Beruflich Dokumente
Kultur Dokumente
4
Emerging Trends in
Substation Technology - I
212
SUMMARY
GETCO network is expanding rapidly to meet the
generation as well as demand requirements in the
state. Also due to non availability of gas,
government policies in the benefit of RE
generation and implementation of merit order
dispatch, power flow pattern has changed
completely in last few years and load pockets have
become generation pocket also. Earlier
generation pockets in Gujarat were in southern
region and power was flowing towards central,
western and northern region. But, now power is
flowing from western region to central, southern
as well as northern parts of the Gujarat.
Moreover, western and northern region is having
predominant agriculture load. Hence, during nonagriculture season load consumption reduces
considerably. In addition to that, transmission lines
connecting these regions with central Gujarat are
quite long. These long lines are loaded below SIL
resulting in generation of excess reactive power
causing high voltage at 400KV Buses in these
areas. Because of Over Voltage, many 400KV
Lines are required to be switched off to maintain
voltage within acceptable limits. This, in turn, is
jeopardizing grid availability and security.
To overcome Over Voltage, GETCO found the
need of Reactors at 400KV strategic location (7
Places) based on system study. But, out of seven,
four locations have the space constraint for
providing Reactor bay. After brain storming, it
was decided to utilize TBC bay as Bus Reactor
bay by providing Bus reactor in Transfer bus
coupler bay. The main consideration behind this
decision was utilization of TBC bay on very few
occasions in a year. On finalization of this
1.
INTRODUCTION
213
400KV
Substation
Jetpur
432
429
429
430
431
Soja
421
418
417
417
419
Chorania
428
423
416
419
419
Kansari
420
415
414
423
423
Amreli
418
418
416
417
418
Vadavi
426
425
425
424
423
Hadala
430
427
428
431
431
2.
PHILOSOPHIES ADOPTED
Fig. 1: 400 kV Transfer BUS Coupler Bay with 400 kV BUS Reactor
214
Fig. 2
z
215
3.
FINALIZATION OF PANEL
REQUIREMENT
Fig. 3
216
4.
Items considered
Relay Panel for Bus reactor (with Energy meter, Indicating meters, WTI, Isolator control switch,
necessary auxiliary / multiplication relays for Isolator & Earth switch etc.) including,
z
Related interface wiring & modification in existing TBC panel with required accessoires
and complete scheme testing.
z
Supply of 36 Window annunciator and retrofitting of same in existing TBC Panel with
related wiring and accessories.
z
Modification in Mimic Diagram of existing TBC panel as per revised bay configuration
along with required accessories and wiring.
PREPARATION OF OPERATION
PHILOSOPHY
1.
2.
Metering:
Reactor BCT Phase side CT (200/1 ratio)
Differential Protection:
TBC Bay PS class CT core & Reactor Neutral side CT
core (500/1 ratio).
217
5.
BENEFITS ACHIEVED
Reduced quantum
commissioning work.
6.
of
erection
and
7.
CONCLUSION
218
L. Bergeld
B. Pahlavanpour
Nynas AB, Sweden
SUMMARY
Furanic compound is generic name of chemical
compounds produced from degradation of
insulating paper in oil filled transformers. These
are polar compounds which are, up to certain
extend, soluble in transformer oil. By
measurement of Fufurals in oil it is considered to
be possible to estimate rate of aging of a
transformer. Water, acids and carbon monoxide
are also byproducts of paper aging and it has been
established that oil deterioration and acid
formation also have effect on degree of
polymerization of insulating paper.
In a laboratory study, of which this paper is based
on, Kraft paper was aged together with copper in
different dielectric fluids, (including a vegetable
ester, a hydrocarbon fluid based on predominantly
noncyclic hydrocarbon chains and two different
naphthenic oils). After conducted ageing water
content, furfural content, and acid number was
measured in both paper and fluids. It was
discovered that fluids with high content of
degradation products in oil not necessary
contained the most amounts of degradation
products in paper. Hence the distribution of
furfural/water/acids between paper and oil is
different for different oils.
The estimation on degree of paper degradation
based on paper degradation by products in oil is
complicated and therefor need more study.
Keywords: Mineral Transformer oil, insulating paper
aging, other insulating liquids, Fufural formation
1.
INTRODUCTION
219
1.3 Esters
An ester (Figure 2) is either present in the raw
material, natural ester, or formed from the reaction
of an alcohol and a fatty acid, synthetic ester.
Mineral oils have been used for a long time and this
has given rise to many different national and
international specifications and standards, one of the
most common one is IEC 60296 [3]. Today there are
also specifications for both synthetic and natural
esters within IEC, IEC 61099 [4] and IEC 62770 [5]
respectively. There are differences between these
specifications when it comes to required tests,
methods and specified limits. Table 1 shows flash
point and oxidation stability from these
specifications, which will be related to in the coming
discussion.
220
IEC 61099
IEC 62770
135
250
250
min
Oxidation stability
2.
IEC 60296
max
1.2 /0.3
0.3
0.6
Sludge, wt%
max
0.8 /0.05
0.01
2.3 DGA
Insulating material within electrical equipment break
down with time and this generate gases within the
unit. The distribution of these gases can also be
related to abnormal conditions such as electrical or
thermal faults and the rate of gas generation can
indicate the severity of the fault. Dissolved gas
analysis can therefore be used as a method to
evaluate the condition of mainly the transformer but
it can also give indications on the status of the
insulating material.
