TASKS
INITIALS
DATE
MECHANICAL CHECKS
1.
2.
Check instrument valves and supply shut off valves for full travel and correct
position. Secure where applicable.
3.
4.
Ensure drain valve is locked in closed position and blind flange/cap is installed.
5.
Fill system with specified mineral lube oil to a level that is sufficient for flushing.
When finished, lock fill cap.
6.
7.
8.
9.
Upon completion of flushing, verify system piping has been reinstated for normal
operation.
10.
Open, clean and inspect rundown tanks. Check level switches for bent rods on
floats.
11.
12.
13.
14.
15.
Check for adequate distance between power, control, and instrument cables.
16.
17.
Rev 0
Page 2 of 3
PWP02
18.
Check means of cable protection against mechanical damage at points where cables
leave cable trays or enter package.
19.
20.
21.
22.
Verify ranges and set points for all instrumentation listed in attachment (GLO
Instrumentation Sheet). Mark each instrument as calibrated or verified in the
appropriate column.
23.
24.
Rev 0