established and documented through relevant QCP T4.250.944 & ITP T-4.250.921 and QCR's.
FSI should also apply to this method of statement. Reference DEP 70.10.70.11
ATTACHEMENTS
9.1
9.2
9.3
9.4
T-4.250.904 Rev. A
Page 43 of 65
Page 44 of 65
Mr. Bilal
Name
2. Permit To Work.
RLIC EMERGENCY NO
583 40 72
474 88 88
Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The LINDE Industrial Hygienist must also approve the work.
2) Use additional sheets as necessary.
3) Details on safety (PPE,Hazard etc) and environmental requirements can be found in LINDE and SHELL Safety and Environment Procedures.
Approval required for hazardous work detailed in the Linde Work Permit Procedure.
Changing conditions and emergency procedures: Stop work. Switch off equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing
employees are reported to Linde HSSE Dept. When all clear is given, check with Linde HSSE before returning to work.
Date
24.11.08
Additional Approvals (Determined by Job Supervisor in correlation with Linde HSSE Manager).
Name
Signature
Discipline Superindent (Linde)
Job Supervisor:
JSA by:
Normal Approvals:
Page No: 1 of 6
Q A T A R
Page 45 of 65
ITEM
Mobilization of
structures and
equipment to site
laydown area
ACTIVITY
Q A T A R
Personnel observation at
work
Ensure safe distance from
the excavations
Injury due to muscle strain
or sprains while lifting
weights
1.3
1.5
1.4
Adequate Banksmen
1.2
HAZARDS / POTENTIAL
CONSEQUENCES
1.1 Lifting and transport
equipment movement
LOW
MED
Rank
Initial Risk
1.5.2
1.5.1
1.4.1
1.3.1
1.2.1
1.1.3
1.1.2
Residual Risk
ADDITIONAL
P C
Rank
CONTROLS
1.1.1.1 Only drivers/operator with Qatar
license & certified operator &
trained personnel are be allowed to
work on site.
Ensure the area is wide enough for the 1.1.2.1 Ensure that every vehicle and
slewing movement.
equipment is fitted with an
automatic reverse alarm and
beacon or strobe light.
1.1.3.1 Barricade working area and
Place the outriggers in level ground
B 2
LOW
provide warning signs.
surface and ensure ground
compaction report required to
accompany lift plan.
Ensure that an adequate number of
1.1.4.1 Proper determination of cg (center
Banksmen are assigned as necessary
of gravity) for each lifts
to control work.
All personnel to be vigilant of each
other and vehicle movements.
Ensure the area is wide enough in the
travelling range.
Ensure employee shall be trained in
safe methods of handling equipment,
assessed & qualified.
1.5.2.1 The weights of each structure or
Assessment of weight of equipment
LOW
B 1
equipment will be specified and
and structure to be noted and
noted before any lift
numbers of person required to be
defined. Rigging & lifting plan to be
submitted for approval.
MAIN
CONTROLS
1.1.1 Ensure that there are no obstacles in
the travelling range.
Page 46 of 65
Unloading of
structures and
equipment prior to
erection
Erection of structure
and equipment
ACTIVITY
ITEM
Q A T A R
Working at heights
3.2
3.3
3.1
2.2
HAZARDS / POTENTIAL
CONSEQUENCES
2.1 Lifting and transport
equipment movement
LOW
MED
HIGH
LOW
LOW
Rank
Initial Risk
2.2.1 Ensure that materials handled are free 2.2.1.1 Proper PPE (personal protective
equipment) required.
from splinters or rough surfaces which
can contribute and affect harm.
LOW
LOW
MED
LOW
Residual Risk
ADDITIONAL
P C
Rank
CONTROLS
2.1.1.1 Only drivers/operator with Qatar
license & certified operator &
trained personnel are be allowed to
work on site.
