Beruflich Dokumente
Kultur Dokumente
1.
What is a project?
2.
What is a program?
3.
What is a portfolio?
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
What is workaround?
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
What is the sequence of actions that should happen when an issue happens?
52.
53.
54.
55.
56.
What is oligopoly?
57.
What is Ethnocentrism?
58.
59.
60.
Answers:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Last step in project closing is gather lessons learned and archive project info
(Organization Process Assets updates) for future use
Choose project with high NPV (i.e high net present value)
Value engineering is less costly method to deliver same scope without
performance degradation
Project sponsor issues project charter
12.
13.
14.
Quality audits, process analysis (includes root cause analysis) are some
techniques in Perform Quality Assurance
15.
16.
17.
18.
Decision tree components are square - decision node, circle- chance node and
triangle - end of branch.
19.
20.
21.
22.
23.
24.
25.
Product scope means the features and functions of the product or service being
built. Project scope means the work that's needed to build the product.
26.
Free float is time that an activity can be delayed from it's early start date without
delaying early start of any immediately following schedule activities.
27.
Total float is time that an activity can be delayed from it's early start date without
delaying the project finish date.
28.
Project scope statement contains deliverables and also the work required to
create those deliverables.
29.
Process is considered out of control when a data point in control chart exceeds
control limit or if seven consecutive points in control chart are above or below (i.e on
one side) of the mean.
30.
31.
32.
33.
34.
Control account is management control point where scope, cost and schedule
are integrated and compared to the earned value for performance measurement.
35.
36.
37.
T&M contracts are hybrid type of contractual agreements that could contain
aspects of both cost-reimbursable and fixed-price type arrangements.
38.
Seven basic tools of quality are Cause and Effect (Fishbone or Ishikawa)
Diagrams, Control Chart, Flowcharting, Histogram, Pareto Chart, Run chart and
Scatter Diagram.
39.
40.
Ways to handle negative risks are Avoid, Transfer, Mitigate and Accept.
41.
Ways to handle positive risks are Exploit, Share, Enhance and Accept.
42.
43.
Maslow's hierarchy of needs from bottom to top are Physiological needs, safety
needs, social needs, self esteem needs and self actualization needs.
44.
Different types of power are Reward power, Coercive (penalty) power, Legitimate
power, Referent power and Expert power.
45.
46.
47.
48.
Gold plating is when the team adds more work to the project that was not
requested by the sponsor or client. It is not scope creep.
49.
The point of total assumption is the point at which the seller assumes the costs.
In a firm fixed price contract, this is the point where the costs have gotten so large
that the seller basically runs out of money from the contract and has to start paying
the costs.
50.
51.
When an issue happens, analyze impact of issue -> submit change request -> if
approved, update schedule and scope baselines -> implement the change.
52.
The scope baseline is made up of Project Scope Statement, WBS and the WBS
Dictionary.
53.
Marginal analysis - The best level of the quality is reached at the point where the
incremental revenue being gained from improvements equals the incremental cost
being spent to secure it.
54.
A Zero Sum reward system is a win-lose recognition program. For example, with
an employee of the month program their will only be one or two team members who
will win the award each month. Reward programs should be more win-win.
55.
56.
Oligopoly - There are few sellers and action of one seller will have impact on
other sellers prizes.
57.
58.
59.
60.
http://www.maxwideman.com/papers/resource/s-curves.htm
A complete determination of the project status and projections to final completion for
management action can perhaps best be tracked by an integrated cost/schedule system
or technique known as "Earned Value and Performance Measurement" (Kerzner 1989).
The earned value, i.e. the Budgeted Cost of Work Performed (BCWP), is determined at
regular intervals during the course of the project. At the same time, the Actual Cost of
Work Performed (ACWP) is also determined, and both are compared to the baseline plan
which is the Budgeted Cost of Work Scheduled (BCWS). By presenting these results
graphically as S-curves, the variances in cost and schedule can readily be seen, and by
analyzing the results relative to the baseline plan S-curve, estimates can be made of
anticipated variations at completion. The key elements of the technique are shown in
Figure 3.
Question from
https://www.linkedin.com/grp/post/5143077-5856287978602651652
http://singhvikash.blogspot.sg/2013/11/pmp-questions-on-costmanagement.html
Q
You have received the following estimates for a complex activity that is critical to the success
of your project. The most likely estimate is $40, the optimistic estimate is $36, and the
pessimistic estimate is $54. Find expected activity cost and standard deviation of this
activity?
A. $ 45, 9
B. $ 45, 3
C. $ 42 ,3
D. $ 42 ,9
Dear All,
Thanks for attempting this question, and most of you have answered it correctly.
Choice C is the correct answer. The expected activity cost is calculated this way: (4 * most likely +
optimistic + pessimistic) / 6.
Therefore, the answer is (4 * 40 + 36 + 54) / 6 = 42. (round figure)
SD= (Pessimistic - Optimistic) / 6 = (54 - 36)/6 = 3.
Please visit the below link for more numerical questions
http://www.whizlabs.com/lp/link/pmp-certification-numerical-questions.html
A project manager made 3-point estimates on a critical path and found the following
results:
Assuming 3 sigma precision level for each estimate, what is the standard deviation
of the allover path?
http://pmzilla.com/3-point-estimates
Some points to remember:
In order to calculate the standard deviation of more than one task (on critical
path), calculate the standard deviation of each task, take a square of standard
deviation of these tasks, sum up the square value, and at the end, calculate the
square root of this summed value.
Easy way to remember the formula between Standard Deviation and Variance
is
o
V=(SD)
Apply above mentioned points for calculating the SD of allover path. Calculate SD of
individual task:
SD of A = (p-o)/6= (24-12)/6= 2
SD of B = 6/6 =1
SD of C = 12/6 = 2
SD of D = 18/6 = 3
SD of E = 18/6 = 3
V of A= (SD of A) = 4
V of B = 1
V of C = 4
V of D = 9
V of E = 9
4+1+4+9+9 = 27
SD = Square root of V