2G Network DT Performance Pre Re-farming Report

2G Network DT Performance
Pre Re-farming Report

HUAWEI

Technologies Co.
Ltd.
All Rights Reserved

Number/Version
Owner unit: RNP

Prepared by
HUAWEI

Approved by
OMANTEL

TABLE OF CONTENTS
1.
1.1.
1.2.

INTRODUCTION..................................................................................................3
SUBJECT BACKGROUND....................................................................................................3
DT TEST REQUIREMENT...................................................................................................3

2.
2015-05-26

GENERAL INFORMATION..................................................................................4
HUAWEI Confidential

Page1, Total28

2G Network DT Performance Pre Re-farming Report

2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.

CLUSTER INFORMATION......................................................................................................4
CLUSTER CELL LIST.........................................................................................................5
DRIVE TEST ROUTE..........................................................................................................6
TEST EQUIPMENT.............................................................................................................7
TEST METHODS............................................................................................................... 7
TEST LEGEND DEFINITION................................................................................................. 8
TEST DAY & TIME.............................................................................................................8

3.
3.1.

KPI SUMMARY.....................................................................................................9
CS DT KPI......................................................................................................................9

3.1.1 Peak time DT KPI..............................................................................................................................9

3.2.

PS KPI..........................................................................................................................10

4.

PEAK TIME DT PERFORMANCE ANALYSIS..................................................11

4.1. COVERAGE PERFORMANCE RESULTSRXLEV SUB (DBM)...............................................11


4.2. COVERAGE PERFORMANCE RESULTSRXLEV FULL (DBM).............................................12
4.3. QUALITY PERFORMANCE RESULTSRXQUAL SUB..........................................................13
4.4. QUALITY PERFORMANCE RESULTSRXQUAL FULL.........................................................14
4.5. C/I AVERAGE PERFORMANCE RESULTS...........................................................................15
4.6. TX POWER CS PERFORMANCE RESULTS........................................................................16
4.7. TA................................................................................................................................. 17
4.8. ISSUE ANALYSIS............................................................................................................. 18
4.8.1. POOR COVERAGE........................................................................................................18
4.9. CALL SETUP FAILURE PLOT............................................................................................19
4.10. HANDOVER FAILURES PLOT.........................................................................................19
4.11. CALL DROP PLOT....................................................................................................... 20
5.
5.1.

CQT PERFORMANCE ANALYSIS....................................................................21


CQT POINT....................................................................................................................21

6.

SUMMARYDAYTIME CQT & PEAKTIME DT....................................................22

7.1. PEAK TIME DT PERFORMANCE SUMMARY..........................................................................22


7.3. CQT PERFORMANCE SUMMARY........................................................................................ 22
7.4. CSSR PERFORMANCE SUMMARY......................................................................................22
7.5. HSR PERFORMANCE SUMMARY........................................................................................23
7.6. CDR PERFORMANCE SUMMARY........................................................................................23
7.7. PS CQT THROUGHPUT SUMMARY.....................................................................................24

1. Introduction
This is a network evaluation report before Re-farming. We follow the following principles to do
series of drive tests.
Full coverage peak time typical period.
All services: CS/GPRS/EDGE, 2G/2G handover and 2G / 3G reselection are tested.
So it is an overall period, overall scene, and overall operation test.

1.1. Subject Background


This report presents drive test results, CQT in peak time before Re-farming.
This document includes the following subjects:
2015-05-26

HUAWEI Confidential

Page2, Total28

2G Network DT Performance Pre Re-farming Report

Peak time performance analysis

CQT performance analysis

Summary CQT & peak time DT

1.2. DT Test Requirement


Drive test result are shown to estimate the coverage and quality before Re-faming.
The KPIs selected will show the network performance before Re-faming.
Short Name
RxQual_Dlink
RxLev_Dlink
HSR
CDR

CSSR

Definition

Measure Object

Percent of DL quality
measurements
Percent of DL Level
measurements
Handover Success /
(Handover Success +
Handover Failure) * 100%
Number of call drops / Call
Setup Success * 100%
Call Setup Success / (Call
Setup Success + Call Setup
Failure due to RF Reasons)
* 100%

Re-faming
Cluster
Re-faming
Cluster
Re-faming
Cluster
Re-faming
Cluster
Re-faming
Cluster

Test Method
Drive Test
Drive Test
Drive Test
Drive Test
Drive Test

2. General Information
2.1. Cluster Information
Below in the map where Re-farming area is located:

2015-05-26

HUAWEI Confidential

Page3, Total28

2G Network DT Performance Pre Re-farming Report


Re-farming Division Map

2.2. Cluster Cell List


There are 14 GSM sites in thecutover area, cell information pre swap as below:

Cluster Number

Number of Sites

Site List

Re-farming Area

425

2G Refarming
Data.xlsx

Site Distribution Map

2015-05-26

HUAWEI Confidential

Page4, Total28

2G Network DT Performance Pre Re-farming Report

2.3. DriveTest Route


Following is the cluster05 DT route to be followed for Pre Re-faming DT route:
Cluster Route

2015-05-26

HUAWEI Confidential

Page5, Total28

2G Network DT Performance Pre Re-farming Report

2.4. Test Equipment


Table lists the data collection test equipment required for each test vehicle.

