Beruflich Dokumente
Kultur Dokumente
REPORT
TATA STEEL LTD
Report
Date:
Title:
Submitted
by:
Mr. ABHISHEK
B.TECH
DHIMAN
(OPERATIONS)
CHANDIGARH GROUP OF
COLLEGES(GHARUAN CAMPUS,MOHALI)
Duration:
Project
Guide:
ACKNOWLEDGEMENT
I take this opportunity to express my sense of
thankfulness to all those who guided me and helped me
whenever going the second difficulty and road ahead
was not visible.
I extend my special thanks to Mr. DAVID WILLIAMS
(SENIOR MANAGER (Engineering & projects) for giving
me this opportunity to enhance my knowledge. I am
also
thankful
to
Mr.Sagar
Bhosekar
(Operations
PROBLEM STATEMENT
PROBLEM DEFINITION:
To study the handling time of wire drawing machine no 107 &
108 and to find a solution to reduce the same
OBJECTIVE :
EXECUTIVE SUMMARY
Project report on To study the handling time of wire drawing
machine no 107 & 108 and to find a solution to reduce the same
TATA STEEL SS-Plant is located at tarapur MIDC at boisar. This
plant is designed to manufacture steel spring wire rods. This plant
comprises of many automatic and manual wire drawing machines.
This project is study of various operations of wire drawing
machine which involves in manufacturing of wires. This operations
requires certain time to complete and this is considered as handling
time.
The project shows the impact of handling time on production,
workers working efficiency and recommended process time for
various operational activities. The operational activities which takes
long setting time or operation time like Program Change, Killing
Setting, Wire Break Issues, Operational Issues, etc, and their impact
on productive time. As this operations take longer time, production
decreases, so this time should be decreased if possible by finding
other method.
Increasing the production with less cost and time and
considering the essential factors is ultimate goal. To achieve this
INDEX
SR
NO.
CONTENT
PAGE
NO.
06
09
15
4
5
6
7
8
9
10
11
17
18
19
26
33
Engineering
Materials
Services
Information
technology
and
communicatio
n
TATA Business
Energy
Consumer
Products
Chemicals
M
I
S
E
C
T
h
n
o
e
a
g
e
&
r
n
t
v
e
m
r
n
i
su
g
ic
r
e
ia
y
ic
m
e
e
s
ls
a
r
e
in
ls
r g
C
P
r
o
o
m
d
u
m
cu
t
sn
ica
Pe
r ce nta g
e
o n
s
t
i
Tata
manufacturing
Technology
CMC,
Computational
research
steel
producers,
with
operations
in
26
The Tata Steel Group, comes under the material sector of the Tatas
business sectors. It had a turnover of US$ 24.82 billion in FY 2012- 2013
and is a Fortune 500 company.
Tata Steels vision is to be the worlds steel industry benchmark
through the excellence of its people, its innovative approach and overall
conduct. Underpinning this vision is a performance culture committed to
aspiration
targets,
safety
and
social
responsibility,
continuous
2.Long Products
4. Bearings
3. Agrico
5. Tata Tubes
6. Tata Wiron
2.2. TATA STEEL GLOBAL WIRES
Tata Steel has brought all its wire manufacturing under the scope of
the Global Wires Business. Manufacturing facilities have spread across
India, China, Thailand and Sri Lanka. The Company has fully integrated
manufacturing cycles, from sourcing of raw materials to in-house steel
making and wire rod rolling facilities. In India, the division is setting up a
world class manufacturing facility at Tarapur and also modernising the
existing facilities at The Indian Steel & Wire Products in Jamshedpur. The
Wire Division has been the sole supplier of pre-stressed concrete strands
used in the construction of precast segments for the 4.7 kms, 8-lanecable-stayed Bandra-Worli Sea link at Mumbai, India.
Fig 3: Global Division
2.3. TATA STEEL WIRE DIVISION, INDIA
Tata Steel Wire Division (TSWD) is the pioneer of steel wire industry
in India and today is the largest manufacturer and leader in India. It was
started as Special Steel LTD in 1958. And it was acquired by TATA Steel in
1984. It had started of as an umbrella ribs manufacturer and now it is
GLOBAL
WIRES
LANKA
SPECIAL
STEELS
LTD., SRI
LANKA
TATA
STEEL
WIRE
DIVISION
WUXI
JINYANG
METAL
PRODUCTS
, CHINA
SIAM
INDUSTRIA
L WIRE CO.
LTD.,
THAILAND
INDIAN
STEEL &
WIRE
PRODUCTS
LTD.
serving four industries of Auto, Construction, Power and Retail. Tata Steel
Wire Division was one of the founder members and has over the years
managed to get many of the medium sized wire manufacturers under
one trade association The Steel Wire Manufacturers Association of India
(SWMAI) to ensure that there is a platform for sharing concerns and a
single-body
representative
customer/supplier.
