Beruflich Dokumente
Kultur Dokumente
Basis of Design
Memorandum
Prepared by :
Consorcio
ICBA
July, 2003
TABLE OF CONTENTS
Section No.
Title
Tab No.
1.0
Introduction
1.1 Project
1.2 Location
1.3 Project Number
1.4 Owner
1.5 Client
1.6 Project Description
2.0
Basis of Design
2.1 Client Furnished Data and Assumptions
2.2 Applicable Codes and Standards
3.0
Methodology
3.1 Pipeline Route Location
3.1.1 Pipeline Corridor
3.1.2 Buildings Intended for Human Occupancy
3.1.3 Locations Classes
3.2 Line Lengths
3.3 Right-of-Way and Trench
3.4 Line Sizing
3.5 Wall Thickness Formulae
3.5.1 Line Pipe Cross Country
3.5.2 Railroad and Road Crossing Pipe
3.5.3 River Crossing Pipe
3.5.4 Charpy Values
3.6 Field Bends
3.7 Weld Bevels
3.8 Blowdown Sizing
3.9 Mainline Valve Setting
3.10 Scraper Traps
3.11 River Crossing Location and Design
3.12 Wet Land Area Design
3.13 Meter Stations
3.14 Pressure Alert Valve
3.15 SCADA System
3.16 Cathodic Protection and Monitoring System
3.17 Hydrostatic Test
Section No.
Title
4.0
Calculation Results
4.1 Location Classes and Design Factor, F
4.2 Line Lengths
4.3 Line Sizing
4.4 Wall Thickness Formulas
4.4.1 Maximum Allowed Operation Pressure
4.4.2 Railroad and Road Crossing Pipe
4.4.3 River Crossing Pipe Wall Thickness
4.4.4 Calculated Charpy Valves
4.5 Weld Bevels
4.6 Blowdown Sizing
4.7 Mainline Valve Settings
4.8 Scraper Traps
4.9 River Crossing Design
4.9.1 Major River Crossings
4.9.2 Minor River Crossings
4.9.3 Creek Crossings
4.10 Wetland Areas
4.11 Meter Stations
4.12 Pressure Control
4.13 SCADA
4.14 Cathodic Protection and Monitoring System
4.15 Hydrostatic Test
5.0
Hydrostatic Calculations
MAWP Pipe
Blowdown Sizing
Stresses in Road Railroad Crossing Pipe
Buoyancy Calculation for wetlands
Ultrasonic Meter Flow rates
Control Valve Sizing
Minor River Scour Calculations|
Tab No.
LIST OF EXHIBITS
Section No.
Title
1a
1b
2
3
4a
4b
4c
4d
5
6
7
8
9
Tab No.
6
6
6
6
6
6
6
6
6
6
6
6
6
LIST OF TABLES
Table No.
1
2
3
4
5
6
7
Title
Tab No.
7
7
7
7
7
7
7
BASIS OF DESIGN
1.0 Introduction
1.1 Project Margarita EFP Project - Flow Line & Export Pipelines
1.2 Location
0670 8300
1.4 Owner/Client
Address:
1.5 Client
Address:
Consorcio ICBA
Km. 3 Carr. Cbba Casilla : 3616
Telfono Piloto: 352 9270
Fax : 352 3713
Santa Cruz de la Sierra
Bolivia.
Management:
Project Director:
Mel Schulze
Cell Ph.:
Ph.:
Fax:
Project Manager:
Jack Bogan
Engineering Manager:
John Belew
Basis of Design
2.1
Pipeline Diameters:
W.T. Grade
Design Pressure:
Pipe Lengths:
Gathering Sys.
Export Liquid Line
Export Gas Line
8.625O.D.
6.625O.D.
10.750O.D.
1.700 psi
1.770 psi
30 Km
54 Km
51 Km
1.500 lbs.
900 Lbs.
900 Lbs.
Corrosion Allowance:
3 mm.
3 mm.
3 mm.
Design Factor:
Location Class 1
River Crossing
Fabrication
0.72
0.72
0.72
0.72
0.72
0.72
0.72
0.72
0.72
External Coating:
Internal
Joint Coating:
Specify Gravity:
0.600
Standard Conditions:
Temperature
Pressure
60 F
14.73 psia
Rigth-of-Way Width:
15 meters Permanent
Block Valves: Full Opening Ball Type spaced to meet Code requirements
2.2
Meter Stations:
Gas Meter is Multi-path Ultrasonic and Liquid Turbine
Applicable Codes and Standards
The last revision of all codes, standards, and applicable governmental
regulations shall be followed except as modified to be more stringent by these
criteria. Legal requirements shall have preference over these criteria unless the
authorized legal authority grants an exception.