Items

Description

Laptop Computer
GPS Receiver
GSMtest system
AC/DC Power Equipment
FTP Address

1.6GHz CPU speed. At least 768MB RAM and 30GB HDD. One for each
team.
A GPS Receiver is used to provide position data for the Drive Test tool. At
least one per test van. Each GPS receiver shall have anexternal antenna.
Normal GSM test phone *3Plus Test and analysis platform
DC power to theequipment in the RF Kit for each phone. An inverter to supply
ACpower to the laptop computers.
85.154.223.30 (Omantel LTE Testing Server)

2.5. Test Methods


The drive test procedure is defined as:
Scenario
s

Test Scope

Test Description

Long Call

Dedicated test will evaluate the


retain ability,mobility and TCH
coverage performanceof the
Network for the voice service.

MSset a MOC Call. If the call drops, a new call is


established after 15 sec. In case of Refused Call (call
establishment failure), a call re-attempt is performed
after 15 sec.

Short Call

Dedicated test will evaluate the


Network Access performance for
the voice service.

MSset a loop of MOC Call with 120 second and 10


secondinterval, If the call drops, a new call is
established after 10 sec. When there is a Refused Call
(call establishment failure), a call re-attempt is
performed after 10 sec.

Idle mode

Idle mode test will evaluate the


network radio link performance.

MS need keep the UE on idle mode without MOC or


MTC.

Walk test will evaluate the indoor


Network performance(Coverage,
CS and PS performance, Cell
Reselection from 2G to 3G).

MS set a MOC call. If the call drops, a new call is


established after 15 sec. In case of Refused Call (call
establishment failure), a call re-attempt is performed
after 15 sec.
Keep online and download files from the FTP server in
CQT mode
Check for 2G to 3G Cell Reselection on all CQT Points

CQT

2.6. Test legend definition


Rxlevel_Sub(Full)Rxqual_Sub(Full)
-10dBm<=Rxlevel
<65dBm
-75dBm<Rxlevel<=65dBm
-85dBm<Rxlevel<=2015-05-26

HUAWEI Confidential

Page6, Total28

2G Network DT Performance Pre Re-farming Report


75dBm
-95dBm<Rxlevel<=0<=Rxqual<=
85dBm
3
-120<=Rxlevel<=3<Rxqual<=4
95dBm
4<Rxqual<=7

C/I Average TX Power CS


20<C/I Average<=35
15<C/I Average<20
9<C/I Average<15
0<=TX Power
5<C/I Average<9
CS<10
0<C/I Average<5
10<TX Power CS<15
-30<=C/I Average<0
15<TX Power CS<20
20<TX Power CS<25

TA
0<=TA<2
2<= TA<4

10<= TA<20

110<=RLC
Throughput<260
80<=RLC
Throughput<110
40<= RLC Throughput
<80

20<= TA<63

10<=RLC Throughput<40

4<= TA<6
6<= TA<10

PS data throughput

25< TX Power CS<30


30<TX Power CS<=40

2.7. Test Day &Time0<=RLC Throughput<10

Test Dates 26/06/2014, 27/06/2014, 28/06/2014, 29/06/2014,


Test Dates 26/08/2014, 27/08/2014, 28/06/2014,
Test Time 6PM to 12AM

3. KPI Summary
3.1. CS DT KPI
3.1.1 Peak timeDT KPI
Before Re-farming
Count
Events
s

2015-05-26

After Re-farming
Count
Events
s

Call Setup Attempts

1830

Call Setup Attempts

Call Setup Failures

13

Call Setup Failures

Call Setup Success

1817

Call Setup Success

Call Dropped

14

Call Dropped

Call Complete

1817

Call Complete

Call Setup Success Rate

99.28%

Call Setup Success Rate

Drop Call Rate

0.77%

Drop Call Rate

HUAWEI Confidential

Page7, Total28

2G Network DT Performance Pre Re-farming Report


Handover Attempts

2760

Handover Attempts

Handover Failures

23

Handover Failures

Handover Success

2737

Handover Success

Handover Success Rate

99.16

Handover Success Rate

Serving Rx level (sub


cumulative) @ -85 dBm
Serving Rx Quality (sub
cumulative) @ 4

98.34
94.14

Serving Rx level (sub


cumulative) @ -85 dBm
Serving Rx Quality (sub
cumulative) @ 4

3.2. PS KPI
GPRS/EDGE CQT KPI as below

Before Re-farming

CQT Point

Download
Speed
(Kbits/s)