DGA diagnostics for mineral oils have a long history
and are today well established. When it comes to
the relatively new insulating liquids such as esters
many aspects of the thermal and electrical design of
transformers have to be considered. Additionally the
diagnostic and condition monitoring methods,
including DGA, have to be adjusted. The DGA results
can be analyzed using various existing interpretation
methods such as the Duval triangle method and
221
3.
3.3 DGA
Depending on what insulating material that is used
there will be differences in the gas formation and
relation to a certain fault and the interpretation of
the DGA results need to take this into consideration.
The method to evaluate gas formation in mineral oil
is well established and it has recently been studied
if new interpretation methods are needed for ester
fluids or if existing methods can be slightly adjusted
to serve the purpose. This study [7] is comparing 4
fluids: 1 mineral oil, 1 synthetic ester and 2 natural
esters. A comparison of differences in gas formation
between the 3 non-mineral oil fluids with the mineral
oil have been used to adjust the zones in the Duval
triangle leading to one triangle per fluid as can be
seen in Figure 7.
222
223
<0,1
17
Uninhibited mineral
oil, Kraft paper
<0,1
0,3
4.
CONCLUSIONS
224
BIBLIOGRAPHY
1.
2.
3.
4.
5.
6.
7.
8.
9.
225
Mangapathirao V. Mynam
Marcos Donolo
Schweitzer Engineering Laboratories, Inc.
ABSTRACT
Large substations often have complex and dynamic
topologies. The voltage available on either side
of an open breaker may originate from a number
of sources. This has led to the development of
centralized systems to carry out synchronismcheck functions to synchronize all breakers within
the substation. Such a system uses the status of
breakers and disconnects to identify a voltage
source for each side of the breaker that is to be
synchronized. Custom logic is required to
accommodate the topology of a particular
substation. In the past, these systems have been
realized using custom hardware or programmable
logic controllers (PLCs) and significant amounts
of wiring. This paper describes in detail a
synchrophasor-based approach that provides a
significant reduction in the effort and cost required
to design, build, and test a centralized
synchronizing system. Phasor measurement and
control units (PMCUs) transmit voltage phasors
and breaker and disconnect status to a central
controller. The central controller time-aligns the
data and selects the correct voltages to use for
synchronizing according to the present status of
the breakers and disconnects. Once the
appropriate checks of the voltages are made, a
close command is sent from the central controller
to the PMCU responsible for the breaker that is
to be closed. A primary objective is to reduce the
requirement for custom logic as much as possible.
The design relies heavily on using the program
organizational units (POUs) described in IEC
61131. These can be developed, tested, writeprotected by passwords, and easily reused in
subsequent projects.
Amy Sinclair
1.
INTRODUCTION
226
2.
CONVENTIONAL CENTRALIZED
SYNCHRONIZING SCHEME
3.
SYNCHROPHASOR-BASED CONTROL
227
A. Time Alignment
Time alignment is a key function in the design of
synchrophasor data concentrators and controllers.
It allows for communications latencies between the
phasor measurement units (PMUs) and the controller
or data concentrator. The measurements are timetagged with a common time reference (typically
Global Positioning System [GPS]). The TA function
opens a time window (message wait time) where it
expects all the measurements with the same time
tag to arrive, independent of their location. Some
implementations force the device measurements that
arrive outside the message wait time to zero and flag
B.
228
Modal analysis
4.
CENTRALIZED SYNCHRONIZING
SYSTEM USING SYNCHROPHASORS
229
A. Time Alignment
Time alignment is described in detail in Section III.
It is carried out automatically and ensures that all
downstream operations are made using timecoherent measurements.
B.
230
C. Arming Logic
Referring once again to Fig. 4, the arming logic
processes close requests. The logic, shown in Fig. 8,
is responsible for opening a window for synchronizing
and for rejecting close requests if synchronizing is
in progress on another breaker.
Table 1: Branch-to-Node Data Array for the Topology Processor when all Branches are Open
Table 2: Branch-to-Node Data Array for the Voltage Processor when all Branche 2 Merges Node 2
and Node 3
231
232
E.
Synchronism-Check Logic
233
F.
5.
ADVANTAGES
234
6.
REFERENCES
1.
2.
3.
4.
5.
CONCLUSION
235
6.
7.
8.
9.
236
S. Vigouroux
Alstom Grid
France
SUMMARY
E. Avinash
Alstom T&D
India
1.
237
2.
238
1.
2.
3.
3.
239
240
241
4.
242
5.
PROTECTION FUNCTION
REDUNDANCY
2.
3.
243
244
1.
2.
3.
4.
245
5.
Fig. 12: Passive redundancy in a conventional substation, spare line relay application
246
across the substation that need to be isolated during testing, whereas previously isolation could be achieved
by simply turning off devices in a single bay. Clearly, careful work will be required across the industry to
make such architectures safe and practical.
6.
247
BIBLIOGRAPHY
1.
2.
3.
4.
5.
6.
7.
248
R.K. Tyagi1
Gunjan Agrawal
Sumit S.H. Ray
Power Grid Corporation of India Ltd., India
ABSTRACT
Large power transformers are expensive and
critical elements of a utility transmission system.
Some transformers are so important that
consequences of their failure are tremendous e.g.
765kV Transformers and Converter Transformers
of HVDC System which are transmitting bulk
power from remote generating stations to load
centers. POWERGRID is operating and
maintaining about 650 Power Transformers, 90
converter transformers and 1000 shunt reactors
installed in 190 substations across the country.
Present task in front of POWERGRID is to
maintain serviceability of such a large fleet of
Transformers/ Reactors which are critical
considering the ageing fleet, large addition of
new Transformers/ Reactors especially at 765kV
level and significant effect on the grid due to any
outage.