Wire
with
Division
has
regulatory
thus
authorities
adopted
the
and
following
Product
s
Institutio
nal
Automot
ive
-Tyre
bead
wire
-Spoke
wire
-Spring
wire
Retail
Infrastruc
ture
Power
Anneale
d
-LRPC
-PC
-Cable
Armour
-ACSR
Card
Clothin
g Wire
Galvani
sed
Welding
TATA
STEEL
WIRE
DIVISION
1. WIRE
ROD MILL
(WRM) AT
TARAPUR.
TARAPUR
WIRE
PLANT
(TWP) 1
TARAPUR
WIRE
PLANT
(TWP) 2
SPRING
STEEL
(SS)
PLANT
2.7.
ARCELORMITTAL.
ESSAR STEEL.
JSW STEEL.
SAIL.
VISA STEEL.
DIVISION.
STEEL WIRE
MANAGING DIRECTOR
DEPUTY MANGING DIRECTOR
VICE PRESIDENT LONG PRODUCTS
EXECUTIVE IN CHARGE
CHIEF
HEAD SR.MANAGER
MANAGER
ASSOCIATE
STAFF
GROUP LEADER
WORKERS
1)VALUES :
INTEGRITY
UNDERSTANDING
UNITY
RESPONSIBALITY
2) VISION STATEMENT :
3) MISSION STATEMENT :
is
accomplished
by
combination
of
tensile
and
compressive stresses that are created by the pulling force at the exit
from the die and by the die configuration.
1)
2)
3)
4.WIRE
DRAWING
PROCESS
ACTIVITY
SEQUENCE DIAGRAM
STEP 1
RM LOADDING
STEP 6
CONTINUE STEP 4 &
5
(AS PER PROGRAM
HOW MANY DIES TO
PASS)
STEP 7
PASSING WIRE
THROUGH FINAL
PASS
STEP 2
RM WELDING
STEP 3
POINTING WIRE
STEP 5
LOADING WIRE
TO DRUM
STEP 4
PASSING WIRE
THROUGH DIE
BOX
STEP 8
KILLING
SETTING
STEP 9
TIE WIRE TO
COIL CATCHER
STEP 11
DISPACTH
STEP 10
MOVING COIL
CATCHER TO
DIVIDE COIL.
1) RM LOADING :
LOAD COIL
TO
PAYOFF
LIFT COIL
BY CRANE
PROCESS DISCRIPTION:
This is the process where operators lift the coils or the RM by the
crane from storage area and load to the Payof for further
processing.
This handling process usually takes time of 8-10 minutes
COMPARATIVE STUDY:
24
23
Time in min.
22
21
20
19
K.B.H
V.S.G
S.Y
S.B.D
P.B.S
V.G.B
DISCRIPTION:
2) WELDING WIRES
CUTTING WIRE
POINTING
WELDING
FINISHING
GRAPHITE PASTING
PROCESS DISCRIPTION:
This is the process where operators join the wires at payof for
the continuation of wire drawing process so that workers need
not repeat the whole process of passing wires through each die
block.
The operators carry out diferent activities in wire joining like
pointing, welding, finishing and graphite pasting. The operators
ensure the welding is proper and will not break.
COMPARATIVE STUDY:
8
cutting
pointing
weilding
finishing
0
V.G.B
Y.A.M S.B.D
S.Y
K.KG
V.S.G K.B.S
P.B.S
graphite pasting
DISCRIPTION:
WIRE UNLOAD
FROM DRUM
JOIN WIRE
BREAK
PROCESS DISCRIPTION:
LOAD WIRE TO
DRUM
This is the process where operators join the wire which breaks
anywhere in the wire drawing machine while in process. The
operators carry out diferent activities in wire break like wire
unloading from machine, wire joining pointing, loading wire
again to drum. The operators ensure the welding is proper and
COMPARATIVE STUDY:
Time in Minutes 42
40
38
36
Name of Operators
DISCRIPTION:
3) PROGRAM CHANGE :
UNLOAD
MACHINE
RM
LOADDING
RM WELDING
DIE CHANGE
POWDER
CHANGE
POINTING
WIRE
LOADING
WIRE TO
DRUM
PASSING
WIRE
THROUGH
ALL DIE BOX
KILLING
SETTING
DISPACTH
MOVING
COIL
CATCHER TO
DIVIDE COIL.
TIE WIRE TO
COIL
CATCHER
PROCESS DISCRIPTION:
in sequence.
First the operator removes the powder and the old wire from the
machine. Then he loads the RM to the payof and welds the two
wire. This process takes more time than all other processes.
Then the operator points the wire by pointing machine so that
the diameter of wire is reduced to pass form all dies .the wires is
then passed from first die block and load to roller drum using
dog chain. Same way it is passed through the die blocks as per
recommended
COMPARATIVE STUDY:
DISCRIPTION:
The above graph shows the time taken by the activities during last
six months.
