Beruflich Dokumente
Kultur Dokumente
Slump test
This is a site test to determine the workability of the ready mixed concrete just before its
placing to final position inside the formwork, and is always conducted by the supervisor on
site. However in mid of concreting process, should the site supervisor visually finds that the
green concrete becomes dry or the placement of concrete has been interrupted, a re-test on the
remaining concrete should be conducted in particular of the pour for congested reinforcement
area.
Step 2: Mixing
1. The pan and paddles were lightly moisturized.
2. Those material were added in order;
a. Coarse aggregate
b. Fine aggregate
c. Sand
3.
4.
5.
6.
Step 3: Testing
1. The following tests were carried out, in order;
a) Workability
b) Plastic Density
2. For the first slump test, our group got collapse slump.
3. The test was repeated, return used concrete to the mixer and re-mix for 30 seconds.
4. For the second slump test, our group successfully got true slump with 7-10 mm
slump.
9. Mark the cube surface with an identification number (say simply 1, 2, 3, etc.) with a
nail or match stick and record these numbers in respect with the concrete truck and
location of pour where the sampled concrete is obtained.
10. Cover the cube surface with a piece of damp cloth or polythene sheeting and keep the
cube in a place free from vibration for about 24 hours to allow initial set .
11. Strip off the mole pieces in about 24 hours after the respective pour is cast. Press the
concrete surface with the thumb to see any denting to ensure the concrete is
sufficiently hardened, or otherwise de-mole has to be delayed for one more day.