During Operation and Maintenance of
Transformers & Reactors in POWERGRID, various
problems/ failures are observed. These failures
were analyzed in detail and various measures are
taken to improve the serviceability of
Transformers & Reactors. In this paper, few case
studies are brought out where failure prevention
of Transformers & Reactors are achieved based
on past failures/ problems encountered in
POWERGRID.
1.
INTRODUCTION
tyagir@powergridindia.com
249
2.
250
Fig. 4
Table 1: DGA Results of Shunt Reactor main tank oil & Bushing
Sample Date
4.4.2008
19.04.2008
4.5.2008
3.11.2008
12.2.2009
6.10.2009
H2
0
28
90
285
350
558
CH4
0
2
2
12
21
56
C2H4
0
1
1
3
3
3
C2H6
0
0
0
2
3
6
C2H2
0
0
0
0
0
0
CO
7
50
74
205
223
351
CO2
155
1821
3496
6770
7474
12708
3.2.2010
07.08.2012
Bushing DGA
11
33
18614
3
9
1750
0
3
1
0
2
114
0
0
0.57
16
282
158
684
6212
593
251
3.
Unit-I
Unit-II
June14
March15
Nov13
H2
1614
18
2857
CH4
70
6
184
C2H4
1
1
6
C2H6
5
1
23
C2H2
0
0
0
CO
208
176
434
CO2
280
604
1696
Fuzzy Interpretation
PD
Normal
PD
Rojers Technique
PD-Corona
PD-Corona
Duval Triangle
PD
T1 fault
IEEE Rojers Ratio No matching
PD
In all the above cases, Partial discharge test and
internal inspection couldnt reveal any abnormality.
These units were taken into service after carrying
out proper vacuum drying and adequate settling time
for oil and no further rise in fault gases appeared
even after one year of re-commissioning.
POWERGRID experienced such type of problem in
number of cases where H2 & CH4 gas disappears
after proper vacuum drying and with adequate
settling time for oil during re-commissioning.
From the above it may be envisaged that any
abnormal rise in H2 & CH4 in a short span of
commissioning may be because of Partial Discharge
due to presence of trapped air. It may be due to
improper vacuum drying process and settling time
during new commissioning/ after any repair work.
In such cases, adequate vacuum drying out and
settling time may resolve the problem.
4.
Dec14
45
15
3
3
0
221
1191
Normal
Unit-III
Dec12
1655
127
3
18
0
1104
3360
PD
PD
T1 fault
PD
March15
85
64
4
11.4
0
765
2865
Normal
252
253
5.
CONCLUSION
Acknowledgement
The authors are grateful to POWERGRID
management for granting their permission to write
and present this paper. The views expressed in this
paper are of the authors only and not of the
management of POWERGRID.
254
U. Parikh
ABB High Voltage Products
India
SUMMARY
Controlled switching, also known as point-onwave switching or synchronous switching, is a
well-established technique for minimizing
switching transients during closing and opening
of a high-voltage circuit breaker. The latest
generation of point-on-wave (POW) controllers,
designed on modern hardware and software
architecture, can offer additional benefits to the
user. These include,
z
michael.stanek@ch.abb.com
A. Parapurath
A. Talluri
ABB Substation Automation Products
India
1.
INTRODUCTION
255
2.
256
3.
257
4.
5.
APPLICATION SETUP
258
compensation curves, )
z
6.
USER INTERFACES
2.
259
7.
DIGITAL COMMUNICATION
260
BIBLIOGRAPHY
1.
2.
3.
8.
CONCLUSIONS
261
ABSTRACT
Accurate positive- and zero-sequence line
impedances are critical for the performance of
distance relaying and fault location. This paper
discusses a method for calculating positive- and
zero-sequence line impedances under singlepole open conditions. Time-synchronized
measurements from both terminals of the line are
captured when one pole of either terminal is open.
This operational condition provides an unbalance
in the three-phase network, which is used to
measure the line impedances. The performance
of the method has been verified using
Electromagnetic Transients Program (EMTP)
simulations and field data provided by Comisin
Federal de Electricidad (CFE). The paper also
discusses existing methods to calculate line
parameters and provides a sensitivity analysis of
these methods. The paper presents an approach
where the calculated impedances can be
compared with the relay impedance settings and
an alarm sent if the difference is greater than a
predetermined threshold.
1.
2.
INTRODUCTION
A. Distance Protection
Distance-based line protection uses positive- and
zerosequence impedances along with voltage and
current measurements to determine if faults are inside
the protection zone. One method to estimate the
262
V2LV2R+12RZ1L)
FL_UNBME = Real
12TZ1L
B.
where:
....(2)
where:
I2 is the negative-sequence current.
The accuracy of the fault location depends on the
accuracy of the line parameter settings, fault
resistance, system nonhomogeneity, and zerosequence mutual impedance (if mutually coupled
lines are present).
....(4)
E.
....(5)
where:
Z1 is the actual positive-sequence impedance value.
Z1 is the error.
To obtain the expression for Z0L, we replace 1 with
0 in (5). Fig. 1 shows the actual impedance Z1 and
the relay setting Z1L with an error with fixed
magnitude and variable phase angle.
263
3.
264
....(8)
4.
B.
265
A. PI Model Approach
B.
Z = R + jX =
Vs2 Vr2
Is VrIr Vs
....(9)
266
Equations (10) and (11) show the positive-, negative, and zero-sequence impedance calculations.
Z1L = (V2yV2x) / I2y = Z2L
....(10)
....(11)
Fig. 11: Estimation error in the positive-sequence line impedance
as a function of the load angle for two different CT and VT
error ratings for the SPO method.
where:
V2x is the negative-sequence voltage calculated at
Terminal X.
