Sie sind auf Seite 1von 41

Holyoke Public Meeting &

Workshop
Reuse Scenarios
May 14th, 2015
Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Tonights Agenda
Introductions
Project Context
Background
Public engagement
Mt. Tom site info

Summary of Last Meeting


Reuse principles
Reuse ideas

Scenario Overview
Three Concepts
Regulatory pathways
Development implications

Discussion / Feedback

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Background
Why are we are doing this study?
What will be the studys outcomes?
What will happen with the study results?

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Public Engagement Process To Date

Kick O
Mee*ng

Site Condi*ons
Mee*ng

(Dec 2014)

(Feb 2015)

Mobile
Workshops &
Survey
(Mar-Apr 2015)

Scenarios
Mee*ng
(May 2015)

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Participant Snapshot
170 par*cipants across all
ac*vi*es (not including tonight)
All ac*vi*es in English &
Spanish
Over 100 project email
subscribers
Over 300 unique page views
since website launch
17 local media stories

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Mt. Tom Parcel


Parcel Size: 128 acres
Plant Opening: 1960
Plant Closure: 2014
Generating Capacity: 146 MW

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Economic Impact of Mt Tom Power Plant


Property Taxes Paid
$1,700,000

$1,300,000

$573,000
$315,000

2009

2011

2013

Year Closing Announced



28 employees as of
year of closing
announcement
3 were Holyoke
residents
~$3.9m wages &
benets last year of
full opera*on

2014

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Development Box
Every project has parameters that establish the op3ons
Few Limits
Many Op*ons

Many Limits
Few Op*ons

Understanding the size of the box is cri3cal


Some factors that inuence the size of
the Box

Clean up costs
Flood plain
Site layout and congura*on
Ecological & environmental issues
Infrastructure like power lines &
pipelines

What follows are our


ndings on the
development parameters
that dene the box

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Site Conditions Summary: Environmental

There are several ash landfills, a former City of


Holyoke landfill, and a private landfill that have
not been closed but a draft closure plan has
been submitted to the Department of
Environmental Protection.
There are topographical barriers (i.e. steep
slopes), which would make recreational access
to the river a challenge.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

Project Context

Site Conditions Summary: River Protection

Any changes within 100-foot buffer to the bank


of the river and the 200-foot Riverfront Area
are subject to local and state regulations that
protect the river banks, habitat areas and a
perennial stream that bisects the site.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

10

Project Context

Site Conditions Summary: Wetlands Protection

The site includes several wetlands and a


perennial stream so is subject to
wetlands protection regulations.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

11

Project Context

Site Conditions Summary: Rare Species Habitat

Portions of the site provide habitat for statelisted rare species including the Bald Eagle,
dragonfly species and mussels (in the river).

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

12

Project Context

Site Conditions Summary: Flood Plain

The majority of the site is located in the 100year floodplain, which means that new uses
must consider the potential for flooding and
adhere to applicable regulations.

AE: hydrological studies


conducted
A: no hydrology studies conducted
to determine base flood elevation
X500: area subject to 500 yr flood
event
Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

13

Project Context

Site Conditions Summary: Zoning

The site is located in a General Industry


Zoning District and a Flood Plain Overlay
District that corresponds to flood zone.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

14

Introductions
Project Context
Summary of Last Meeting
Scenario Overview
Discussion / Feedback

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

15

Summary of Last Mee5ng

Reuse Principles from the Community


Generate tax revenue
Go Green (e.g. green energy, carbon neutral)
Make it multi-purpose (e.g. more than one use)
Connect the community to the river
Use existing infrastructure (e.g. rail and electric
switchyard).

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

16

Summary of Last Mee5ng

Reuse Ideas
Demonstra*ng energy
op*ons. Mul*ple use of the
facility: solar energy, river
access for boa*ng, a color
eld for nature. We suggest
using exis*ng infrastructure
as much as we can

It will never be the slam-dunk it


was before in terms of jobs and tax
revenue. But can we use the site for
innova*ve technology and
partnership with universi*es? Maybe
workforce training and development?
Build a solar eld and train
unemployed folks in Holyoke to
install solar? Or do this with other
green power?

Green energy thats truly


green (maybe solar farms
to *e into electric
switches), agriculture, river
access and recrea*on;
protec*ng the Connec*cut
River watershed

Solar farm seems like the most economical


op*on because the ini*al investment is
probably less than other things and since it
is in a ood plain so we have to assume at
some point we will get a ood. But we
arent talking about major infrastructure.
We already have power lines coming in and
out so thats good. River access would be
great. A pathway through solar farm and
green space with the rest of it.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

17

Introductions
Project Context
Summary of Last Meeting
Scenario Overview
Discussion / Feedback

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

18

Scenario Overview

Reuse Scenarios Structure


Scenarios crafted based on principles, ideas and
discussion points developed with public input
Site maps created to understand how much can fit
given the parameters of the site and design
characteristics of the uses
Explains the regulatory pathway to development
Provides economic implications
All scenarios include assumption the facility will remain
in place
Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