B 1
LOW
2.1.2 Ensure the ground are level to prevent 2.1.1.2 Area to be barricaded off with sign
boards mwntioning lifting in
structures and equipment from
progress.
distortion
MAIN
CONTROLS
2.1.1 Ensure that no obstacle within the
laydown area
Page 47 of 65
ITEM
ACTIVITY
Q A T A R
Tampering Electrical
equipment
Risk of Fall
3.5
3.6
3.7
HAZARDS / POTENTIAL
CONSEQUENCES
3.4 Electrical hazard.
HIGH
LOW
LOW
MED
Rank
Initial Risk
3.5.1
3.4.4
3.4.2
3.4.3
3.4.1
MED
LOW
LOW
LOW
Rank
Residual Risk
MAIN
ADDITIONAL
CONTROLS
CONTROLS
3.4.1.1 Ensure all electrical equipment
Check electrical equipment prior to
were properly grounded and built
use. Ensure it is properly inspected,
with ELCB at their source.
color coded for the month and properly
documented.
Ensure good electrical connection.
Dont allow any live electrical parts to
touch the ground.
Dont touch electrically live parts with
skin or wet clothing.
Ensure that only qualified and trained
electrical technician will carry out in
setting up lights in work area.
Page 48 of 65
6.1
5.4
Personnel or Tools
falling
5.3
Overturning
5.2
5.1
Utilizing
Utili i equipment
i
t ffor
other purpose.
Structural Failure
4.4
44
Operation of Crane
4.3
Overturning
4.2
Operation of Areial
work platform
ACTIVITY
LOW
HIGH
MED
MED
MED
MED
MED
MED
MED
MED
Rank
Initial Risk
ADDITIONAL
CONTROLS
4.1.1.1 Duly certified equipment will be
used.
LOW
LOW
LOW
LOW
LOW
LOW
LOW
LOW
Rank
Residual Risk
MAIN
CONTROLS
4.1.1 Ensure equipment reliability &
complete inspection.
HAZARDS / POTENTIAL
CONSEQUENCES
4.1 Structural Failure
ITEM
Q A T A R
Page 49 of 65
ACTIVITY
Operation of HILTI
DX76 fastening tool
Permit Holders
ITEM
Q A T A R
9.1
HAZARDS / POTENTIAL
CONSEQUENCES
8.1 Utilizing of the unit.
LOW
HIGH
Rank
Initial Risk
8.1.4
8.1.3
8.1.2
8.1.1
LOW
LOW
Rank
Residual Risk
MAIN
ADDITIONAL
CONTROLS
CONTROLS
Ensure the users are trained to
8.1.1.1 Training is required for all user.
operate the tool.
Only authorised users have to operate
the unit.
8.1.1.2 Proper PPE for operator
The operator has to understand what
the tool is cabable off.
8.1.1.3 Discuss in TSTI.
Proper attention is required & could
cause hazard if incorrectly used; as
personal injury.
Q A T A R
INSTALLATIONOFLIFELINEFORBUNDLESERECTIONAT
ACC
Doc.Title
Date
: 12thNovember2008,RevE
1. SCOPE:
The procedure applies to the installation or erection of the secondary & primary bundles for ACC at
C2 Area.
2. PURPOSE:
The main purpose is to describe the procedures on how the bundles will be erected & to ensure that
3. DESCRIPTION OF BUNDLES:
Secondary Bundles:
L x W = 10600mm x 2193mm
Wt.
= 3.403 Tonnes
Total number to be erected per ACC
= 24 nos.
Primary Bundles
L x W = 11100mm x 2193mm
Wt.
= 3.597 Tonnes
Total number to be erected per ACC
= 168 nos.