V2y is the negative-sequence voltage calculated at
Terminal Y.
I2y is the negative-sequence current calculated at
Terminal Y.
V0x is the zero-sequence voltage calculated at
Terminal X.
5.
267
Fig. 13: Faulted phase voltages and currents at both terminals for
a fault at 242 kilometers from MZD
268
Fig. 15: Logic to detect SPO condition with the remote terminal
closed
Positive
Sequence
(primary ohms)
Zero
Sequence
(primary ohms)
LCC program
7.2 + j97.32
86.52 + j323.4
SPO
8.16 + j97.27
80.59 + j323.3
269
Method
Positive
Sequence
(primary ohms)
Zero
Sequence
(primary ohms)
PI model
6.96 + j 95.59
NA
SPO
5.96 + j96.54
86.11 + j324.7
6.
FIELD RESULTS
Fig. 20: Measured (Z0m and Z1m) and computed (Z0lcc and
Z1lcc) values for a 6.5-kilometer 230 kV line. Note the disparity
between Z0m and Z0lcc
270
B.
271
272
7.
Positive
Sequence
(primary ohms)
Zero
Sequence
(primary ohms)
LCC program
7.2 +j97.32
86.52 + j323.4
SPO
8.45 +j91.66
73.42+j269.45
273
8.
CONCLUSION
Relay engineers calculate transmission line positiveand zero-sequence impedances that are needed to
set the relay distance and fault location functions
using conductor properties, line geometry, and
ground resistivity as inputs to line parameter
calculation programs.
In some cases, they apply reduced primary voltages
at one end of the line while the remote end is
connected to ground to measure these impedances
and verify the results from the line parameter
calculation program. While this approach provides
accurate impedance values, it does not consider VT
and CT errors and that impedance value
measurements are difficult to obtain.
Sending
End
Receiving
End
A-Phase Voltage
44.914.81 V
8.024.59 V
B-Phase Voltage
65.68110.64 V
74.11126.34 V
C-Phase Voltage
65.29126.17 V
76.33134.15 V
A-Phase Current
7.469.93 A
5.8182.95 A
B-Phase Current
1.1388.76 A
1.1391.23 A
C-Phase Current
0.31141.44 A
0.3138.56 A
This paper presents a method to estimate positiveand zero-sequence impedances, including VT and CT
errors, without the need for signal injection. This
method requires line-side VTs, breakers with singlepole trip/close mechanisms, voltage and current
synchronized measurements, a load angle greater
than 5 degrees, and an operating condition where
one pole is open at one of the terminals while all of
the poles at the remote terminal remain closed. We
can use this method to verify the line parameters
obtained with line parameter calculation programs
and signal injection methods.
Acknowledgement
1.
2.
3.
9.
REFERENCES
APPENDIX
274
4.
5.
6.
7.
8.
9.
275
276
Vikas Dabeer
K. Tekletsadik
P. Lubicki
J. Ludlum
P. Murphy
S. Kodle
A.Sinha
Applied Materials India Pvt.Ltd., India
SUMMARY
The need for Fault Current Limiters are driven by
rise in the fault current levels as the energy
demand increases and more generation,
distribution and distributed energy generation
such as wind, solar, gas powered generation and
diesel generators are added to an already
overburdened system.
Several Fault Current Limiter (FCL) technologies
have matured from R&D and demonstration
projects into commercially available systems
worldwide. So far, the technical knowledge about
FCL systems, design parameters and impact
analysis on utility equipment is primarily
contained within the FCL manufacturers technical
expertise. The time has come to further
disseminate the technical knowledge to utility
engineers so that they can design fault current
management systems with the technical expertise
that enables them to specify FCLs for their
applications. Applied Materials is developing
Superconducting Fault Current Limiters (SCFCL)
and Solid State Fault Current Limiters (SSFCL)
for transmission and distribution voltage levels.
Both FCL technologies are being subjected to
testing and in-grid demonstration.
This paper is aimed at describing how utility
engineers may consider selectinga FCL for a
specific location and application, based on the
authors experience. It is not intended as a manual
or guide to be used or relied upon without
independent testing or verification. Italso
discussesthree FCL demonstration projects
of Applied Materialsincluding SCFCLs
in California and New York, and a SSFCLin
Australia.
S. Nickerson
1.
INTRODUCTION
277
2.
3.
278
4.
INSTALLATIONS
Reactors
Cryostat - Super
conductor Unit
279
6.
7.
5.
COST DRIVERS
SYSTEM REQUIREMENTS
280
220
KV rms
1500
A rms
25
kA rms
12.5
kA rms
5.08
63.5
kV rms
Zsh = Zs
1CR
281
282
8.
CONCLUSION
BIBLIOGRAPHY
1.
2.
3.
283
ABSTRACT
SF6 gas has been classified as a potent Green
House Gas by environmental and climate change
organizations. Releasing of SF6 in atmosphere
will be aggravating the current scenario of global
warming and climate change. However, SF6 is
also a popular dielectric used in High Voltage
switchgears, and contrary to the popular notion,
SF6 does decompose and lose its dielectric
strength. This requires quality checks and
regeneration of SF6 in a timely manner.
Commonly used Terms: SF6, Green house gas, Partial
Discharge, PD, Switching, Arcs, Breakdown,
Analysis, Reclaimation.
1.
INTRODUCTION
2.
3.
hm@syselec.net
PHYSICAL PROPERTIES
Density
6.14 kg/m3
Thermal Conductivity
0.0136 W/mk
Critical Temperature
Critical Density
730 kg/m3
Critical Pressure
4.