Upload
Speed
(Kbits/s)

CQT point 01

65.0

47.1

CQT point 02

55.3

35.6

CQT point 03

65.3

35.6

CQT point 04

72.0

44.4

CQT point 05

65.2

45.0

2015-05-26

After Re-farming

Coding
Schemes

CQT
Point

Download
Speed
(Kbits/s)

Upload
Speed
(Kbits/s)

Coding
Schemes

CS1, CS2,
CS3, CS4
CS1, MCS3,
MCS6,
MCS7,
MCS8, MCS9
CS1, MCS3,
MCS6, MCS7,
MCS8, MCS9
CS1, MCS1,
MCS5, MCS6,
MCS7, MCS8,
MCS9

CS1, MCS1,
MCS5, MCS6,
MCS7, MCS8,
HUAWEI Confidential

Page8, Total28

2G Network DT Performance Pre Re-farming Report


MCS9
Average

64.56

41.54

Average

4.1. Coverage Performance ResultsRxLev Full (dBm)

RxLev Full Plot

2015-05-26

HUAWEI Confidential

Page9, Total28

2G Network DT Performance Pre Re-farming Report

RxLev Full Distribution

2015-05-26

KHASB

BURAYMI

SOHAR

KHABOORA

HUAWEI Confidential

Page10, Total28

2G Network DT Performance Pre Re-farming Report

SUWAIQ

IBRI & RUSTAQ

4.1. Coverage Performance ResultsRxLev Sub (dBm)

RxLev Full Plot

2015-05-26

HUAWEI Confidential

Page11, Total28

2G Network DT Performance Pre Re-farming Report

RxLev Sub Distribution

KHASB

2015-05-26

BURAYMI

HUAWEI Confidential

Page12, Total28

2G Network DT Performance Pre Re-farming Report

SOHAR

KHABOORA

SUWAIQ

IBR I & RUSTAQ

4.1. Coverage Performance Results RxQual Sub

2015-05-26

HUAWEI Confidential

Page13, Total28

2G Network DT Performance Pre Re-farming Report

RxQual Sub Plot

RxQual Sub Distribution

2015-05-26

HUAWEI Confidential

Page14, Total28

2G Network DT Performance Pre Re-farming Report

KHASB

BURAYMI

SOHAR

KHABOORA

SUWAIQ

IBR I & RUSTAQ

4.1. Coverage Performance Results RxQual Full


2015-05-26

HUAWEI Confidential

Page15, Total28

2G Network DT Performance Pre Re-farming Report

RxQual Full Plot

RxQual Full Distribution

2015-05-26

HUAWEI Confidential

Page16, Total28

2G Network DT Performance Pre Re-farming Report

KHASB

BURAYMI

SOHAR

KHABOORA

SUWAIQ

IBR I & RUSTAQ

4.1. C/I Average Performance Results


2015-05-26

HUAWEI Confidential

Page17, Total28

2G Network DT Performance Pre Re-farming Report

C/I Average Plot

C/I Average Distribution

2015-05-26

HUAWEI Confidential

Page18, Total28

2G Network DT Performance Pre Re-farming Report

KHASB

BURAYMI

SOHAR

KHABOORA

SUWAIQ

IBR I & RUSTAQ

4.1. TX Power CS Performance Results


2015-05-26

HUAWEI Confidential

Page19, Total28

2G Network DT Performance Pre Re-farming Report

TX Power CS Plot

TX Power CS Distribution

2015-05-26

HUAWEI Confidential

Page20, Total28

2G Network DT Performance Pre Re-farming Report

2015-05-26

KHASB

BURAYMI

SOHAR

KHABOORA

SUWAIQ

IBR I & RUSTAQ

HUAWEI Confidential

Page21, Total28

2G Network DT Performance Pre Re-farming Report

4.2. Timing Advance Distribution Result

Timing Advance Plot

Timing Advance Distribution


2015-05-26

HUAWEI Confidential

Page22, Total28

2G Network DT Performance Pre Re-farming Report

2015-05-26

KHASB

BURAYMI

SOHAR

KHABOORA

SUWAIQ

IBR I & RUSTAQ

HUAWEI Confidential

Page23, Total28

2G Network DT Performance Pre Re-farming Report

4.3. Call Dropped Plot

4.1. GSM Handover Plot

4. CQT Performance Analysis


5.1. CQT point

2015-05-26

HUAWEI Confidential

Page24, Total28

2G Network DT Performance Pre Re-farming Report

CQT Points Locations

5. SummaryDaytimeCQT&Peaktime DT
7.1.Peak time DT Performance Summary
Category
CoveragePerformance
Mean
QualityPerformance
Mean
C/I Average Mean
Tx Power CS Mean
TA Mean