5. PROCEDURE
Bundles will be erected in the following sequence; first secondary & then the primary
bundles
Ensurethatallheatexchangerprotectivecoversareremoved&cleanedbeforeinstallation
BundleswillbeliftedfromthegroundusingthecraneavailableatACCarea
Bundles will be lifted in 30 inclination and to be placed into the erected AFrame. The
wholeweightwillbesupportedbytheinstalled(CCM)collectingcondensatemanifoldatthe
bottom & anchored on top of the AFrame. The two opposite bundles will be joined by
weldingonthelatestage
Sequence of lift will be alternate i.e. starting from the left to the right; or right to left
whicheverapplicabletopreventunbalancingatthestructure
During primary bundles erection, the lifeline system will be bolted into the edge of the
bundles & will cover the entire length of the street. This will provide access to trained
personnelintheexecutionoftheirworksi.e.joining,alignmentandweldingofbundles
Page 50 of 65
Q A T A R
INSTALLATIONOFLIFELINEFORBUNDLESERECTIONAT
ACC
Doc.Title
Date
: 12thNovember2008,RevE
The lifeline will be later removed during the erection of the (SDM) steam distribution
manifold
Manliftwillbeutilizedtofastenthemobilepostforlifelineandwillbespacedmorethan4
meter or at two bundles interval. At least two lines will be erected; & wire rope will be
minimum10mm.
6. ATTACHMENT:
Page 51 of 65
Page 52 of 65
Page 53 of 65
FOR CONSTRUCTION
0
03.11.2008
N.KUMAS
Rev.
Date
Description
Prepared
Customer
Engineering
A.GKDALAY
F.TN
Approved
Checked
G
PEARL-GTL PROJECT
QATAR
ERECTION CORP.
Document Title
HORIZONTAL LIFELINE SYSTEM
DESIGN CALCULATION NOTES
Document No.
000-101-S0041-CN01
Rev.
0
Page 54 of 65
Document No:
000-001-S0041-CN01
Page No:
Rev
TABLE OF CONTENTS
Page No
Table of Contents
1.0 GENERAL
i
1-5
1.1 Scope
1.2 System
1.3 Units
1.4 Materials
2.0 CALCULATIONS
3.0 CONCLUSION
10
Page 55 of 65
Document No:
000-001-S0041-CN01
Page No:
Rev
1. 0 GENERAL
1.1. SCOPE
This report is prepared for the design of the mobile post and horizontal lifeline system at
Fan Deck Sub-structure of ACC. The system is checked for the safety of wire ropes for a
factor of safety greater than 2 as well as the mobile posts to resist for the cable force.
Assuming some type of shock-absorbing/self-retracting lanyards are used; 410 kg (900
lbs) force for one worker is applied at midspan of the horizontal lifeline system for
design/analysis purposes and it is assumed that both top or mid-rail of the system could
be used.
As can be seen on the drawing at the next page; the support system is designed as
braced for both top and mid-rail at the corners as well as at the ends where the lifelines
coincide. The horizontal distance of the bracing form the vertical supports are considered
as 1.2 m providing an angle of 25.15 for the top rail with vertical support. The bracings
profiles are the same as the vertical supports of pipes with 38.1 mm diameter and 4.1 mm
wall thickness.
1.2. SYSTEM
System of the structure is indicated at the following page.
Page 56 of 65
Page 57 of 65
Page 58 of 65
Page 59 of 65
Page 60 of 65
Document No:
000-001-S0041-CN01
Page No:
Rev
1.3. UNITS
Throughout this report the following units will be used.