284
5.
A. ISO 14064
In line with IPCC directive and Kyoto Protocol, The
ISO 14064 standard, published in 2006, revolves
around environmental management and quantifying,
monitoring, reporting and verifying greenhouse gas
emissions. The standard is published in three parts:
ISO 14064-1: 2006 specifies principles and
requirements at the organisation level for
quantification and reporting of greenhouse gas
emissions and removals. It includes
requirements for the design, development,
management, reporting and verification of an
organisations greenhouse gas inventory.
6.
ORIGIN OF CONTAMINATION
285
B.
Contamination by Leakage
C. Contamination by Desorption
During the assembly of the equipment itself,
accumulation of Humidity and gases within the inner
surfaces of the equipment or in the bulk materials
are released within SF6 during its normal operation
and at elevated internal temperature. Polymeric
materials such as epoxy are highly hygroscopic and
have poor moisture retention capability at increased
temperatures. Adsorbers which have not been
properly handled may contain both humidity and
adsorbed SF6 decomposition products which can be
released during evacuation or at elevated
temperature. The quantities of the desorbed
substances are difficult to estimate because they
depend on the specific materials employed,
production methods, quality control and the
assembling and maintenance procedures.
Spark Discharges
Switching arc
Failure Arcs
Partial Discharge
E.
286
H. Failure Arcs
Failure Arcs are a result of insulation breakdown or
switch gear interruption failure and occur extremely
rarely. In these events, the arc burns mainly between
metallic minerals, which are not designed for arcing
such as aluminium, copper and steel. These materials
have relatively high arc erosion rates.
I.
Fig. 1: Traces of flashover on a busbar (left)and surface carbon
deposition due to failure arcs (right)
F.
Spark Discharges
G. Switching Arcs
Switching arcs occur during the load
breakingoperation of power circuit breakers. At the
centre of high current breaking arc, the temperature
rises to be as high as 20000 K. As the arc cools,
recombination of sulphur and fluorine to form SF6
occurs rapidly, often in the microseconds scale. In
the presence of oxygen, H2O and metal vapour,
resulting of electrode heating, the recombination
process is altered which leads to the formation of
various arc by-products. The high current flow in
these arcs leads to substantial erosion of the contacts
and insulation material by the hot arc. The main cause
for SF6 decomposition is the reaction of these erosion
products with the fragments of thermally dissociated
SF6 and other trace gases such as moisture and
oxygen. The most important of these reactions can
be expressed by the below three formulae:
7.
SF6 IMPURITIES
287
Specification
according to 60376
Air
0.05% by volume
CF4
0.05% by volume
H2O
122 ppmv
Specification
according to 60480
3% by volume
H2O
200 ppmv
HF
25 ppmv
SO2
50 ppmv
D. Heat Transfer
z
8.
EFFECTS OF CONTAMINATION
Health risk
Corrosion
Heat transfer
A. Health Risk
SO2 and HF constitute a health risk, whereby they
might cause irritation effect in eyes and nose and
lead to difficulty in breathing. HF, one of the highly
corrosive gases, causes severe skin burns if it comes
in contact with the skin of human personnel.
B.
Corrosion
C. Insulation Performance
9.
288
NDIR (Non-dispersive
Infrared)
Spectroscopic Analysis
Highly reliable as it is a
non-contact based
measurement
Highly susceptible to
temperature and
humidity drifts
Slow responding
HF detection is not
possible as it corrodes
the sensor
HF detection is possible
since it is a non-contact
based measuring method
Expensive technology
A. Reclaiming Equipment
Gas reclaimers have been used successfully since the
introduction of SF6 technology. They are
commercially available in a variety of sizes, gas
processing capacities and storage capacities and range
from units that can be hand carried to larger trailer
mounted systems. The appropriate type and size of
the reclaimer should be chosen according to the gas
capacity to be handled.
B.
C.
Filters
289
Filter type
Particle Filter
Tasks
Removes solid
decomposition
products and
other particles
at input of
reclaimer
Major
Characteristics
Pore size 1 m
Gas/Humidity Removes
Filter
Gaseous
Decomposition
Products
Residual Humidity
<100ppmv
Residual SO2
<10 ppmv
Residual Reactive
products
Detoxification Reduces
Filter
reactive
decomposition
products
Same as prefilter
Oil Filter**
Special Filter
equipped with Visual
Oil Indicators
Removes Oil
H. Refilling
The reclaimer must have the provision to allow
refilling of gas, from the storage vessel into an
electrical equipment, the refilling procedure
requirements will vary according to storage method
employed.
I.
Hose Connection
Adsorbents
Contaminants Removed
Molecular Sieve 4A
J.
Activated Alumina
Soda-Lime
(CaO-NaOH)
Water, SO2F2,HF
Activated Charcoal
Oil Vapour
Pipe Work
D. Vacuum Pump
vibration proof
E.
F.
Gas/Humidity Filter
G. Storage Module
The SF6 storage module is used to store SF6
290
11. CONCLUSION
3.
4.
5.
REFERENCES
1.
2.
291
Wojceich Koltunowich
OMICRON Energy Solutions, Germany
SUMMARY
Failure statistics of power transformers show that
the majority of failures are caused by insulation
defects. Almost half of these insulation problems
originate at the bushings. A commonly used DGA
(dissolved gas analysis) sensor detects insulation
problems inside the tank only, but not at the
bushings. Therefore supplementary online bushing
monitoring is vital.