Item
RxLev Sub
RxLev Full
RxQual Sub

Pre Re-farming
Value
-67.43 dBm
-67.39 dBm
0.58

RxQual Full

0.86

C/I Average
Tx Power CS
TA

19.47
22.83
1.72

Post Re-farming
Value

7.3. CQT PerformanceSummary


Category
2015-05-26

Item
HUAWEI Confidential

Pre Re-farming

Post Re-farming
Page25, Total28

2G Network DT Performance Pre Re-farming Report

Coverage Performance Mean


Quality Performance Mean
C/I Performance Mean
Tx Power CS Mean
TA Mean

RxLev Sub
RxQual Sub
C/I Average
Tx Power CS
TA

Value
-63.00 dBm
0.42
18.07
11.38
0.17

Value

7.4. CSSR PerformanceSummary


The following form is a summary about peak time DT call access capacity:
Events

Pre Re-farming time


Counts
1830
13
1817
3323.31 ms

Post Re-farming time


Counts

Pre CQT Counts


15
0
15
3170.66 ms
0
15
100%

Post CQT Counts

Call Setup Attempts


Call Setup Failures
Call Setup Success
Call setup timing delay
Call Dropped
14
Call Complete
1803
Call Setup Success Rate
99.28%
The following form is a summary about CQT call access capacity:
Events
Call Setup Attempts
Call Setup Failures
Call Setup Success
Call setup timing delay
Call Dropped
Call Complete
Call Setup Success Rate

7.5. HSR PerformanceSummary


The following form is a summary about peak time DT mobility:
Events
2015-05-26

Pre Re-farming time


HUAWEI Confidential

Post Re-farming time


Page26, Total28

2G Network DT Performance Pre Re-farming Report


Counts
2760
23
2737

Counts

Pre CQT Counts


0
0
0
N/A

Post CQT Counts

Handover Attempts
Handover Failures
Handover Success
Handover Success Rate
99.16%
The following form is a summary about CQTmobility:
Events
Handover Attempts
Handover Failures
Handover Success
Handover Success Rate

7.6. CDR PerformanceSummary


The following form is a summary about peak time DT call retain ability:
Pre Refirming
Post Refirming
time Counts
time Counts
Call Dropped
14
Call Setup Success
1817
0.77 %
Drop Call Rate
The following form is a summary about CQT call retain ability:
Events

Events

Pre CQT Counts

Call Dropped
Call Setup Success

0
15

Drop Call Rate

0%

PostCQT Counts

7.7. PSCQT Throughput Summary


Before Post Re-farming

CQT Point

Download
Speed
(Kbits/s)

Upload
Speed
(Kbits/s)

CQT point 01

65.0

47.1

CQT point 02

55.3

35.6

CQT point 03

65.3

35.6

CQT point 04

72.0

44.4

2015-05-26

After Post Re-farming

Coding
Schemes

CQT
Point

CS1, CS2,
CS3, CS4
CS1, MCS3,
MCS6,
MCS7,
MCS8, MCS9

CQT point
01

CS1, MCS3,
MCS6, MCS7,
MCS8, MCS9
CS1, MCS1,
MCS5, MCS6,
MCS7, MCS8,
MCS9
HUAWEI Confidential

Download
Speed
(Kbits/s)

Upload
Speed
(Kbits/s)

Coding
Schemes

CQT point
02

CQT point
03
CQT point
04
Page27, Total28

2G Network DT Performance Pre Re-farming Report

CQT point 05

65.2

45.0

CS1, MCS1,
MCS5, MCS6,
MCS7, MCS8,
MCS9

Average

64.56

41.54

CQT point
05
Average

7.8. Conclusion
This report shows cluster05 network DT performance analysis before&after swap. Overall coverage (like rx level,
rx quality, C/I average, TX Power CS) is better from pre swap. CS KPIs (like call setup success rate, call drop
rate, handover success rate, call setup delay time) are also improved after swap. In all CQTs DL & UL throughput
have have shown improvement.We are looking forward to have closer cooperation with Omantel in future, to
provide more of our world leading products and services for Omantel.

2015-05-26

HUAWEI Confidential

Page28, Total28