Unless otherwise noted, references made herein to codes, standards and
specifications are to the latest edition.
Methodology
3.1 Pipeline Route Location
3.1.1
Pipeline Corridor
The Gathering & Export Pipelines will be located in a corridor
extending 500 meters each side of the pipeline location supplied by
MAXUS Bolivia Inc.
A map showing the preliminary route location is included as Exhibits
1a and 1b.
Any pipeline relocation outside of this corridor will be submitted to
MAXUS Bolivia Inc. for approval. Explanations for the recommended
relocation are to given.
3.1.2
3.1.3
Location Classes
Gas pipeline will be divided into random sections of 1.5 Km. in length
such that the sections will include the maximum number of buildings
intended for human occupancy.
The location Class and Design Factor F will then be determined in
accordance with ASME B31.4 & B31.8.
Q (38.774)(10 )(d
Where:
2.5
T
)( F ) b
Pb
P12 P22
(G )(T f )( Z avg )( L)
0 .5
Line Pipe
INTEC Engineering uses the Steel Piping Design Formula from ASME
B31.4 & B31.8 to determinate the appropriate wall thickness and/or
maximum allowable working pressure/design pressure of the line in
accordance with ASME B31.4 & B31.8 requirements.
The formula is as follows:
P=
Where:
3.5.2
P
S
=
=
D
T
F
E
T
=
=
=
=
=
2S t
FET
D
3.5.3
3.5.4
Charpy Valves
In detail design description in Project Execution Plan.
3.6
Field Bends
Large angle bends shall be broken down into several smaller angles to insure
the maximum allowable bend per joint of pipe is not exceeded. The maximum
field bend per joint of pipe shall not exceed 1- degrees per pipe diameter
length after allowance for leading and trailing tangents required by bending
machine. An internal mandrel will be specified for all field bends. All bends
shall be located within the right of way. Wrinkle or mitre bends will not be
allowed.
3.7
Weld Bevels
All joints will be designed for a 100% joint efficiency. Bevels and transitions
will comply with B31.4 & B31.8 requirements.
3.8
Blowdown Sizing
The following formula will be used for determining valve sizing for pipeline
blowdown time:
(0.0588)( P1 )1 / 3 (G )1 / 2 ( D 2 )( L )( Fc )
Tm=
( d ) 2 ( n)
Where:
Valves for F c
Fc
1.6
1.8
2.0
3.2
Regime analysis
-
Hydrology
-
Routing the SPF and/or the PDF through the stream crossing. All
routing will use Mannings Equation:
Q=
Where:
1.486
(A)(R 2 / 3 )(S 1 / 2 )
n
Field Reconnaissance
Potential problem areas will be studied in detail including potential cutoffs,
evidence of valley wall instabilities and crossing constructability.
Stream Surveys
Stream surveys consisting of:
-
Channel Hydraulics
Depth of scour will be calculated by using Blenchs equations for regime
depth:
dr =
Q2
Fb
Where:
Q=
Qscour
= Unit discharge
bavg
d r = regime depth
b = channel breadth
F b = bed factor = F bo ( 1 + 0.12C )
F bo = zero bed factor
C = bed load charge
The value of F bo is determined from one of the following equations
(whichever is greater):
F bo = 48
D 0.5
d
or
F bo = 7.3 D 0.25
Where:
d=
D=
Conditions
Bankfull
1.4 2.50
1.4 1.75
1.5 2.00
1.75 2.50
1.75 2.50
1.4 4.0
1.4 2.5
2.0 3.0
2.5 4.0
2.5 4.0
Depth of Pipe
d p =ds +dd +S
Where:
Bank vegetation
3.10
A special design will be used for all the wetlands areas in order to provide
sufficient pipeline negative buoyancy and to mitigate damage to the
environment.
3.11
Meter Stations
Qf
V
Qf =
Tf
Pb
Q
x
x
xZ
P1
1440 Tb
Pf Tref Z ref
Pref T f Z f
3.12
Pressure Alert Valve (PAV) will be sized and installed at terminal of each
pipeline to protect plant from overpressure. Each PAV will have a monitoring
valve, which will be set at a difference range than the PAV and will operate
only when PAV fails to alert the pressure to meet delivery requirements.