This paper describes a new on-line method for
capacitance and dissipation factor measurements
of high voltage bushings, for recording grid
transients and for partial discharge monitoring at
power transformers. The needed accuracy for
reliable detection of failures is in the range of 5
pF for capacitance and 0.1 % for dissipation factor.
For reaching this goal, a relative comparison of
the bushing currents of the three phases, measured
at the bushing taps, does not provide sufficient
accuracy due to imbalances in the network.
Additionally, simultaneous ageing, as it can be
anticipated for a three phase transformer, will not
be detected. To overcome these shortcomings, this
paper introduces an absolute method for
measuring capacitance and dissipation factor of
HV bushings. Even under field conditions
measurement accuracy similar to accurate off-line
power factor tests was reached. Partial discharges
are an early breakdown indicator for HV
dielectrics. With the measurement on the HV
bushing tap, not only failure of the bushings
dielectric but also of the transformer insulation
system can be detected. As for off-line
measurements, the discrimination between noise
and true internal discharges is the key for
successful diagnosis. Strategies for sensitive
partial discharge measurements under disturbed
1.
292
Voltage in kV
No. of layers
Change in %
123
14
7.1
245
30
3.3
420
40
2.5
550
55
1.8
RIP
OIP
RBP
DF IEC60137
<0.7%
PF IEEE C57.19.01
<0.7% <1.5%
293
2.
Fig. 2: Architecture of the monitoring system applied for comparison and reference method
294
Minutes
Centiradians
0.1
0.1
0.15
0.2
0.2
10
0.3
0.5
0.5
20
0.6
1.0
1.0
40
1.2
3.0
3.0
Not
Specified
Not
Specified
Class
Phase Displacement
I B = 2 f C B U High C B =
IB
2 f U High
....(1)
295
Fig. 5: Example of PRPD patterns measured by conventional method (left) and UHF method (right) for a known internal PD defect
3.
296
4.
PD MONITORING
297
298
4.3 Transients
Figure 18 shows an example of transient overvoltages with the amplitudes between 1.25 and 1.77
p.u. recorded in four months after installation of a
monitoring system.
The transient with the highest amplitude (1.77 p.u.)
is shown in Figure 18(a), Figure 18(b) and 18(c) show
other transient over-voltages recorded during the
monitoring period. Even with such amplitudes, these
transients represent a threat to the insulation of the
bushings and windings because of the resonant
phenomena which can lead to higher voltage
distribution between the turns. The number of
transients cannot be controlled but their monitoring
can help identify defective equipment which
generates over-voltages, near the transformer.
Fig. 18: Time stamp and shape of the transients detected at the bushings
5.
CONCLUSIONS
REFERENCES
1.
2.
3.
299
5.
6.
7.
9.
300
M. Boucherit
A. Procopiou
Alstom Grid, France
SUMMARY
Digital devices such as numerical protection
relays and digital systems such as substation
control are prevalent as the technology of choice
in substations today. This article looks at other
substation areas into which digital technology has
permeated, such that progressively, substations
can become fully digital in their implementation.
Denmark is taken as an example, having a
significant number of windfarms on a number of
islands. These are interconnected using 400kV
hybrid lines. To avoid disfiguring the beauty of
certain environmentally protected areas,
underground
cables
were
installed.
Nonconventional fully-digital instrument
transformers were selected due to their low mass
and slimline construction, replacing conventional
wound current transformers. Correct application
of IEC61850 standards allows a lot more of the
substation engineering to be undertook in the
controlled environment of the factory, rather than
on the substation site where outage times and
site labour are at a premium.
The paper builds on the in-service advantages
realized using IEC 61850-8-1 for the DCS,
including full protection and control, extending
the implementation to include the process bus.
Process bus deployments replace the traditional
hardwiring to primary equipment with an Ethernet
link, and also convert the primary current and
voltage measurement channels to protection
relays and other IEDs (intelligent electronic
devices) to fibre-optic too. Digital implementation
helps to reduce the substation physical size, move
as much configuration and testing to the FAT stage
(factory acceptance testing), and also decouples
Ritesh Bharat
Alstom T&D, India
1.
INTRODUCTION
2.
301
Improved safety
3.
ARCHITECTURE OF DIGITAL
SUBSTATIONS
IEC 61850 is the international standard for Ethernetbased communication in substations. IEC 61850
allows for the full digitizing of the signals in a
substation and is necessary for the large amount of
data to be managed and communicated for the realtime management of a smarter, modern power grid.
IEC 61850 is designed for interoperability and
longevity, in order to be independent from any
supplier.
z
302
4.
DIGITAL INSTRUMENT
TRANSFORMERS
303
conductor. The sensor output becomes a lowlevel voltage measurement, which can be
accurately correlated to the primary current.
6.
5.
7.
304
8.
305
9.
TESTING PLATFORM
306
10. CONCLUSION
Digital substation implementation allows the lifetime
total cost of ownership of the substation to be
reduced. The reduced size and weight of digital
instrument transformers, and the protection and
control panels provide attractive benefits, allowing
placement in compact substations where space may
be limited. The Energinet project shows the increasing
confidence in the application of digital substations
307
John Luksich
Alan Sbravati
Cargill
SUMMARY
Natural Ester insulating liquid has been used in
distribution and power transformers for many
years now. The experience in thousands of power
transformers with natural esters, in new and
retrofilled units, up to the largest 420 kV power
transformer, is traced back to the beginnings in
the early 2000s. Field operation data as well as
laboratory studies provided from power
transformers and reactors are discussed in this
paper to demonstrate that natural esters are a
reliable long term dielectric insulation and
coolant. In this paper, a case history and
laboratory testing data from samples collected
during routine maintenance intervals indicate that
natural ester fluid results can be used to reliably
diagnose operating problems and suggest
corrective actions.
