OCTOBER 2009

SAFETY ALERT FLASH


RISKS LINKED TO STORED ENERGY

Some examples for complementary


operation after lock-out
Before any intervention:
− Put the arm of the reclaimer on the
material stock pile or on the ground before
intervening
− Balance the kiln and the mill in order to
prevent movement
− Unload the compressed fluids or isolate
the circuits under pressure by opening a purge
valve and by discharching the pressure with
Several accidents have occurred in the the tap below the isolating valve of the circuit
past due to stored energy. The EI under pressure
standard will be focussing on the − Ground the electrical circuit or energized
importance of releasing the stored equipment.
energy before any work.
For example, one of the most dramatic When the zero-energy state cannot be
took place in LICHTENBURG (South reached, take appropriate measures. For
Africa Cement) in September 2008 example:
which took the life of an electrician. − Block the equipment appropriately
Most of the root cause analyses after (unbalanced crusher rotor, equipment being
these types of accidents show that dismantled…)
being unaware of the risk of sudden − Block systematically the mobile piece of a
movements of machinery is one of the bucket elevator or an inclined unbalanced belt
main causes. conveyor which can not be unloaded or that
Accidents could happen because the will be unbalanced by the work (dismantling of
stored energy is not obvious (the bucket, intervention on the belt of the
machine may be stopped and even conveyor …).
locked out). Stored energy could be
present in the following forms and Such stored energy risks can be
could result in serious accidents or prevented by:
fatalities: − Using this alert to raise general
awareness around stored energy
− The weight of the equipment or a
− Ensuring measures are taken into account
piece of the equipment
in the risk analysis to remove or isolate the
− The weight of the material in a kiln stored energy.
or in a mill under load − Follow the mandatory LOTOTO sequence
− The weight of the material in a from the LOTOTO Advisory (including Step 6:
bucket elevator or in an inclined Zero Energy State)
conveyer belt suddenly stopped
− The weight of a piece of
equipment unbalanced by the
intervention (partial dismantling of
hammers on a crusher or buckets on
an elevator…)
− Compressed
Group Communicationsfluids (air, oil, liquid
– to Sr Management, BU managers, Health & Safety & Communications networks for posting
and discussion at all sites
OCTOBER 2009

SAFETY ALERT FLASH


RISKS LINKED TO STORED ENERGY

Pictures of the Lichtenburg plant below which illustrate the difficulty in identifying the lethal risk linked to stored
energy for what is considered to be a simple task at a material reclaimer.

Pictures of the Stockbridge site (US A&C) above which illustrate the
wheel loader crushing fatality linked to stored energy in hydraulic lines.

The bucket, which was initially extended to allow the mechanic to access the hydraulic lines,
contracted and crushed the mechanic when the hydraulic lines were de-pressurized.

The reclaimer is in working position. The disintegrated low speed reducer


Purpose of the task: change the motor which controlled the boom incline
cable gland
The electrical lockout was carried out but not the mechanical lockout. A risk analysis was not carried out because
the task was considered simple. The energy stored by the arm of the reclaimer in a high position while the employee
was working on the boom incline control motor was not taken into account.

Mechanic was caught and crushed in pinch


Mechanic accessed the
point hydraulic
here
lines indicated here, in this position

Group Communications – to Sr Management, BU managers, Health & Safety & Communications networks for posting
and discussion at all sites