Length
m and mm
Area
m2
Force
Pressure
kN/m2 (kPa)
Stress
N/mm2 (MPa)
Elevations
1.4. MATERIALS
Structural Steel
: S235JR
Eurocode 3-Design of Steel Structures-1993 Part1-1: General rules and rules for
buildings
Page 61 of 65
Page 62 of 65
= 600.44 cm
By doing iteration for t2 until the difference btw L2 and L22 converge to zero (see the next page);
Tangential cable tension at mid-span under its own weight and concentrated load t2 is calculated as
t2: 3690 kg
16.82 kg
16.73 kg
8 f 12
S .1 +
3s 2
w .s 2
8 . f 1
2
w.s
2
t1 +
Nominal diameter, d:
Cross-sectional area, A:
Distance btw. anchor points,S:
Cable weight:
Modulus of elasticity:
Mid-span applied concentrated load for 3 workers:
Minimum breaking load:
Sag of cable under its own weight:
000-001-S0041-CN01
2.0 CALCULATIONS
Document No:
Document Title:
Page No
Rev
Page 63 of 65
301.52326
301.50848
301.4939
301.47954
301.46538
301.45143
301.43767
301.42411
301.41073
301.39755
301.38455
301.37173
301.35908
301.34661
301.33432
301.32219
301.31022
301.29841
301.28677
301.27528
301.26394
301.25275
301.24171
301.23082
301.22007
301.20946
301.19899
301.18865
301.17844
301.16837
301.15842
301.1486
301.13891
301.12934
301.11988
301.11055
301.10133
301.09223
301.08323
301.07435
0.9041143
0.8661115
0.8285369
0.7913823
0.7546397
0.7183013
0.6823595
0.6468066
0.6116356
0.5768391
0.5424103
0.5083424
0.4746287
0.4412628
0.4082382
0.3755489
0.3431887
0.3111517
0.2794321
0.2480243
0.2169227
0.186122
0.1556167
0.1254018
0.0954722
0.065823
0.0364491
0.0073461
-0.021491
-0.050066
-0.078385
-0.10645
-0.134267
-0.16184
-0.189173
-0.216269
-0.243133
-0.269769
-0.29618
-0.322369
603.04654
603.01697
602.98782
602.95909
602.93078
602.90287
602.87535
602.84823
602.82148
602.79511
602.76911
602.74347
602.71818
602.69324
602.66865
602.64438
602.62045
602.59684
602.57355
602.55057
602.52789
602.50552
602.48344
602.46165
602.44015
602.41893
602.39798
602.37731
602.3569
602.33675
602.31686
602.29722
602.27783
602.25868
602.23978
602.22111
602.20267
602.18446
602.16648
602.14872
L2
602.142429
602.150856
602.159283
602.16771
602.176138
602.184565
602.192992
602.201419
602.209846
602.218273
602.2267
602.235128
602.243555
602.251982
602.260409
602.268836
602.277263
602.28569
602.294117
602.302545
602.310972
602.319399
602.327826
602.336253
602.34468
602.353107
602.361535
602.369962
602.378389
602.386816
602.395243
602.40367
602.412097
602.420524
602.428952
602.437379
602.445806
602.454233
602.46266
602.471087
L22
2040
2050
2060
2070
2080
2090
2100
2110
2120
2130
2140
2150
2160
2170
2180
2190
2200
2210
2220
2230
2240
2250
2260
2270
2280
2290
2300
2310
2320
2330
2340
2350
2360
2370
2380
2390
2400
2410
2420
2430
t2
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
S
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
1.131
A
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
0.00558
000-001-S0041-CN01
L2-L22
Document No:
Document Title:
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
630000
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
410
F
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
25.098425
t1
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
600.4444444
8
L1
Page No
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
0
f1
Rev
Page 64 of 65
S ( 2 F + ws )
8t 2
T2=
102.93 kN
T2.cos()= q. sin()
= 31.61
- Reaction on the inclined support q = 7040.76 kg
1.46
= 16.73 cm
F + ws
t22 +
S
cos()= 2
= 0.99845
s
= 603.54 cm
= 3695.78 kg
Sag of the cable under its own weight and concentrated load f2=
= 300.47 cm
3
S
. 2
s = 600.93 cm
(t 2 t1).L1
+ L1
AE
S
w 2 .
2
2. s +
24.t 2 2
s 2 S ( 2 F + ws )
+
4
8t 2
L22=
Length of cable under its own weight and concentrated load L2=
000-001-S0041-CN01
Document No:
Document Title:
3.19
L2 - L22 -= 2.61 cm
Page No
Rev
Page 65 of 65
>
3690.05 kg
As a result, the horizontal lifeline with the support system is found to be safe.
1 - The cable tension load is less than the cable breaking load with a factor of safety equal to
2.79
2 - The axial load on tubular column is less than allowed load with a factor of safety equal to
1.46
3 - The baseplate weld capacity of the is greater than the applied load with a factor of safety equal to 1.80
The horizontal lifeline fall arrest system has been analyzed using the principle described above and the following results are gathered.
3.0 CONCLUSION:
>
= 277 Mpa
f vw.d= ( fu / 3 )/( w * M2 )
000-001-S0041-CN01
- Baseplate welds;
Document No:
Document Title:
Rev