19

Scenario Overview

Base Case

The site sits unused with structures either


remaining or torn down with clean up at the
required levels based on a no reuse
scenario
An active transmission line exists along the
river edge heading north it is reflected in
the following scenario maps

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

20

Scenario Overview - Concepts

Mt. Tom Reuse Scenarios Snapshot


Scenario 1
Solar PV System
+
Reten5on of exis5ng farm

Scenario 2
Solar PV System
+
Public Access to River
+
Reten5on of exis5ng farm

Scenario 3
Solar PV System
+
Public Access to River
+
Expanded Ag Use
+
Anaerobic Diges5on
+
Reten5on of exis5ng farm

Note: the exis*ng farm lease has not been renewed


Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

21

Scenario Overview - Concepts

Holyoke Reuse Scenarios Structure

Existing power
plant

Existing
agriculture

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

22

Scenario Overview - Concepts

Reoriented Site Map

Existing agriculture

Existing power plant

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

23

Development Implications

Scenario 1: Large Solar Installation


6.5 acres

11.3 acres

Existing agriculture
2.5 acres
Parking and
support

9.2 acres

Approximate solar
capacity: 5.9 MW
Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

The placement of these


zones for solar energy
development takes into
account regulatory
setbacks, shading, and
topography.
The solar arrays are
within Rare Species
Habitat and wetlands
buffers, which will require
permitting.
24

Development Implications

Scenario 2: Solar Installation and Public Amenities


Path will require
stream crossing

1.5 mile 8ft wide path


shares transmission line
right-of-way
6.5 acres

21.5 acres existing


agriculture, lease not
renewed

Site for
potential
kayak/small
boat launch

11.5 acres

2.5 acres
Parking and
Support

9.2 acres
Unused space is
flood storage
capacity

Approximate solar
capacity: 5.9 MW
Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

The placement of these


zones for solar energy
development takes into
account regulatory
setbacks, shading, and
topography.
The solar arrays are
within Rare Species
Habitat and wetlands
buffers, which will require
permitting.
25

Development Implications

Scenario 3: Solar, Anaerobic Digestion, Agriculture


& Public Amenities
Path shares transmission
line right-of-way

Path will require


stream crossing

Solar, 6.5 acres


Site for
potential
boat/kayak
launch

Greenhouse
agriculture, 17.6
acres
(5.2 acres shown
here under
greenhouses)

Parking and
processing
Solar, 9.2 acres

Parking and
processing
Anaerobic
Digestion
Facility, 4 acres

Requires Right of
Way across Rail

Approximate solar
capacity: 3 MW

The anaerobic digestion


facility includes two 100
diameter storage tanks
and two 50 diameter
storage tanks. The
buildings dimensions are
250 by 250.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

26

Scenario Overview Regulatory Pathway

Scenario 1 Large Solar


LOCAL PERMITTING
Zoning
Competing zoning
Flood plain overlay district (FPOD) vs solar facilities which takes precedent?
Depending on answer if FPOD, requires a change in allowed uses
Solar not presently allowed in FPOD
Solar site plan review required for installations over 250kw
Wetlands
Not a barrier may require some mitigation
Bordering Land Subject to Flooding (BLSF), requires an Order of Conditions from
the Holyoke Conservation Commission (ConCom)
200ft riverfront encroachment may trigger some mitigation
Compensatory flood storage offsets possible
If new material is needed for construction
Capping of landfill

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

27

Scenario Overview Regulatory Pathway

Scenario 1 Large Solar


STATE/FEDERAL PERMITTING
Rare Species
Priority habitat area for significant portions of the proposed solar farm
Depending on which species are present could present challenges
Potential need for Take of a Threatened or Endangered Species
If found Conservation and Management Permit required with mitigation
that creates a net benefit to the species
Survey required and additional information from Fish & Wildlife
Solid Waste
Closure of landfills require approval of a Corrective Action Design (CAD)
Previously submitted CAD may require modification
Closure of ash landfills may require approval of US EPA
Regulations for coal ash presently under review

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

28

Scenario Overview Regulatory Pathway

Scenario 2 Solar Installation & Public Amenities


LOCAL PERMITTING
Zoning
Same issues as Scenario 1
Bike path & boat ramp allowed if municipal owned
FPOD requires a special permitting process
Wetlands
Boat ramp creates a Bank and Land Under Water (BLUW) impact
Ramp under 50ft wide and less than 5000sft permissible under BLUW
Local variance required from ConCom for 50ft No Disturb Zone for boat
ramp and bike path

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

29

Scenario Overview Regulatory Pathway

Scenario 2 Solar Installation & Public Amenities


STATE / FEDERAL PERMITTING
Rare Species
Same issues as Scenario 1
Boat ramp potential impact on rare species
Ch. 91 / Army Corp / DEP Water Quality
Triggered by boat ramp
Requires Ch. 91 license from MASS DEP
Army Corp permit
401 Water Quality Certification from DEP
Solid Waste
Same as Scenario 1