The valve sizing will be done using the following formula:
Q=
Where:
3417
520
x C g P 1 SIN
GT
C1
P1
DEG
C 1 = C g /C v
C g = gas sizing coefficient
G = gas specific gravity
P 1 = valve inlet pressure, psia
3.13
SCADA System
3.14
Project design drawing will show the type and location of all cathodic
protection test stations to be installed.
Test stations will be installed, where possible, in areas that are reasonably
accessible to collect test data. Property or ownership boundaries will be the
generally preferred locations.
Test Stations will be installed at intervals of two kilometers. The test stations
installed at specific locations as outlined below will be counted toward
achieving this spacing.
SPECIFIC LOCATIONS
-
At high voltage power transmission lines at the point where the power
line crossed the pipeline, or, in the case of a parallel power line, at the
points on the pipeline where the power line becomes and ceases to be
parallel to the pipeline. When practical and the power line towers are
metallic, the test station will be physically located near a tower.
3.15
Hydrostatic Test
and 2,375 psig (1,900 psig for 8); and a maximum pressure that will produce
a hoop stress equal to 110 % SMYS.
During the design phase preliminary hydrostatic test sections will be plotted
on the profile sheets to determinate if pipe yielding will occur during test
elevation differential.
Consideration will be given to installing short sections of heavy wall pipe in
low and other critical areas to prevent pipe yielding and/or to reduce the
numbers of test sections.
If the test sections are modified, they shall be submitted to INTEC
Engineering for review and approval.
Calculation Results
4.1 Location Classes and Design Factors F
Initially the entire line is classified as Location Class 1 with a design factor
0.72. The house count and Location Classes are summarized in Table 1.
The House Count performed along with the survey confirmed the Location
Class 1 classification for most of the line.
The pipe for Location Class 1 will be:
o 8.625O.D.
W.T. Grade
6.625O.D.
10.750O.D.
Line Pipe
Table 4 summarizes the MAWP of the pipe to be used for the different design
factors in order to achieve the MAOP of 1,700 psig. for 6 & 10, and 1,900
psig for 8.
4.4.2
Wall thickness calculations for major river crossings will be based a Design
Factor of 0.60. The pipe is to be manufactured by the ERW process.
Calculations will be based on river water with a specific gravity of 1.25.
Wall thickness calculations for minor river crossing will be based on a Design
Factor of 0.72. The pipe is to be manufactured by the ERW process.
Calculations will be based on river water with a specific gravity of 1.25.
Special construction pipe provided with a continuous concrete coating will be
used on the minor river crossing.
The pipe will be installed at a minimum depth of 10 ft. (3 meters) from the
lowest point of the river bed. These crossings will be open cut.
Pilcomayo River
Gathering Line will crosses on the existing bridge.
Palos Blancos River
Exportation Line will installed at a minimum depth of 10 ft. (3 meters)
from the lowest point of the river bed. These crossings will be open cut.
Exact location of the crossing will be show in the Typical Major River
Crossing Exhibit.
Isiri River
Exportation Line will installed at a minimum depth of 10 ft. (3 meters)
from the lowest point of the river bed. These crossings will be open cut.
Exact location of the crossing will be show in the Typical Major River
Crossing Exhibit.
Los Monos River
Exportation Line will installed at a minimum depth of 10 ft. (3 meters)
from the lowest point of the river bed. These crossings will be open cut.
Exact location of the crossing will be show in the Typical Major River
Crossing Exhibit.
4.9.5
Creek Crossings
4.13
SCADA System
The flow computers at the meter stations will be linked to the SCADA
system. All the meter runs will be monitored from the central control room
located in Santa Cruz. Where no telephone, radio or cellular
communication is available at the meter station sites, a V-SAT unit will be
installed.
4.14
4.15
Hydrostatic Test
The pipeline will be hydrostatically tested to a minimum pressure of 1.25 x
MAOP (1,700 psig for 6 & 10) or 2,125 psig and 2,375 psig (1,900 psig
for 8); and a maximum pressure the lesser of 0.2 % deviation on a P-V
plot. A pressure that will produce a hoop stress equal to 110 % SMYS.
The minimum hold period will be four (4) hours.
Table 1
House Count and Location Classes Summary
LOCATION
Location Design
Section
Class Factor F
From
To
KP
KP
30
54
E.
51
E.
PIPE
MAOP
Lines
O.D.
