Purpose/Scope
Contractor Representative
Customer Representative
GE Representative
Printed Name:
Printed Name:
Printed Name:
Printed Title:
Printed Title:
Printed Title:
GE Representative
Signature/Date:
Rev 0
Signature/Date:
Signature/Date:
Page 1 of 3
IWP25
TASKS
INITIALS
1.
Seal all joints and transitions inside plenum with Sikaflex221 silicone.
2.
DATE
NOTICE
DO NOT ALLOW RTV TO BE LEFT PROTRUDING FROM JOINTS IN AIR FILTER
HOUSE.
3.
4.
5.
Close all doors and check for light penetration. (Apply silicone until no light
penetrates into air filter enclosure).
6.
NOTICE
WHEN CLEANING AIR INLET ASSEMBLY AND PLENUM WIPE ENTIRE ASSEMBLY
DOWN TO ENSURE NO DIRT OR CONTAMINATION REMAINS INSIDE INLET AREA.
PAY PARTICULAR ATTENTION TO LOW POINT AREAS WHERE DIRT, DUST, SLAG
AND OTHER OBJECTS MAY HAVE FALLEN AND ACCUMULATED.
7.
Inspect inlet areas for signs of corrosion and deterioration, treat areas as required
(reference Intake Inspection and Cleaning Procedure).
8.
For units with chillers, ensure piping is properly run and there is no chaffing.
NOTICE
TO INSTALL FILTER MEDIA IN FILTER CELL, FIRST STAGE SEPARATOR WILL
HAVE TO BE REMOVED.
Rev 0
Page 2 of 3
IWP25
GE ENERGY
TASKS
INITIALS
9.
10.
Clean intake housing before filters are installed (reference Intake Inspection and
Cleaning Procedure).
11.
Tilt bottom of filter bag outwards and Place top of filter bag into groove. Push
bottom of filter into cell and down.
12.
DATE
NOTICE
IF SEALS APPEAR DAMAGED, FLATTENED, OR DETACHED, THEY SHOULD BE
REPLACED.
13.
14.
15.
Rev 0
Page 3 of 3