LM2500+ G4 LSPT Installation

IWP27

Electrical Walk Down

GE ENERGY

GENERAL GUIDELINES
Purpose/Scope
This work package encompasses all

requirements for electrical system walk


downs to verify integrity and completeness
of the system according to the designed
and approved F&IDs and electrical
drawings, to include all systems and
subsystem unique to the package. The
electrical package walk down is the initial
observation to verify installation
completeness.

Special Tooling - Equipment


Flashlight
Rags
References
System control wiring diagrams
Equipment layout drawings
System F&IDs

Suggested Manpower and Duration


One Electrician
One Helper
Duration Two Days

Precautions
Ensure drawing numbers and supplied equipment are as
specified.
Special attention should be given to cableways, conduit
routing, and terminations to ensure proper construction
guidelines were followed. Walk each system from start
to finish and ensure the following:
Ensure all cableways are free of debris.
Inspect cableways, instruments, and other
components for damage.
Verify signal wire and power lead separation.
Ensure all box covers and bulkhead penetrations are
sealed.
Ensure cabinets and ductworks are clean.
Verify cable ratings are acceptable for application.
V if
t i t
t
i t ll d
di t

TASK START DATE

Contractor Representative

TASK COMPLETION DATE

Customer Representative

GE Representative

Printed Name:

Printed Name:

Printed Name:

Printed Title:

Printed Title:

Printed Title:

GE Representative
Signature/Date:

Rev 0

Signature/Date:

Signature/Date:

Page 1 of 2

LM2500+ G4 LSPT Installation


GE ENERGY

IWP27

Electrical Walk Down

TASKS
1.

Inspect for visible damage to any cable or termination.

2.

Check mounted instruments for proper installation and application.

3.

Verify cables and connectors are properly fixed with appropriate brackets.

4.

Check cable freedom of movement and ensure no chafing occurs.

5.

Check all junction boxes and conduit for integrity of installation.

6.

Verify gas turbine package against electrical drawings.

7.

Verify control wiring diagram against installation.

8.

Ensure proper installation of wire ways.

9.

Check manufacturers connections, all grounding, and field connections for loose
terminations.

10.

Check nameplates and identification tags to ensure instruments, cables, etc. are
properly labeled.

11.

Inspect for damage of vent dampers and door switches.

12.

Verify the following records have been updated;

INITIALS

DATE

Equipment Installation Log


Redline Drawing (Submitted for as-built revision)
Nonconformance Report
Nonconformance Log

Rev 0

Page 2 of 2