W.T.
API 5L
MAWP
inches
Inches
grade
psig
psig
0,72
0,375 / 0,500
X-60
4050 / 5400
3757 / 5009
Gathering
0,72
0,280 / 0,344
X-60
4032 / 4954
3652 / 4486
Export. Liq
0,72
10
0,365 / 0,500
X-60
3154 / 4320
2934 / 4019
Export. Gas
Table 2
Line Lengths
O.D.
Suveyed
length
As-builts
Length
Inches
km
km
Gathering Line
30
54
10
51
TOTAL
135
Section
Table 3
: 6 5/8"
Altura Min.
:423
( 602
psig )
Espesor
: 0,280"
Altura Max.
:1.283
( 1.824
psig )
Especificacin
: API-5LX60
Dif. Altura
:860
( 1.223
psig )
Longitud
: 20.000 m
Presin Min.
:2.125
psig
( 1.494
PMO
: 1.700 psig.
Presin Max.
:4.080
psig
( 2.869
Fecha : 31/10/02
Puntos
KP
Altura (m)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
00+000
00+400
00+680
00+800
01+760
01+950
02+620
03+100
03+260
03+420
03+500
03+760
03+920
06+078
06+283
06+945
07+600
08+570
09+619
14+895
19+855
17+000
17+700
18+000
19+000
20+000
597,658
687,098
598,076
663,017
525,000
597,820
500,755
587,527
538,042
558,939
536,070
652,293
570,000
1.283,000
1.265,000
1.249,000
1.198,000
1.234,000
1.261,000
1.096,000
800,000
720,621
690,096
566,811
462,099
423,221
Presin
(m)
2.272
2.182
2.271
2.206
2.344
2.271
2.368
2.282
2.331
2.310
2.333
2.217
2.299
1.586
1.604
1.620
1.671
1.635
1.608
1.773
2.069
2.149
2.179
2.302
2.407
2.446
Table 4
Pipe MAWP vs. MAOP
Presiones Optimizadas
(psig)
3.230
3.103
3.230
3.137
3.333
3.230
3.368
3.245
3.315
3.285
3.318
3.152
3.269
2.256
2.281
2.304
2.376
2.325
2.287
2.521
2.942
3.055
3.099
3.274
3.423
3.478
(m)
2.222
2.132
2.221
2.156
2.294
2.222
2.319
2.232
2.281
2.260
2.283
2.167
2.249
1.536
1.554
1.570
1.621
1.585
1.558
1.723
2.019
2.099
2.129
2.253
2.357
2.396
(psig)
3.159
3.032
3.159
3.066
3.263
3.159
3.297
3.174
3.244
3.214
3.247
3.082
3.199
2.185
2.210
2.233
2.306
2.254
2.216
2.451
2.872
2.984
3.028
3.203
3.352
3.407
MAWP
psig
MAOP
psig
F = 0.72
F = 0.72
4.050
3.757
5.400
5.009
4.032
3.652
4.954
4.486
3.154
2.934
4.320
4.019
Pipe
Table 5
Roads and Railroad Crossing Pipe
Proposed
Section
Gathering
Line
Exportation
Lines
Crossing
O.D.
Inches
W.T.
Inches
API 5L
grade
Process
type
Public Road
8.625
0.375
X-60
ERW
Private Road
8.625
0.375
X-60
ERW
Railroad
8.625
0.500
X-60
ERW
Public Road
6.625 / 10.750
0.280 / 0.365
X-60
ERW
Private Road
6.625 / 10.750
0.280 / 0.365
X-60
ERW
Railroad
6.625 / 10.750
0.280 / 0.500
X-60
ERW
Table 6
Mainline Valve Settings
MLV No.
Line
Use
Location
X-3
By Pass
Header
By Pass
5
6
Plant
8"
Gear
MLV
MLV
MLV
10
Header
X-1
11
Header
X-3
Check
Plant
MLV
6"
MLV
MLV
MLV
Hot Tap
1
2
Ball
MLV
MLV
Operator
X-1
Wellhead Tie in
Valve
Ball
Gear
Ball
Gear
Plant
10"
MLV
MLV
Hot Tap
Table 7
Scraper Traps Location
Location
Km. Post
Type
000
Launching 8
030
Receiving 8
000
Launching 6
000
Launching 10
051
Receiving 6
054
Receiving 10
Section Line
Gathering
Gathering
Exportation
Exportation
Exportation
Exportation