The blue bar in graph shows the time taken by diferent activities
and red line shows the action to be taken on activities which cuts at
80.
To reduce the handling time and increase the productive time the
activities to which red line cuts at 80 should be focused first as this
DISCRIPTION:
The above graph shows the wire break held at which block of
machine. The blue bar in graph shows the time taken by diferent
action.
Here researcher found that Block no 1, Block no 2, Block no 3,
and Payoff Entanglement are major problems of wire break in
machine no 107.
IDLE TIME
30
25
20
15
10
5
0
IDLE TIME
DISCRIPTION:
The above graph shows the wire break reasons of machine no 107.
The blue bar in graph shows the time taken by diferent reasons of
wire break during last six months.
7.4 DISCRIPTION:
The above graph shows the time taken by diferent activities under
80.
To reduce the handling time and increase the productive time the
activities to which red line cuts at 80 should be focused first as this
DISCRIPTION:
determined approximately.
The program change time can vary from operator to operator,
depending on his efficiency, skill and experience.
DISCRIPTION:
The above graph shows the time taken by diferent activities under
the Program Change.
DISCRIPTION:
The above graph shows the time taken by diferent activities under
the Program Change. The graph is based on observation during
internship .
In the above graph there is comparison of actual time taken for
program change by operators and recommended time to be taken
by operators.
Here the researcher found that actual time taken by the operators
due
to
high
The above graph shows the time taken by the activities during last
six months.
The blue bar in graph shows the time taken by diferent activities
and red line shows the action to be taken on activities which cuts at
80.
To reduce the handling time and increase the productive time the
activities to which red line cuts at 80 should be focused first as this
has major impact and then rest of activities.
W/B AT 108
70
70
69
68
67
66
65
64
63
62
61
67
64
IDLE TIME
DISCRIPTION:
The above graph shows the wire break held at which block of
machine. The blue bar in graph shows the time taken by diferent
action.
Here researcher found that Block no 1, Block no 2, Block no 3,
and Payoff Entanglement are major problems of wire break in
machine no 107.
72
70
IDLE TIME
DISCRIPTION:
The above graph shows the time taken by diferent activities under
the Program Change.
DUTTY DESIGNED
:-
1st
(OTO) type.
blocks.
blocks.
with str
-aightners and non riding stripper.
of spec
-Ial alloy forged steel and the drawing portion
induction harde
-ned. To 55-58 HRC For high wear resistance and are
fastened
To cast iron hub.
Cooling Of Blocks And DiesA complete piping system for water cooling of the
blocks and
0
to 32 c
Additionally
Types Of
Bearings
Taper Roller
Brg.
Taper Roller
Brg.
Deep Groove
Ball Br
1
2
3
Bearing No.
33024
30209 j2/Q
6005-2Z
3302
33024
33024
23122CC/W33
33024
23122CC/W33
Stripper Assembly
1
51104
S.T. Assembly
1
3303A-2Z
6305-2Z
22207-CC
6213-2Z
6213-2Z
6208-2Z
6005-2Z
61907-2Z
Drive Assembly
1
2
30316J2
30314J2/Q
Roller Assembly
1
2
6004-2Z
6305-2Z
6001-2Z
6305-2Z
TION
FOR
Sr.
NO.
Types
of
Lubrica
nt
Grade
Applicat
i-on
Grease
oil
change
Interval
s
Grease
Servog
en 2 or
3
Bearings,
slides
chain
and
guides
Every
200
operatin
g hours
ISO VG
220
Gear
Box,Pivchain
Type
Change
every
10000
operatin
g hours
Change
every
20000
operatin
g hours
Fill Every
15 Days
Once
Gear
Box Oil
Hydrauli
c
POWRE
Pack oil
ISO VG
68
Hydrauli
c
Cylinders
Pneuma
tic
Lubricat
or Oil
ISO VG
10
Lubricati
on of
Pneumat
ics
DRAWINGS MACHINE
LUBRICA
CHART
WIRE
SUGGESSIONS
1) Lunchtime could be utilized for cleaning and lubricating machine
and machine parts to ensure longetivity.
2) M.M.D and E.M.D work of regular maintenance should be performed
during long operations like program change
3) SMED if implemented can reduce the handling time and can lead to
increase in productive time.
4) DIE SET should be directly changed instead of removing it and
changing die in it, this will result in saving the time of handling and
result in increase of productive time .
5) Payof should be installed with hydraulic jacks as the arms are
heavy and need to lift them manually to load coils.
6) Crane should be utilized alternatively for coil loading, coil catcher
unloading as it is used for both the 107 and 108 machine.
BIBLIOGRAPHY
1)
2)
3)
4)
5)
www.Wikipedia.com
www.TataSteel.com
www.
Companys reports
Daily CommunicationBook
6) Machine Record Book.