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

30

Scenario Overview Regulatory Pathway

Scenario 3: Solar, Anaerobic Digestion, Agriculture


& Public Amenities
LOCAL PERMITTING
Zoning
Same as Scenario 1& 2
Under IG Zone
Anaerobic Digestion should qualify as an electric plant
Greenhouses may qualify as agriculture
Flood Plain Overlay District (FPOD)
Limited to manufacturing and assembly uses
May require a change in the FPOD for these additional uses
Wetlands
Bordering Land Subject to Flooding (BLSF) is more problematic due to
the loss of flood capacity, requiring a larger compensatory flood storage
basin to be created

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

31

Scenario Overview Regulatory Pathway

Scenario 3: Solar, Anaerobic Digestion, Agriculture


& Public Access
STATE/FEDERAL PERMITTING
Rare Species
Same issues as Scenario 1 & 2
Depending on species may be more complex given the nature of the buildout
Ch. 91 / Army Corp / DEP Water Quality
Same
Recycling, Composting & Conversion Permit from DEP
Solid Waste
Same as Scenario 1

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

32

Scenario Overview Development Implications


Relationship between Development & Remediation

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

33

Scenario Overview Development Implications

Landfill Closure Costs


Regardless of scenario; based on current rules which are slated to change
Assumptions/Rules of Thumb
To close 1.2 acres of solid waste
landfill & 36.5 acres of ash landfill
Based on current proposed caps
Per acre costs for:
Vegetation & Grubbing: $20,000
Hydroseeding: $7,500
Solid Waste Landfill Cap:
$200,000
Ash Landfill Cap: $75,000
Does not consider additional site
grading, fill for grading/shaping,
removal of stumps or other materials
or permitting

Depending on specic clean up


requirements, expenditures in
the range of $3 to $8 million are
possible

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

34

Scenario Overview Development Implica5ons

Development Patterns Side by Side


Scenario 1

Scenario 3

Scenario 2

Solar PV System
+
Reten5on of exis5ng farm

Power plant remains



New solar: 29.5 acres

Solar PV System
+
Public Access to River
+
Reten5on of exis5ng farm

Solar PV System
+
Public Access to River
+
Expanded Ag Use
+
Anaerobic Diges5on
+
Reten5on of exis5ng farm

Power plant remains



Solar:
15.6 acres

Digester: 4 acres

Wholesale Greenhouse:
17.6 acres with 5.2 acres of
greenhouse space

Ped/Bike Path: 8m wide
path lacks direct connec*on
to exis*ng trail system

Massachusetts Clean Energy Center

Power plant remains



New solar: 29.5 acres

Ped/Bike Path: 8m wide
path lacks direct
connec*on to exis*ng trail
system

Noble Wickersham and Heart Consensus Building Institute |

35

Scenario Overview Development Implica5ons

Economic & Employment Side by Side


Scenario 1

Scenario 2

Scenario 3

Economic

Power:
~ 6MW solar power
produc*on

Power:
~ 6MW solar power
produc*on

Power:
~ 3MW solar power
produc*on

500kw digester

Greenhouse:
produc*on varies widely
by crop & method

Employment

Solar: 1-3

Solar: 1-3

Solar: 1-3
Digester: 2-5

Greenhouse: 30-40

Total wages: $200k


Avg Salary
Solar: $30-40k

Total wages: $480k


Avg Salary
Solar: $30-40k
Digester: $40k
Greenhouse: $20k-30k


Wages

Total wages: $200k


Avg Salary
Solar: $30-40k

Note: it is assumed exis*ng farm stays and not included in these calcula*ons.

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

36

Scenario Overview Development Implica5ons

Property Taxes Side by Side


Annual Tax
Poten*al
(PILOT)
Municipal services
impact

Scenario 1

Scenario 2

$30k


$30K

minimal

minimal

Scenario 3
Solar =$15k
AD (Full/PILOT) = $99k / $10k
Greenhouse = $226k

minimal

Notes:

Conserva*ve es*mates: reects only new developments: excludes land, any remaining buildings

Solar Array: Exis*ng city PILOT of $5k per MW

Anaerobic Digester: Likely taxed as commercial/industrial $39.93/$1000 or PILOT of $20,000 / MW

Greenhouse: Likely taxed as commercial/industrial $39.93/$1000

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

37

Questions for Consideration by the City


Which zoning framework will take precedent -- flood
plain overlay or solar facilities?
Should the city take ownership of any of the public
amenities to ease the permitting process?
How will the property be classified for purposes of
taxation particularly if structures are removed?
Create connection of site bike path to larger bike
trail system?

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

38

Key Questions for the Workshop


What did we miss?
Based on the findings should any of the
scenarios be eliminated?
Based on the findings should any of the
scenarios be revised? If so, how?

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

39

Introductions
Project Context
Summary of Last Meeting
Scenario Overview
Discussion / Feedback

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

40

Next Steps
Community feedback on potential reuse
options (see project website for survey)
Final report expected fall 2015

Noble Wickersham and Heart Consensus Building Institute | Massachusetts Clean Energy Center

41

Das könnte Ihnen auch gefallen