Keywords: Power Transformers, Natural ester,
transformer insulation, retro-fill, transformer oil,
ester fluids, field experience with natural esters,
oxidation stability
1.
INTRODUCTION
Sabine Bowers
Rajaram Shinde
308
2.
2.1 Overview
The numbers of natural ester liquid-filled units that
are presented in this paper and the various
transformer types are based on cumulative data as
per our records. Not all transformers which have
been filled with Natural Ester can be included and
presented in this overview since it is impossible to
track every end-customer of transformers with this
fluid.
The majority of natural ester-filled power
transformers include over 25,000 small power
substation units above 38 kV and between 2 to 10
MVA in power from various transformer
manufacturers. Figures 2 and 3 provide a summary
of the voltage and power ranges between medium
to large power transformers containing natural ester
liquids.
309
310
Fig. 6b: Brazilian climate map showing the location where the
reactor is installed
311
312
Fig. 11: Dissipation factor of the natural ester liquid from the
reactor, with the red line indicating the suggested limit of
continuous operation as per IEEE C57.147 [16]
Fig. 10: Breakdown voltage of the natural ester from the reactor,
with the red line indicating the suggested minimum value for the
fluid after contact, prior to energization (new)
313
3.
CONCLUSION
BIBLIOGRAPHY
1.
2.
3.
4.
5.
6.
7.
8.
9.
314
315
SUMMARY
In a conventional substation the primary
equipments i.e. instrument transformers, circuit breaker, disconnectors etc. are connected to
control and relay panels / bay controllers through
hard wiring - copper control cables. This requires
much labour and it is time consuming job. It is
also very difficult to identify the mistakes / faults
in wiring. These all together ultimately contribute
to long project delivery time. The primary
equipments themselves are also not having any
intelligence. Some inherent issues associated with
conventional primary equipments can not be
eliminated. For example, the conventional CT is
still with the probabilities of secondary open
circuit, saturation, inability to produce exact
replica of primary current particularly high
frequency wave forms/harmonics. Complete
monitoring of circuit breaker and disconnectors
further adds cabling and separate devices. As far
as conventional secondary equipments,
particularly protection system, is concerned, it is
required to share the information among the relays
which again need inter relay hard wiring if relays
are with different protocols/standards.
The digital substation is the solution to address
the above issues. Also, to transform real time data
and control to master control centre and to reap
maximum benefits of information technology and
digital technology in control, protection and
automation, the digital substation is todays need
to keep pace with the changing power system
scenario.
Since it eliminates hard wiring, the operational
1.
Scheme 2
Scheme 3
2.
z
deengg.getco@gebmail.com
316
IEC 61850
adopted at
process
bus
Optical
CTs and
Electronic
VTs
3.
z
z
No ferromagnetic resonance
Reduced size & Light Weight - Very
compact - Requires less foot print and
reduces erection time
Requires no maintenance
(ii) Electronic VT
In this CT, the ring type current sensor
(surrounds the current carrying conductor)
consists of few turns of optical fibre which
carries polarized light generated by the
Electronics circuit (also called Merging Unit) -
317
4.
(i) Optical CT
GETCO has installed Alstom make 220 KV optical
CTs in one bay - Achhalia Line No.3 at existing 220
318
Site Photographs
220 KV
Optical
CT
Performance
319
220 KV
Optical CT
5.
320
7.
CONCLUSION
Digital Substation
6.
EXPECTATIONS
IEC 61850 - 9.2 compliant Bus Bar Protection Not available even with many of the leading
Relay manufacturer
BIBLIOGRAPHY
1.
2.
321
Sl. No.
A.
Annexure-1
Sl. No.
Digital Inputs
CB R-Ph Open
Sl. No.
CB R-Ph Closed
CB Y-Ph Open
CB Y-Ph Closed
CB B-Ph Open
CB B-Ph Closed
CB - Local Mode
CB - Remote Mode
CB - AC supply Healthy
10
CB - DC supply - 1 Healthy
11
CB - DC supply - 2 Healthy
12
CB - Spring Charged
10
13
CB - Lockout - 1 Optd
11
14
CB - Lockout - 2 Optd
12
15
CB - PDR Optd
13
16
14
17
CB - Ready
15
18
Sl. No.
Digital Outputs
CB Open command - 1
CB Open command - 2
CB Close command
Sl. No.
Digital Inputs
4, 5
6, 7
CB - TC - 1 Y-Ph Trip
8, 9
CB - TC - 1 B-Ph Trip
10, 11
CB - TC - 2 R-Ph Trip
12, 13
CB - TC - 2 Y-Ph Trip
14, 15
CB - TC - 2 B-Ph Trip
322
Sl. No.
Digital Outputs
10
Isolator I/L
11
12
Sl. No.
13
14
15
16
323
S. Gaikwad
Doble Engineering, India
SUMMARY
This paper looks at transformer health indices,
and the generation of an index so as to quickly
provide value to an organization. A transformer
health index is a number which represents the
health of a transformer it can be used to rank
transformers for replacement, to identify those
most likely to fail, to identify those which can be
left alone.
There are many ways to generate an index, some
of which are more useful than others. The key is
to understand that we are making decisions about
a large asset, but we are generating condition data
which may be indicative of a particular condition,
and that to link the condition data to the asset we
have to address failure modes. If the generated
condition data does not indicate a failure mode,
it may be of limited value. If it does indicate a
failure mode, how strongly is that failure mode
indicated, and how confident are we in the
diagnosis? Relevance of a data source to a failure
mode is useful to determine whether a particular
mode is active, based on several data sources.
