SHELL LOBP PROJECT MONAS

DOCUMENT TITLE

METHOD STATEMENT OF
METAL WALL
INSTALLATION WORK

DOCUMENT No

V-3140-001-A-841

REV

01E

Page 1 of 4

General
1.1 Purpose
The purpose of thisStatement is todescribethe methodsemployed in the installation of
Metal wall, in particularsafe workpractices for working atheighti.e.100%fallprotection
policy.
1.2 Scope
ThisStatementisapplicableforinstallationofmetalwallinstallationwork.PT.EnconaInti
Industri will provide equipment, manpower, supervision, and inspection of metal wall
installationwork.
1.3 WorkProvidebyJGC
MetalwallmaterialandmainaccessroadtoinstallationareawillbesecuredbyJGC

Reference
2.1 ApplicableSpecifications

S0001340001BuildingGeneralSpecification

S0001520005QCRequirementforSubcontractor

S0001654010HSEPlan

S0001654020HSSEAspectIdentification,AssessmentandControlProcedure

S0001654030JobSafetyAnalysis(JSA)

S0001654050PersonalProtectionEquipment(PPE)Procedure

S0001654060HSSESignandColorCodingProcedure

S0001654070HSSECommunicationProcedure

S0001654080EmergencyResponseProcedure

S0001654280WorkingatHeightProcedure
2.2 Applicablecodesandregulation

MBMA(MetalBuildingManufactureAssociation)

AISCrelatedworksorequivalent

IndonesianNationalStandard(SNI)andotherapplicablelaws,regulationandcodes
2.3 ApplicablePT.EnconaIntiIndustriDocuments

V3140001A512QualityPlan

V3140001A503ITPforSteelStructureerectionWork

Material
3.1 Materialsourceandsupplier
MaterialsourceandsupplierwillbeJGCScope.

SHELL LOBP PROJECT MONAS

DOCUMENT TITLE

DOCUMENT No

METHOD STATEMENT OF
METAL WALL
INSTALLATION WORK

V-3140-001-A-841

REV

01E

Page 2 of 4

3.2 Transportationandstorage
Transportation up to Project Site will be JGC scope. EII will check and verify material
received from JGC. The quality, sizes and material condition will be checked. JGC will be
notifiedincaseofthereisdiscrepancythatcouldaffecttheerectionprocedure

WorkProcedure
4.1 Preparation

Beforeinstallingmetalwall,makesurethatallgirtsandsagrodswerecompleted

Asetonscaffoldingwillbeusedformetalwallinstallation,apulleywillbeinstalledon
scaffolding,andthisallowspullingwallsheetsafelybypeopleonthegroundoronthe
scaffolding

Wallpanelwillbemovedtotheirpositionalongthewalltoinstall

4.2 MetalWallinstallation
4.2.1 LiftingMetalWall

Drillaholewithapprox.dia3mmatthemiddleofthewallpanel,150mmfar
fromthetopforhookingwireropetothewallpanel

Liftingupandadjustpaneltorightpositionbeforeattachedtothegirt

WorkersworkingonscaffoldingmustwearPPEand100%tieofffallprotection

Rope to pull wall panel


PEB Steel Structure

Metal Sheet

4.2.2 MetalWallInstallation

AscaffoldingasattachedwillbeusedforMetalWallInstallation

SHELL LOBP PROJECT MONAS

DOCUMENT TITLE

DOCUMENT No

METHOD STATEMENT OF
METAL WALL
INSTALLATION WORK

V-3140-001-A-841

REV

01E

Page 3 of 4

Worker stand on scaffolding which stand on ground and attached to girts or


scaffoldingtoavoidfalldown,willfixcladdingtothegirts

Needtobeinstallathreadtomakesurethescrewswereinstalledstraight

HealthSafetyandEnvironmentalControl
Health,SafetyandEnvironmentalControlcanbeseeninPermittoWork

ITP
RefertoITPforSteelStructureErectionwork