Getting use from a health index should not require
every possible piece of data building a system
which can start with limited data sets, such as off
line DGA alone, and then build up by adding in,
for example, test and maintenance data, or asset
specific history, is a means to provide value early,
and to get user feedback on asset health systems.
This paper will describe the generation of health
indices from a simple Delphic approach, through
basic DGA analyses on to complex statistical
approaches based on relevant standards; in each
case practical examples are given and discussed.
sgaikwad@doble.com
1.
324
4.
2.
timescale
transformer is on active list for replacement
within 2 years
325
Within C57.104 there is a table of condition codes relating to both individual gases and total dissolved
combustible gas (TDCG), as shown below.
Table 1: Dissolved Gas Concentrations
Factor
Scale
Transformer 1
Transformer 2
Transformer 3
0-10
10
Dielectric
0-10
10
Thermal
0-10
Mechanical
0-10
10
Oil
0-10
0-10
Operational
0-10
10
Design/manufacturer
0-10
10
0-10
10
Sum
0-90
33
33
33
326
It should be apparent in the above table that we have three transformers with identical overall scores. The
action required in each case is very different as the contributory factors to the score are different in each
case. We can say, however, that each transformer should have a similar urgency.
When we add weighting to the factors we can lose sight of the contributory factors. The table below shows
a system for weighting contributory factors for a tap changer.
Factor
Raw Score
Weight,%
Weighted Score
0.1
10
0.3
Ethylene
15
1.2
Methane
15
0.3
Acetylene
0.1
Ethylene/Acetylene Ratio
15
0.6
15
0.3
10
0.1
Operation Count
10
0.1
SUM
25
100
3.1
3.
CONCLUSION
BIBLIOGRAPHY
1.
327
N. Nallarasan
Mohit Joshi
POSOCO, India
SUMMARY
The benefits of a large interconnected electricity
grid are reaped by all. Though the planning of
power system in India started with the concept of
regional self-sufficiency, the same was reviewed
considering resource concentration, load growth
areas and the importance of integration of
regional grids. This is furthermore important in a
country like India which has not only diverse
culture but also diverse power system portfolio
of each region. This diversity could be harnessed
to provide power to all at all-time only by
integrating the grids. In 1991, North Eastern
Region (NER) was synchronised with Eastern
Region (ER) followed by synchronisation of
Western Region (WR) in 2003 and Northern
Region (NR) in 2006. Till 2013, two grids namely
North-Eastern-North Eastern-Western (NEW) grid
and Southern Region (SR) Grid were in existence.
The synchronisation of SR with NEW grid was
done on 31st December 2013 over 765 kV RaichurSholapur. Prior to synchronisation, a number of
activities such as designing of additional System
Protection Schemes (SPS), testing of HVDC
frequency controllers and review of the Under
Frequency Relay (UFR) defense plans etc. were
done to ensure smooth synchronisation and
operation of National Grid. Oscillations of the
order of 0.2 Hz frequency was observed while
synchronizing and during other instances of major
load or generation tripping also. Subsequently,
in June 2014, the second circuit of 765 kV RaichurSholapur has also been commissioned which has
strengthened the AC interconnection between
NEW and SR Grid. Synchronisation of SR grid with
rest of the country has not only improved the
power transfer towards the southern region but
also brought about several improvements. The
1
Pradeep Reddy
1.
BACKGROUND
srnarasimhan@posoco.in
328
NR
WR
ER
NER
Total
49.2
2160
2060
820
100
5140
49.0
2170
2070
830
100
5170
48.8
2190
2080
830
100
5200
48.6
2200
2100
840
100
5240
Total
8720
8310
3320
400
20750
B.
C.
D.
2.
329
G.
H.
3.
FREQUENCY CONTROLLERS
SETTINGS
(ii) The SPS 1000 scheme of HVDC TalcherKolar Bipole was to be kept in service. In
addition to it, 600 MW additional
generation backing down in eastern region
as per the agreed scheme was implemented.
Modification to Kundankulam SPS was
implemented.
330
4.
5.
HVDC Talcher-Kolar
HVDC
Gazuwaka BTB
HVDC
Bhadrawati BTB
Bhadrawati : 500 MW/Hz
KEPT OFF
48.5 Hz 51.5 Hz
48.5 Hz 51.5 Hz
48.8 Hz 51.2 Hz
48.8 Hz 51.2 Hz
331
Initiating Condition
Action
332
6.
SYNCHRONISATION OF SOUTHERN
REGION
333
Fig. 5: PMU plots of Frequency, Voltage magnitude of Raichur/Sholapur and 765kV Raichur-Sholapur line flow
7.
OPERATIONAL EXPERIENCE
1.
2.
334
3.
4.
Fig. 9: PMU Plot of 765 kV Raichur-Sholapur line flow and frequency of 765 kV Agra & 765 kV Sholapur at 1620 hrs on 22.01.14
335
Fig. 10: Plot of Maximum, Minimum and Average frequency of SR from 2013 to 2014
5.
6.
8.
CONCLUSION
336
Acknowledgement
Authors are grateful to the power system fraternity
and POSOCO Management for the encouragement.
Authors also express their gratitude to all those who
have contributed towards synchronisation of
Southern Region. The views expressed in this paper
are those of the authors and not necessarily of the
organization they belong to.
BIBLIOGRAPHY
1.
available on https://sustainabledevelopment.
un.org/content/documents/interconnections.
pdf
2.
3.
4.
5.
337